Actvity No.

LP

TEST

WORK
STATOR

METHOD
TURBINE
INSPECTION

-
THREAD-OUT

TM-04 CONTROL VALVE

REVISIONING OF

CONDENSER TUBE
REROUTING WORK
TM-08 ROTOR ALIGNMENT
TM-07 GEMERATOR ROTOR

TM-10 MODIFICATION AND

NRV REPOSITIONING
BEARING BOXUP, OIL
TM-01 BARRING GEAR STOP

HPH, LPH DRAIN LINE


REPLACEMENT WORK
& GENERATOR ROTOR

CRH NRV BONNET SEAL


TURBINE BEARING AND

TM-13 MODIFICATION AND ITS


OVERHAUL ACTIVITY

THREAD-IN AND BOXUP

TM-09 FLUSHING AND AIR LEAK


TM-06 GENERATOR ROTOR AND

CEP DISCHARGE PIPELINE


TURBINE MAINTENANCE

GENERATOR
TM-05 REPLACEMENT AND PIVOT

TM-11 CLEANING BY BULLET SHOT


TM-03 GENERATOR DISMANTLING

TM-12 VACUUM PUMP SERVICING

0
0
0
0
0
0
0
POWER CYLINDER SHAFT 0
0
0
0
0

Status
Status
Status
Status
Status
Status
Status
Status
Status
Status
ALLIGNMENT CHECKING, Status
TM-02 BEARING COVER OPENING Status
Status

Actual
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Actual
DECOUPLING OF ROTORS, Actual
Actual
Actual

Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule

12/30/1899
WIP

5-Aug
5-Aug
4-Aug
5-Aug
8-Aug
6-Aug
6-Aug
4-Aug
3-Aug

30-Jul

16-Aug
18-Aug
14-Aug
8/5/2018
8/3/2018

WITHHOLD
Start Date

COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED

9-Aug
5-Aug
3-Aug

15-Aug
11-Aug
10-Aug
19-Aug
21-Aug
19-Aug
18-Aug
15-Aug
10-Aug
14-Aug
End Date

8/3/2018

8/3/2018 8/21/2018
8/6/2018 8/21/2018
8/4/2018 8/21/2018
8/11/2018 8/23/2018
8/17/2018 8/21/2018
8/10/2018 8/21/2018
8/17/2018 8/21/2018
7/30/2018 8/27/2018
8/29/2018
8/4/2018 8/21/2018
8/4/2018 8/21/2018
7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018
1

7/28/2018
7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018
2

7/29/2018
7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018
3

7/30/2018
7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018
4

7/31/2018
8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018
5

8/1/2018
8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018
6

8/2/2018
8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018
7

8/3/2018
8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018
8

8/4/2018
8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018
9

8/5/2018
8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018
10

8/6/2018
8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018
11

8/7/2018
8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018
12

8/8/2018
8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018
13

8/9/2018
8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018
Unit # 10 AOH Progress Review Status and Bar-chart

14

8/10/2018
8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018
15

8/11/2018
8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018
16

8/12/2018
3x660MW KORADI THERMAL POWER STATION

8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018
17

8/13/2018
8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018
18

8/14/2018
8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018
19

8/15/2018
Date

8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018
20

8/16/2018

Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review

8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018
:

21

8/17/2018
8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018
22

8/18/2018
8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018
23

8/19/2018
8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018
24

8/20/2018
8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018
25

8/21/2018
8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018
26

8/22/2018
8/29/2018

8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018
27

8/23/2018
8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018
28

8/24/2018

8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018
29

8/25/2018

8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018
30

8/26/2018

8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018
31

8/27/2018

8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018
32

8/28/2018

8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018
33

8/29/2018
Actvity No.

TM-20
TM-19
AND
WORK

WORKS
ITS

CLEANING
NRVOVERHAUL
TM-13 MODIFICATION

BARRING GEAR
ALLIED WORKS)

TM-18 SYNCHRONIZING
TM-15 NDCT POND BASIN

CW & ACW SYSTEM

TM-17 RESTORATION OF TG
REPOSITIONING

ASSOCIATED

SERVICING AND OTHER


AND ITS
ACTIVITY

TM-16 (INTERNAL INSPECTION,


CEP DISCHARGE PIPELINE

Miscellanious Actvites - 2 0
0
0
0
0
0
TM-14 AUXILLIARIES WITH ALLIED 0
0

Status
Miscellanious Actvites - 1 Status
Status
Status
Status
Status
TDBFP TURBINE OVERHUAL Status

Actual
Actual
Actual
Actual
Actual
Actual
Actual

Schedule
Schedule
Schedule
Schedule
Schedule
Schedule
Schedule

WIP
WIP
WIP
WIP
31-Jul

8/1/2018
8/1/2018
Start Date

7/28/2018
7/28/2018
8/24/2018
7/30/2018
7/31/2018
7/30/2018

COMPLETED
COMPLETED

NOT YET STARTED


17-Aug
End Date

8/29/2018
8/24/2018
8/29/2018
8/24/2018
8/24/2018
8/20/2018 8/23/2018
8/20/2018 8/22/2018
8/29/2018
8/15/2018
8/4/2018 8/28/2018
8/4/2018 8/20/2018
8/29/2018

7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018 7/28/2018
7/28/2018
7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018 7/29/2018
7/29/2018
7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018 7/30/2018
7/30/2018
7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018 7/31/2018
7/31/2018
8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018 8/1/2018
8/1/2018
8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018 8/2/2018
8/2/2018
8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018 8/3/2018
8/3/2018
8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018 8/4/2018
8/4/2018
8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018
8/5/2018
8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018 8/6/2018
8/6/2018
8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018 8/7/2018
8/7/2018
8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018 8/8/2018
8/8/2018
8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018 8/9/2018
8/9/2018
8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018 8/10/2018
8/10/2018
8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018 8/11/2018
8/11/2018
8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018 8/12/2018
8/12/2018
8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018 8/13/2018
8/13/2018
8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018 8/14/2018
8/14/2018
8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018 8/15/2018
8/15/2018
8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018 8/16/2018
8/16/2018

Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review
Progress Review

8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018 8/17/2018
8/17/2018
8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018 8/18/2018
8/18/2018
8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018 8/19/2018
8/19/2018
8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018 8/20/2018
8/20/2018
8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018 8/21/2018
8/21/2018
8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018 8/22/2018
8/22/2018
8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018 8/23/2018
8/23/2018
8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018 8/24/2018
8/24/2018

8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018 8/25/2018
8/25/2018 8/25/2018

8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018 8/26/2018
8/26/2018 8/26/2018

8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018 8/27/2018
8/27/2018 8/27/2018

8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018 8/28/2018
8/28/2018
8/28/2018 8/28/2018

8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018 8/29/2018
8/29/2018
8/29/2018 8/29/2018
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
SN OVERHAUL ACTIVITY

BARRING GEAR STOP


From To
TM-01 Scheduled 31-Jul 31-Jul
Status Select
Actual 3-Aug Select

BEARING COVER
OPENING
From To
TM-02
Scheduled 1-Aug 2-Aug
Status COMPLETED
Actual 4-Aug 16-Aug
DECOUPLING OF ROTORS, ALLIGNMENT
CHECKING, GENERATOR DISMANTLING &
GENERATOR ROTOR THREAD-OUT
From To
TM-03 Scheduled 1-Aug 8-Aug
Status COMPLETED
Actual 4-Aug 20-Aug

TURBINE BEARING AND CONTROL VALVE


INSPECTION

TM-04 From To
Scheduled 2-Aug 14-Aug
Status WIP
Actual 4-Aug Select

CRH NRV BONNET SEAL REPLACEMENT AND


PIVOT POWER CYLINDER SHAFT REPLACEMENT
WORK
TM-05 From To
Scheduled 30-Jul 10-Aug
Status WIP
Actual 30-Jul Select

REVISIONING OF GENERATOR ROTOR AND STATOR


From To
TM-06 Scheduled 8-Aug 15-Aug
TM-06
Status WITHHOLD
Actual NOT STARTED Select

GENERATOR ROTOR THREAD-IN AND BOXUP

TM-07 From To
Scheduled 14-Aug 18-Aug
Status COMPLETED
Actual 10-Aug 15-Aug

LP TURBINE - GENERATOR ROTOR ALIGNMENT


From To
TM-08 Scheduled 18-Aug 19-Aug
Status COMPLETED
Actual 18-Aug 20-Aug

BEARING BOXUP, OIL FLUSHING AND AIR LEAK TE

TM-09 From To
Scheduled 16-Aug 21-Aug
Status WIP
Actual NOT STARTED Select

HPH, LPH DRAIN LINE MODIFICATION AND


REROUTING WORK
From To
TM-10 Scheduled 5-Aug 16-Aug
Status NOT YET STARTED
Actual NOT STARTED Select

CONDENSER TUBE CLEANING BY BULLET SHOT


METHOD

TM-11 From To
Scheduled 31-Jul 9-Aug
Status COMPLETED
Actual 4-Aug Select

VACUUM PUMP SERVICING

TM-12
From To
Scheduled 30-Jul 5-Aug
TM-12

Status COMPLETED
Actual NOT STARTED 16-Aug

CEP DISCHARGE PIPELINE MODIFICATION AND


ITS NRV REPOSITIONING WORK
From To
TM-13
Scheduled 3-Aug 15-Aug
Status COMPLETED
Actual 3-Aug 15-Aug

TDBFP TURBINE OVERHUAL AND ITS


ASSOCIATED AUXILLIARIES WITH ALLIED WORKS

TM-14

From To
Scheduled 31-Jul 17-Aug
Status WIP
Actual 30-Jul Select

NDCT POND BASIN CLEANING

TM-15
From To
Scheduled 31-Jul 18-Aug
Status NOT YET STARTED
Actual NOT STARTED Select

CW & ACW SYSTEM (INTERNAL INSPECTION,


SERVICING AND OTHER ALLIED WORKS)

TM-16

From To
Scheduled 31-Jul 15-Aug
Status WIP
Actual 30-Jul Select

RESTORATION OF TG BARRING GEAR


From To
TM-17
TM-17 Scheduled 20-Aug 22-Aug
Status NOT YET STARTED
Actual NOT STARTED Select

SYNCHRONIZING
From To
TM-18 Scheduled 24-Aug 24-Aug
Status NOT YET STARTED
Actual NOT STARTED Select

Miscellanious Actvites - 1
From To
TM-19 Scheduled 28-Jul 24-Aug
Status WIP
Actual 30-Jul Select

Miscellaneous Actvites - 2

TM-20

From To
Scheduled 28-Jul 24-Aug
Status WIP
Actual 30-Jul Select
7/28/2018
7/29/2018
7/30/2018
7/31/2018
8/1/2018
8/2/2018
8/3/2018
8/4/2018
8/5/2018
8/6/2018
8/7/2018
8/8/2018
8/9/2018
8/10/2018
8/11/2018
8/12/2018
8/13/2018
8/14/2018
8/15/2018
8/16/2018
8/17/2018
8/18/2018
8/19/2018
8/20/2018
8/21/2018
8/22/2018
8/23/2018
8/24/2018
8/25/2018
8/26/2018
8/27/2018
8/28/2018
8/29/2018
TODAY Start 28.07.2018
WIP
NOT YET STARTED
TODAY Completed
COMPLETED
WITHHOLD
Select
7/28/2018

7/29/2018
STARTED
Select

NOT

7/28/2018
Select

WIP

COMPLETED

7/28/2018
7/29/2018
7/30/2018
7/31/2018
8/1/2018
8/2/2018
8/3/2018
8/4/2018
8/5/2018
8/6/2018
8/7/2018
8/8/2018
8/9/2018
8/10/2018
8/11/2018
8/12/2018
8/13/2018
8/14/2018
8/15/2018
8/16/2018
8/17/2018
8/18/2018
8/19/2018
8/20/2018
8/21/2018
8/22/2018
8/23/2018
8/24/2018
8/25/2018
8/26/2018
8/27/2018
8/28/2018
8/29/2018
8/30/2018
8/31/2018
9/1/2018
9/2/2018
9/3/2018
9/4/2018
9/5/2018
9/6/2018
9/7/2018
ERMAL POWER STATION
iew Status

PROGRESS REVIEW STATUS, as on


30 August 2018
Executve Engineer (TM-660)
28.07.2018
7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
29 August 2018

All work completed.

All work completed.

Both MSV Inspection and checking work by M/s. LMTG in


coordination with C&I is in progress.

All work completed.


All work completed.

All work completed.

All work completed.

All work completed.

All work completed.

All work completed.


All work completed.

TDBFP-A Control oil & lube oil filter modification WIP.


TDBFP - B barring gear assembly boxup work is in progress.
Also pedestral cleaning work is in progress.

NDCT all work completed. CW channel gates opened.


Clearence given for NDCT charging.

ACW system & CW 10 A clearence given.


CW 10 B mechanical seal resetting work done by M/s.
Leakproof. Minor leakage from seal in static condition , '
may subside during pump running condition'. Dewatering
of suction forbay is kept in sevice.

Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs.


Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs.

Boiler blowdown pump no 1 restoration work is in progress.


Unit # 8
suction forbay strainers work in progress.

1) GSC header drain routing work in progress.

2) TDBFP A and B MOT vapour fan


modification WIP. 3) H2 purging line additional valve
(65 NB) fitting work completed.
4) Kaydon filters modification for COP
machine work is in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
28 August 2018

All work completed.

All work completed.

Both MSV Inspection and checking work by M/s. LMTG is in


progress.

CRH NRV LHS boxup work completed. Power cylinder shaft


Boxup work completed.
CRH NRV RHS, boxup work completed.
All work completed.

All work completed.

All work completed.

HRH drain Main MIV LHS boxup work in progress.

All work completed.

All work completed.


All work completed.

Flash tank Pump installation work completed. Coupling


work in progress.
TDBFP-A Control oil & lube oil filter modification WIP.

U# 10 NDCT RHS basin cleaning work completed.


LHS basin cleaning work completed.
12 mtr fills & nozzles fitting work completed.
Pipe End caps and broken pipes repairing and replacement
work accomplished. NDCT gate
opening WIP.

CW 10 B mechanical seal resetting work done by M/s.


Leakproof. Minor leakage from seal in static condition , '
may subside during pump running condition'. Dewatering
of suction forbay is kept in sevice.
ACW system & CW 10 A clearence given.

Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs.


Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs.

Boiler blowdown pump no 1 restoration work is in progress.


DM feed
pump F assembly work in progress.
Unit # 8 suction forbay strainers work in
progress.

1) GSC header drain routing work in progress.


2) Quick fill CV boxup WIP.
3) TDBFP A and
B MOT vapour fan modification WIP. 4) H2 purging
line additional valve (65 NB) fitting WIP.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on PROGRESS REVIEW STATUS, as on
27 August 2018 25 August 2018

All work completed. All work completed.

All work completed. All work completed.

Both MSV opening problem - Inspection and checking work Both MSV opening problem - Inspection and
will be taken up by M/s. LMTG on 28.08.2018 checking work will be taken up by M/s. LMTG on
28.08.2018

CRH NRV LHS boxup work completed. Power cylinder shaft CRH NRV LHS boxup work completed. Power cylinder
Boxup work completed. shaft Boxup work completed.
CRH NRV RHS, boxup work completed. CRH NRV RHS, boxup work completed.
All work completed. All work completed.

All work completed. All work completed.

All work completed. All work completed.

HRH drain Main MIV LHS boxup work in progress. HRH drain Main MIV LHS boxup work in progress.

All work completed. All work completed.

All work completed. All work completed.


All work completed. All work completed.

Flash tank Pump installation work completed. Coupling Flash tank Pump installation work completed.
work in progress. Coupling work in progress.
TDBFP - A coupling work completed. TDBFP -B coupling TDBFP - A coupling work completed. TDBFP -B
work completed. coupling work completed.
TDBFP-A Control oil & lube oil filter modification WIP. TDBFP-A Control oil & lube oil filter modification WIP.

U# 10 NDCT RHS basin cleaning work completed. U# 10 NDCT RHS basin cleaning work completed.
LHS basin cleaning work completed. LHS basin cleaning work completed.
12 mtr fills & nozzles fitting work completed. 12 mtr fills & nozzles fitting work completed.
Pipe End caps and broken pipes repairing and replacement Pipe End caps and broken pipes repairing and
work accomplished. replacement work accomplished.

CW 10 B mechanical seal resetting work done by M/s. CW 10 B mechanical seal resetting work done by
Leakproof. Minor leakage from seal in static condition , ' M/s. Leakproof. Minor leakage from seal in static
may subside during pump running condition'. Dewatering condition , ' may subside during pump running
of suction forbay is kept in sevice. condition'. Dewatering of suction forbay is kept in
sevice.

Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs. Barring gear restored on dtd. 23.08.2018 @ 13.00
Hrs.
Barring gear restored on dtd. 23.08.2018 @ 13.00 Hrs. Barring gear restored on dtd. 23.08.2018 @ 13.00
Hrs.

Boiler blowdown pump no 1 restoration work is in progress. Boiler blowdown pump no 1 restoration work is in
DM feed pump F assembly work in progress. DM feed pump F
progress. Unit # 8 assembly work in progress.
suction forbay strainers work in progress. Unit # 8 suction forbay strainers work
in progress.

1) Dearator level control bypass MOV valve boxup work 1) Dearator level control bypass MOV valve boxup
completed. work in progress
2) GSC header drain routing work in progress. 2) GSC header drain routing work in progress.
3) Quick fill CV inspection WIP. 3) Quick fill CV inspection WIP.
4) TDBFP A 4) TDBFP A and B
and B MOT vapour fan modification WIP MOT vapour fan modification WIP

Executve Engineer (TM-660) Executve Engineer (TM-660)


7/29/2018 7/30/2018

7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
24 August 2018
Executve Engineer (TM-660)
7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
23 August 2018

All work completed.

All work completed.

GV 1 spindle, special nut & connecting rod and coupling box-up work
completed.

CRH NRV LHS boxup work completed. Power cylinder shaft Boxup
work in progress.
CRH NRV RHS, boxup work completed.
All work completed.

All work completed.

Bearing no 7 and 8 top half boxup work completed. Generator


manhole boxup work completed.

All work completed.

All work completed.


All work completed.

Flash tank Pump installation work completed. Coupling work in


progress.
TDBFP - A coupling work completed. TDBFP -B coupling WIP
TDBFP-A Control oil & lube oil filter modification WIP.

U# 10 NDCT RHS basin cleaning work completed.


LHS basin cleaning work 85% completed.
12 mtr fills & nozzles fitting WIP, 90% work completed.
Pipe End caps and broken pipes repairing and replacement WIP

CW 10 B inlet channel dewatering WIP, 80% bay level down.

Barring gear restored today @ 13.00 Hrs.


Barring gear restored today @ 13.00 Hrs.

DM feed pump F , pump lifting WIP.

1) Dearator level control bypass MOV valve lapping WIP. Final blue
match to be taken today.
2) DMCW TG PHE 1 boxup completed.
3) DMCW TG 1 alignment work completed.
4) GSC header drain routing work in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
22 August 2018

All work completed.

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

GV 1 spindle, special nut & connecting rod and coupling received at


site, box-up WIP.

CRH NRV LHS flap assy spindle received at site. Flap assembly boxup
done, bonnet, gland packing work in progress. Power cylinder shaft
awaited at site.
CRH NRV RHS, bonnet, gland packing and segment fitting work
completed. Top cover boxup work completed.

In Generator seal float pump discharge NRV near air side filter (outlet
line), there was spring loaded seat found missing. (It is missing since
comissioning stage). That’s why gland seal float pump is not
developing required pressure. The matter is taken up M/s LMTG
In Generator seal float pump discharge NRV near air side filter (outlet
line), there was spring loaded seat found missing. (It is missing since
comissioning stage). That’s why gland seal float pump is not
developing required pressure. The matter is taken up M/s LMTG

Work completed.

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

Bearing no 7 and 8 top half boxup work in progress.

Work completed.

Work completed.
Work completed.

Flash tank Pump installation WIP,


TDBFP - B coupling work completed.
TDBFP-A Control oil & lube oil filter modification WIP.

U# 10 NDCT RHS basin cleaning work completed.


LHS basin cleaning work 85% completed.
12 mtr fills fitting WIP, 90% work completed.
Nozzles repairing work is in progress.

CW 10 B inlet channel dewatering WIP, 6 mtr level down.

Work completed
Work completed

1) Dearator level control bypass MOV valve lapping WIP


2) DMCW TG PHE 1 boxup WIP
3) DMCW TG 1 alignment work in progress.
4) GSC header drain routing work in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
21 August 2018

All work completed.

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

GV 1 spindle, special nut & connecting rod and coupling sent for
machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle received at site. Flap assembly boxup
work in progress. Bonnet, gland packing work in progress. Power
cylinder shaft awaited at site. CRH NRV RHS, bonnet, gland packing
and segment fitting work completed. Top cover boxup work
completed.

In Generator seal float pump discharge NRV near air side filter (outlet
line), there was spring loaded seat found missing. (It is missing since
comissioning stage). That’s why gland seal float pump is not
developing required pressure. The matter is taken up M/s LMTG
In Generator seal float pump discharge NRV near air side filter (outlet
line), there was spring loaded seat found missing. (It is missing since
comissioning stage). That’s why gland seal float pump is not
developing required pressure. The matter is taken up M/s LMTG

All work completed.

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

Bearing no 7 and 8 top half boxup work in progress.

All work completed.

All work completed.


All work completed.

Flash tank Pump installation WIP. All four nos flash tank pump oil
replacement work completed.
TDBFP - A coupling work completed. TDBFP -
B alignment work in progress.
TDBFP-A Control oil & lube oil filter modification WIP. MDBFP all
work completed.

U# 10 NDCT RHS basin cleaning work completed. LHS basin cleaning


work 80% completed.
12 mtr fills fitting WIP. 80% work completed. Nozzles
repairing work is in progress.

CW suction forebay dewatering WIP. 3mt. level dewatering done,


after gate sealing.
ACW strainer boxup Work completed. . ACW O/L
strainer no 1 bolt tightning work completed. CW 10 B onlet
channel dewatering WIP.

Barring gear assembly installation work in progress.


Barring gear assembly installation work in progress.

1) Dearator level control bypass MOV valve lapping WIP


2) HPBP valve coupling done. C&I work in progress.
3) WDC valve both box-up done. C&I work in progress.
4) DMCW TG 2 PHE Boxup done. PHE 1 boxup WIP
5) DMCW SG-2, SG-1, TG-2, TG-3 Pump alignment done. EM work is
in progress. 6) DMCW TG 1
alignment work in progress. 7) CEP A,B,C oil topup
and bearing greasing work completed.
8) Both stator water pump oil topup work completed.
9) GSC header drain routing work in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
20 August 2018

All bearing cover box-up done

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

GV 1 spindle, special nut & connecting rod and coupling sent for
machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle received at site. Power cylinder shaft
awaited at site. CRH NRV RHS, bonnet, gland packing and segment
fitting work completed. Top cover boxup work is pending.

Generator H2 side seal oil PHE box-up done. Generator sealring


movement test will be taken in the evening.
Generator H2 side seal oil PHE box-up done. Generator sealring
movement test will be taken in the evening.

Generator rotor inserted. Work completed

LP-2 to generator rotor alignment work completed. Decouple runout


and coupled runout taken, found ok. Coupling done.

Bearing no 1,2,3,4,5,6, 7 & 8 oil flushing work completed. Bearing no


7 and 8 top half boxup work pending. H2 side & Air side oil flushing
work completed.

Tube cleaning work completed. Condenser fill test taken upto 9 mtr.
No leakages observed through tubes. Condenser, Debris filter and
OLTC all manholes boxup work completed.

work completed
work completed

Flash tank Pump installation WIP.


TDBFP A Turbine to GB alignment work completed, GB to booster
pump alignment work completed. Gearbox Boxup completed. Now
coupling WIP.
TDBFP-A Control oil & lube oil filter modification WIP. MDBFP all
work completed.

U# 10 NDCT RHS basin cleaning work completed. LHS basin cleaning


work 80% completed.
12 mtr fills fitting WIP. 70%work completed. Nozzles
repairing work is in progress.

CW suction forebay dewatering WIP. 3mt. level dewatering done,


after gate sealing.
ACW strainer top cover fitting Work completed. ACW
U#10 interconnection of 900 NB line work completed. ACW O/L
strainer no 1 bolt tightning work is in progress. CW 10 B onlet
channel dewatering WIP.

Barring gear assembly installation work in progress.


Barring gear assembly installation work in progress.

1) Dearator level control bypass MOV valve lapping WIP


2) HPBP valve box-up done. coupling WIP
3) WDC valve both box-up done. C&I work in progress.
4) DMCW TG 2 PHE Boxup done. PHE 1 boxup WIP
5) DM OH tank inspection and boxup done.
6) DMCW SG-2, SG-1, TG-2, TG-3 Pump alignment done. EM work is
in progress.
7) EH oil system fresh oil topup work done.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
18 August 2018

Bearing cover box-up done

LP-2 to generator rotor alignment WIP

GV 1 spindle, special nut & connecting rod and coupling sent for
machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site;


CRH NRV RHS flap assy spindle box-up done, flap freenes checking
done found ok, bonnet boxup WIP

Generator H2 side seal oil PHE box-up done.


Generator H2 side seal oil PHE box-up done.

Work completed

LP-2 to generator rotor alignment WIP

Bearing no 1,2,3,4,5,6, 7 & 8 oil flushing WIP. Bearing no 7 and 8 top


half boxup work pending. H2 side & Air side oil flushing WIP.

Tube cleaning completed, Tube leakage inspection work pending.

work completed
work completed

Flash tank Pump installation WIP.


TDBFP A Turbine to GB alignment work completed, GB to booster
pump alignment WIP. Gearbox Boxup completed.
TDBFP-A Control oil & lube oil filter modification WIP.

U# 10 NDCT RHS basin cleaning WIP.


12 mtr fills fitting WIP.

CW suction forebay dewatering WIP. 3ft level dewatering done, after


gate sealing.
ACW strainer top cover fitting Work completed.
1) Boiler blow down pump-3 restoration work done.
2) N-pit discharge line leakage attended near NDCT U#9, (MSRL pipes
replaced with PTFE pipes)

1) Dearator level control bypass MOV valve lapping WIP


2) Servomotor box up done, valve box-up WIP.
3) WDC valve box-up WIP.
4) DMCW TG 2 PHE Boxup done.
5) DM OH tank inspection done.
6) DMCW SG-2 Pump alignment done
7) DMCW TG-3 Alignment WIP.
8) CPU B resin trap boxup done.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
17 August 2018

LP 2 to Generator rotor alignment work will be taken in evening after


clearence.

GV 1 spindle, special nut & connecting rod and coupling sent for
machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site; CRH NRV RHS flap assy
spindle & stuffing box received from workshop. Now cleaning WIP.
Boxup work will start soon.

Generator H2 side seal oil PHE leakage observed during pneumatic


test. So leakage arrested now boxup work in progress.
Generator H2 side seal oil PHE leakage observed during pneumatic
test. So leakage arrested now boxup work in progress.

Bearing no 1,2,3,4,5,6 oil flushing WIP. Clearence given to start JOP.


During running of JOP oil leakage observed near bearing no 8. So JOP
stop and leakage arresting WIP by M/s. LMTG. Bearing no 7 and 8 top
half boxup work pending.

Condenser both inlet Pass A and B tube cleaning work completed.


Outlet pass A 10600 Nos. Tube cleaning work completed. Now outlet
pass B tube cleaning WIP. 6000 nos. tubes completed uptill now.
Condenser debris filter manholes boxup WIP.
TDBFP B flash tank pump B civil work completed.Pump installation
WIP. TDBFP B barring gear dismantling work completed. Now
cleaning work in progress. TDBFP A barring gear motor dismantling
work completed. TDBFP A main pump to turbine alignment work
completed & coupling boxup done. TDBFP A Turbine to GB and GB to
Booster pump alignment WIP. Gearbox Boxup WIP. MOT tank cleaning
done. MDBFP oil topup work completed. Line flushing work
completed. Main pump DE side bearing inspection WIP. TDBFP a lub
oil filter and control oil filters modification WIP.

U# 10 NDCT LHS basin cleaning work completed. Dewatering of RHS


basin completed and cleaning work in progress. Nozzles and
distribution pipes repairing work is in progress. Distribution pipes
from cocrete channel repairing work is done by civil.

u#10 NDCT BYPASS VALAVE LHS repositioning work completed as per


operation requirement. U#10 acw outlet strainers interconnections
900 NB pipe work is in progress. Cw pump 10 B PUMP inlet isolating
gates sealing work is in progress ( crane to be operated by EM staff
manually). Acw outlet strainer 1 boxup work is in progress. (All 5 nos
iso gates inserted.) ACW outlet strainers, both are inserted to its
vessel, boxup work is in progress.
1) Dearator level control bypass MOV valve lapping WIP 2) HPBP valve
boxup work completed. Servomotor opening WIP. 4) WDC valve
switchyard side blue matching work completed. WDC boiler side blue
matching work completed. 5) DMCW TG 2 PHE cleaning work
completed. Boxup WIP. 6) EH oil system oil draining and new oil topup
WIP. 7) CPU B resin trap boxup WIP. 8) DM OH tank opening and
inspection WIP.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
16 August 2018

Bearing no 1,2,3,4,5 and 6 bearing cover boxup work


completed.

Generator excitor side and LP 2 side top end shill boxup


work completed. Generator bearing no 7 and 8 top half
boxup work pending.

GV 1 spindle, special nut & connecting rod and coupling


sent for machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site; CRH NRV
RHS flap assy spindle & stuffing box received from
workshop. Now cleaning WIP.
Bearing no 7 and 8 top half boxup work pending.

Condenser both inlet Pass A and B tube cleaning work


completed. Outlet pass A 10600 Nos. Tube cleaning work
completed. Now outlet pass B tube cleaning WIP.

HP vacuum pump A andB alignment completed. LP


vacuum pump A and B alignment work completed. All VP
shutoff trial taken found ok.
CEP discharge line NRV repositioning done; Discharge
header line modification work completed.

TDBFP B flash tank pump B civil work in progress. TDBFP


B barring gear dismantling work completed. Now
cleaning work in progress. TDBFP A barring gear motor
dismantling work completed. TDBFP A main pump to
turbine alignment work completed & coupling boxup
work in progress. MOT tank cleaning WIP. MDBFP oil
topup work completed. Line flushing work completed.
Main pump DE side bearing inspection WIP.

U# 10 NDCT LHS basin cleaning work is in progress. 60%


work completed. Dewatering of RHS basin completed and
cleaning work started. Nozzles and distribution pipes
repairing work is in progress. Distribution pipes from
cocrete channel repairing work is in progress by civil.

u#10 NDCT BYPASS VALAVE LHS repositioning work


completed as per operation requirement. U#10 acw
outlet strainers interconnections 900 NB pipe work is in
progress. Cw pump 10 B PUMP inlet isolating gates
sealing work is in progress ( crane to be operated by EM
staff manually). Acw outlet strainer 1 boxup work is in
progress.
1) Dearator level control bypass MOV valve lapping WIP
2) HPBP valve boxup work completed. Servomotor
opening WIP. 4) WDC valve switchyard side blue matching
work completed. Boxup WIP. WDC boiler side lapping
WIP 5) DMCW TG 2 PHE cleaning work completed. Boxup
WIP. 6) EH oil system oil draining and new oil topup WIP.
7) All CEP, TDBFP A, TDBFP B and MDBFP suction strainer
boxup work completed.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
14 August 2018

Bearing cover 4, 5 and 6 boxup work completed. Bearing


no 3 cover boxup work in progress.

Generator excitor side and LP 2 side top end shill boxup


work in progress.

GV 1 spindle, special nut & connecting rod and coupling


sent for machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site; CRH NRV
RHS flap assy spindle & stuffing box sent to workshop for
machining. Machining WIP

Generator stator water filter 1 cartraige ( 36 NOS ) filters


replaced. Generator H2 side seal oil PHE cleaning and
boxup work completed.
Generator stator water filter 1 cartraige ( 36 NOS ) filters
replaced. Generator H2 side seal oil PHE cleaning and
boxup work completed.

Generator rotor insertion activity completed. Genarator


seal ring and gland seal bracket boxup work completed.

Bearing 2,3,4,5 & 6 bearing box up done; Thrust bearing


boxup work completed. Bearing no 1 inspection and
boxup work completed.

Condenser inlet Pass B 10500 nos. tube cleaning work


completed. Now outlet pass A Tube cleaning WIP

HP vacuum pump A andB alignment completed. LP


vacuum pump A and B alignment WIP.
CEP discharge line NRV repositioning done; Discharge
header line modification WIP

TDBFP B flash tank pump B civil work in progress. TDBFP


B barring gear dismantling WIP. TDBFP A barring gear
motor dismantling work completed. TDBFP A Turbine to
gear box and gear box to booster pump alignment WIP.
MDBFP oil draining work completed. Now line flushing
and fresh oil top up work in progress.

U# 10 NDCT LHS basin cleaning work is in progress.


Dewatering of RHS basin 90% done. Nozzles and
distribution pipes repairing work is in progress.
Distribution pipes from cocrete channel repairing work is
in progress by civil.

u#10 NDCT BYPASS VALAVE LHS repositioning work is in


progress as per operation requirement. U#10 acw outlet
strainers interconnections 900 NB pipe work is in
progress. Cw pump 10 B PUMP inlet channel inspection
by divers is in progress. Acw outlet strainers cleaning
work is in progress.
clear water pump no 1 work completed

1) Dearator level control bypass MOV valve seat sent for


machining 2) HPBP valve blue matchining work
completed. Now boxup work in progress. 4) WDC valve A
and B valve body seat machining WIP 5) DMCW TG & SG
pumps decoupling done 6) MDBFP hydraulic coupling oil
draining work completed. Now cleaning WIP.7) DMCW TG
2 PHE cleaning WIP

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
13 August 2018

Bearing cover 5 and 6 boxup work in progress.

Hydrogen cooler cleaning work completed

GV 1 spindle, special nut & connecting rod and coupling


sent for machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site; CRH NRV
RHS flap assy spindle & stuffing box sent to workshop for
machining. Machining WIP
Generator rotor insertion activity completed. Genarator
seal ring and gland seal bracket boxup work completed.

Bearing 2,3,4,5 & 6 bearing box up done; Thrust bearing


boxup work completed. Bearing no 1 inspection and
boxup work completed.

Condenser water box Pass A 10500 nos. of tube cleaninig


work completed. Pass B 3500 nos. tube cleaning work
completed. Tube cleaning WIP

HP & LP vacuum pumps gearbox oil flushing and new oil


topup done; All PHE cleaning & box up done. HP vacuum
pump B alignment completed. HP vacuum pump A
alignment done.
CEP discharge line NRV repositioning done; Discharge
header line modification WIP

TDBFP B flash tank pump B civil work in progress; TDBFP


A main pump NDE Bearing box up done and allignment
work completed. TDBFP B barring gear dismantling WIP.
TDBFP A barring gear motor dismantling WIP

NDCT LHS basin cleaning work is in progress. RHS basin


dewatering work is in progress (level down by 10 feet).
Acw outlet both 1 and 2 strainers cleaning work is in
progress. Acw outlet strainer no 2 drain leakage
attending work is in progress.

NDCT nozzles repairing work is in progress. Cw pump 10


B seal leakage work held up due to crane problem vfd
trial work is in progress by EM/T.. CLEAR WATER PUMP
NO 1 WORK IS IN PROGRESS. ACW outlet strainers 900
NB line interconnection work is in progress.
No work taken up.

1) Dearator level control bypass MOV valve seat sent for


machining 2) HPBP valve lapping work completed. Final
inspection & blue matchining work in progress. 4) WDC
valve A and B valve body seat dismentling for machining
WIP 5) DMCW TG & SG pumps decoupling done 6)
MDBFP hydraulic coupling oil draining work completed.
Now cleaning WIP.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
12 August 2018

Bearing cover 5 and 6 boxup work in progress.

Hydrogen cooler cleaning work completed

GV 1 spindle, special nut & connecting rod and coupling


sent for machining by M/s LMTG and awaited at site.

CRH NRV LHS flap assy spindle awaited at site; CRH NRV
RHS flap assy spindle & stuffing box sent to workshop for
machining. Machining WIP
Generator rotor insertion activity completed

Bearing 2,3,4,5 & 6 bearing box up done; Thrust bearing


inspection work completed. Bearing no 1 dismentling
WIP

Condenser water box Pass A 10500 nos. of tube cleaninig


work completed. Tube cleaning WIP

HP & LP vacuum pumps gearbox oil flushing done; All


PHE cleaning done; HP vacuum pump A & B PHE box up
done; LP vacuum pump PHE boxup WIP. HP vacuum
pump B alignment completed. HP vacuum pump A
alignment WIP.
pump B alignment completed. HP vacuum pump A
alignment WIP.

CEP discharge line NRV repositioning done; Discharge


header line modification WIP

TDBFP B flash tank pump B civil work in progress; TDBFP


A main pump NDE Bearing box up done and allignment
work completed. TDBFP B barring gear dismantling WIP

NDCT LHS basin cleaning work is in progress. RHS


basin dewatering work is in progress. Acw outlet
strainers both 1 and 2 strainers removal work completd.
No work taken up.

1) Dearator level control bypass MOV valve seat sent for


machining 2) HPBP valve lapping work completed. Final
inspection work in progress. 4) WDC valve A and B valve
body seat dismentling WIP 5) DMCW TG & SG pumps
decoupling done 6) MDBFP hydraulic coupling oil draining
WIP

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
11 August 2018

Bearing no 2,3,4 & 5 top cover guard reparinng work


completed.

Hydrogen cooler cleaning work completed

GV 1 spindle, special nut & connecting rod and coupling


sent for machining. ICV 1,2 & 3 BOX UP DONE; Bearing
2,3,4,5 & 6 bearing box up done; Thrust bearing
dismantling WIP

CRH NRV LHS flap assy spindle awaited at site; CRH NRV
RHS flap assy spindle & stuffing box sent to workshop for
machining.
Generator rotor insertion activity completed

Bearing 7 & 8 bottom half box up done

Condenser water box pass A 6500 nos of tube cleaninig


done; WIP

HP & LP vacuum pumps gearbox oil drainning done; All


PHE cleaning done; HP vacuum pump A & B PHE box up
done; HP vacuum pump B alignment WIP
CEP discharge line NRV repositioning done; Discharge
header line modification WIP

TDBFP B flash tank pump B civil work in progress; TDBFP


A main pump NDE thrust collar fitting done; Bearing box
up work in progress; TDBFP B barring gear dismantling
WIP

NDCT pond basin LHS dewatering done. Divers reported


at site and gate sealing done. Now LHS basin cleaning
work in progress.

CW 10 B pump insertion work is in progress.


No work taken up.

1) Dearator level control bypass MOV valve seat sent for


machining 2) HPBP valve lapping work in progress. 4)
WDC valve A and B valve lapping WIP 5) DMCW TG & SG
pumps decoupling done 6) MDBFP hydraulic coupling oil
draining WIP

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on PROGRESS REVIEW STATUS, as on
10 August 2018 9 August 2018

Bearing no 2, 3, 4, 5 top cover guard repairing work Bearing no 2,3,4,5 top cover guard repairing work in
completed. progress.

Hydrogen cooler cleaning work in progress. Hydrogen cooler cleaning work in progress.
Generator Exciter End cleaning work completed.

GV 1 spindle, special nut, connecting rod and coupling GV 1 spindle, special nut, connecting rod and,
sent for machining by M/s. LMTG. Bearing no. 2, 3, 4, 5, coupling sent for machining by M/s. LMTG. Bearing
and 6 top and bottom half DPT and UT work completed. no 2,3,4,5,6 top half and bottom half DPT and UT
Bearing no. 2, 3, 4, 5, and 6 bottom half fitting and boxup work in progress. MSV 1 and 2 cleaning and
work completed. ICV 2 and 3 assy. work in progress. RSV inspection done. Boxup done. ICV 1,2,3,4 cleaning
1 and 2 bonnet cleaning and servicing work in progress. and servicing work in progress. RSV 1 and 2 bonnet
GV 3 and 4 fitting and boxup work in progress. cleaning and servicing WIP. GV 2 and 4 bonnet
cleaning and boxup WIP

CRH NRV LHS flap assembly spindle awaited at site. CRH CRH NRV LHS flap assembly sipindle awaited at site.
NRV RHS flap assembly spindle and stuffing box sent to CRH NRV RHS flap spindle and stuffing box sent to
workshop for machining work. Machining work in workshop for machining work.
progress.
Generator rotor insertion activity completed today. Now
bearing no 7 and 8 bottom half boxup work in progress.

Condenser waterbox manhole 10 nos. opened. Condenser waterbox manhole boiler side opening
Condenser tube cleaning work started and 300 nos. of work in progress. Also both outlet pass waterbox top
tubes cleaning work completed. Debris filter and OLTC manhole opening work in progress. Condenser
inspection work in progress. waterbox inlet pass scaffholding WIP. Debris filter
and OLTC inspection WIP.

HP vacuum pump A and B PHE cleaning work completed. HP vacuum pump A and B motor to gearbox and
Motor to gearbox and gearbox to pump coupling work in gearbox to pump decoupling done. Gearbox ol
progress. LP vacuum pump A and B PHE cleaning work in drained. HP vacuum pump A PHE cleaning done and
progress. HPVP B PHE cleaning WIP. LP vacuum pump A and B
decoupling done.
progress. HPVP B PHE cleaning WIP. LP vacuum pump A and B
decoupling done.

CEP discharge NRV welding work in progress and pipeline CEP discharge NRV welding work in progress and
repositioning work is in progress. Pipeline repositioning work is in progress.

TDBFP B flash tank pump B civil work is in progress. TDBFP B flash pump B civil work is in progress.
TDBFP A main pump NDE side mech. seal assy. fitting and TDBFP A mech seal assembly sent for machining by
boxup work completed. Bearing cover and Thrust collar M/s. Eagle Burman and awaited at site. TDBFP B HP
fitting and boxup work in progress. TDBFP B barring gear and LP pilot valve inspection, cleaning and boxup
opening and dismantling WIP work completed. Trip Block cleaning work
completed. Barring gear opening and dismantling
WIP.

NDCT pond basin LHS dewatering done. Divers reported NDCT pond basin LHS dewatering work in progress.
at site and gate sealing done. Now LHS basin cleaning Level down by 6 feets and gates sealing work is in
work in progress. progress by divers.

ACW top cover lifting work completed. Oil topup and ACW outlet bypass second strainer cleaning work
gland replacement work completed. CW 10 B pump and main strainer bolts loosening work completed
inspection work is in progress. now top cover lifting work is in progress. CW 10 B
pump inspection work in progress.
Boiler blowdown pump no. 3 work accomplished. Trial CMB pump no 1 overhaul work is completed.
taken found ok.

1) Dearator control CV 2 boxup done. 2) Dearator control 1)Dearator control CV 2 boxup work in progress. 2)
bypass MOV lapping WIP. 3) HPBP lapping work in HPBP dismantling done inspection work in progress.
progress. 4) WDC valve A and B spindle and valveseat 3) Ammonia and hydrazine dozing MOV removal WIP
sent to workshop for machining by M/s. EFCO 4) Dearator bypass MOV lapping work in progress. 5)
H2 drier inlet and outlet flange boxup WIP 6) WDC
valve A and B dismantling done.

Executve Engineer (TM-660) Executve Engineer (TM-660)


7/29/2018 7/30/2018

7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on PROGRESS REVIEW STATUS, as on
8 August 2018 7 August 2018

Bearing no 2,3,4,5 top cover guard repairing WIP Bearing top cover guard 2,3,4,5,6 & 7 having crack at
welding joint, reaparing work in progress

Hydrogen cooler cleaning work in progress. Exciter Generator rotor THREAD-OUT removed; Bottom half
End cleaning work in progress. end shied TE & EE removed; hydrogen cooler
removed, cleaning WIP

GV 1 spindle, special nut and connecting rod and New GV 1 valve spindle and new special nut handed
coupling sent for machining by M/s. LMTG. Bearing over to M/S LMTG for inspection; Bearing 2,4 & 6
no 2,3,4,5 DPT and UT taken. Found ok. Bottom bottom half removed; ICV 1,2,3 & 4 assy removed
bearing no 2,3,4,5 DPT and UT work in progress. ICV
1,2,3,4 cleaning WIP.

CRH NRV LHS flap assy spindle awaited at site. CRH CRH NRV LHS flap assy spindle awaited at site; CRH
NRV RHS flap spindle & stuffing box sent to NRV RHS flap spindle & stuffing box sent to
workshop for machining work. workshop for machining
Condenser tube cleaning agency reported at site. Condenser Manhole opened; Huge amount of
Debris filter and OLTC inspection WIP. debris; plaster flakes and concrete material found.
Tube cleaning Agency yet to report at site; Debris
filter & OLTC agency reported at site

HP vacuum pump A PHE cleaning WIP, boroscopy HP VACUUM PUMP A gearbox to motor and gearbox
done. to pump decoupling done; grid coupling inspection
WIP; Gearbox oil draining done; PHE cleaning WIP
CEP discharge NRV Welding WIP. Pipeline CEP discharge NRV cutting work, pipeline cutting
repositioning WIP. work and NRV repositioning work in progress

TDBFP B flash tank pump B levelling done. Civil work TDBFP B flash tank pump B civil work done; pump
in progress. TDBFP A mech seal assy sent for frame fitting,leveling and positioining WIP; TDBFP A
machining by M/s Eagle burman. TDBFP B HP pilot MAIN PUMP NDE mech seal spare assy box up done;
valve cleaning and inspection WIP Mech seal fittment WIP. Agency reported.

NDCT pond basin LHS dewatering WIP. Level down NDCT pond LHS Basin dewatering work in progress.
by 4 ft.

ACW outlet bypass second strainer cleaning WIP ACW outlet bypass strainer top cover bolts removal
and main strainer bolt loosing WIP. CW 10 B WIP. Its drain line work in progress. CW 10 B
inspection WIP. inspection work in progress.
CMB pump no 1 overhaul WIP.

1) DMCW SG PHE 1 cleaning done. 2) Dearator 1) DMCW TG 2 PHE dismantling WIP 2) Deaerator
control CV 2 inspection done. 3) HPBP dismentling bypass MOV internal inspection WIP 3) Deaerator
WIP 4) Ammoni aand Hydrazine dozing MOV vent line flange cutting and line welding done HPH
removal WIP 5) Dearator bypass MOV agency vent to deaerator new valve installed 4) Ammonia &
awaited for lapping work. 6) H2 drier inler and outlet Hydrazine dozing MOV removal WIP 5) Deaerator CV
flange dismantling done Dummy found inside flange. 1 box up done 6) Deaerator CV 2 dismantling WIP 7)
HP bypass dismantling WIP

Executve Engineer (TM-660) Executve Engineer (TM-660)


7/29/2018 7/30/2018

7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on PROGRESS REVIEW STATUS, as on
6 August 2018 5 August 2018

Front pedestal top cover removed. Bearing pedestal Front pedestal top cover removed. Bearing
cover 2,3,4,5 & 6 top half removed. pedestal cover 2,3,4,5 & 6 top half removal
WIP.

End shield bottom half EE side stuck due to fouling of LP2- GENERATOR decoupling done. Gland seal
concrete block. Informed to Civil to remove bracket TE & EE side top and bottom
obstruction. removed. Bearing 7 & 8 top and bottom half
bearing removed. Seal ring assy. Removed.
End shield top half TE & EE side removed

Bearing no 2,3,4,5 & 6 top half inspection WIP; GV Bearing no 2,3,4,5 & 6 top half & top pedestal
2,3, & 4 assy. inspection WIP. MSV LHS & RHS valve cover removed. GV 1, 2 ,3 & 4 actuator
assy insection WIP removed. MSV LHS & RHS valve dismantling
done. GV 1 valve spindle thread found
damage, special nut (fixing to Valve spindle)
thread found damage

CRH NRV LHS flap assy spindle awaited at site; CRH CRH NRV RHS flap freeness checking done but
NRV RHS flap assy spindle and bush clearance not fully closed. So shaft removal done.
inspection WIP. Internal parts cleaning done. Bush clearance
inspection WIP. CRH NRV LHS flap assy spindle
awaited at site.
Condenser manhole switch yard side 04 Nos. Permit issued. Condenser manhole opening
opened. Other manhole opening and CW I/L line and work started.
O/L line ARV opening work in progress.

Agency reported at site. Pump servicing work Permit applied but agancy not reported yet
started.
CEP discharge NRV cutting work, pipeline cutting CEP discharge NRV cutting work, pipeline
work and repositioning work in progress. cutting work and repositioning work in
progress.

TDBFP B flash tank pump B foundation work and TDBFP A & B gearbox foundation support
new pump installation work held up due to CIVIL work completed. TDBFP A Main pump to
work; TDBFP B BARRING gear motor removal WIP by turbine decoupling work WIP. TDBFP B flash
EM/ET; TDBFP B interstage MOV found stuck in open tank pump B foundation work and new pump
condition, valve made free and trial found ok; TDBFP installation work in progress.
A main pump NDE mech seal lock ring fitment work
not carried out due to thread issue. Informed to
agency.

NDCT pond LHS Basin dewatering work started with t NDCT Forbay return isolating Gates inserted.

ACW outlet bypass strainer top cover bolt loosing ACW outlet bypass strainer top cover bolt
work in progress. Two isolating gates sealing work loosing work in progress. Two isolating gates
held up due to crane problem. sealing work held up due to crane problem.
CMB Pump no 2 overhaul work is completed. CMB Pump no 2 overhaul work is in progress.

1) DMCW TG 2 PHE dismentaling work in progress. 2) 1) DMCW TG 2 PHE dismentaling work in


Dearator Bypass MOV intenal inspection work in progress. 2) Dearator Bypass MOV intenal
progrss 3) Dearator vent cutting and orifice welding inspection work in progrss 3) Dearator vent
WIP. 4) ammonia & Hydrazine dozing MOV removal cutting and orifice welding WIP. 4) ammonia &
WIP. 5) Dearator control station CV 1 inspection Hydrazine dozing MOV removal WIP. 5)
done, box up WIP Dearator control station CV 1 opened and
cleaning WIP. 6) GS header MIV bonnet gasket
replacement done. 7) CPU A resin trap
cleaned and boxup work completed.

Executve Engineer (TM-660) Executve Engineer (TM-660)


7/29/2018 7/30/2018

7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
4 August 2018
Barrig gear stopped.

Barring Gear assembly removed. Spacer removed. Barring gear wheel


removed.

Generator LP 2 CRO taken. LP 2-Generator coupling bolts removed.

CRH NRV LHS power cylinder internal spring and pistion assembly
removed. Shaft removed & runout taken. CRH NRV RHS flap assembly and
shaft freeness work in progress. CRH NRV LHS shaft inspection work in
progress.
Permit applied but not yet issued. Line draining work in progress.

Permit applied but agency not yet reported.


CEP discharge NRV cutting work, pipeline cutting work and repositioning
work in progress.

TDBFP A and B gearbox foundation support work in progress. TDBFP B


mainpump to turbine decoupling work in progress. Also barring gear
motor and side cover removal work in progress. TDBFP A main pump NDE
side mech. Seal assy. Fitting and boxup work in progress. TDBFP B flash
tank pump B foundation work and new pump installation work in
progress.

ACW outlet bypass strainer top cover bolt loosing work in progress. Two
isolating gates sealing work held up due to crane problem.
CMB Pump no 2 overhaul work is in progress.

1) DMCW TG 2 PHE dismentling work in progress. 2) Dearator control


station bypass MOV internal inspection work in progress. 3) Dearator vent
cutting and orifice welding work in progress. 4) Ammonia and Hydrazine
dozing MOV removal work in progress. 5) Dearator control station CV 1
v/v dismentling work in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
3 August 2018

CRH NRV LHS flap assembly removed. Pivot Shaft, bearing and bush
assembly removed. Shaft inspection work in progress. Power cylinder
internal spring and piston assembly removal work in progress.
Permit applied but not yet issued.

Permit applied but agency not yet reported.


Permit issued CEP discharge pipeline modification work started. NRV
cutting work, pipeline cutting work and repositioning work is in progress.

TDBFP A main pump NDE side mechanical seal assembly fitting and boxup
work in progress. TDBFP A and B gear box foundation straingthining work
in progress. TDBFP B coupling guard and main pump to turbine, turbine
to GB, GB to booster pump decoupling work in progress. TDBFP A MOT oil
removal work in progress. TDBFP B flash tank pump B foundation
modification and new pump installation work is in progress.

ACW outlet bypass strainer top cover bolt loosing work in progress. Two
isolating gates sealing work held up due to crane problem.
CMB pump no 2 overhaul work is in progress.

1) Dearator one manhole boxup work completed. 2) DMCW TG 2 PHE


dismentling work is in progress. 3) Dearator control station bypass MOV
dismentling work completed & internal inspection work is in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
2 August 2018

CRH NRV LHS bonnet removed and side arm power cylinder
dismentling work completed. Now both CRH NRV internal
inspection work in progress. CRH NRV LHS flap assembly removal
work in progress.
Permit applied but not yet issued.

Permit applied but agency not yet reported.


TDBFP A main pump NDE side mechanical seal assembly removed.
Inspection carried out. New mechanical seal assembly fitting and
boxup work in progress. TDBFP b flash tank pump B foundation
modification and new pump installation work in progress.

CW 10 B radial bearing inspection work and greasing work


completed. Two isolating gates sealing work interupted due to
crane problem.
Clarifier B oil replacement work completed.

1) Dearator manhole opened and inspection work completed. 2)


DMCW TG 2 PHE dismentling work in progress. 2) CV 1 & CV 2
scaffholding work in progress. 4) GCS vapour fan NRV scaffholding
work in progress.

Executve Engineer (TM-660)


7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on PROGRESS REVIEW STATUS, as on
1 August 2018 31 July 2018

Both CRH NRV top cover removed. Segment removed and Scaffolding work completed. Top
press ring removed. CRH NRV RHS (Boiler Side) bonnet Cover Bolt loosening in progress.
removed and CRH NRV LHS bonnet removal work in progress.
Permit applied but not yet issued. Permit applied but not yet issued.

Permit issued but Agency not yet reported. Permit issued but Agency not yet
reported.
Permit applied but not yet issued. Permit applied but not yet issued.

TDBFP A & B suction strainer removed. MDBFP suction Permit issued. TDBFP - A suction
strainer removed. TDBFP A main pump NDE thrust bearing strainer removed and TDBFP - B
and journal brg. Assy. Removed. Thrust collar removed. And suction strainer removal WIP.
mech. Seal assy. Removal WIP. TDBFP A main pump to
turbine, turbine to GB and GB to booster pump decoupling
done. TDBFP B flash tank pump B removed; Informed to CIVIL
and civil work in progress.

Permit appied but not yet issued.

CW 10 B thrust bearing oil replacement & cooling coil Permit issued. Three isolating gates
inspection work completed. Two isolating gates sealing work inspection WIP
interupted due to crane problem. Radial bearing greasing
work in progress.
Clarifier B oil replacement work is in progress.

1) CEP A, B, C suction strainer removed. 2) DMCW TG 2 PHE


measurement taken and dismentaling work in progress 3)
Dearator manhole scaffholding WIP 4) Dearator control
station CV 1 and CV 2 scaffholding work in progress.

Executve Engineer (TM-660) Executve Engineer (TM-660)


7/29/2018 7/30/2018

7/29/2018 7/30/2018
PROGRESS REVIEW STATUS, as on
30 July 2018

Scaffholding work in progress. Permit issued.


Permit applied but not yet issued.

Permit issued but Agency not yet reported.


Permit applied but not yet issued.

Permit issued. TDBFP - A suction strainer removed and TDBFP - B


suction strainer removal WIP.

Permit appied but not yet issued.

Permit issued. Three isolating gates inspection WIP


Executve Engineer (TM-660)
7/29/2018 7/30/2018

7/31/2018 7/31/2018

7/31/2018 8/1/2018
8/1/2018 8/2/2018

8/2/2018 8/3/2018

8/3/2018 8/4/2018

8/4/2018 8/5/2018

8/5/2018 8/6/2018

8/6/2018 8/7/2018

8/7/2018 8/8/2018

8/8/2018 8/9/2018

8/9/2018 8/10/2018

8/10/2018 8/11/2018
8/11/2018 8/12/2018

8/12/2018 8/13/2018

8/13/2018 8/14/2018

8/14/2018 8/15/2018

8/15/2018 8/16/2018

8/16/2018 8/17/2018

8/17/2018 8/18/2018

8/18/2018 8/19/2018

8/19/2018 8/20/2018

8/20/2018 8/21/2018
8/21/2018 8/22/2018

8/22/2018 8/23/2018

8/23/2018 8/24/2018

8/24/2018
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
PROGRESS REVIEW STATUS, as on
SN OVERHAUL ACTIVITY
30 August 2018
BARRING GEAR STOP
From To
TM-01 Scheduled 31-Jul 31-Jul
Status Select
Actual 3-Aug Select
BEARING COVER
OPENING
From To
TM-02 Scheduled 1-Aug 2-Aug
Status COMPLETED
Actual 4-Aug 16-Aug

DECOUPLING OF ROTORS, ALLIGNMENT


CHECKING, GENERATOR DISMANTLING &
GENERATOR ROTOR THREAD-OUT
TM-03 From To
Scheduled 1-Aug 8-Aug
Status COMPLETED
Actual 4-Aug 20-Aug
TURBINE BEARING AND CONTROL VALVE
INSPECTION
From To
Scheduled 2-Aug 14-Aug
Status WIP

TM-04

Actual 4-Aug Select

CRH NRV BONNET SEAL REPLACEMENT AND


PIVOT POWER CYLINDER SHAFT REPLACEMENT
WORK
TM-05 From To
Scheduled 30-Jul 10-Aug
Status WIP
Actual 30-Jul Select
REVISIONING OF GENERATOR ROTOR AND STATOR
From To
TM-06 Scheduled 8-Aug 15-Aug
Status WITHHOLD
Actual NOT STARTED Select
GENERATOR ROTOR THREAD-IN AND BOXUP
From To
TM-07 Scheduled 14-Aug 18-Aug
Status COMPLETED
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
TM-07 PROGRESS REVIEW STATUS, as on
SN OVERHAUL ACTIVITY
30 August 2018
Actual 10-Aug 15-Aug
LP TURBINE - GENERATOR ROTOR ALIGNMENT
From To
TM-08 Scheduled 18-Aug 19-Aug
Status COMPLETED
Actual 18-Aug 20-Aug

BEARING BOXUP, OIL FLUSHING AND AIR LEAK TE

From To
TM-09
Scheduled 16-Aug 21-Aug
Status WIP
Actual NOT STARTED Select
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
PROGRESS REVIEW STATUS, as on
SN OVERHAUL ACTIVITY
30 August 2018
HPH, LPH DRAIN LINE MODIFICATION AND
REROUTING WORK

TM-10 From To
Scheduled 5-Aug 16-Aug
Status NOT YET STARTED
Actual NOT STARTED Select
CONDENSER TUBE CLEANING BY BULLET SHOT
METHOD
From To
TM-11
Scheduled 31-Jul 9-Aug
Status COMPLETED
Actual 4-Aug Select
VACUUM PUMP SERVICING
From To
Scheduled 30-Jul 5-Aug
TM-12 Status COMPLETED

Actual NOT STARTED 16-Aug

CEP DISCHARGE PIPELINE MODIFICATION AND


ITS NRV REPOSITIONING WORK
From To
TM-13
Scheduled 3-Aug 15-Aug
Status COMPLETED
Actual 3-Aug 15-Aug

TDBFP TURBINE OVERHUAL AND ITS


ASSOCIATED AUXILLIARIES WITH ALLIED WORKS

From To
TM-14 Scheduled 31-Jul 17-Aug
Status WIP

Actual 30-Jul Select

NDCT POND BASIN CLEANING


From To
TM-15 Scheduled 31-Jul 18-Aug
Status NOT YET STARTED
Actual NOT STARTED Select
CW & ACW SYSTEM (INTERNAL INSPECTION,
SERVICING AND OTHER ALLIED WORKS)
From To
TM-16
Scheduled 31-Jul 15-Aug
Status WIP
Actual 30-Jul Select
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
PROGRESS REVIEW STATUS, as on
SN OVERHAUL ACTIVITY
30 August 2018

RESTORATION OF TG BARRING GEAR

From To
TM-17
Scheduled 20-Aug 22-Aug
Status NOT YET STARTED
Actual NOT STARTED Select
SYNCHRONIZING
From To
TM-18 Scheduled 24-Aug 24-Aug
Status NOT YET STARTED
Actual NOT STARTED Select
Miscellanious Actvites - 1
From To
TM-19 Scheduled 28-Jul 24-Aug
Status WIP
Actual 30-Jul Select
3x660MW KORADI THERMAL POWER STATION
Unit # 10 AOH Progress Review Status
Secton : TURBINE MAINTENANCE
PROGRESS REVIEW STATUS, as on
SN OVERHAUL ACTIVITY
30 August 2018
Miscellaneous Actvites - 2
From To
Scheduled 28-Jul 24-Aug
Status WIP
TM-20

Actual 30-Jul Select

Executve Engineer (TM-660)