No Job step Hazard Risk Level Solution Residual Risk Acceptance Risk monitoring
- To double check the survey data for position of bore
Hazard of shifting or pile
misplaced during positioning - To close monitor and measure the river water level
1
of the berg due to water and anchor chain tension
level. - Use experienced labout only
Hazard during preparation, transportation and erection of steel truss member and solution
No Hazard identified Solution
-Conduct preventive maintenance for all lifting gears
and machineries
- Used only certified operators for lifting
Hazard related to lifting of
1 - Held the lifting tool box meeting before lifting
heavy members
operation
- Engineer must calculated the detail of lifting
operation such as lifting angle, position
- Install the working platform with handrail
- Install safety net to below the working area at
Hazard of falling from height height
2
due to slippery surface - Use sufficient PPE such as safety belt
- Checked the condition of scaffold after installation
- Ensure good house keeping practices
- Conduct sufficient preparation ground training
Hazard of mishandling of
before the erection of steel truss
3 erection works due to poor
- Install proper communication system, signalling
visibility, windy weather
system and lighting system for erection of steel truss
- Conduct sufficient training for all the erection
Hazard of mishandling
workers and techinician
erection works due to
4 - Allow new worker only under the supervision of
inexperience or unskilful
experienced workers
labour
- Use the fool proof procedure as long as possible
- Use temporary support method to reduce the
Hazard of bridge member
chance of collapse during erection
5 collapse due to storm or
- Prepare sub-assembly on the ground yard
earthquake during erection
- Wear body harness during erection at height
- Conduct regular maintenace to crane and boom
Hazard of crane boom - Use skilful crane operator
6
collapse during lifting - Deploy sufficient signal men to monitor both crane
and stand pipe condition during lifting
- Use protective equipement such as glove ,safety
Hazard of electrical cushion shoes, google for welding process
7
during bolt and nut tightening - Use safety breaker for electrical connection
- Use only certified electrician for operation
- Install the working platform with handrail
Hazard of tools, equipment - Install safety net to below the working area at
8 and members falling into the height
river - Use sufficient PPE such as safety belt
- Checked the condition of scaffold after installation