METHOD OF BACK FILL SOIL

TOOL
- Measuring instruments (survey); Theodolite and Auto Level
- Excavator
- Dump truck
- Baby Roller
- Water pump
- And others

WORK STEPS
- Preparation
a. Review the conditions and conditions of the field.
b. Predicting the volume of the back fill, taking into account the area, the back fill
volume can not be predicted equals 100% of the volume in the image, due to the
shrinkage factor after the soil is compacted. Need volume = ± 130% image
volume (shrink factor = ± 30%).
c. Ascertained from the start the volume is the volume of the image and not the volume
of the treble dump truck, in order to avoid misunderstanding.
d. If the location is large and the volume is very large, there is the possibility of using 2
pieces of excavator, with a relay system for dump truck waiting time is not too
long.
e. Need to be analyzed, if back fill land imported from outside the location, how long it
takes 1 dump truck to bring the soil from the location of the retrieval to the
location to be back fill, so after the data obtained, it can be calculated between the
schedule with the number of dozers, dump trucks, and excavator required.
f. Back Fill types:
~ Back fill field wide without obstacles. The motion of the heavy equipment
is freer and seems easier so that the number of dump trucks and heavy equipment
fleet is very important to the implementation schedule.
~ Back fill edges of structures or between structures. Relatively more difficult
and longer duration of work, sometimes the compaction edge area can not use the
machine, simply with a stamper, baby roller, etc.
Back Fill

a. Cleans locations to be exposed to wood, bushes or other trash.


b. Providing good quality of urban soil.
c. Creating boundaries, stakes, pulling the yarn from one peg to another, in order to
obtain the average ground level in accordance with the expected l

Plan Back fill.


d. The location to be back fill prepared in advance so there is a good relationship
between the ground and soil back fill later.
e. The soil moisture is carried out layer by layer (every 75 cm) and each layer is
followed by solidification.
f. For compaction using tools according to their needs (Stamper, Baby roller or heavy
compaction equipment).