Beruflich Dokumente
Kultur Dokumente
Abstract— In this paper, a phase balancing algorithm is In this paper, backward sweep nodal phase balancing
developed for secondary distribution network by rephasing the algorithm for secondary distribution system is developed by
consumer service laterals. The algorithm is proposed for rephasing both three phase and single phase service laterals. It
rephasing of three and single phase consumer service laterals does balancing by rephasing both feeder lateral and service
(service wire connecting home and supply line) at each node from laterals at each node from tail end to feeder origination. Here
tail end of the feeder. Formulation of algorithm includes average the rephased node’s load is considered as lumped/ immovable
load per phase and average load per service with an objective to load at next monitoring node. Proposed algorithm is developed
minimize loss and number of phase moves/ rephasings of service to improve system reliability, peak load supplying capability,
laterals. To demonstrate the performance of proposed
voltage profile and reduces the power loss incurred.
algorithms, IEEE 13 node test feeder is selected. Their
corresponding results’ validating the proposed algorithm is
presented. II. PROPOSED PHASE BALANCING ALGORITHM
An Algorithm is developed to obtain rephasing
Keywords—each node; loss reduction; phase balancing;
arrangement of single phase and three phase consumer service
rephasing; secondary distribution network
laterals at each node with incentive of power loss reduction,
neutral current diminution, and enhanced voltage profile. It
I. INTRODUCTION uses simple mathematical terms such as average load per
The increase in load demand and sensitivity of loads phase, average number of services per phase and all possible
demands distribution utilities to serve reliable power with combinations of required number of services. These simple
improved power quality, minimum loss and lower cost. mathematical parameters are sufficient to obtain the rephasing
Distribution networks are unbalanced due to unbalanced arrangement, as numbers of consumer service laterals at a node
loading at node and presence of single, two phase feeder are very few. Phase sequence is the significant characteristic to
laterals. be taken into account while rephasing service laterals. A three
phase lateral with ABC sequence can be rephased to either
Unbalance in system deteriorates power quality, peak load BCA or CAB sequence. Single phase lateral can be rephased to
supplying capability and elevates power loss, which results in any of other two phases.
high electricity cost. The unbalanced feeder can be balanced by
implementing phase balancing at each node. Phase balancing is Balancing technique is applied at each node from tail end to
a technique to rephrase service laterals such that the load on all the feeder originating point. At any monitored node, first three
three phases is balanced. Rephasing is carried out at zero phase service wires undergo balancing, and then single phase
crossing voltage using load selector switch [1]. wires undergo balancing by considering three phase laterals
load as lumped load. Similarly, load of preceding node which
According to the literature, there are different types of is balanced prior to the monitoring node is taken as lumped
phase balancing algorithms with different techniques as shown load. The order of execution is single phase feeder lateral, two
in Table I. Most of the algorithms concentrated on feeder phase feeder lateral and three phase feeder lateral (first three
lateral rephasing where as algorithms based on mixed integer phase service wires then single phase service wires) as shown
programming and simulated annealing carried out phase in flow diagram of Fig. 1. Single phase feeder laterals are
balancing by rephasing only single phase laterals at monitored consider as a lumped load on preceding node and rephased
nodes i.e. nodal balancing. Unbalancing emphasizing power accordingly. In case of two phase feeder laterals, first balance
loss, voltage drop, neutral current and no of phase moves is not existing load among two phases and then it is considered as a
addressed so far for nodal phase balancing. lumped load on preceding node.
Serv No Type Seq Pa (kW) Pb (kW) Pc (kW) Qa (kVAr) Qb (kVAr) Qc (kVAr) Bus No
1 3 0 1.29 5.08 8.93 0.76 2.91 5.23 2
2 3 0 3.88 15.14 26.79 2.27 8.67 15.70 2
3 3 0 2.37 9.29 16.35 1.39 5.32 9.58 2
4 1 0 0.91 0.00 0.00 0.53 0.00 0.00 2
5 1 1 0.00 3.56 0.00 0.00 2.04 0.00 2
6 1 2 0.00 0.00 6.30 0.00 0.00 3.69 2
Bus 2 Total load 8.46 33.06 58.37 4.95 18.93 34.20
7 3 0 24.64 18.49 18.49 16.85 13.77 13.77 4
8 3 0 16.96 12.75 12.75 11.60 9.50 9.50 4
9 3 0 2.31 1.72 1.72 1.58 1.28 1.28 4
10 1 0 41.84 0.00 0.00 28.63 0.00 0.00 4
11 3 0 26.70 20.05 20.05 18.27 14.93 14.93 4
12 1 0 47.79 0.00 0.00 32.69 0.00 0.00 4
13 1 1 0.00 35.89 0.00 0.00 26.72 0.00 4
14 1 1 0.00 31.44 0.00 0.00 23.41 0.00 4
15 1 2 0.00 0.00 35.89 0.00 0.00 26.72 4
16 1 2 0.00 0.00 31.44 0.00 0.00 23.41 4
Bus 4 Total load 160.24 120.35 120.35 109.63 89.61 89.61
17 1 1 0.00 24.36 0.00 0.00 17.76 0.00 5
18 1 1 0.00 32.89 0.00 0.00 23.98 0.00 5
19 1 1 0.00 3.19 0.00 0.00 2.33 0.00 5
20 1 1 0.00 17.05 0.00 0.00 12.43 0.00 5
21 1 1 0.00 41.65 0.00 0.00 30.37 0.00 5
22 1 1 0.00 37.57 0.00 0.00 27.40 0.00 5
23 1 1 0.00 6.75 0.00 0.00 4.92 0.00 5
Serv No Type Seq Pa (kW) Pb (kW) Pc (kW) Qa (kVAr) Qb (kVAr) Qc (kVAr) Bus No
24 1 1 0.00 7.03 0.00 0.00 5.13 0.00 5
Bus 5 Total load 0.00 170.49 0.00 0.00 124.31 0.00
25 1 1 0.00 6.20 0.00 0.00 3.55 0.00 6
26 1 1 0.00 0.52 0.00 0.00 0.30 0.00 6
27 1 1 0.00 28.33 0.00 0.00 16.22 0.00 6
28 1 1 0.00 43.91 0.00 0.00 25.14 0.00 6
29 1 1 0.00 48.42 0.00 0.00 27.73 0.00 6
30 1 1 0.00 35.58 0.00 0.00 20.37 0.00 6
31 1 1 0.00 7.29 0.00 0.00 4.17 0.00 6
32 1 1 0.00 42.35 0.00 0.00 24.25 0.00 6
33 1 1 0.00 8.46 0.00 0.00 4.84 0.00 6
34 1 1 0.00 8.98 0.00 0.00 5.14 0.00 6
Bus 6 Total load 0.00 230.06 0.00 0.00 131.72 0.00
35 3 0 11.76 12.45 13.23 6.73 7.13 7.58 7
36 3 0 20.05 21.26 22.61 11.48 12.17 12.94 7
37 3 0 23.39 24.82 26.34 13.39 14.21 15.08 7
38 3 0 37.79 40.14 42.61 21.64 22.98 24.40 7
39 3 0 25.90 27.51 29.20 14.83 15.75 16.72 7
40 1 1 0.00 112.95 0.00 0.00 64.67 0.00 7
41 1 0 83.74 0.00 0.00 47.95 0.00 0.00 7
42 1 2 0.00 0.00 119.89 0.00 0.00 68.64 7
43 1 1 0.00 88.95 0.00 0.00 50.93 0.00 7
44 1 2 0.00 0.00 94.42 0.00 0.00 54.06 7
45 1 0 106.31 0.00 0.00 60.87 0.00 0.00 7
46 1 0 16.92 0.00 0.00 9.69 0.00 0.00 7
47 1 0 37.66 0.00 0.00 21.56 0.00 0.00 7
48 1 0 29.90 0.00 0.00 17.12 0.00 0.00 7
49 1 1 0.00 17.96 0.00 0.00 10.29 0.00 7
50 1 1 0.00 40.01 0.00 0.00 22.91 0.00 7
51 1 1 0.00 31.76 0.00 0.00 18.19 0.00 7
52 1 2 0.00 0.00 19.05 0.00 0.00 10.91 7
53 1 2 0.00 0.00 42.48 0.00 0.00 24.32 7
54 1 2 0.00 0.00 33.71 0.00 0.00 19.30 7
Bus 7 Total load 393.43 417.81 443.54 225.26 239.22 253.96
55 1 2 0.00 0.00 48.44 0.00 0.00 43.35 8
56 1 2 0.00 0.00 16.10 0.00 0.00 14.40 8
57 1 2 0.00 0.00 18.48 0.00 0.00 16.54 8
58 1 2 0.00 0.00 6.74 0.00 0.00 6.04 8
59 1 2 0.00 0.00 79.66 0.00 0.00 71.29 8
Bus 8 Total load 0.00 0.00 169.42 0.00 0.00 151.61
60 3 0 126.84 17.82 75.79 49.20 15.63 55.26 9
61 3 0 21.86 3.08 13.09 8.48 2.70 9.54 9
62 3 0 33.10 4.66 19.80 12.84 4.09 14.43 9
63 1 0 40.23 0.00 0.00 15.60 0.00 0.00 9
64 1 1 0.00 5.64 0.00 0.00 4.95 0.00 9
65 1 0 90.72 0.00 0.00 35.19 0.00 0.00 9
66 1 2 0.00 0.00 54.22 0.00 0.00 39.53 9
67 1 0 71.60 0.00 0.00 27.77 0.00 0.00 9
68 1 1 0.00 12.74 0.00 0.00 11.18 0.00 9
69 1 1 0.00 10.04 0.00 0.00 8.80 0.00 9
70 1 2 0.00 0.00 42.79 0.00 0.00 31.20 9
71 1 0 21.35 0.00 0.00 8.28 0.00 0.00 9
72 1 2 0.00 0.00 24.04 0.00 0.00 17.53 9
73 1 1 0.00 3.01 0.00 0.00 2.64 0.00 9
74 1 2 0.00 0.00 12.77 0.00 0.00 9.31 9
75 1 0 79.90 0.00 0.00 30.99 0.00 0.00 9
76 1 1 0.00 11.20 0.00 0.00 9.82 0.00 9
77 1 2 0.00 0.00 47.75 0.00 0.00 34.82 9
Bus 9 Total load 485.60 68.19 290.24 188.35 59.81 211.62
78 1 0 128.13 0.00 0.00 85.79 0.00 0.00 11
79 1 2 0.00 0.00 170.00 0.00 0.00 80.03 12
Total load 1175.9 1040.0 1251.9 614.0 663.6 821.0
*Pa, Pb,and Pc are active power in phase A,B and C respectively. Qa, Qb,and Qc are reactive power in phase A,B and C respectively.
TABLE III. INDEXING FOR PHASE SERVICE LATERALS
(a)
Phase Type Sequence Phase Pattern
3 0 ABC
3 1 BCA
3 2 CAB
1 0 A
1 1 B
1 2 C