Sie sind auf Seite 1von 24

Lesson-learning in

Nuclear Construction
Projects
Title: Lesson-learning in Nuclear
Construction Projects
Produced by: World Nuclear Association
Published: April 2018
Report No. 2018/002

Cover image: Georgia Power Company

© 2018 World Nuclear Association.


Registered in England and Wales,
company number 01215741

This report reflects the views


of industry experts but does not
necessarily represent those of any
of the World Nuclear Association’s
individual member organizations.
Contents

Executive summary 2

Members of the new build lesson-learning task force 3

1. Introduction 5

2. Good project management in nuclear construction 6

3. Capturing lessons 13

4. Benchmarks for successful project delivery 14

5. Recommendations 17

Glossary18

1
Executive summary

There are many examples from around the world of nuclear construction
projects that have progressed well, especially in countries with a wealth of
recent experience, knowledgeable vendors, and a pool of skilled workers.
However, there have been several recent cases where lengthy hiatuses in new
build have undermined the capability of the nuclear supply chain. Significant
delays and project cost escalation have occurred in some well-publicized
instances, threatening those projects’ ultimate completion and eroding the
appetite for building further nuclear power plants. The purpose of this report
is to help the nuclear community take advantage of the lessons learned and
contribute to the preception of nuclear power among policy-makers, regulators
and civil society.

In reviewing lessons from recent projects, the World Nuclear Association’s New
Build Lesson-learning Task Force has concluded that vendor capability and
experience, important as these are in achieving high performance, must be
supplemented by excellence in project management, driven from the start by
the asset owner and the project’s sponsor.

One of the main lessons from the Asian experience is that nuclear power plants
have been built on time and budget because the project is managed well and
much of this is attributable to collaborative working relations. A collaborative or
partnership approach will enable a wider set of procurement strategies to be
employed and facilitate team working and knowledge sharing.

Incentives are an important contributor to ensuring the interests of key


stakeholders are aligned and the project risks are allocated fairly and
effectively. The right package of incentives can motivate the key stakeholders
to resolve problems as they arise while discouraging obstructive behaviours
that are designed primarily to limit the parties’ individual liability. Standard
contractual arrangements may not be sufficient to ensure this and appropriate
procurement arrangements and project delivery models are needed to support
such a mode of collaborative working.

Comprehensive planning within a collaborative approach will reduce the


inherent uncertainties associated with complex nuclear projects. It requires
the project manager to gather all relevant parties together to share their
knowledge. Vendors should be brought into the planning process at an early
stage. If, because institutional knowledge has been forgotten or is not available
(because, for example, it is a first-of-a-kind project), then the asset owner must
allow more time for the design and construction process. Lesson-learning and
a commitment to continual improvement, to prevent mistakes recurring, will be
bolstered by a strong culture of safety at the project.

Wider stakeholder engagement with local communities and taking an


accommodative approach towards local community concerns will remove the
potential of the project to generate opposition.

2
Participants in the new build
lesson-learning task force
David SLEDZIK (Chair) Vice President Product Management & International NPP Projects,
GE Hitachi Nuclear Energy
Charles POTTER (Vice-Chair) Director, Reactor Operations Support, UK National Nuclear Laboratory
Antônio MÜLLER Director, Associação Brasileira para Desenvolvimento de Atividades Nucleares
João Carlos DERZI TUPINAMBÁ Associação Brasileira para Desenvolvimento de Atividades Nucleares
Fernando HENNING Executive Vice President, Associação Brasileira para Desenvolvimento de
Atividades Nucleares
Aninda DUTTA RAY Senior Nuclear/Mechanical Engineer, AMEC Foster Wheeler
Shengke ZHI AMEC Foster Wheeler
Nicole DELLERO Senior Strategic Marketing Manager, AREVA
Jean-Noel LACROIX Vice President International Affairs, AREVA
Armand LAFERRERE Senior Vice President, Commercial Development, AREVA
Tomás VYTISKA ČEZ Group
Sylvain HERCBERG Director of Technology Prospective, EDF
Xavier POUGET-ABADIE Executive, Nuclear Engineering Division, EDF
Melanie SACHAR HPC Project Delivery Model Lead, EDF
Maksym NEZHURA Section Head, International Cooperation Department, Energoatom
Ioana NEAMU Licensing Safety & Operations Manager, Engie
Barry CULLIGAN Senior Manager, Nuclear Commercial, Koeberg, Eskom
Sadika TOUFFIE Senior Manager, Koeberg, Eskom
David POWELL Vice President – European region, Nuclear Plant Sales, GE Hitachi Nuclear Energy
Shailesh SETH Vice President – Digital, Nuclear Power Projects, GE Hitachi Nuclear Energy
Yasunori SOTA Project Manager, Hitachi Europe
Ivor SHEPPARD Commercial Director, Horizon Nuclear Power
Rafael JIMENÉZ LOPEZ Director, Nuclear Fleet Sustainability Program, Iberdrola Nuclear
Simon EMENY Global Head of the Nuclear Services and Inspection Division, Lloyd’s Register
King LEE Nuclear Product Development Manager, Lloyd’s Register
Hideharu ZAISHO Engineering Manager, Nuclear Plant QA, Mitsubishi Heavy Industries
M Vann MITCHELL Consultant, Mitsubishi Heavy Industries
Milton CAPLAN President, MZ Consulting
Edward KEE Nuclear Economics Consulting Group
Stephen WOODS Overseas NEIL
Fred GATTE Underwriter, Nuclear Risk Insurers
Elina TEPLINSKY Partner, Pillsbury Winthrop Shaw Pittman
Richard DARTNELL Legal Director, Pinsent Masons

3
Will HARRISON-CRIPPS Assistant Director, PricewaterhouseCoopers

Alexey ALTYNOV Chief Commercial Officer, Rusatom Overseas

Alexander BOLGAROV Head of Licensing & Technical Regulation, Rusatom Overseas

Anton MOSKVIN Vice President Marketing & Business Development, Rusatom Overseas

Tatiana RAKITSKAYA Rusatom Overseas

Alexander RENEV Chief Technology Officer VVER, Rusatom Overseas

Ilya SESYUTCHENKOV Head of Marketing, Rosatom International Network

Oleg SIRAZETDINOV Director, Equipment Procurement & Supply, Rusatom Overseas

Kuan-Shen CHIANG Department of Fuels, Taiwan Power Company

Takashi AISAKA Project Manager, Toshiba International (Europa) Ltd.

Hideki NISHIYAMA Group Manager, Third QA Group, Toshiba Corporation

Yusuke SUZUKI Quality Assurance Planning, Toshiba Corporation

James HARRIS Managing Director, Turner Harris

Mika LIANG-PRICE Development Manager Asia-Pacific, Turner Harris

Celia A SPENCE Sustainability Director, Westinghouse Electric Company

David VARNER Vice President & Chief Procurement Officer, Westinghouse Electric Company

Secretariat
Greg KASER Staff Director – Supply Chain, World Nuclear Association

Kangjun LEE Visiting Research Officer (seconded from KEPCO), World Nuclear Association

Shah Nawaz AHMAD Senior Adviser, India, World Nuclear Association

Henri PELIN Senior Adviser (seconded from EDF), World Nuclear Association

Other organizations
Richard COACKLEY CBE Director of Energy Development, AECOM

Don WARD Chief Executive, Constructing Excellence

Tina TAYLOR Electric Power Research Institute

Berta PICAMAL VICENTE Executive Advisor, FORATOM European Atomic Forum

Marco COMETTO Analyst, Nuclear Development, OECD Nuclear Energy Agency

Geoffrey ROTHWELL Principal Economist, Nuclear Development, OECD Nuclear Energy Agency

Nima ASHKEBOUSSI Senior Project Manager, Nuclear Energy Institute

Suzanne PHELPS Director of Fuel Cycle Programs, Nuclear Energy Institute

Chris SAVAGE Vanbrugh Consulting and UK Nuclear Industry Association

4
1 Introduction

The rate of at which nuclear power projects meant that the supply A Task Force on New Build Lesson-
plants are built must be increased chain lost the knowledge and learning was set up in 2015 by
in order to meet the goal of a low- experience it had acquired and the World Nuclear Association to
carbon economy – according to the needed to re-gain proficiency in collate and review the issues that
World Nuclear Association’s Harmony the rigorous quality management contributed to construction delays
vision. The necessary investment that the nuclear industry demands. and cost overruns and to draw out the
in nuclear energy will not be Suppliers also had to reinforce their lessons for good project management
forthcoming unless the expectations safety culture in order to meet new practice. The World Nuclear
of project sponsors are met. This regulatory and utility requirements Association sought examples of case
means completing the construction and expectations. Reactor vendors studies from amongst its members
and commissioning of the plant on were forced to raise the level of and reviewed published material. The
schedule and within budget. supplier oversight and review their task force analyzed and discussed
procurement arrangements as these findings over the course of
Recent experience has shown a supply issues arose, which added several meetings. Good practice from
general shortening in the length of significantly to the costs of some other industries was also reviewed.
time for completing a nuclear power recent projects.
plant project, as is evident from This report presents an analysis
Figure 1. There have nonetheless The scale and scope of nuclear of these findings to obtain a better
been a number of well-publicized power plants have grown as a understanding why some projects
cases where projects have not result of escalating regulatory and can go awry and why others go well.
been completed to schedule or utility requirements, which, along It complements work undertaken
budget and impaired the reputation with political pressures, impact the by the UK-based Royal Academy
and viability of the companies project’s complexity. In a review of of Engineering and by Constructing
concerned. As capital-intensive recent construction experience, the Excellence on improving productivity
projects, the economics of nuclear Nuclear Energy Agency summarized in design, engineering, procurement
energy may be compromised the problem as “managing complexity and construction of nuclear projects.
severely by schedule delays. in a changing environment.”1 These Taking advantage of lessons learned
cases are not unique to the sector will contribute to lowering the costs of
In North America and Europe and ‘mega-projects’ have a history of construction and improving nuclear
especially, the long intervals being hard to manage and expensive technology’s reputation among policy-
between nuclear power plant to complete. makers, regulators and civil society.

Figure 1. Average nuclear reactor construction times (months)

140
120
120

100 92
84 81
80 76
Months

66
60 58

40

20

0
5

5
98

99

99

00

00

01

01
-1

-1

-1

-2

-2

-2

-2
81

86

91

96

01

06

11
19

19

19

19

20

20

20

1
Year NEA, 2015, Nuclear New Build: Insights into
Financing and Project Management, Paris:
Source: World Nuclear Association, IAEA PRIS OECD-NEA: p. 11.

5
2 Good project
management in nuclear
construction
Terms highlighted in orange Ideally a project is completed project. Since the scope of the project
are defined in the Glossary quickly and at the lowest cost whilst has to be defined in relation to the
ensuring the highest product quality. aims of the key stakeholders, these
In practice it is commonly accepted have to be identified and negotiated
that this is not easy to accomplish at an early stage. This should limit
and there is a risk that one or more design complexity and reduce the risk
of these three goals may have to be that any design inconsistencies lead
sacrificed (see Figure 2). to non-conformity further along the
supply chain. Figure 3 illustrates how
Nuclear power plants are capital- these factors – quality, scope, cost
intensive projects with a lengthy and schedule – interact and add to
timescale for licensing, development the project’s complexity and risks to
and construction. These capital costs completion.
must be financed by the project
sponsor. Projects are therefore very The risks of delay and budget
sensitive to any construction over- overrun are especially significant in
runs, as this increases the amount of first-of-a-kind (FOAK) engineering
interest payable before any revenue projects. They have also arisen as
is generated. In the case of a nuclear novel techniques are employed, such
power plant, a key consideration is as modularization. The costs can
safety in operation and this implies escalate exponentially as the project
that the quality of manufacturing management organization tries to
and construction must be of an resolve multiple inconsistencies while
exceptional standard. manufacturing and construction
are underway. Excellence in project
The scope of the project must be management thus entails hitting the
clearly defined and should incorporate ‘sweet spot’ without compromising
the aims of the key stakeholders, safety and quality or relaxing either
which should be identified and the budgetary constraints or the
negotiated at an early stage in the schedule.

Figure 2. The triple constraints of project management2

Time
2
Adapted from Milton D Rosenau, 1984,
Project Management for Engineers,
Belmont, CA: Lifetime Learning
Publications: p. 13.
3
See IAEA, 2016, Maintaining the Integrity Fast
of Nuclear Installations throughout
their Operating Life; A Report by the
International Nuclear Safety Advisory
Group, INSAG-19, Vienna: International
Poor
Atomic Energy Agency: paras. 5, 10
Quality Expensive
and 12; World Nuclear Association,
2015, Design knowledge and design
change management in the operation of
nuclear fleets, London: World Nuclear
Association: pp. 3-4; and World Nuclear
Association, 2017, Implementation of Cheap Late Good
the Design Authority within a Nuclear
Operating Organization, London: World
Nuclear Association: pp. 6-8 and 15-17. Cost Quality

6
Figure 3. Drivers of project cost overrun and delay operator. It implies that the operator
needs to understand the whole
Risk of Multiple Design project design process, including any
non-conformity attributes complexity changes made during construction,
well in advance of assuming design
authority for the plant’s operation.
Quality
issues Quality x Scope = Cost x Time Delays
The relationship between the project
sponsor, the technology vendors,
the architect-engineer and the future
Safety Lots of stakeholders Project operator is therefore a partnership
first to satisfy scale where risks are managed through
collaboration. The contracts between
these top tiers must reflect their
interconnected responsibilities and
Adopt a collaborative approach procurement and construction mutual reliance upon each other for
The regulatory environment under (EPC) company. In addition, by the navigating the regulatory hurdles to
which a nuclear power plant is time the plant is handed over for project completion.
designed, built and operated operation, the operator must have
imposes a relatively unusual the capability to act as the design Organize the project to secure
distribution of responsibilities among authority to maintain design integrity resources at the time they are
the organizations undertaking the and preserve design knowledge over needed
project. The sponsor of a nuclear the lifetime of the plant.3 The utility,
Good project governance provides
power plant project is often a utility, as the licensee for operation, often
well-founded, clear and timely
which contracts with the reactor assumes design authority in a staged
decisions and accountability to
technology vendor and other key process as the works are completed.
stakeholders, and will help secure the
suppliers to undertake construction, In doing so, the utility takes over the sponsor’s objectives. It demonstrates
and then takes over the plant at its as built design and accepts the plant compliance with laws, regulations
commissioning. However, this is not as ready for operation. and other requirements, and
always the case, and the investors respects basic rights and ethical
can establish a special purpose Although the reactor vendor is principles. Processes for ensuring
entity, in which the utility may have a responsible for the design of the leadership, delegating authority
stake, to act as the project’s sponsor nuclear reactor itself, once it is under and securing accountability, and for
and manage the construction and contract to the project sponsor, the communication must be supported
commissioning. reactor vendor is simply considered by institutional arrangements,
by the regulatory authority to be a including mandates, organizational
Utilities are understandably reluctant ‘responsible designer’. The project structures, roles and responsibilities,
to take on the risks associated with sponsor’s architect-engineer, who is and procedures (see Figure 4).
design approval and construction usually the designer for architectural,
but they will become, nonetheless, structural, mechanical and electrical, Among the procedures are standards
the operators and often assume and landscaping elements of the and controls, which ensure that the
ownership of the asset on the project, is also deemed to be a requisite level of performance is
project’s completion. The utility will responsible designer. The formal achieved. A common set of tools
have usually specified particular separation of asset owner, the project and methodologies will ensure
requirements that the design must sponsor, its contractors, and the that activities can be tracked and
meet for operation. Moreover, licensed operator introduces a series accountability is maintained.
as an ‘intelligent customer’ the of interfaces between organizations
sponsor must supervise the project which must be managed in order to Project execution relies upon the
management organization, even if ensure that the design knowledge is sufficient and timely availability of
this is contracted to an engineering, ultimately taken over by the plant’s resources: human, financial, technical

7
Figure 4. Project governance architecture

Evaluation

y
ilit

Le
ab

a
de
t
un

rs
co

hi
p
Ac
Structures Preparation
Inspection

Roles Mandates

Procedures
n
io
at

Procurement

Au
c
ni

th
u

o
m

rit
om

y
C

Production

and natural. But resources enter the can learn and develop to do things
project as ‘pre-packaged’ goods better. The drive to achieve higher
and services (Figure 5). The human productivity through multi-skilling,
resources inputs arrive as labour standardization, lean production,
services, as already trained and just-in-time delivery, modularization
qualified workers under contract as and rigorous quality control is more
direct employees or through a service advanced in manufacturing although
providing organization. Financial its application to construction has
resources are procured under been demonstrated in Japan in
covenants with banks, or as internal particular.4 Enhancing productivity
funding secured from the issue of in nuclear construction has been
corporate bonds, and so on. The recognized as essential and the
different forms that resources come in World Nuclear Association has joined
mean that they are not fungible. This with Constructing Excellence, a UK-
means that they cannot be substituted based industry body, to promote the
for one another but must be managed concepts and tools needed.5
as distinct contributors to a portfolio of
capability. There are limits to the extent Involve key suppliers in
4
See World Nuclear Association, 2014, The
that workers from different trades can comprehensive planning
World Nuclear Supply Chain: Outlook 2030,
London: World Nuclear Association: pp. 149- be used flexibly for a range of tasks, The complexity of project
150 and 165-166. for example, and this has important management can be lessened by
5
Constructing Excellence, 2017 (forthcoming), implications for productivity. improving the quality of knowledge,
Construction Factory Thinking: Ideas for
thereby reducing uncertainty, and by
responding to the productivity challenge,
London: Constructing Excellence.
It is generally recognized that broadening the areas of stakeholder
6
Constructing Excellence and Nuclear
productivity in construction tends agreement. Acquiring and applying
Industry Association, 2011, Japan’s Nuclear to be lower than manufacturing knowledge is an important factor
Construction Industry: Report of the UK Study productivity. Construction projects in the effective management of
Tour in March 2011, Watford: Constructing
present greater diversity than a all mega-projects. Involving key
Excellence: p. 18.
7 manufactured product that has stakeholders in a comprehensive
See Engineering the Future, 2010, Nuclear
Lessons Learned, London: Royal Academy of come off a production line. Usually a planning exercise brings in the
Engineering. factory has a stable workforce who knowledge which they possess and

8
Figure 5. Sequence for product realization

Resources
Inputs
- Human Processes Outputs Results
- Materials
- Financial For product - Products - Benefits
- Goods
- Natural realization - Value
- Services
- Technical

will help the project management to nuclear power plant projects is basis for the safety case needed to
organization address the inherent shown in Figure 6. obtain a construction license. Delays
complexity of the project. have also been caused when the
Initially a utility must review the sponsor has authorized construction
The comprehensive planning reactor vendor’s conceptual design to commence without finishing the
involving key stakeholders that and assess whether this meets detail design.7
is undertaken in the Japanese regulatory and its own requirements.
construction sector has resulted If it is not an already licensable Some of these difficulties arose
in some of the fastest build times design, the utility will need to agree because the reactor vendor was
for nuclear power plants in the with the reactor vendor on any design constrained financially and could
world. About one year is spent changes needed. Some safety not undertake the design work fully
in construction planning before regulators provide an early design until receipt of the design and build
construction starts in collaboration assessment process to give the contract from its customer, the utility,
with the supply chain.6 project sponsor greater assurance who, in turn, sought a fixed price
that the design can be licensed, as for the project. As a result the utility
The benefits of thorough and detailed is the case in Canada and the UK embarked upon a project with an
planning apply particularly to the for instance. The sponsor’s final immature design and inadequately
phasing of design, engineering and investment decision will usually be specified scope of work. In theory
procurement. The phase-gate model taken on receipt of the construction the fixed price insulated the project
has proved useful in the engineering licence, by which time the detailed sponsor from bearing the additional
construction industries generally, design should already have been cost of unforeseen work. In practice
whereby the project is divided into completed. Project delays have the contractual arrangements shifted
stages with clear criteria established arisen when the sponsoring utility has responsibility for project completion
at each ‘gate’ to allow review before submitted a preliminary design to the onto the technology vendors without
progressing to the next stage. An safety regulator that has not been providing a means through which the
illustration of how this can be applied sufficiently worked out to provide the project risks could be addressed.

Figure 6. Stages in the design and engineering of a nuclear power plant project

Conceptual Preliminary Basic Detailed

Business case, Schematic layouts, Budgeting, Specification &


Procurement
Feasibility

Constructability

Financing

pre-project schedule, and cost execution plan, supplier


planning and estimation safety case and qualification, and
review of environmental limited work
requirements impact assessment authorization

Site licence Licensable Construction


application design licence application

9
Allocate project risks through integrated project management
appropriate procurement structure. Adequately resourcing the
strategies project management organization
Contracting creates relationships and ensuring good communication
between the key stakeholders across interfaces are also necessary.
and thus provides a framework to
manage the disruptions that are Uncertainty about the future cannot
inevitable along the critical path. be eliminated altogether so there
But contracts may also create exist residual risks that are by their
obstacles to project management nature not amenable to estimation
if incentives are misaligned and an but must nevertheless be managed
inappropriate project structure is by the sponsor.9 Risks that can be
adopted. A standard engineering estimated are priceable and thus
and construction contract, like those financeable so it is in the sponsor’s
issued by FIDIC8 or the International interests to reduce the degree of
Chamber of Commerce, assumes uncertainty by as much as possible.
that variations can be managed by
negotiation or third party arbitration Align the interests of key
and that penalties in the form of stakeholders
liquidated damages – which are Complexity reduces when the
capped at a fraction of the contract interests of key stakeholders
price – will exert sufficient pressure are aligned. Key stakeholders
on the main contractor and its include the owners, the investors
suppliers to maintain the schedule. and bankers, the operator (the
These are suitable where the risks licensee), the regulators, the staff
can be defined and allocated and contractors, and the customers.
between the parties. However, where Ensuring that suppliers fulfil the
the parties are operating in a complex expectations of the licensee and
environment these assumptions may the regulators without intrusive
be invalidated. The tendency for (and expensive) supervision will
claims and counter-claims to escalate be assisted if interests are aligned
in value well beyond the contracted properly. Such close supervision of
price creates an untenable situation suppliers can be time-consuming
in which the relationship between and will tie up the resources of
the parties may break down and the quality management and
there is a risk that one or other side engineering staff.
will abandon the project altogether.
Alternative forms of contract have Aligning the interests of key
8
International Federation of Consulting
been adopted for mega-projects in stakeholders can be achieved in
Engineers (Fédération Internationale des
Ingénieurs-Conseils). the UK (including a nuclear project) many ways. In some countries the
9
World Nuclear Association, 2017, to allow project partners to share utility and the reactor vendor are
Nuclear Power Economics and Project risks and rewards. members of the same corporate
Structuring, London: World Nuclear group. In others, a project sponsor
Association: pp. 29-30 and 34.
10
A collaborative or partnership may establish a special-purpose
World Nuclear Association, 2017,
Nuclear Power Economics and Project
approach should allow the sponsor’s entity in which the reactor vendor is a
Structuring, London: World Nuclear project management organization to shareholder along with the intended
Association: p. 40. access the knowledge held by key long-term asset owner. Governments
11
World Nuclear Association, 2014, The stakeholders during the design and could also take a shareholding in
World Nuclear Supply Chain: Outlook
planning processes. It will enable a the special-purpose entity to secure
2030, London: pp. 150-151.
12 wider set of procurement strategies long-term investments in reliable
McKinsey & Company; 2016, Imagining
construction’s digital future, Singapore: to be employed and facilitate team energy supplies to the country. Once
McKinsey & Company. working on the project through an the plant is operating, the reactor

10
operator and the government can sell company places too much emphasis project management organization)
their shares in the special-purpose on an externalized procurement if difficulties arise can be used
entity. No nuclear power plants strategy, especially if this is combined where the riskiness of the activities
have yet been built as stand-alone with a threat to buy elsewhere if warrant it. Well-defined expectations
merchant plants through a project the supplier does not reduce its regarding performance need to
finance model because the regulatory prices sufficiently, then, inevitably, be set by the project management
and construction risks have proved to the supplier will not be motivated to organization and the lines of
be so hard to control.10 become a project partner. Identifying accountability and communication
just who are the critical suppliers must also be clear.
In the first instance, nuclear and choosing the appropriate
power plant projects must meet procurement strategy is therefore of The licence conditions appertaining
challenging regulatory requirements great importance. to a nuclear project require the
and sometimes inconsistent project sponsor to demonstrate
expectations from decision-makers Communicate expectations that the plant’s structures, systems
and communities. These factors along the supply chain and components will function under
will impact on the scope of the Some projects have encountered potentially extreme conditions and
project’s design and the quality of technical and managerial interface therefore suppliers must show
manufacturing and construction to issues. Technical interface issues they have adhered to strict quality
be achieved. They in turn will drive up arose during project execution as standards during manufacture and
the complexity and risks associated a result of design inconsistency construction. The stringency of the
with the project. To manage a project or ambiguity. Managing interfaces quality control measures applied
effectively asset owners must build between organizations and between by suppliers to critical processes
relationships with key stakeholders activities could also be disruptive. should be commensurate with the
to limit uncertainty, and thus be in a FOAK projects are especially risk to safety posed by the product
position to control the risks. vulnerable to technical interface according to a graded approach.
problems but the complexity of It is important that the sponsor
Incentivize contractors the project means that this will and the top tier vendors provide
Key stakeholders require incentives remain a source of disruption to suppliers with sufficient information
to ensure a high level of performance the critical path and the necessity on the safety significance of their
is maintained but contractual for re-work is difficult to eliminate product so that resources are used
arrangements may not be sufficient altogether. Interoperability can be effectively and to avoid unnecessary
and adopting a collaborative improved if the design is accessible cost escalation.
way of working will bolster these to all key stakeholders and there are
relationships. Lower tier suppliers clear and workable procedures to Deploy digital tools and
can be incentivized through early introduce design changes well before establish a controlled
completion bonus payments or project execution begins. Common construction environment
targeted cost saving clauses (and procedures for work execution will Digital tools such as Building
penalized through the imposition also reduce the risk of interface Information Modelling and open
of liquidated damages in case of issues arising and these must be system platforms allow teams to
delays). Nonetheless, and depending negotiated and prepared in advance. collaborate more easily and preserve
upon the criticality of their inputs, information. Project management
some suppliers may also need to be The risk analysis should categorize has moved from using spreadsheets
brought into the project management the activities carrying the largest risks and stand-alone software tools
team and a stable relationship with to project fulfilment. The procurement towards integrated platforms
the project sponsor/EPC company strategy should then form part of the that provide real-time information
will help ensure this. risk mitigation plan. Processes where spanning design, planning,
a fixed price can be agreed may be procurement, manufacturing,
Collaboration will give critical identified, while contracts permitting construction, commissioning,
suppliers a voice in project planning; the supplier supplementary resources operation, maintenance, and
it also implies that they will share in on a basis of reimbursement of decommissioning.12 These tools will
the project’s construction risk.11 If time and materials (subject to a assist the utility to take on its role as
the technology vendor or the EPC cap and by agreement with the the design authority.

11
Pre-assembly of components in the cause. The main driver of opposition
factory has helped avoid unexpected may well be locally-rooted opposition
problems arising on site later. to the impact of the development
Modular construction techniques itself, rather than generalized fears
are used and temporary structures over the safety of the facility.
shelter site and installation works at
the nuclear island.13 There is general Extensive stakeholder engagement
acceptance within the industry that with local communities and taking a
performance and conformity are genuinely accommodative approach
improved if work is undertaken in a towards local community concerns
controlled sheltered environment. will reduce the potential for the
project to generate opposition.
Engage with stakeholders in the
community
International experience indicates A collaborative or partnership
that concerned citizen groups target approach should allow the sponsor’s
specific sites and investments in project management organization to
order to mobilize support for their access the knowledge held by key
point of view and make an impact stakeholders during the design and
on the national political scene. Such planning processes. It will enable a
tactics exploit the tendency within a wider set of procurement strategies
local community to worry about risks to be employed and facilitate team
that they feel are being imposed working on the project through an
upon them without consultation or integrated project management
compensation. Organized citizen structure. Good interface
groups can become the main management and internal project
source of information on a project or communication; the establishment
incident and as the news media is of enduring collaboration with key
duty-bound to report all sides of the stakeholders; quality control and
story, distortions may spread widely supplier oversight; and human
and exacerbate fears. Gaining public performance improvement will
confidence, then, involves tackling the enrich the relationships between key
local anxieties first and foremost, and stakeholders. Adequately resourcing
realizing that concern over ‘safety’ is the project management organization
the sign of dissent, not necessarily its is also necessary.

13
Constructing Excellence and Nuclear
Industry Association, 2011, Japan’s Nuclear
Construction Industry: Report of the UK Study
Tour in March 2011, Watford: Constructing
Excellence: pp. 8 and 18-19.

12
3 Capturing lessons

Information is not the same as correcting problems for ensuring


knowledge. It must be processed that there is continual improvement.
and codified by the knowledge A project culture (including safety
management system to be used culture) that spans the many
intelligently in an organization. organizations involved should be
An organization’s knowledge promoted by the project sponsor.
management system must be able to
create, share and use the information While the nuclear industry has gone
and experience gained from its a long way towards establishing
activities and that of others.14 mechanisms for capturing and
sharing knowledge through the
A key success factor is therefore promotion of a culture of safety and
the quality of knowledge, as already learning, this has for the most part
mentioned. Planning at the start involved operational experience
of a project may be impaired if, for rather than construction experience.
example, there is a lack of knowledge Other industries have already
about how the supply chain operates pioneered the application of digital
in practice or about the aims and technologies to assist in design
interests of external stakeholders (i.e. and engineering and the nuclear
the local political representatives or industry is now taking strides in
sections of the community). this direction. Digital platforms
for managing construction and
If the client side of the project manufacturing are developing
(investors, sponsor, operator) is rapidly. For many nuclear service
poorly informed it may not be able companies, those good operational
to act as an intelligent customer. practices are already embedded in
Close collaboration and a trusting their management systems and are
relationship between the project available for deployment in managing
sponsor and the Tier 1 partners project complexity. The industry
are essential to unlocking the must transfer this good knowledge
knowledge and capabilities of lower and management practice to the
tier contractors. On the contractor/ nuclear supply chain in order to
vendor side, lack of knowledge due achieve exceptional performance in
to inexperience in working outside of manufacturing and construction.
its ‘comfort zone’ or usual ‘domestic’
arena can hamper performance, Regarding the regulatory authorities,
especially on an international project the construction experience (ConEx)
where teams have been drawn from a program at the Nuclear Energy
wide range of backgrounds. Agency offers regulators some
guidance on the scope of their
Fostering a culture where oversight and the sort of checks they
established practices and thinking should undertake during a project.
can be questioned has been At this point, the NEA ConEx database
recognized as important for safety. A is the only platform where construction
questioning attitude and openness experience is gathered systematically.
are not necessarily disruptive
14
See Harry Scarbrough, J Preston since learning can reinforce good High performance depends upon
and Jacky Swan, 1999, Knowledge
management: A literature review,
practices. An organization can learn organizational and individual
London: Institute of Personnel and from its successes that it is doing capability, but also on a willingness to
Development: p.1; and Shan L Pan and things right just as much as from improve, in order to prevent mistakes
Harry Scarborough, 1999, Knowledge
incidents which indicate something recurring. Lesson-learning is part of
management in practice: An exploratory
case study, Technology Analysis and has gone wrong. Celebrating good this process and will be bolstered by
Strategic Management, 11, 3: p. 360. performance is as important as a strong culture of safety.

13
4 Benchmarks for
successful project
delivery
Taking account of the best performers These ‘building blocks’ can
and when organized correctly, it be combined into a table that
should be possible to complete summarizes the lessons learned
projects within 120 months or less (Table 1). The complexity of nuclear
(see Figure 7). A construction period construction projects calls for a
of 50 months from the pouring of team whose interests are aligned
the concrete for the nuclear island (relationships), who understand what
base mat until grid connection may has to be done (knowledge), and
be achievable with nth-of-a-kind who can draw upon the necessary
(NOAK) designs and uninterrupted technical, human and financial
experience as a result of repeat resources.
ordering. In Figure 7 it is assumed
that construction takes 70 months, Lastly, it has to be recognized that
which approximates to the average project risks cannot be eliminated
construction period for 90 percent of altogether. The time-quality-cost
the 600 reactor units built over the trilemma is not entirely under the
past 60 years: 71.8 months.15 project sponsor’s control since the
quality goal is determined ultimately
These targets are achievable and by the regulatory bodies. The risks
learning the lessons from recent associated with nuclear power plant
construction project experience projects – including regulatory,
will help developers bring forward project delivery, operational and
new projects with a high degree of market risks – can be mitigated
confidence that the project will remain through good project management,
within its budget and schedule. planning and partnership. All such
risks must be allocated to the
A collaborative approach will appropriate stakeholder in the best
permit key stakeholders to put position to take on and manage
in the requisite effort to plan the that risk, and often this will be the
project down to its last detail. But project sponsor through insurance
it takes time and has to be paid for and contingency provisions. Given
up-front. If, because institutional the intractable nature of uncertainty,
knowledge has been forgotten or is it may be desirable, in some
not available (because it is a first- situations, for the government or the
of-a-kind project), then the project energy market regulator to permit
sponsor must be realistic and cost-recovery arrangements or
allow more time for the design and provide loan guarantees in order
construction process. to attain national energy security
through a diverse portfolio of energy
Conceptually, collaboration and technologies, which includes nuclear.
sharing knowledge can be combined
with what management consultants This wider picture is important.
15
Excludes the 10 percent of exceptionally
PwC has suggested are the critical Competitive pricing of electricity
delayed projects due to political factors; success factors for project execution: offers consumer benefits but
see World Nuclear Association, 2016,
• Planning and governance; customers expect an uninterrupted
World Nuclear Performance Report,
power supply and not simply cheap
London: World Nuclear Association: p. 19. • Standards and controls;
16 supply. Market authorities need to
PwC, 2012, Projects without Borders:
• Human resource management; take notice of this in establishing
It’s all about execution, London:
PricewaterhouseCoopers: p. 21. • Project funding.16 energy markets. Unfortunately the

14
Figure 7. Typical project completion schedule

Developer
contracts with Limited work Final investment First
reactor vendor authorization decision by the sponsor revenue

Detail design
Prepare Plant construction
application Commissioning

Operating
Order Construction licence
EIA approved long-lead items licence issued issued

0 10 20 30 40 50 60 70 80 90 100 110 120


Months
EIA: Environmental Impact Assessment

market design in some countries


has created a potentially unreliable
electricity supply system. Short-
term wholesale energy markets
have had to be fixed by setting
up additional markets for spare
stand-by capacity and other grid
stability services. Capital-intensive
projects find it difficult to recover
their investment unless season-
ahead markets or other long-term
electricity pricing arrangements exist.
Such arrangements will enable the
project sponsor to obtain financing at
commercial rates. Leadership on the
client side by the project sponsor to
assemble a coalition of public, private
and civil society partners to argue
for an appropriate energy market
design is thus crucial to underpin
the successful completion of nuclear
power plant projects.

15
Table 1. Main lessons for nuclear power plant projects

Dimensions of Governance, design Standards and Human resource Financial resource


complexity and planning controls management management

Management of • Licensee possesses • Licensee ensures • Attention to • Project preparation


relationships with capability to that the scope of conflicting priorities needs to be funded
key stakeholders independently verify that the project is well- • Open reporting of by the project
licence requirements are defined at the outset non-conformances sponsor
being met • Effective and timely and risks • Contingencies
• Integrated management communication • High level of should be allocated
system (including active in quality control employee in line with the
interface management) processes engagement responsibilities for
• Common vision • Phase-gate process managing risks
• Celebration of good
• Empowerment of project with well-defined performance • Graded approach
management organization milestones to supplier oversight
• The flow-down of will focus resources
• Collaborative contractual
requirements to on critical processes
relationships
suppliers should
• Commitment to resolving
follow a graded
social and environmental
approach and be
issues
properly supervised

Quality of knowledge • Design and engineering • Regulations and • Wide understanding • Project preparation
(reducing uncertainty) apply a proven technology guidance are of the importance of needs to be funded
• Front-end planning, understood safety culture by the project
engineering and design • Project design is • High and sustained sponsor

• Basic design to licensable level of human


incorporate stakeholder • Well understood performance
knowledge quality management encouraged

• Risk assessment system

• Cautious localization • Proven methods of


working

16
5 Recommendations

By applying lessons learned the • An appropriate set of


nuclear industry can meet the procurement strategies should
expectations of asset owners, other be employed to facilitate
investors and vendors to prepare and integrated team working on the
deliver nuclear power plant projects project, help ensure collaboration
effectively and avoid the pitfalls. The in execution, and address the
main recommendations from this risks inherent in mega-projects.
review of lessons learned may be Risks should be allocated to the
summarised as follows: parties in the best position to
• The asset owner is ultimately take on and manage them.
responsible for managing • Incentivize key stakeholders,
the project. The asset owner including project partners and
sponsors the project and should vendors, to ensure a high level of
supervise all stages of the performance is maintained.
project. The sponsor must act • Wide and multi-stage
as the ‘intelligent customer’ and stakeholder engagement with
oversee the transfer of design local communities and taking
authority to the licensed operator. a genuinely accommodative
• Comprehensive planning to approach towards local
reduce the inherent uncertainties community concerns will reduce
and broaden the area for the potential of the project to
stakeholder agreement will generate opposition.
help the project management • Deploy digital tools to design and
organization address project plan the project comprehensively
complexity. The project sponsor in advance of execution.
should engage with customers, • Controlled construction
project partners and local environments will help achieve
community representatives in high levels of quality as will off-
defining (and controlling) the site pre-assembly of modules
project’s scope and in preparing and raise productivity.
a practical and comprehensive
• Communicate high expectations
project execution plan.
according to a graded approach
• A collaborative or partnership for quality along the supply
approach should allow the chain. The project sponsor
project management organization should encourage the transfer
to access the knowledge held of good practice, including
by key stakeholders during the knowledge management,
design and planning processes. along the supply chain in
Vendors should be brought into order to achieve exceptional
the planning process at an performance throughout nuclear
early stage. manufacturing and construction.
• A well-organized project will • High performance depends
secure resources at the time they upon on a willingness to
are needed. Project execution improve, in order to prevent
relies upon the sufficient mistakes recurring. Lesson-
availability of resources: human, learning is part of this process
financial, technical and natural. and will be bolstered by a
Good project governance strong culture of safety.
provides well-founded, clear
and timely decisions so that Ultimately it is the project sponsor
resources can be procured and who must guide the project to its
deployed on time. completion.

17
Glossary

The following terms are used in this report:17

Activity: A unit of work with four characteristics: 1) defined duration; 2) logical


relationship with other activities; 3) transformation of inputs into outputs;
4) a measurable cost in terms of resources consumed and money. It is an
alternative term for a task.

Collaboration: A collaborative or partnership approach to working can take


different forms but must be based upon a shared culture to be successful in a
commercial environment. The vision and values of the project sponsor should
shape the project’s culture and governance, guide partner selection and thus
frame the contractual relationships between the key stakeholders. Clear rules
should be established for resolving issues and for disengagement in the event
of a breakdown of relations.

Complexity: The complexity of a project varies according to the number of


interconnections between the activities necessary to deliver the project’s goals
which are undertaken by autonomous agents who are accountable to different
authorities for their performance.

Critical path: The longest sequence of activities that must be finished on time
for the project to be completed by its due date. An activity on the critical path
cannot be started until its predecessor activity is finished and if it is delayed
the project is delayed (unless the subsequent activity is completed faster
than planned).

Design authority: The licensed operator of a nuclear power plant has the
responsibility and authority for approving and maintaining the licensing basis
of the plant, including design changes, and for ensuring that the requisite
knowledge is established, preserved and extended with operating experience.
The licensed operator is responsible for any changes to the plant’s design and
licensing bases throughout the plant’s lifetime. The reactor vendor normally
retains proprietary design information and is known as the responsible
designer.

Goal: The goals of the project are its desired results. Goals are normally
specific, measurable, achievable, relevant and time-bound (SMART). The
interests of the key stakeholders in the project will normally determine the goals
set for the project.

Graded approach: A regulatory approach to controlling a process under which


the stringency of the control measures applied is commensurate with the risk
to safety.

Interoperability permits the exchange of information at interfaces between


systems, between activities or between stakeholders.
17
Adapted from the Business Dictionary
(http://www.businessdictionary.com/
Knowledge differs from information in that it is contextual, that is to say, it exists
definition/) and IAEA, 2007, IAEA Safety in relation to a field (or family) of ideas that are related to one another. This field
Glossary: Terminology used in Nuclear is sometimes called a paradigm, that is, a set of theories that guide a person or
Safety and Radiation Protection, Vienna:
an organization’s actions. New knowledge must fit into an existing paradigm of
International Atomic Energy Agency
at <http://www-pub.iaea.org/MTCD/ knowledge to be useful. From time to time, in science, new knowledge leads to
publications/PDF/Pub1290_web.pdf>. a ‘paradigm shift’ and a novel way of looking at the world emerges.

18
Knowledge management is the process of creating, acquiring, capturing,
organizing, preserving, sharing and utilizing knowledge to enhance learning
and performance in organizations. An organization has both tacit and explicit
knowledge at its disposal, but in order to be a learning organization it must be
able to communicate its reserves of tacit knowledge to people joining it or to
external organizations.

Learning is the process of acquiring knowledge or modifying existing


knowledge from observations and experience. Learning is a key attribute of an
organization that can adapt and manage change.

Licence: An authorization from a regulatory body to perform specified activities.


The holder of a license is a licensee. The project’s ‘social licence’ is granted if
the project’s stakeholders give their consent to the specified activities.

Mega-project: A large and complex infrastructure project.

Outcome: The results from putting the product into use. The electricity
generated by an operating nuclear power plant is an outcome of the
construction project.

Performance: Performance describes the extent to which the planned activities


are accomplished and/or the goals of the project are achieved.

Productivity: While often used interchangeably with efficiency, productivity may


be considered as the ratio of an output to the inputs used in an activity related
to the production process.

Project: A project comprises an interrelated set of activities that result in a


product. A nuclear power plant is the product from the design, manufacturing
and construction activities.

Project sponsor: The project sponsor is responsible for identifying the


business case for the investment, maintains the project’s alignment with the
investor’s business strategy and risk appetite, and for ensuring that anticipated
benefits are realized. The project manager is responsible for planning,
controlling, monitoring and delivering the project with delegated authority from
the project sponsor.

Resources: A factor of production required to deliver an activity. The project will


draw upon the resources furnished by the key stakeholders in order to realize
the project’s goals. Resources are always limited and are thus a potential
constraint upon the project as much as they are necessary for its completion.

Risk: The combination of exposure to an undesirable event (uncertainty) and


the severity of the impact of such an event (loss).

Scope: The scope of a project defines the goals to be achieved. It is usually


broken down into a set of activities, each of which delivers one or more of
the goals.

Special-purpose entity: A legal entity established to fulfil a specific or


temporary objective, such as a capital expenditure project. A special-purpose

19
entity may be owned by several organizations and is aimed at isolating the
financial risk attached to the project.

Stakeholder: A stakeholder is a person or organization with an interest in the


outcome of a project. A key stakeholder is a stakeholder whose cooperation
is critical to the achievement of the project’s goals, since these agents
furnish the necessary resources. Among the key stakeholders in a nuclear
power plant construction project are the owners, the investors and bankers,
the operator, the regulators, the staff and contractors, and the customers.
Other stakeholders include the plant’s neighbours, the wider community and
their political representatives. All may have some influence, in that the local
community may pressure the political authorities to authorize the regulators to
issue instructions to the plant’s operator – in this case, the community and its
representatives have an indirect influence on the operator, while the regulator
has a direct influence.

Uncertainty: A situation where, in the current state of knowledge, events are


unpredictable and credible probabilities for outcomes cannot be assigned.

20
World Nuclear Association +44 (0)20 7451 1520
Tower House www.world-nuclear.org
10 Southampton Street info@world-nuclear.org
London WC2E 7HA
United Kingdom

The World Nuclear Association is the international organization supporting


the people, technology and enterprises that comprise the global nuclear
energy industry.

Our membership encompasses uranium mining, conversion, enrichment and


fuel fabrication; reactor vendors; major nuclear engineering, construction, and
waste management companies; and the majority of world’s nuclear generation.
Other members provide international services in nuclear transport, law, insurance,
brokerage, industry analysis and finance.

Lesson-learning in nuclear construction projects reports on the work of the


World Nuclear Association’s New Build Lesson-learning Task Force. The report
reviews and analyzes recent nuclear power plant construction projects to
identify good practice and lessons learnt.

Lesson-learning in Nuclear Construction Projects


© 2018 World Nuclear Association. Registered in England and Wales, company number 01215741

Das könnte Ihnen auch gefallen