Beruflich Dokumente
Kultur Dokumente
The bid estimate was completed and bids was formally retained by the piling
submitted to the owner on July 24, 2000. subcontractor to perform design work for the
Crane Hogan Structural Systems of two piers located in the Genesee River.
Rochester, NY, was the apparent low
bidder. MCDOT officially awarded the Cofferdam Designed for Anticipated
general contract, and a groundbreaking was Conditions
held on September 27, 2000. Shortly after
that, the general contractor awarded a The original pier design required
subcontract in the amount of $4.2 million construction of a cofferdam with plan
dollars ($US) to the piling subcontractor to dimensions approximately 14 meters by 35
perform minor water side demolition work, meters (45.9 feet by 114.8 feet). Rock was
bearing pile, fender pile, and fender timber anticipated to slope approximately 12
installation, drilled shafts for river dolphins degrees, or 3 meters (9.8 feet), toward the
anchoring the fender system, river river across the width of the cofferdam and 5
cofferdam installation, and cofferdam degrees, or 3 meters (9.8 feet), along the
excavation work. After the subcontract was length of the cofferdam; thus, across a
finalized, the cofferdam design consultant diagonal connecting opposite corners of the
cofferdam, the maximum anticipated change construction. The cofferdam designed for
of elevation of the rock was 6 meters (19.7 anticipated conditions is shown in Figure 2.
feet). The soil surface was level along the The components are standard materials
cofferdam length but sloped at consisting of Z-shape sheet piling, pipe
approximately 12 degrees, similar to the struts, and W-section wales. A tremie
rock, across the cofferdam. The foundation concrete seal was to be placed on the
design called for 24 rectangular flat areas to excavated rock and would extend upward to
be excavated into the rock, all at different the elevation of the bottom of the pier
elevations. The rock at the site is known to foundation.
be shale at the elevations involved in the
Because of the steeply sloping rock only two Considering the multiple difficulties
rows of bracing could fit into the rock associated with the deep cofferdam, the
excavation geometry. As a result of this, the owner elected to modify the design of the
lower wale now consisted of double pier foundation. Extensive work was
W920x271 (W36x182) beams. The finished required for redesigning the pier in order to
row of bracing was so heavy that the crane resolve difficulties associated with the rock
slope and seismic considerations. The system as constructed are shown in
redesigned pier and resulting cofferdam Photograph 1 and Figure 4.
The cofferdam design and construction both of the pier footing. Horizontal restraint was
faced challenges but the system was much still required to resist the unbalanced
safer for construction personnel, primarily horizontal load. The revised design used
divers, and the pier foundation was much circular cells and connecting arcs as
more reliable. In overall concept, the pier is anchorage and tension members connected
supported on 24 drilled shafts, and a tremie the cofferdam to the cells. Use of the
seal was installed to allow dry construction circular cells for anchorage was enhanced
because the load was reduced by
excavating soil from the area between the
cells and the rectangular cofferdam. The
rock slope beneath the circular cells was
less severe than beneath the pier and this
mitigated concerns related to the cellular
structures sliding on the rock.