Sie sind auf Seite 1von 10

COOPERATIVE EFFORT OVERCOMES PROBLEMS WITH PIER AND

COFFERDAM CONSTRUCTION CAUSED BY ROCK SLOPE

Herbert F. “Buck” Darling, III, Herbert F. Darling, Inc., Williamsville, NY


Richard J. Hartman, Hartman Engineering, Clarence, NY

A bridge replacement project in Rochester, NY, encountered difficulties when it was


determined that rock below one pier was sloping downward toward the river at an angle
of 42 degrees versus anticipated 12 degrees. Cofferdam design and construction
became very difficult. The unanticipated subsurface conditions delayed the project by
eighteen months and increased the cofferdam cost by almost $3.0 million ($US) when
direct costs and associated delays were taken into account. The initial approach after
discovery of the problem was to use the same type pier design and modify the
cofferdam accordingly. This resulted in a cofferdam 12 meters (39.4 feet) deep on the
shore side and 18 meters (59.0 feet) deep on the water side. The design used a master
pile system to attain required wall strength and used rock anchors to prevent the
cofferdam from moving toward the river. The pier foundation was then redesigned by
the owner using revised seismic parameters. The original stepped footing carved into
rock was replaced by caissons socketed into the rock beneath a large tremie concrete
placement. The revised pier and cofferdam designs caused a shift from a mostly land
based cofferdam, excavation, and rock removal project into an almost entirely water
based cofferdam, caisson drilling, and tremie construction project. These design
changes resulted in a reliable, safe, and unusual cofferdam and construction method.
All of this was accomplished within a very narrow worksite with a railroad on one side,
and the river with its public and commercial freighter traffic on the other. In addition,
the existing two-leaf drawbridge was to be maintained in place which put further
limitations on the water borne equipment. The engineering and construction
considerations, problems, and solutions related to these cofferdams and pier
foundations are presented.

History piers would require cofferdams in the river.


The two abutments were to be supported by
The Stutson Street Bridge over the Genesee HP305x79 (HP12x53) piles. Pier 1, located
River in Rochester, NY was built in 1917 as in the river, was to be founded on rock.
a double leaf bascule bridge. It provided Piers 2 through 4 were to be supported by
access to both sides of the river while HP356x174 (HP14x117) piles, with Pier 2
allowing recreational and commercial boat also a river pier. Herbert F. Darling, Inc.,
traffic. Having reached the end of its service (HFD) elected to bid the piling portions of
life, and due to the fact that commercial the project as the piling subcontractor.
freighter traffic and cruise traffic were still
using that portion of the river, a new lift Early on in the bidding process, it was
bridge was required to replace the existing apparent that one of the two river piers,
one. In July of 2000, the Monroe County Pier 1, would not be of normal construction.
Department of Transportation (MCDOT) in Pier 2 was constructed using standard
conjunction with the New York State methods; it utililzed an H-pile foundation, a
Department of Transportation (NYSDOT), large tremie concrete placement inside a
which provided the conceptual design and typical cofferdam, all designed in
which would provide construction oversight, accordance with the original bid documents.
let out for bid the contract documents for Pier 2 was located only 50 meters (164.0
what would become the new Colonel Patrick feet) face to face from Pier 1 which was
O’Rorke Bridge. The bridge was so named founded on rock at approximately 15 meters
in honor of a local Civil War hero. The (49.2 feet) depth. Pier 2 required
design of the new bridge called for two HP356x174 (HP14x117) piles 27 meters
abutments and four piers, and two of the (88.6 feet) long to reach rock. Pier 1,
however, was to be especially difficult with the available information. A soil boring
because of differential water and soil depths location plan is shown in Figure 1.
to rock across the cofferdam width, the large
size of the pier, the need to excavate A cofferdam design was then discussed and
contaminated river sediments to rock, and to bid, based upon the assumption that
also excavate rock underwater to a stepped conditions would be as presented in the
pattern. As a result of these perceived contract bid documents. That is, that a
difficulties, Hartman Engineering was rectangular steel sheet piling cofferdam with
retained as the cofferdam design consultant multiple rows of bracing would be founded
to provide pre-bid and post-bid consultation on rock believed to slope at approximately
for methods and means of river cofferdam 12 degrees across the width of the cell. This
construction. As early as the middle stages cofferdam would allow excavation of the
of the bidding process, there were concerns river sediments and excavation of the
regarding elevations of the rock at Pier 1, stepped foundation in the rock.
but nothing specific could be determined

Figure 1 – Boring Location Plan

The bid estimate was completed and bids was formally retained by the piling
submitted to the owner on July 24, 2000. subcontractor to perform design work for the
Crane Hogan Structural Systems of two piers located in the Genesee River.
Rochester, NY, was the apparent low
bidder. MCDOT officially awarded the Cofferdam Designed for Anticipated
general contract, and a groundbreaking was Conditions
held on September 27, 2000. Shortly after
that, the general contractor awarded a The original pier design required
subcontract in the amount of $4.2 million construction of a cofferdam with plan
dollars ($US) to the piling subcontractor to dimensions approximately 14 meters by 35
perform minor water side demolition work, meters (45.9 feet by 114.8 feet). Rock was
bearing pile, fender pile, and fender timber anticipated to slope approximately 12
installation, drilled shafts for river dolphins degrees, or 3 meters (9.8 feet), toward the
anchoring the fender system, river river across the width of the cofferdam and 5
cofferdam installation, and cofferdam degrees, or 3 meters (9.8 feet), along the
excavation work. After the subcontract was length of the cofferdam; thus, across a
finalized, the cofferdam design consultant diagonal connecting opposite corners of the
cofferdam, the maximum anticipated change construction. The cofferdam designed for
of elevation of the rock was 6 meters (19.7 anticipated conditions is shown in Figure 2.
feet). The soil surface was level along the The components are standard materials
cofferdam length but sloped at consisting of Z-shape sheet piling, pipe
approximately 12 degrees, similar to the struts, and W-section wales. A tremie
rock, across the cofferdam. The foundation concrete seal was to be placed on the
design called for 24 rectangular flat areas to excavated rock and would extend upward to
be excavated into the rock, all at different the elevation of the bottom of the pier
elevations. The rock at the site is known to foundation.
be shale at the elevations involved in the

Figure 2 – Anticipated Cofferdam

Design and construction of the cofferdam Construction was anticipated to proceed


presented technical challenges resulting along conventional lines. The three levels of
primarily from the changes in elevation of bracing would be pre-fabricated, stacked
the soil and rock. Due to the soil slope, together, and set in location on spud piles
diagonal bracing was required between the (piles driven to support the dead loads of the
st nd
1 (upper) wale level and the 2 (middle) bracing prior to attachment to the sheet
wale level in order to prevent movement of piles). Sheet piling would be set and driven
st
the 1 level of bracing toward the water. around the perimeter. Excavation of soil
nd nd rd
Due to the rock slope, the 2 wale level and would proceed until the 2 and 3 levels of
rd
3 (lowest) wale level were required to slope bracing, still stacked together, could be
nd
approximately 3 degrees parallel to the lowered so that the 2 level was in final
cofferdam length in order to remain above position. Diagonals and posts would be
st nd
the highest rock and still control sheet piling installed between the 1 and 2 bracing
spans at the locations where the rock was levels. Then soil would be excavated as
rd
lowest. necessary to allow the 3 level to be
lowered into final position. After lowering permission of the owner to enter the water to
rd
the 3 level, the remaining soil would be perform the probing, citing the need to
excavated. When the soil excavation was complete the cofferdam design and order
completed, the rock would be excavated to the sheet piles to allow cofferdam
form the 24 rectangles required for the construction to start on the first unrestricted
foundation. day in the river. Access was denied. The
New York Department of State had
Provisions were made in the design for jurisdiction over all other regulating bodies
normal variations in rock elevation. The involved in the construction process. After
elevation of the bottom of each sheet pile repeated requests and negotiation,
would be monitored; this would ensure that permission was granted to access the water
the occurrence of gaps between the sheet in order to perform the probing.
piling and rock would be detected, and they
st
could then be closed. In addition, if sheet Preliminary probing began November 21 ,
piles extended deeper than anticipated, toe and the data showed a much steeper rock
pins cut from steel rod would be set into slope at Pier 1 than had been anticipated.
holes drilled in the rock to restrain the Formal written notice of the changed
bottom of the sheet piling. condition was forwarded to the general
contractor for transmission to the owner.
From a constructability standpoint, this This notice was written to include the
conventional type design would presumably opinion that major delays and cost increases
have few difficulties associated with it. It were likely due to the unexpectedly steep
would be possible to install the sheet piling rock slope.
from land, and the bracing could be installed
in pieces sufficiently small and of In the meantime, mobilization of a crew and
appropriate weight for the crane to handle equipment to the site occurred on November
th
and eventually lower into place. Excavation 14 in preparation for the first non-restricted
th
would be incrementally performed and the water work date of November 16 . The first
bracing elements sequentially lowered to order of business was to build a new
their proper positions. In summary, it would docking structure for trans-loading materials
be a normal cofferdam installation utilizing and docking of water equipment. Then work
typical, readily available materials and would begin on the Pier 2 cofferdam
construction methods. template and sheet piling. This would allow
the unexpectedly more complicated design
The Start of Cofferdam Construction of the cofferdam for Pier 1 to be undertaken
with the least disturbance possible to the
With the early phases of the general overall project schedule.
contractor’s work on the project proceeding
on schedule and knowing that the river piers Discovery of Unanticipated Rock
were in the critical path, the piling Conditions
subcontractor began the submittal process
for all its required work. In order to The piling subcontractor conducted a
purchase sheet piling necessary for Pier 1 program to map the top elevation of the soil
installation, more accurate elevation data and rock in the vicinity of the cofferdam
was required to determine the proper location. Soil elevations were established
lengths. The piling subcontractor wished to using a weighted tape and rock elevations
perform a probing program utilizing a long H were determined using an H-Pile probe
pile and a vibratory hammer along specific driven with a vibratory hammer. Soil
section lines in order to determine the rock elevations were found to be essentially as
elevations. anticipated. However, the top surface of the
rock sloped toward the river, or across the
Unfortunately, no work was allowed in the cofferdam, much steeper than anticipated.
th
river until November 15 in order to protect The originally anticipated 12 degree slope
spawning salmon, trout, and steelhead. On was found to be 42 degrees, resulting in 13
September 13, 2000, and again on October meters (42.7 feet) of elevation change
26, the piling contractor requested special across the 14 meter (45.9 feet) cofferdam
width. Rock slope along the cofferdam particles if placed in water and slightly
length was found to be approximately 5 agitated. These rock properties presented
degrees, resulting in 3 meter (9.8 feet) additional major difficulties for both design
elevation change along the length; this was and construction.
consistent with the previous data. However,
the change from 12 degree to 42 degree Deep Cofferdam with Rock Excavation
slope across the cofferdam width presented
major problems. Whereas the anticipated Meetings were then conducted among the
difference in rock elevation diagonally owner, contractors, and the contractors’
across the cofferdam was 6 meters (19.7 consultants in order to determine the best
feet), it was now 16 meters (52.5 feet). solution to the problems. The owner wished
to maintain the same type of pier foundation,
After the probing established that the i.e., a tremie concrete seal placed on top of
elevation of the rock surface was much horizontal rectangular platforms excavated
different than anticipated, borings were into the rock; the number of rectangles was
taken and soil samples and rock cores were reduced to 8 from the original 24. Figure 3
collected. Soil was confirmed to be a typical shows the primary features of the cofferdam
mixture of sand and silt. Rock cores system designed for the deep excavation.
confirmed that the rock was shale but The design presented numerous challenges
examination of the rock and experimentation and construction was anticipated to be very
with it established that the rock was very difficult.
poor quality; it lost all its strength when
disturbed, and it would disintegrate into

Figure 3 – Deep Cofferdam with Rock Excavation


An obvious problem was the long spans, up sections and would be set into holes drilled
to 16 meters (52.5 feet), to which the walls into the rock. The master pile system with
were subjected. They required a wall with flat sheets was selected for two reasons.
strength greater than can be provided by First, a larger distance could be used
conventional sheet piling. There were two between master piles, thus reducing the
options. One was a master pile system, number of master piles and the number of
which utilizes W section master piles with holes that must be drilled for rock sockets.
flat sheet piles (PS type) between the Second, the piling subcontractor was
master piles. The other was a combination concerned about the difficulties associated
wall system which utilizes W section master with alignment of the master piles and
piles with Z-shape piles between. In both considered that the system using flat web
cases the master piles would be W36 sheet piles provided more flexibility.
could not be used to lower it into final
Another problem was that the very steep position. Thus, a mechanical system utilizing
rock slope resulted in a large unbalanced hydraulic cylinders, threaded rods, nuts, and
force applied to the cofferdam. The method plates was designed for hanging the wale
selected to resist the unbalanced force was above the water, and later, lowering the
a set of 14 rock anchors installed along the bottom wale into place.
wall on the land side. As shown in Figure 3,
soil would be placed between the cofferdam The selected master piles were W920x201
and shore in order to provide passive (W36x135) and W920x253 (W36x170)
resistance to allow testing and loading of the sections with cover plates welded to one
rock anchors. flange, and a specially bent PS27.5 flat
sheet pile welded to the other flange. The
From a construction standpoint, this design size and weight of the material was
represented an increase in complexity over increasing significantly. The weight of these
the initial design. A routine land based materials would become unmanageable
installation became a complicated water given the availability of standard equipment.
based operation. Constructability and The drill rig to install the master piles would
material availability were becoming major have to be mounted on a barge in order to
issues. The schedule was slipping away, so access all the master pile locations. Finally,
no materials could be used that would the sheer enormity of the drilling task led to
require long lead times. This system would schedule concerns. There were a total of 38
require a large amount of pre-fabrication to holes that would need to be drilled.
allow bracing installation below water by Paradoxically, and in accordance with
divers. In order for this installation process previous experience, the very rock that
to be planned and to allow for tolerance in could not be counted upon to carry the
placement of the drilled piles, wales were design loads of the pier once exposed to
designed to be smaller than the inside water would likely be very difficult to drill in-
dimensions of the sheet piles by 0.3 meters situ. This could lead to accuracy problems in
(1.0 feet). In order to then fill in this gap, the placement of the piles. The piling
thus effectively blocking the wale to the pile, subcontractor was also concerned that there
special upper and lower steel wedge blocks would not be sufficient room for error in
would be fabricated. Special plates designed being able to install the flat web sheet piles
to hang from the outside face of the wale between the master piles given the
would be fabricated with a sloping face uncertainty of the master pile final locations.
toward the master pile to accept the
wedges, all of which could be handled by a Revised System Using Drilled Shafts to
diver. Support the Pier

Because of the steeply sloping rock only two Considering the multiple difficulties
rows of bracing could fit into the rock associated with the deep cofferdam, the
excavation geometry. As a result of this, the owner elected to modify the design of the
lower wale now consisted of double pier foundation. Extensive work was
W920x271 (W36x182) beams. The finished required for redesigning the pier in order to
row of bracing was so heavy that the crane resolve difficulties associated with the rock
slope and seismic considerations. The system as constructed are shown in
redesigned pier and resulting cofferdam Photograph 1 and Figure 4.

Photograph 1 – Cofferdam for Pier 1 and


Completed Pier 2

Figure 4 – As Built Cofferdam with Drilled Shafts

The cofferdam design and construction both of the pier footing. Horizontal restraint was
faced challenges but the system was much still required to resist the unbalanced
safer for construction personnel, primarily horizontal load. The revised design used
divers, and the pier foundation was much circular cells and connecting arcs as
more reliable. In overall concept, the pier is anchorage and tension members connected
supported on 24 drilled shafts, and a tremie the cofferdam to the cells. Use of the
seal was installed to allow dry construction circular cells for anchorage was enhanced
because the load was reduced by
excavating soil from the area between the
cells and the rectangular cofferdam. The
rock slope beneath the circular cells was
less severe than beneath the pier and this
mitigated concerns related to the cellular
structures sliding on the rock.

The drilled shafts were installed at the same


time as the cellular structures and prior to
the cofferdam. The casings extending
upward from the shafts supported the
cofferdam bracing. Sheet piling was then
installed on the cofferdam perimeter. In Photograph 3 – Completed Cofferdam
order to expedite installation of the bracing Ready for Pier Construction
system and reduce associated diver work,
an “unfolding” post and diagonal system was As the final cofferdam design was
used between the two levels of bracing. completed, submitted and approved,
After excavation had progressed sufficiently arrangements were in process for creation
nd
to allow positioning of the 2 level of of the mechanisms to pay for the changes.
nd
bracing, the 2 level was lowered and the They resulted in an addition to the general
posts and diagonals “unfolded” into their contract in excess of ten million dollars. The
design location. They were then secured by original bid specifications contained an item
bolts installed by personnel standing on the for escrow of all bidding documents to be
upper brace level. Photograph 2 shows the opened and used in just such a case. They
cofferdam with the shaft casings and bracing would be used to determine the items
system still in place. Photograph 3 shows originally included in the general contractors
the cofferdam after removal of the casings bid, and used as a starting point for
and the bracing system when the area is assessing costs for new work if it became
ready for construction of the pier footing. necessary. New items were created, old
items deleted or modified, and coordination
Administrative and construction difficulties with other items were undertaken in order to
with the final design were numerous. Much account for previous and future impacts.
care and consideration for constructability
and material availability were incorporated With the introduction of the drilled caissons
into this final design. However, constructing into the footing design, the project changed
the final product was still a challenge. from a land based operation to a water
based installation using rented floats and
contractor owned spud barges and tugboat.
In addition, the river work was required to
comply with the calendar restrictions placed
on the project by regulating authorities.

One of the major problems was to ensure


the location and dimensional accuracy with
which the newly redesigned footing needed
to be constructed. The caissons were
required to be located accurately so that the
cofferdam could be built around them to the
correct size. Due to the large size of the
cofferdam, even minor increases in size
resulted in larger quantities for excavation,
Photograph 2 – Cofferdam with Bracing tremie concrete, and backfill. Conversely,
in Place there was no tolerance for having the
cofferdam and tremie be smaller than
designed. This led to great effort being
expended in the fabrication and placement became a concern. Thus, the excavated
of templates to ensure accurate location of material was required to be transported by
the permanent casings for the caissons. barge to a confined disposal facility operated
Due to the extremely limited reach of the by the U.S. Army Corps of Engineers in
caisson equipment on the barge, only one Buffalo, NY. The round trip including transit
row of casings could be vibrated into the soil of the Welland Canal and unloading the
at a time. After the casings were in place in contaminated spoils required 2 to 3 days,
the soil, the drilling subcontractor could slowing the excavation process and causing
clean them out and proceed with rock large amounts of downtime for equipment
drilling. Casing installation and drilling were and personnel both at the site and at the
performed in very close quarters and that disposal facility. However, there was much
resulted in implications for safety. It was only labor intensive hand cleaning of the caisson
after all of the caissons were installed that casings, the in-bays of the sheet piling, and
work on the steel sheet piling cofferdam the top of rock that had to be performed by
could be started. The cofferdam portion of divers working in water with no visibility.
the work proceeded without significant Much of this was done during the delay time,
difficulty. thus reducing downtime charged to the
owner.
Working on the water, there were to be no
impacts to the use of the navigable channel After the first stage of excavation and
during pier construction. There were cleaning operations were completed,
numerous recreation vessels and two major bracing installation occurred in a manner
commercial users of the river. This reach of very similar to that of the first redesign. The
the river is a primary access point for boat two rings were fabricated in place atop one
traffic to and from Lake Ontario. There was another and sequentially lowered and
a dinner cruise ship and a commercial blocked into place utilizing the wedge block
cement freighter that required full and procedure described previously. The final
unrestricted use of the channel. The size of excavation, rock and casing cleaning, brace
the freighter and the narrowness of the lowering and wedging operations were
channel made it necessary to completely performed in stages.
clear the channel for its passage. A full hour
was required to move all barges offline prior Once all the excavation, bracing, and mud
to the arrival of the ship. Then it took about cleaning operations were complete, the
another hour for the ship to clear. The piling truss posts and diagonals were secured. As
subcontractor could then move back into described earlier, these were prefabricated
position to work, but then would have to as much as possible to allow them to be
move again for the ship to go back out to the placed from above water elevation and
lake either the same day or the next “unfolded” into place. They were bolted to
depending on arrival time. The freighter the upper level brace by workers in dry
returned every one to two weeks, conditions. This was successful because of
sometimes more often. Total time lost was extensive planning and prefabrication.
on the order of 3 to 6 hours of work per
appearance depending upon the timing. Simultaneous with work on the water, a crew
on shore installed the circular cells to be
Once installation of the caissons and the used as an anchor for the sheet pile
steel sheet pile cofferdam were complete, cofferdam. As soon as the rear wall of the
excavation of river sediments and placement cofferdam and the circular cells were
of the bracing were undertaken. Due to the completed, the two were connected using
depth of excavation, the water based HP sections as tension members.
operation, and the contaminated nature of
the excavated materials, the excavation was Well before completion of the steel sheet
performed by crane and clam bucket (the pile cofferdam, circular cells, bracing and
excavation of contaminated material would excavation, plans were being made for
be a problem no matter which design was installation of the tremie concrete. This was
undertaken). Concerns for environmental a major operation due to its location.
problems during the disposal of the spoils
The access for equipment behind the crane, resulting in re-cutting of the sheet
cellular structures consisted of a linear piles.
roadway, approximately 15 meters (49.5
feet) wide sandwiched between an operating Conclusion
railroad line and the circular cell structure.
Space was required to set up the concrete A relatively straightforward job became a
pump, to maintain access for two concrete complex series of engineering and work
trucks at the pump, and to maintain room to tasks requiring great effort on the part of all
stage at least two more trucks in the event parties associated with the project. A
they arrived early. Concrete was required to change in the geology underlying one pier of
be delivered from two plants simultaneously the bridge caused a massive redesign and
in order to maintain anticipated production of construction effort.
the pump. The concrete suppliers could
guarantee the production of their plants only Eighteen months passed from the start to
if the tremie were placed during off hours. the finish of the design and planning phases
This was both to dedicate the plants to the for Pier 1. This occurred because it was
project, and to reasonably assure no traffic required that parties agree on what needed
delays for the transit trucks. Therefore, it to be done, how it would be done, how much
was decided that the tremie installation it would cost, who was going to pay for the
would begin at the end of the normal first increases, and what payment mechanisms
shift and go on through the night. Great would be put in place to pay $3.0 million
effort was expended to ensure uniform and design, construction, and delay cost
accurate top elevation of the tremie overruns for the cofferdam. The general
concrete. It was night time and there was no contractor incurred additional costs including
visibility through the 2.5 to 3.0 meter (8 to 10 delays, installation of the caissons, overruns
feet) of water above the top of tremie on the disposal of excavated soil, and
elevation. Concern for the elevation of the placement of additional tremie concrete. In
top of the tremie concrete was a result of the total, the cost increase exceeded $10
lesson learned at the Pier 2 location at million.
which the top of tremie was too high varying
from 2 inches to 16 inches, thus requiring a The redesign and construction required the
massive expenditure of labor and equipment combined effort of three design engineers,
to grind, chip, and clean the top down to the the general contractor, two subcontractors,
proper elevation. and two departments of transportation. All
parties were required to take into account
Upon completion of the tremie placement, all constructability and material availability in
of the bracing was removed and the open order to complete the project in the fastest
cofferdam is shown in Photograph 3. This and safest manner possible.
allowed construction of the pier footing and
pier to take place in dry conditions. After the Typical of subsurface work, none of the
footing and pier stem were completed, the additional planning, construction, and cost is
sheet piles were cut off at the top of tremie now apparent when viewing the bridge. But
elevation by divers. The cutting and removal everyone involved knows the detail and
of the sheet pilling was a very slow effort required to complete the project and
operation. Limited or no visibility in the water can be pleased with the final product.
caused incomplete cuts to go unnoticed until Without the cooperation and commitment of
attempting to remove the pieces with the every participant, it would certainly have
taken even longer and cost more.

Das könnte Ihnen auch gefallen