Minutes of Site Meeting No. 13
held
1.00 pm - Thursday 18 July, 1996
Contractual Items
Other
Claim (13 days) received for time lost due to preparing steel JA
shop drawings. Following original rejection GB has submitted
additional information to substitute claim. Main reason for
claim is lack of detail on Architectural drawings and some
changes to steel structure as a result. This is being
considered.
Business Arising
SITE SERVICES
Electrical
1.10 Power Supply - If later than this could cause delay.
The cost associated with providing revised electrical site HE
reticulation works is $7,073. Reason being to cater for URGENT
Stages 2 and 3. Approved at site meeting to proceed
subject to HE confirming price is reasonable. Funds to be
allocated against Stage 2.
10.1 Electrical
Car Park Lights - GB to provide price on providing car GB
lighting plus a sensor light to Administration relocatable.
Price provided $10,524. College to advise.
Sewer
Nil
Water Mains
Nil
Communications
Nil
BUILDING SERVICES
Technical data and samples as specified in tender GB/HE
documents are being provided to HE for approval.
Electrical
6.2 Number of power Bollards required being investigated. Will HE/JA
be resolved during construction (cost savings). Need to be
resolved over next two weeks.
11.3
Sweep Fans HE
Mechanical is responsible for wiring sweep fans back to
controls. This may incur additional costs as it is not
included in documents. Site instruction issued.
4.7 HE
Switchboard URGENT
Final Electrical Drawing - HE have provided comments
on revised shop drawings. Revised shop drawings provided
to HE. Awaiting approval.
Security Light JA
10.2 Security light above new external door in GPC. Price
provided $169 approved. Also require exit emergency light
- $249.
9.2 Mechanical
Mechanical Shop drawings being prepared by contractor. GB/HE
Access panels to Science not required. Shop drawings to
include Saw Dust Extractor and exhaust fans.
Hydraulics
Nil
Communications
Nil
General
12.4 Oval
Warranty period for oval expires 26 July 1996. Final LA
inspection to be carried out. Landscape Architect to
inspect.
12.6 Security
GB to provide name of security subcontractor who has to GB
be an approved DSE subcontractor.
New Business
13.2 Telephones
GB to formally apply to Telstra for connection. GB
13.14 MATV
Scope of works as specified on page 63 of electrical Note
specification.