Sie sind auf Seite 1von 7

Karnataka - Goa Border Road Project

Karnataka Goa Border Road Project


Camp / Area in Survey Name of the Application
Location Distance Taluk District Status
Quarry Acre no Village date

Quarrys

Ramnagara Uttara
Quary 9.35 Plot No. 308 Karwar Road 3.6 Km 43A Joida 8/3/2018 Registration pending
( Adali) Kannada

Ramnagara Uttara
Quary 4.38 Plot No. 335 Karwar Road 1.7 Km 43A Joida 8/3/2018 Registration pending
( Adali) Kannada

Camp

Existing
Camp 33.925 57+700 1.0 Km 26A Akrali Khanapur Belagavi April'18 Acquired via lease
Alignment
Bangalore - Mysore Project Logistic
Package-1 - Bangalore - Nidagatta
Camp / Area in Name of Application
Camp Location Side Distance Survey no Taluk District
Quarry Acre the Village date

Existing 124/2,121,1 Kaniminiki Bangalore Bangalore


Camp-1 20 24+500 LHS 0 Mtr NA land
Alignment 26,122 Village south Urban

Ramanagar
Camp-2 22 32+190 Bidadi Bypass RHS 1.5 Km 68,69,70 Avaragare Ramanagara
a

Manchegow Ramanagar
Quarry-1 14 34+640 Oriental Quarry LHS 14 Km Ramanagara
danapalya a

Manchegow Ramanagar
Crusher-1 15 34+640 Oriental Quarry LHS 14 Km Ramanagara
danapalya a

Manchegow Ramanagar
Quarry-2 8.5 34+640 Quarry LHS 14 Km Ramanagara
danapalya a

Existing Sugganahall Ramanagar


Quarry-3 3 39+000 RHS 2.5 Km 165 Ramanagara 7/28/2018
Alignment i village a

Ramnagara Ramanagar
Quarry-4 4 50+000 RHS 2.5 Km 97 Arehalli Ramanagara 7/28/2018
Bypass a

Ramnagara Ramanagar
Camp-3 19 51+000 RHS 50 Mtr 266 Bilagumba Ramanagara 8/4/2018
Bypass a

Ramnagara Ramanagar
Quarry-5 8 52+000 RHS 15 Km 13 Kottagarahalli Magadi
Bypass a

Channapatana
Quarry-6 11 61+000 RHS 20 Km
Town

Ramnagara Ramanagar
Camp-4 9 65+360 RHS 0 Mtr
Bypass end a
Camp-5
Existing Channapatta Ramanagar
Main 30 71+000 LHS 0 Mtr Belekere 7/10/2018
Alignment na a
Camp
Pkg-2 Nidagatta- Mysore
Area in Name of
Camp Location Side Distance Survey no Taluk District
Acre the Village

K.Honnalag
Quarry-7 6 74+200 Existing Road LHS 7 Km 109 Maddur Taluk Mandya
ere Village

Existing Kudaragund
Camp-6 28 84+000 RHS 100 Mtr Maddur Taluk Mandya 26.07.2018
Alignment i Village

Sadhbhav / 10
Ummadahall
Camp-7 10 94+740 Acre Mandya RHS 500 Mtr Mandya Mandya 26.07.2018
i
Bypass Start

Mandya Bypass
Camp-8 12 104+410 RHS 500 Mtr Induvallu Mandya Mandya 26.07.2018
End

Existing Sriranga
Camp-9 10 117+000 RHS 800 Mtr Ganagoor Mandya 26.07.2018
Alignment patna

Existing Sriranga
Quarry-8 30 119+000 LHS 6.5 Km 21 Kalenahalli Mandya 28.05.2018
Alignment patna

Srirangapattana Sriranga
Camp-10 8 130+000 RHS 100 Mtr Bramhapura Mandya 26.07.2018
Bypass end patna
ore - Mysore Project Logistic
kage-1 - Bangalore - Nidagatta
Status

Application to be submitted for PCB NOC for


Establishment of camp

NOC from Bididi Municipal Council Obtained


on 06.08.2018. Application to be submitted
for PCB NOC for Establishment of camp

Existing Leased Quarry

Land to be final

Existing Leased Quarry

Application submitted to Deputy Director


Mines, Ramanagara. Awaiting for Forest
NOC
Application submitted to Deputy Director
Mines, Ramanagara. Awaiting for Forest
NOC

Application submitted for Village panchayth


NOC for establishment of Camp

Existing Leased Quarry Agreement in


progress

NOC from Village Panchayath obtained.


Application to be submitted for PCB NOC for
Establishment of camp
NOC from Village Panchayath obtained on
07.08.2018. Application to be submitted for
PCB NOC for Establishment of camp
Pkg-2 Nidagatta- Mysore
Status

Existing leased Quarry. Lease Agreement


has been done for 6Acres

PCB NOC Cleared for Camp Establishment.


CFE applied on 26.07.2018 for Plants and
Fee paid
PCB NOC Cleared for Camp Establishment.
CFE applied on 26.07.2018 for Plants and
Fee paid
PCB NOC Cleared for Camp Establishment.
CFE applied on 26.07.2018 for Plants and
Fee paid
PCB NOC Cleared for Camp Establishment.
CFE applied for Plants and Fee paid. Applied
for Crusher establishment at DC offcice on
26.07.2018

Asst.Commissioner's NOC clerared, Forest


NOC is pending since 28.05.2018.

PCB NOC Cleared for Camp Establishment.


CFE applied on 26.07.2018 for Plants and
Fee paid

Das könnte Ihnen auch gefallen