PRINCE2

PRINCE2 (PRojects IN Controlled Environments) is a


structured project management method[1] and practitioner
certification programme. PRINCE2 emphasises dividing
projects into manageable and controllable stages.

It is adopted in many countries worldwide, including the UK,


western European countries, and Australia.[2] PRINCE2
training is available in many languages.[3]

PRINCE2 was developed as a UK government standard for


information systems projects. In July 2013, ownership of the
rights to PRINCE2 was transferred from HM Cabinet Office to PRINCE2 - Structure
AXELOS Ltd, a joint venture by the Cabinet Office and Capita,
with 49% and 51% stakes respectively.[4]

Contents
History
Overview of PRINCE2
Management Products
Principles
Integration with other techniques
Quality review technique
Training and Certifications
Advantages and criticisms
Differences from PMP
See also
References
External links

History
PRINCE was derived from an earlier method called PROMPT II (Project Resource Organisation Management
Planning Techniques). In 1989 the Central Computer and Telecommunications Agency (CCTA) adopted a version of
PROMPT II as a UK Government standard for information systems (IT) project management. They gave it the name
'PRINCE', which originally stood for "PROMPT II IN the CCTA Environment". PRINCE was renamed in a Civil
service competition as an acronym for "PRojects IN Controlled Environments". It soon became regularly applied
outside the purely IT environment, both in UK government and in the private sector around the world.[5] PRINCE2
was released in 1996 as a generic project management method.[6] PRINCE2 has become increasingly popular and is
now a de facto standard for project management in many UK government departments and across the United Nations
system.[7] In the 2009 revision, the acronym was changed to mean 'PRojects IN a Controlled Environment'.
There have been two major revisions of PRINCE2 since its launch in 1996: "PRINCE2:2009 Refresh" in 2009, and
"PRINCE2 2017 Update" in 2017. The justification for the 2017 update was the evolutions in practical business
practices and feedbacks from PRINCE2 practitioners in the actual project environment.[8]

Overview of PRINCE2
PRINCE2 is based on:

Seven principles: Continued Business Justification, Learn From Experience, Defined Roles And Responsibilities,
Manage By Stages, Manage By Exception, Focus On Products, Tailor To Suit The Project Environment.
Seven themes: Business Case, Organisation, Quality, Plans, Risk, Change, Progress.
Seven processes:

1. Starting Up A Project, in which the project team is appointed including an executive and a project manager,
and a project brief is produced
2. Initiating A Project, in which the business case is completed and Project Initiation Documentation assembled
3. Directing A Project, which dictates the ways in which the Project Board oversees the project
4. Controlling A Stage, which dictates how each individual stage should be controlled, including the way in which
work packages are authorised and distributed
5. Managing Product Delivery, which has the purpose of controlling the link between the Project Manager and
the Team Manager(s) by placing formal requirements on accepting, executing and delivering project work.[9]
6. Managing Stage Boundaries, which dictates how to transition from one stage to the next
7. Closing A Project, which covers the formal decommissioning of the project, follow-on actions and evaluation of
the benefits.

Management Products
The PRINCE2 manual contains 26 suggested templates for documentation associated with the project, which it terms
management products and which are divided into baselines, records and reports. Some examples of management
products are:

Benefits Review Plan: defines how and when a measurement of the project’s benefits, expected by the Senior
User, can be made.
Business Case: used to capture financial justification for the project. It is a PRINCE2 principle that a project must
have continued business justification. As soon as a Business Case fails to make sense, change or stop that
project.
Checkpoint Report: a progress report created by the Team Manager and sent to the Project Manager on a
regular basis to report the status of the Work Package.
Communications Management Strategy: a description of the methods and frequency of communication to
stakeholders, covering the flow of information in both directions to and from stakeholders (Information required to
be provided from the project and information required to be provided to the project).
Configuration Item Record: provides a record of the product History, Status, Version, Variant, Details of any
relationships between items/products, and Product owner/Product copy holders.
Configuration Management Strategy: used to identify how the project’s products will be identified, controlled
and protected, this document is created by the Project Manager in the Initiating a Project process.
Daily Log: used to record informal issues.
End Project Report: reviews how the project performed against the original Project Initiation Documentation
(PID)
Issues Register: an issue log of notes about change requests, problems and complaints sent by all project
members.
Lessons Log: a set of notes of lessons learned which may be useful to future projects
Project Brief: used by the Project Board to authorize the Initiation Stage (1st stage of the project). In the Initiating
a Project process, the contents of the Project Brief are extended and refined and the Project Brief evolves to form
the Project Initiation Documentation (PID)
Quality Register: details of all planned quality control activities, dates, and personnel involved.
Risk Register: a record of identified risks (threats and opportunities) relating to the project
Principles
The PRINCE2 principles can be described as a mindset that keeps the project aligned with the PRINCE2 methodology.
If a project does not adhere to these principles, it is not being managed using PRINCE2.

1. Continued business justification: The business case is the most important document, and is updated at every
stage of the project to ensure that the project is still viable. Early termination can occur if this ceases to be the
case.
2. Manage by exception: regular meetings, like weekly team meetings, are inefficient and unnecessary. Instead,
work packages are assigned by team managers to team members including deliverables with time and quality
tolerances, and only if something exceeds these tolerances is communication and management required between
the workers and team managers.
3. Learn from experience: each project maintains a lessons log and projects should continually refer to their own
and to previous and concurrent projects' lesson logs to avoid reinventing wheels.
4. Defined roles and responsibilities: Roles are separated from individuals, who may take on multiple roles or
share a role. Roles in PRINCE2 are structured in four levels (corporate or programme management, project
board, project manager level and team level).
5. Manage by stages: the project is planned and controlled on a stage by stage basis. Moving between stages
includes updating the business case, risks, overall plan, and detailed next-stage plan in the light of new evidence.
6. Focus on products: each work package is defined by one or more deliverable products, preferably with
tolerances to time, cost, scope and quality quantified in advance. Even management activities such as stage
planning are defined by their final output, such as a physical report containing the new stage plan. This allows all
parties to clearly specify what is required, and to allocate responsibility for delivering and controlling it.
7. Tailor to suit project environment: PRINCE2 should not be applied in a dogmatic form, but tailored to specific
projects. Formal reports and project documents may be replaced by informal verbal or email equivalents, the
structure of the project board and management team may be altered to reflect the goals of the project, multiple
roles may be assigned to individuals on smaller projects, and increased emphasis may be placed on stage
replanning for research-intensive projects which may need to change directions as new findings are delivered.
Not every aspect of PRINCE2 will be applicable to every project, thus every process has a note on scalability. This
provides guidance to the project manager (and others involved in the project) as to how much of the process to apply.
The positive aspect of this is that PRINCE2 can be tailored to the needs of a particular project. The negative aspect is
that many of the essential elements of PRINCE2 can be omitted sometimes resulting in a PINO project – Prince in
Name Only.

Integration with other techniques


The 26 Management Products described by PRINCE2 are only used for the "high-level" management of the project.
Within its tasks, task managers must still decide on their own project management framework. Some suggestions
given in the PRINCE2 manual are product based planning, change control, quality review technique, Gantt charts,
PERT charts and critical path analysis.

PRINCE2 can also be used to manage projects that use agile software development methods.[10]

Quality review technique


The quality review technique ensures a project's products are of the required standard (i.e. meet defined quality
criteria). This takes place in a quality review meeting, which identifies errors in the product. The quality review
meeting will not attempt to solve the problems it identifies. The meeting brings together people who have an interest
in the project's outputs (or products) and people on the project team able to address issues identified.

Training and Certifications


PRINCE2 certifications, awarded by AXELOS, require the user to undertake a training course with an Accredited
Training Organization (ATO) followed by an exam. The training and exam may be online or in person.[11] AXELOS
requires that any organisation providing official PRINCE2 training must go through an accreditation process in order
to validate the quality of the course content and delivery. Once approved, the organisation can use the title Accredited
Training Organisation (ATO)[12]. Trainers must be re-accredited every 3 years and undergo a surveillance check every
12 months.[13]

There are four levels of certifications for PRINCE2: [14]

1. PRINCE2® 2017 Foundation: confirms the holder has sufficient knowledge and understanding of the PRINCE2
method to be able to work in a project management team working with this method.
2. PRINCE2® 2017 Practitioner: confirms the holder has achieved sufficient understanding of how to apply
PRINCE2 in a scenario situation and will, with suitable direction, be able to start applying the method to a real
project. Qualified PRINCE2 Practitioners who go on to study for the APMP qualification of the Association for
Project Management (APM) are exempt from certain topics of the syllabus that are covered in the PRINCE2
Practitioner qualification.[15]
3. PRINCE2® Agile Foundation: was released in June 2018 and confirms the holder has sufficient knowledge and
understanding of the PRINCE2 method and agile way of working and how agile can be combined to PRINCE2.
4. PRINCE2® Agile Practitioner: confirms the holder is able to apply the project management principles of
PRINCE2 whilst combining agile concepts such as Scrum and Kanban.
AXELOS publishes a successful candidate register which can be searched on the web.[16]

Advantages and criticisms


PRINCE2 provides a method for managing projects within a clearly defined framework, but project management is a
complex discipline and using such a framework is no guarantee of a successful project.

Some of the advertised benefits of PRINCE2 are: increased quality of the finished products, efficient control of
resources, avoidance of either "heroic" (under-regulated) or "mechanistic" (over-regulated) working, and increased
confidence among the project team.

PRINCE2 is sometimes considered inappropriate for small projects or where requirements are expected to change,
due to the work required in creating and maintaining documents, logs and lists. The deliverable structure may also
lead to focus on producing deliverables for their own sake, to "tick the boxes" rather than do more useful work.

The general response of PRINCE2's authors to criticism has been to point out that the methodology is scalable and can
be tailored to suit the specific requirements and constraints of the project and the environment.[17] This strong
emphasis on tailoring has led some users to complain that PRINCE2 is unfalsifiable, i.e. it is impossible to tell whether
PRINCE2 "works" or constitutes "best practice" if any problems encountered with a project can be blamed on
inappropriate application of PRINCE2 rather than on PRINCE2 itself.

The experiences of the Blair administration in the UK between 1997 and 2007 (and of subsequent UK governments)
arguably undermine PRINCE2's claim to be "best practice", given the string of high-profile failed IT projects charged
to the taxpayer during that time,[18][19][20] and the controversy surrounding the financial relationship between the
Blair government and PRINCE2's co-owners Capita.[21][22] PRINCE2's training material addresses these failures,
blaming them on inappropriate tailoring of PRINCE2 to the project environment, and advocating for more PRINCE2
training for government project managers to solve the problem.

Differences from PMP


Project Management Professional (PMP) may be seen as a competitor of PRINCE2. In general, UK, Australia and
Europe prefer PRINCE2, and the USA and American countries prefer PMP. Asia, Africa and the Middle East area have
no strong preference for PMP or PRINCE2.[23] The important thing is that PMP (PMBOK) can be used with PRINCE2
[24]
PRINCE2 and PMP acknowledge each other's existence in their advertising material and attempt to position
themselves as complementary products – PRINCE2 as a "methodology"[25] and PMP as a "standard"[26] – which can
be used alongside each other. In practice, companies and practitioners choose one system or both depending on the
project environment, their geographical location and costs involved.

See also
Agile software development
Comparison of project-management software
Gantt chart
List of project management topics
Project Management Institute (PMI)
Project Management Professional (PMP)
Work breakdown structure

References
1. "What is PRINCE2®?" (https://www.axelos.com/best-practice-solutions/prince2/what-is-prince2). AXELOS.
Retrieved 1 February 2017.
2. PRINCE2® - PRojects IN Controlled Environments - Consulting Organisations List (http://www.prince-officialsite.c
om/ConsultingOrganisations/ConsultingOrganisationsList.asp)
3. "PRINCE2 STUDY Guide) ® Handbook" (https://books.google.com.au/books?id=lVVf-qoDZiUC&pg=PT16&lpg=P
T16&dq=prince2+delivered+in+17+language&source=bl&ots=rJXFHRdR1a&sig=9sr2I2h6IQAoZ0Zt59_iIKC1Sjc&
hl=en&sa=X&ved=0ahUKEwjf6qeapovYAhUIVbwKHVPQCVYQ6AEIcjAJ#v=onepage&q=prince2%20delivered%
20in%2017%20language&f=false) (PDF). Project Management Institute. Retrieved Dec 15, 2017.
4. Reid, Amy (2013-07-30). "Capita acquires majority stake in ITIL and PRINCE2" (https://www.apm.org.uk/news/ca
pita-acquires-majority-stake-itil-and-prince2). Association for project management. International project
management association. Retrieved 2016-02-22. "AXELOS has been revealed as the name of the new joint
venture between Capita and the Cabinet Office set up to manage the best management practice training tools
and accreditations, including PRINCE2, and ITIL. [...] Capita and the Cabinet Office have established a 51:49 per
cent stake in the new organisation that will own the intellectual property (IP) of this portfolio of products [...]"
5. OGC - PRINCE2 - News (http://www.best-management-practice.com/officialsite.asp?FO=1325692)
6. "OGC brings its shining quartet back into the limelight" (http://www.ogc.gov.uk/news_2005_4333.asp) (Press
release). Office of Government Commerce. 2005-12-14.
7. Official PRINCE2 website (http://www.prince-officialsite.com/)
8. "Introducing the PRINCE2 2017 Update" (https://www.axelos.com/prince2-2017) (Press release). Axelos. 2017-
12-11.
9. PRINCE2 manual
10. "PRINCE2® Agile" (https://www.axelos.com/best-practice-solutions/prince2/prince2-agile). www.axelos.com.
Axelos. Retrieved 6 March 2015.
11. [1] (https://www.axelos.com/qualifications/prince2-qualifications)
12. Find an Accredited Provider (https://www.axelos.com/find-a-training-provider)
13. - PRINCE2 accreditation scheme (http://www.prince-officialsite.com/accreditation/accreditationscheme.aspx)
14. PRINCE2 2017 update from AXELOS (https://www.axelos.com/certifications/prince2)
15. "- APMP for PRINCE2 Practitioners" (https://web.archive.org/web/20131101111918/http://www.apm.org.uk/APMP
2). Archived from the original (http://www.apm.org.uk/APMP2) on 1 November 2013. Retrieved 30 October 2013.
16. AXELOS Successful Candidates Register (https://www.axelos.com/successful-candidates-register)
17. OGC Best Management Practice - PRINCE2 (http://www.best-management-practice.com/Knowledge-Centre/Best
-Practice-Guidance/PRINCE2/)
18. "The Blair IT projects" (http://www.zdnet.com/article/the-blair-it-projects/). ZDNet.com.
19. The Blunders of our Governments. 2013. ISBN 978-1780742663.
20. "The costly trail of British government IT and 'big bang' project disasters" (https://www.theguardian.com/technolog
y/2014/aug/19/costly-trail-british-government-it-disasters-universal-credit). theguardian.com.
21. "Blair avoids MPs' questions on Capita" (https://www.telegraph.co.uk/finance/2935817/Blair-avoids-MPs-question
s-on-Capita.html). Telegraph.co.uk.
22. "Capita chairman quits after criticism of loans to Labour" (https://www.theguardian.com/politics/2006/mar/24/uk.pa
rtyfunding). theguardian.com.
23. "PRINCE2 vs PMP Certification 8 Important Differences" (https://www.educba.com/prince2-vs-pmp-certification/).
www.educba.com. Retrieved 7 December 2017.
24. "PRINCE2 with PMBOK" (https://athem.net.br/prince2-com-pmbok/). www.athem.net.br. Retrieved 6 July 2018.
25. </ "what-is-prince2" (https://www.prince2.com/uk/what-is-prince2). www.prince2.com. Retrieved 7 December
2017.
26. "Project Management Professional (PMP) ® Handbook" (http://www.pmi.org/certification/~/media/pdf/certification
s/pdc_pmphandbook.ashx) (PDF). Project Management Institute. Retrieved September 18, 2009.

External links
Official website (https://www.axelos.com/best-practice-solutions/prince2)
Guidelines for Managing Projects (fully consistent with PRINCE2) (http://webarchive.nationalarchives.gov.uk/2009
0609003228/http://www.berr.gov.uk/files/file40647.pdf) from the UK Department for Business, Enterprise and
Regulatory Reform (BERR)

Retrieved from "https://en.wikipedia.org/w/index.php?title=PRINCE2&oldid=861246548"

This page was last edited on 26 September 2018, at 03:31 (UTC).

Text is available under the Creative Commons Attribution-ShareAlike License; additional terms may apply. By using
this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia
Foundation, Inc., a non-profit organization.