Beruflich Dokumente
Kultur Dokumente
DOCUMENT TITLE
TECHNICAL SPECIFICATION
FOR
GSS END ERECTION, TESTING,
COMMISSIONING (ETC) WORK
DOCUMENT NO.
ACME-KR3-00-EE-224-TS-001
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 1
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
st
00 16-05-18 1 Issue MKG SP
HOD
CV EL INST.
Engg.
Rev Date Description
Checked App. by
Approved : 16-05-18 SP
PROPERTY AND CONFIDENTIAL THE INFORMATION CONTAINED IN THIS DRAWING ARE THE SOLE PROPERTY OF ACME. ANY
REPRODUCTION, IN PART OR AS A WHOLE, WITHOUT THE WRITTEN PERMISSION OF ACME IS PROHIBITED.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 2
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
CONTENTS
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 3
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 4
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
ACME Cleantech Solutions Pvt. Ltd., one of the leading Solar Power
companies in India. ACME is planning to develop 15MW & 20MW Solar
PV Power Plant in Karnataka state.
6-Sites, 15MW & 20MW each 3 Nos, Solar PV Power shall be designed for
life span of 25 years & it shall be commissioned in different locations with
105MW capacity.
2. PROJECT DETAILS
MW Substation
Sl No. District Taluka Substation Name
Capacity Coordinate
110/33/11kV 16.065523,
1 Bagalkot 15MW Guledgudda
Guledgudda 75.808401
110/33/11kV 16.253200,
2 Belagavi 15MW Hukkeri
Sankeshwar 74.499980
110/33/11kV M K 15.682871,
3 Belagavi 15MW Kittur
Hubli 74.715703
14.927778,
4 Ballari 20MW Sandur 66/11kV Choranuru
76.527512
220/66 kV Kudligi 14.862772,
5 Ballari 20MW Kudligi
SS 76.357528
13.473652,
6 Chkkaballapura 20MW Sidlaghatta 66/11kV Pallicherlu
77.904364
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 5
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
3. INTENT OF SPECIFICATION
M/s ACME Cleantech Energy Solutions Pvt. Ltd. is going to set up 105 MW
Solar PV Power Plants at in the State of Karnataka. The locations of the
plant GSS End Sub-Stations are as mentioned above.
Complete Liasoning pertaining to Bay End Works shall be in the scope of the
Contractor.
Any other miscellaneous electrical work/ item required for completion and
handing over of complete Bay shall be in bidder’s scope.
a) Bidder shall prepare and submit the complete set of drawings &
documents required to be approved by KPTCL. Coordination with
KPTCL for approval of drawings will also be in bidder’s scope.
b) Any manufacturing done prior to the approval of drawings/data shall be
rectified in accordance with the approved drawings/ data by the
contractor at his own cost and the equipment shall be supplied within
the stipulated period.
4. SCOPE
This Specification provides for collection of the materials supplied by the
employer from employer's stores, procurement and supply of balance
materials to complete the work, transport of all materials to site, execution of
civil works in the switchyard, construction of control house/extension if
applicable, erection of structures, bus-bars, Bus extension, equipments in
Feeder Bay and control room etc. setting to work and for performance
guarantee of bay extensions. The contractor shall execute the works to the
extent required to complete the work as a whole for Substation/Bay.
Preparation of all required Bay end drawings & their approval from KPTCL
will also be in Bidder’s scope. Any Liasoning pertaining to Bay end shall be in
the scope of the contractor.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 6
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Detailed BOQ for supply & services scope of Contractor has been attached
with this specification.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 7
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
5.2 All electrical equipment shall also conform to the latest Electricity
rules as regards safety and other essential provisions
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 8
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Design classes for indoor enclosed switchgear and control gear for
IEC 62271-304 rated voltages above 1 kV up to and including 52 KV to be used in
severe climatic conditions
IS: 2208 HRC cartridge fuse links for voltage upto 650V.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 9
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
IS 432(Part-1& Mild steel and medium tensile steel bars and hard drawn steel wire for
Part-2)/1982 concrete reinforcement
Technical supply conditions for threaded steel fasteners - Product
IS 1367 (part II)
grade and tolerances
IS 1363 (part III) Hexagon Nuts(size range M5 to M64)
IS 3063/1994 Fastners - single coil rectangular section spring washers
IS2629/1985 Recommended practice for Hot dip galvanizing on Iron & Steel
IS4759/1984 Hot dip Zinc coatings on structural steel and allied products
IS486(Part-I)/ Metal fittings of Insulators for overhead power lines with normal
1993 voltage greater than 1000V - General requirements & Tests
IS2486(Part-2)/ Insulator fittings for overhead power lines with a nominal voltage
1989 greater than 1000V - Dimensional requirements
IS4984 P.V.C. Pipes
Also, all parts of fittings shall be suitable for use in atmospheric condition
indicated elsewhere in the specification inherently resistant to atmospheric
corrosion or be suitably protected against corrosion both during storage and in
service. The connector shall be capable of withstanding dynamic and thermal
stresses without any damage or deterioration.
Unless otherwise specified works shall be carried out in accordance with the
Indian Electricity Act. 1910, Indian Electricity Rules 1956 or any other revisions
thereof which may be issued during the currency of the contract and the
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 10
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
requirements of any other regulations and Acts in India to which the employer
may be subjected to.
The contractor himself has to arrange for the permits required for the operation
of the vehicles used in construction works and such other permits not being
arranged by the employer/Engineer.
On completion of works all materials left surplus from those supplied by the
employer under the contract for erection shall be handed over to the employer
at the employer's stores in good condition. The contractor shall furnish a
statement giving full details of all materials received from the employer,
quantities utilized on works (based on the drawings given to him) and the
balance returned to the employer and obtain a clearance certificate from the
Executive Engineer, within one month after completion and handing over of
the substation/bay extension. It may be noted that returning of all materials
and rendering of accounts for the materials received is a pre-condition for
release of payment against final bill and also the deposit towards performance
at a later date.
8.2
[
REPLACEMENT
In the event of the material handed over to the contractor for the execution of
this contract being lost, damaged or destroyed while being in the custody of
the contractor before being taken over by the employer, the contractor shall be
liable to make good the loss. In case the contractor fails to return the balance
surplus materials, the cost of materials will be recovered from the contractor’s
bills in accordance with the provisions in employer's Commercial Accounts
Manual.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 11
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The requisite quantities of materials specified in the detailed BOQ required for
the completion of sub-station/bay extensions will be handed over to contractor
at the Employer's stores indicated, progressively based on the program of the
contractor and the actual progress obtained. If additional quantities of
materials (in excess of those to be issued as per contract) become necessary
due to damage or loss on account of mishandling and negligence of the
contractor to complete the work, the contractor shall requisition such quantities
duly explaining the circumstances under which the additional quantity has
become necessary. Such materials shall be issued by the Engineer only on
the written requisition from the contractor and the costs of such materials
calculated in accordance with the provisions in employers Commercial
Accounts Manual, will be recovered from the payments to be made to the
contractor. The contractor will be responsible for the proper handling and
maintenance of the materials from the time of receipt by him up to the time of
handing over of the completed works to the employer and return of surplus
material if any, at the employer's stores. The cost of such handling and storage
shall be covered in the quoted prices detailed in bill of quantities. On
completion of the works all surplus materials shall be handed over to the
engineer at the employer's stores. This shall be done with in a maximum
period of one month after completion and handing over of the sub-station/bay
extension works. If the materials are not returned with in this period and/or in
the opinion of the engineer are not in a fit condition for use, such surplus
materials will be treated as sold to the contractor at the rate calculated in
accordance with the provisions in employer’s commercial accounts manual
and recoveries made accordingly. The retention amount against the contract
will be released only after all the balance materials are handed over at
employer's stores in proper shape and material accounts are rendered.
8.4.1 The quantities indicated in the schedule of the prices are only
provisional and are likely to change during actual execution. When
quantities of work of any item are likely to exceed the scheduled
quantity, the Contractor shall bring the fact to the notice of ACME &
Construction three weeks in advance and take orders for going ahead
with the work. Without approval of this office, the Contractor shall not
go ahead with the work wherever there is increase in quantities.
8.4.2 The contractor is bound to execute all supplemental items that are
found essential, incidental and inevitable during execution of main
works, at the rates to be worked out as detailed below:
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 12
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Similar items the rates for which cannot be directly deduced from
the original agreement.
Purely new item which do not correspond to / any item in
the agreement. The rate shall be estimate rate plus or minus
overall tender percentage.
NOTE : The term estimate rate used in (i) and (ii) above means the rate
corresponding to the respective item in the sanctioned estimate
whose value is shown in the Schedule – A while calling for the tenders
for the work
or if no such rate is available in the estimate, the rate derived
with reference to the schedule of rates adopted in the sanctioned
estimate.
8.4.7 If the new item is in substitution of an old item which allowed for
importation of labour, labour amenities, dewatering etc. Those factors
may be taken into account in computing the substituted items also at
the same rates at which they were originally provided.
In respect of the new items the case has to be considered on its merits
and provision for importation of labour, labour amenities, dewatering
etc., has to be fully justified.
During construction the contractor shall keep the work site and storage area
used by him free from accumulation of waste materials or rubbish and before
completing the works the contractor shall, at his own cost, remove or dispose
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 13
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
[ The successful bidder shall establish a temporary store at his cost at the
sub-station site for storing cement, equipment such as panels etc. This store
should be dismantled and site cleared after the work is completed by him.
[[
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 14
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The bidder is expected to familiarize with the site conditions and facilities
available before quoting. Water supply and electric power supply
arrangements shall be in Contractors scope
12. LEVELLING:
surplus earth left over after back filling structure foundations. If surplus earth is
not adequate for levelling, the levelling should be done by excavating earth in
any portion of substation site whatever type of soil is met with and filling should
be done with such earth for levelling switchyard. If this is not sufficient, the
switchyard is to be leveled by supplying gravel from the approved borrowed
areas. Clearing of the entire site by removing bushes, hedges, unwanted plant
growth and other things are in the scope of levelling work. The work shall be
carried out as per IS 301,302 and 138.
13. COMPACTION:
Anti weed treatment and anti termite treatment for excavation in the site shall
be done as per KPTCL Technical Specification.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 15
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The anti weed treatment should be given only after moisture content of the soil is
brought below 29%. After completion of spraying of the anti-weed chemicals and
before taking up the next activity, a period of 24 hours should be allowed for
penetration of the chemical in to the soil.
14.2.1 SCOPE:
The scope of work is to be set up a chemical barrier against attack
by subterranean termites in the areas like cable trenches etc.
14.2.2 GENERAL:
All work shall in general be executed as specified in IS:6313 part -II
and as per approved specification of the agency having special know-
how for the job. All necessary work to ensure uniform distribution and
proper penetration of treating solution shall be done according to the
instructions of the Engineer. Soil treatment shall not be done when it
is raining or when the soil is wet with rain or sub soil water. Once
formed, the treated soil barrier shall not be distributed.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 16
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
14.2.7 I.S. CODE: Relevant code applicable for this specification: IS:6316
(part-II)- 1971: Code of practice for Anti-termite measures in building.
The work involves spreading of 20 mm HBG metal for 100 mm thick in switch
yard by providing suitable PCC gauge blocks of 100mmX100mm size and 100
mm depth at 2mX2m intervals. Kerb wall of size 400x75x300 mm in RCC (1:2:4)
shall be buried in the ground upto 100mm deep. The joints shall be filled with CM
(1:3) and Kerb wall shall be provided in the switchyard to retain the metal all
along the periphery of the metal spreading wherever it is required. The Kerb wall
shall be plastered in CM (1:3) and painted with 2 coats of Janata Cem. Before
spreading the HBG metal, care shall be taken to remove all the vegetation and
roots of the plant. The trimming of the earth surface for perfect level ground
should be carried out and the surface should be watered and rammed for
consolidation with suitable means and the earth surface should be given
chemical treatment for anti-vegetation growth.
Required metal quantity may be stacked at suitable area for easy handling for
pre- measurement. Higher size metal may be separated and removed from the
stacks. The crushed metal shall be free from dust. HBG metal shall be brought
from the approved Quarry as directed by Engineer-in-charge and samples of the
HBG metal to be used may be shown to the Engineer in-charge and prior
approval of the engineer shall be taken before use. Spreading should be carried
out by dumping the metal at lower heights.
SCOPE :
The contractor shall furnish all labour, materials, tools and plants and equipment
necessary for complete installation of permanent storm water drainage system
and sewage disposal system.
These shall be as per drawing for structure foundations and as per the
Technical specifications for excavation, CC/RCC, Back filling etc. The scope of
work is detailed here under.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 17
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Earth excavation has to be done in all types of soils which can be excavated
with pick axe & crow bars in all conditions such as dry, wet, slushy etc., and in
hard rock requiring blasting including shoring, shuttering and dewatering
wherever necessary covering initial lead and lift. Back filling the foundations
with excavated earth after laying the foundations.
The rock obtained during excavation is the Board’s property and it shall not be
used under any circumstances by the contractor. Rock excavated shall be
stacked by the successful tenderer at a convenient place within the Substation
switchyard as directed by the Engineer-in-charge at no extra cost.
[[[[ Laying foundation for main and auxiliary structures, transformer plinths etc.,
including dewatering the pits before and during the process of laying concrete
in the proportion of RCC 1:2:4 using 20mm HBG metal and CC 1:4:8 using
40mm HBG metal as per the drawings for structural foundations enclosed to
the specification and curing for 14 days including cost of cement,
reinforcement steel.
17.3 CEMENT
17.4 REINFORCEMENT
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 18
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
17.5
[[[
BACK FILLING:
After completion of foundation, footings and walls and other construction below
the elevation of the final grades and prior to back filling, all forms of temporary
shoring, timber, etc., shall be removed and the excavation cleaned of all trash,
debris and perishable materials. Back filling shall begin only with the approval
of the Engineer- in charge. Back filling shall be done with inorganic materials
obtained from the excavation of borrow pits, if suitable, and subject to the
approval of the Board's Engineer-in-charge. Back fill shall not be dropped
directly upon or against any structure or facility where there is danger of
displacement or damage. Backfill shall be placed in horizontal layers not to
exceed 60 cm. in thickness. Each layer shall be compacted with proper
moisture content and with such equipment as may be required to obtain a
density equal to or greater than 95% of maximum as determined by the
relevant Indian Standards. Trucks or heavy equipment for depositing or
compacting back-fill shall not be used within 1.5 m of the
foundation/structures, or other facilities which may damage by their weight or
operation. The methods of compaction shall be subject to approval of the
Engineer-in- charge. Backfill adjacent to pipes shall be hand placed free of
stones, concrete, etc., compacted uniformly on both sides of the pipe and
where practicable, to a depth of 300 mm over the top of pipes, when tampering
around piping care should be taken to avoid unequal pressures.
17.6 PLASTERING:
Plastering foundation plinths 12mm thick in (1:3) cement mortar and white
washing (two coats) with Janatacem cement paint. All projections of plinths
and masonry above ground level shall also be provided with Janatacem
cement paint.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 19
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
structures shall be done after their approval. The structural drawings & bill of
material will be issued by the Board. The technical specifications for
procurement of steel, fabrication and galvanisation of structures shall be as
per KPTCL. Galvanised bolts, nuts, pack and spring washers required for the
assembly of the fabricated pieces to form into a composite structure of
standard quality shall be supplied by the contractor. The 'U' bolts for Bus
stringing and foundation bolts for main and/or auxiliary structures are also to
be procured, supplied, fabricated and galvanised by the contractor. The
Galvanised nuts required for these bolts are also to be procured and supplied
by the contractor.
18.1 STEEL:
Procurement of steel, such as MS angles, plates, channels, RS Joists, MS
rounds foundation bolts and earthing electrodes etc, required for fabrication
of structures and reinforcement steel for structural foundations are within the
scope of contract. The following provisions shall apply in connection with the
procurement of steel by the tenderer.
b) The tenderer shall take into account the fabrication wastage while quoting
the rate. The Board will not accept any liability in connection with the wastage
of steel during fabrication or otherwise.
d) The steel shall be procured exclusively from the main steel producers
approved by the employer. However, sections not rolled by main producers
can be procured from re-rollers approved by the employer provided that
Re-rolling of structural steel sections is done from billets/ingots of tested
quality & Re-rolled sections are duly tested as per relevant standards.
e) Bolts, Nuts and Spring washers are under the scope of contract and these
shall be procured from approved suppliers of the Employer. The bolts and nuts
shall conform to the following Standards.
The bolts shall conform to IS-12427/1988 and its latest revision if any. The
bolts shall be of product grade C as specified in IS:1367(Part-2) 1979.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 20
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
iii) The nuts to be used for the above bolts shall conform to the requirements
of IS-1363 (Part-3) 1984. The nuts shall be of a property class 5 as specified
in IS-1367 (Part-6) 1980. The proof stress value shall be as follows:
M 16 490
M 20 500
The bolts shall be of property class 5.6 as specified in IS-1367 (Part-3) 1979.
The bolts and nuts shall be hot dip galvanized in accordance with the
requirement of IS-1367 (Part-3) 1983.
18.3 GALVANISING :
All members of structures and special structures "U" bolts etc shall be hot dip
galvanised. Stubs and foundation bolts shall also be hot dip galvanised upto
one third length of stub and foundation bolts from top.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 21
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
and metal nodules and there shall be no clogging of bolt holes due to the stay
of zinc in the holes after galvanising.
18.4 MARKING:
Each part of steel structure shall be clearly stamped with 20mm steel stamping
die with identification number mark or symbol to facilitate erection
corresponding to those shown in erection drawings. These marks shall be
applied before painting/galvanising and shall be clearly visible after painting.
Galvanised bolts and nuts and plain spring washers required for the
assembly of the fabricated pieces to form into a composite structure of
standard quality shall be supplied by the Contractor. The U-Bolts for stringing
and foundation bolts for main and auxiliary structures are however to be
fabricated and supplied by the tenderer. The required MS rounds for U-bolts
and foundation bolts shall be procured by the tenderer. The fabrication of
U-bolts and foundation bolts will be under the fabrication item. The nuts
required for these bolts shall be procured by the tenderer.
18.6 PACKING:
The materials shall be packed in bundles securely wrapped four times around
at each end with No.9 SWG wire with ends twisted as per the practice of latest
ISS.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 22
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
in a horizontal position and not erected vertically. For the check assembly,
bolts and nuts shall be no more than finger tight.
The weight of structures as per bills of materials will be considered for the
payment of supply, fabrication, galvanisation and erection bills. If the designed
steel section is not available, higher section shall be used only after obtaining
prior approval from the Board. In case of such approvals the cost of supply,
fabrication, galvanisation and erection for extra weight shall be borne by the
Bidder.
19.1 All support insulators, circuit breaker interrupters and other fragile equipment
shall preferably be handled with cranes having suitable booms and handling
capacity.
19.2 The slings shall be of sufficient length to avoid any damage to insulator due to
excessive swing scratching by sling ropes etc.,
19.3 Handling equipment, sling ropes etc., should be tested periodically before
erection for strength.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 23
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
19.4 Bending of compressed air piping if any should be done by a bending machine
and through cold bending only. Bending shall be such that inner diameter of pipe
is not reduced.
19.5 Cutting of the pipes wherever required shall be such as to avoid flaring of the
ends. Hence only a proper pipe cutting tool shall be used. Hacksaw shall not be
used.
19.6 Muslin or leather cloth shall be used for cleaning the inside and outside of hollow
insulators.
19.7 All the equipment, instruments and auxiliaries required for testing and
commissioning of equipment shall be arranged at site by the contractor.
19.8 STORAGE
The contractor shall provide and construct adequate storage shed for proper
storage of equipments, where sensitive equipments shall be stored indoors. All
equipments during storage shall be protected against damage due to acts of
nature or accidents.
The storage instructions of the equipment manufacturer/owner shall be strictly adhere to.
20.1 The 110 kV bus will be formed with single/Twin/ Quadruple Drake conductor and
shall be strung to required tension as per site Engineer's direction and as per
switchyard layout drawing.
20.2 The stringing of bus conductors covers installation of tension insulator strings,
suspension insulator strings, post type insulator stacks and other accessories
alongwith tensioning of conductor and clamps.The jumpering to various
equipment and the ground wire stringing are also under the scope of this work.
The G.I. Ground wire shall be strung as detailed in the layout drawing.
20.3 The insulator strings shall be assembled on the ground. These shall be cleaned,
and examined before hoisting. All the parts including current carrying parts shall
be clean without grease, paint and dirt. Insulators with cracks or chips or those
having glazing defects exceeding 0.5 Sq. Cm shall not be used.
20.4 The sag of bus conductor shall not be more than 1%. Damaged conductors shall
not be used. No joints are to be made. The conductor surface shall be clean and
smooth without any projections, sharp points, cuts or abrasions, etc., and the
conductor shall be continuous in span.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 24
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
21.1 Cabling shall be on cable racks, in built-up trenches, vertical shafts, excavated
trenches for direct burial pulled through pipes and conduits laid in concrete ducts,
run bare and clamped on wall/ceiling/steel structures etc. The contractor shall
route these as directed by the owner.
This section covers laying of cables, in cable trenches, cable ducts in switch
yard, control room etc, cable jointing, termination at both ends and testing of the
complete cable installation. At the existing substations where there is no cable
duct in the switchyard the cables shall be buried in the sand in the ground after
digging trenches of 300mm deep,300mm width and these trenches shall be filled
with sand. The trench shall be levelled to the formation level of the yard. The
cable route length is indicated in the annexure to the schedule of quantities. The
cable route is to be marked at regular intervals of 10M by providing cable route
marking pegs.
21.2 The control cables will be copper wires of 2.5 sq.mm with number of cores being
2,4,6,10 or 12 and sizes specified by KPTCL. Aluminum cables (2,4,6 cores ) of
4 sq.mm shall be used as per the directions. Three and half core aluminum
power cable shall be used for yard lighting and A.C. Supply to equipment. Co-
axial cable supplied by the employer for PLCC has to be laid.
21.3 The cable schedules will be provided to the contractor by the Engineer. The
cable laying shall be done strictly in accordance with these schedules. The length
of each cable issued shall be judiciously cut minimizing the wastage as per
approval of Engineer.
21.4 All the electric equipment is to be set in place and aligned. Contractor shall
provide power and auxiliary connection to the equipment and shall work in
cooperation with suppliers representative in obtaining correct direction of rotation
and commissioning of the equipment. Cable laying shall also include termination
of cables i.e. at both ends of cable of equipment switchgear, control and
protection panels, etc., as well as equipment to marshalling boxes and
marshalling boxes to switchgear panels.
21.6 Double compression cable glands and Cable lugs shall be provided by the
contractor. Dressing/bunching of all individual cores of the cables shall be done
in a neat fashion. The contractor shall drill holes suitable for the cables in cable
gland plate.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 25
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
21.7 Cable lugs shall be compressed on the conductor ends by means of tools.
Insulating sleeves shall be furnished and covered over the bare ends of the
connections so as to prevent accidental contact with the ground or with the
adjacent terminals.
21.8 The insulating sleeve shall be fire resistant, and long enough to over pass the
conductor insulation and shall be of correct size of the conductor used.
21.9 Cables entering the control room from out door areas shall be sealed. Spare
glands shall be sealed for control panels and some marshalling boxes.
21.10 Standard cable grips and seals shall be utilised for cable pulling after pulling
cable, the contractor shall put and attach aluminum cable markers at both
ends of the cables and at the control room entry. The cable number and other
data shall be punched and the cable markers are to be securely attached to the
cables.
21.11 Normally cable shall not be jointed for deviation, the approval of the Engineer
shall be taken.
21.13 Cables shall cross control room basement wall in 4" R.C.C. Hume Pipe
embedded in cement concrete in basement wall. Supply of 4" R.C.C. Hume
Pipes is in the scope of contract.
21.14 In each cable run some extra length shall be kept at a suitable point to enable
one or two straight through joints to be made, should the cable develop fault at a
later date.
21.15 The contractor shall pull sufficient lengths of each cable to permit neat
arrangement of all cables. Cables should be extend above the glands for 10 to
15 cms and identification should be tied up to the cable. Cables coming out from
marshalling boxes should be supported by mesh tray and tied up with nylon
ropes.
21.16 Cable splices shall not be permitted except where called for or where permitted
by the purchaser.
21.17 At cable terminal points where the conductor and cable insulation will be
terminated, termination shall be made in a neat, workman like and approved
manner by men specialised in this class of work.
21.18 Before any cable terminal connections are made, conductor's insulation shall
be pulled out, at the end and identifying ferrules shall be fixed according to
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 26
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
the wiring diagrams. Connection shall be made according to the wiring diagram
to be supplied by the purchaser.
21.19 Polarity, or phasing shall be checked before connections are made and
corrections of polarity, phasing or rotation shall be made by the contractor
without additional cost.
21.20 Control cable terminations shall be made in accordance with wiring diagram
using colour codes established by the purchaser for the various control circuits,
by code marked wiring diagrams furnished to the contractor for this purpose or
any other approved means of identification. It is the intent that the contractor
shall terminate the cable which he installs.
21.21 Additional work of testing and reconnecting where leads have been brought by
the contractor to the terminal boards and connected, but where on further
testing, reversed or other rearrangement of load turns out to be necessary
shall be performed by the contractor without additional cost.
21.22 Any cable cut short shall be replaced and installed by the contractor at his
expense.
21.23 Jointing of cables shall be in accordance with Indian Standard codes. The
manufacturers special instructions on materials and tools required for cable
jointing work shall be arranged by the contractor.
21.24 Metal sheath and armour of the cable shall be binded to the earthing system of
the station by a steel strip wire. Bending the metal sheaths of single core cables
in close threefold formation shall be as stipulated in the relevant codes of
practices.
21.25 The contractor shall fabricate and install mounting arrangements for the support
and installation of all the cables on angles in the trenches. These mounting
structures/cable racks shall be fabricated from structural steel members
(channels, angles and flats) of the required size. The fabrication, welding and
erection of these structures shall conform to the relevant clauses of chapter –
structures, in addition to the specification given herein.
Cable racks and supports shall be painted after installation with two coats of
metal primer (comprising of red oxide and zinc chromate in a synthetic medium)
followed by two finishing coats of aluminum paint. The red oxide and zinc
chromate shall conform to IS: 2074. All welding works inclusive of the
consumables required for fabrication and installation shall be in the scope of the
contractor.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 27
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
21.26 All interpole cables (both power and control) for all equipment, shall be laid in
cable trenches conduit pipes of FB 50/100 mm diameter, class medium as per IS
: 1239/part – I and IS : 4736 which shall be buried in the ground at a depth of 250
mm. The interpole cabling piping of breakers shall be laid in cable trenches. The
scope shall include all labour, material, equipment for transporting, laying,
burying etc., including required bends and end seals
Cables shall be generally located adjoining the electrical equipment through the
pipe insert embedded in the floor, In the cable of equipments located away from
cable trench either pipe inserts shall be embedded in the floor connecting the
cable trench and the equipment on incase the distance is small, notch/opening
on the floor shall be provided. In all these cases necessary bending radius as
recommended by the cable contractor shall be maintained. Cabling in the control
room shall done on ladder type cable trays.
21.27 Cables from the equipment to trench shall run in conduits. Necessary conduits of
adequate size and length shall be supplied and installed by the contractor.
Flexible conduit should be used between fixed conduit/cable trays (perforated
type) and equipment terminal boxes, where vibrations are anticipated. The
flexible conduit shall be as per the relevant IS.
21.28 Power and control cables shall be laid in separate tires. The order of laying of
various cables shall be as follows for cables other than directly buried.
Power cables on top tires.
Control instrumentation and other service cables in bottom tires.
21.29 Single core cables in trefoil formation shall be laid with a distance of three times
the diameter of cable between trefoil centre lines. All power cables shall be laid
with a minimum centre to centre distance equal to twice the diameter of the
cable.
21.30 Trefoil clamps for single core cables shall be of pressure die cast aluminum
(LNP-6) Nylon – 6 or fibre glass and shall include necessary fixing GI nuts, bolts,
washer etc., these are required at every 2 meter of cable runs.
21.31 Power and control cables shall be securely fixed to the trays/supports with self
locking type nylon ties with de-interlocking facility at every 5 meter interval for
horizontal run. Vertical and inclined cable runs shall be secured with 2.5 mm
wide and 2 mm thick aluminum strip clamps at every 2 m.
21.32 Cables shall not be bent below the minimum permissible limit. The permissible
limits are as follows:
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 28
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
21.34 Where cables cross roads, drains and rails tracks, these shall be laid in
reinforced spua concrete or steel pipes buried at not less than one meter depth.
21.35 In each run some extra length shall be kept at a suitable point to cable one (for
LT cables)/two (for HT cables) straight through joints to be made in case the
cable develop fault at a later date.
21.36 Selection of cable drums for each run shall be so planned as to avoid using
straight through joints. Cable splices will not be permitted except where called
for by the drawings, unavoidable or where permitted by the owner. If straight
through joints are unavoidable, the contractor shall use the straight through joints
kit of reputed make.
21.37 Control cable termination’s inside equipment enclosure shall have sufficient
lengths so that changing of termination in terminal blocks can be done without
requiring any splicing.
21.38 Metal screen and armourof the cable shall be bonded to the earthing system of
the station, wherever required by the owner.
Rollers shall be used at intervals of about two meters while pulling cables. All
due care shall be taken during unreeling laying and termination of cable to avoid
damage due to twist, kinks, sharp bends, etc., Cable ends shall be kept sealed
to prevent damage. Inspection on receipt, unloading and handling of cables shall
generally be in accordance with IS: 1255 and other Indian standard codes of
practices.
Wherever cable pass through floor or through wall openings or other partitions,
wall sleeves with bushes having a smooth curved internal surface so as not to
damage the cable, shall be supplied, installed and properly sealed by the
contractor at no extra charges.
21.39 Contractor shall remove the RCC steel trench covers before taking up the work
and shall replace all the trench covers after the erection work in that particular
area is completed or when further work is not likely to be taken up for some time.
21.40 Contractor shall furnish three copies of the report on work carried out in a
particular week indicating cable numbers, date on which laid, actual length and
route, testing carried out, terminations carried out, along with the marked up copy
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 29
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
of the cable schedule and interconnection drawing wherever any modification are
made.
21.41 Contractor shall paint the tray identification number on each run of trays at an
interval of 10 m.
The contractor shall perform all tests and inspection to ensure that material and
workmanship are according to the relevant standards. Contractor shall have to
demonstrate all tests as per specification and equipment shall comply with all
requirements of the specification.
Test for galvanizing (Acceptance Test)
The test shall be done as per approved standards.
A 2.5 Mtr straight section of 300mm, 600mm wide cable tray shall be simply
supported at two ends. A uniform distributed load of 76Kg / m shall be applied
along with the length of the tray. The maximum deflection at the mid – span
shall not exceed 7mm.
Contractor shall supply and install all grid conduits, mild steel pipes, flexible
conduits, hume pipes etc., including all necessary sundry materials such as
tees, elbows, check nuts, bustling, reducers, enlargers, coupling cap,
rupples, gland sealing fittings, pull boxes etc as specified and to be shown
in detailed drawing. The size of the conduit pipe shall be selected on the
basis of 40 % fill criteria
Contractor shall have his own facility for bending, cutting and threading the
conduits at site. Cold bending should be used. All cuts and threaded ends
shall be made smooth without leaving any sharp edges. Anticorrosive paint
shall be supplied at all field threaded portions.
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 30
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Conduit run sleeves shall be provided with the bushings at each end.
Meatlic conduit runs at termination shall have two locknuts and a bushing
for connection. Flexible conduits shall also be suitably clamped at each end
with the help of bushings. Bushings shall have rounded edges so as not to
damage the cables.
Where embedded conduits turn upwards from a slab or fill the termination
dimensions shown on the drawings, if any shall be taken to represent the
position of the straight extension of the conduit external to and immediately
following the bend. At least one half of the arc length of the bend shall be
embedded.
All conduits/pipes shall have their ends closed by caps until cables arc
pulled. After cables are pulled, the ends of conduits pipes shall be sealed in
an approved manner to prevent damage to threaded portions and entrance
of moisture and foreign material.
Contractor shall supply unload store and install conduits required for the
lighting installation as specified. All accessories fittings required for making
the installation complete including but not limited to pull out boxes ordinary
and inspection Tees and elbows chuck nuts male and female bushings (
Brass or Galvanised steel), caps square headed male plugs mipples gland
sealing fittings full boxes conduit terminal boxes, gaskets and box covers,
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 31
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
saddle terminal boxes and all steel supporting work shall be supplied by the
contractor. The conduit fittings shall be of the same material as conduits.
All unarmoured cables shall run within the conduits from lightning panels to
lighting fixtures, receptacles etc.,
Exposed conduits shall be run in straight lines parallel to building columns,
beams and walls. Unnecessary bends and crossings shall be avoided to
present a neat appearance.
Wherever conduits are along with cable trays, they shall be clamped to
supporting steel at an interval of 600 mm.
For directly embedding in soil, the conduits shall be coated with an asphalt
base compound. Concrete pier or anchor shall be provided wherever
necessary to support the conduit rigidly and to hold it in place.
Conduits shall be kept, wherever possible at least 300 mm away from hot
pipes, heating devices, etc., When it is evident that such proximity may
reduce the service life of cables.
Slip joints shall be provided when conduits cross structural expansion joints
or where long run of exposed conduits are installed, so that temperature
change will cause no distortion due to expansion or contraction of conduit
run.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 32
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
For long conduit run, pull boxes be provided at suitable intervals to facilitate
wiring.
Conduits joints and connections shall e made thoroughly water tight and
rust proof by application of a thread compound which insulates the joints.
While lead is suitable for application on embedded conduit and red lead for
exposed conduit.
Field bends shall have a minimum radius of four (4) times the conduit
diameter. All bends shall be free of kinks, indentations of flattered surfaces.
Heat shall not be applied in making any conduit bend. Separate bends
may be used for this purpose.
Lightning fixtures shall not be suspended directly from the junction box in
the main conduit run.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 33
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
runs cable tags shall be provided inside the switchgear, motor control
centers, control and relay panels etc., wherever required for cable
identification, where a number of cables enter together through a gland
plate.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 34
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The cable glands shall also be tested as per 6121. they shall comprise of
duty brass casting, machine finished and nickel plated, to avoid corrosion
and oxidation. Rubber components used in cable glands shall be
neoprene and of tested quality. Cable glands shall be of approved make.
The cable glands shall also be tested for dust proof and weather proof
termination. The test procedure has to be discussed and agreed to
between owner and cable gland manufacturer.
If the cable end box or terminal enclosure provide on the equipment is
found unsuitable and requires modification, the same shall be carried out
by the contractor, as directed by the owner.
Crimping tool used shall be of approved design and make.
Cable lugs shall be tinned copper solderless crimping type conforming to
IS: 8309 & 8394. Cable lugs shall be of approved make.
Solderless crimping of terminals shall be done by using corrosion
inhibitory compound. The cable lugs shall suit the type of terminals
provided.
22.1 The earthing shall be in accordance with requirements of KPTCL. The earth mat
design is furnished by KPTCL and the work shall be carried out as per the
design.
22.2 Neutral points of system of different voltages, metallic enclosures and frame
works associated with all current carrying equipments and extraneous metal
works associated with electric system shall be connected to a single earthing
system unless stipulated otherwise.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 35
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
22.3 Earthing and lightning protection system installation shall be in strict accordance
with the latest editions of Indian electricity rules, relevant Indian electricity rules,
relevant in the locality where the system is installed.
a) Code of practice for earthing IS: 3043
b) Code of practice fort he protection of Building and allied structures against
lightning IS: 2309
c) Indian electricity rules 1956 with latest amendments.
d) National electricity safety code IEEE – 80
f) Pipe earth electrode (in treated 100 mm dia. 2750 C.I. pipe
earth pit) as per IS. mm long
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 36
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 37
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
g) Light poles, junction boxes on the poles, cable and cable boxes/glands,
lockout switches etc., shall be connected to the earthing conductor running
along with the supply cable which in turn shall be connected to earthing grid
conductor at a minimum two points whether specifically shown or not.
h) Railway tracks within switchyard area shall be earthed at a spacing of 30 m
and also at both ends.
i) Earthing conductor shall be buried 1500 mm away from the switchyard
fence. All the gates and every alternate post of the fence shall be
connected to earthing grid. As specified in earthmat design.
j) Flexible earthing connectors shall be provided fot he moving parts.
k) All lighting panels, junction boxes, receptacles fictures, conduits etc., shall
be grounded in compliance with the provision of I.E. rules.
l) A continuous ground conductor of 16 SWG wire shall be run all along each
conduit run and bonded at every 600 mm by not less than two turns of the
same size of wires. The conductor shall be connected to each oanel ground
bus. All junction boxes, receptacles, lighting fixtures etc., shall be
connected to this 16 SWG ground conductor.
m) 50 mm x 6 mm MS flat shall run on the top tier and all along the cable
trenches and the same shall be welded to each of the racks. Further this
flat shall be earthed at both ends and at an interval of 30 Mtrs. The M.S. flat
shall be finally painted with two coats of red oxide primer and two coats of
post office red enamel paint.
22.7 Jointing
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 38
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Metallic sheaths and armour of all multicore power cables shall be earthed at
both equipment and switchgear end. Sheath and armour of single core power
cables shall be called at switchgear end only.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 39
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
a. All support insulators, circuit breaker interrupters and other fragile equipment
shall preferably be handled with cranes having suitable booms and handling
capacity.
b. The slings shall be of sufficient length to avoid any damage to insulator due
to excessive swing scratching by sling ropes etc.,
f. Muslin or leather cloth shall be used for cleaning the inside and outside of
hollow insulators.
g. All the equipment, instruments and auxiliaries required for testing and
commissioning of equipment shall be arranged at site by the contractor.
25. STORAGE
a. The contractor shall provide and construct adequate storage shed for proper
storage of equipments, where sensitive equipments shall be stored indoors.
All equipments during storage shall be protected against damage due to
acts of nature or accidents.
26.1 Details of conductor: ACSR conductor will be supplied and erected in line with
ACSR conductor used in existing substation
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 40
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
26.2 WORKMANSHIP
a) The finished conductor shall be smooth, compact from uniform and free
from all imperfections including spills, die marks, scratches, abrasions, scuff
marks, kinks (protrusion of wires), dents, press marks, cut marks, wire
cross over, over riding, looseness (wire being dislocated by finger/hand
pressure and/or unusual bangle noise on tapping), material inclusions,
while rust powder formation or black spots (on account of erection with
trapped rain water etc.,) dirt, grit etc.,
b) All the aluminum and steel strands shall be smooth, uniform and free from
all innerfections such as spills and splits, die marks, scratches abrasions
and kinks after drawing.
c) The steel strands shall be hot dip galvanized and shall have a minimum
zinc coating of 260 gm/sq. mm after stranding of the uncoated wire surface.
The zinc coating shall be smooth, continuous and of uniform thickness, free
from imperfection and shall with stand minimum three dips after stranding in
standard prerce test. The finished stands and the individual wire shall be of
uniform quality and have the same property and the characteristics as
prescribed in ASTM designation: B498-74 and relevant IS.
d) The steel strands shall be preformed and post formed in order to prevent
the spreading of the strands in the event of cutting of composite core wire.
Care shall be taken to avoid damage to galvanization during performing
and post forming operation.
a) Aluminum wires
No joints shall be permitted in the individual wire in the outermost layer of a
finished conductor. However joints in the 12 wire and 18 wire inner layers
of the conductor shall be allowed but these joints shall be made by cold
pressure but twelding shall and be such that no such joints are within 15
Mtr. of each other in the complete stranded conductor.
b) Steel wire
There shall be no joints of any kind in the finished wire entering into the
manufacture of the strand. There shall also be no strand splices in any
length of the completed stranded steel core of the conductor.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 41
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
26.4 Tolerance
The manufacturing tolerance to the extent of the following limits only shall be
permitted in the diameter of individual aluminum and steel strands and lay-ratio of
the conductor:
26.5 Materials
Aluminum
The aluminum strands shall be hard drawn from electrolytic aluminum rods
having purity not less than 99.5% and a copper content not exceeding 0.04%
Steel
The steel wire strands shall be drawn from high carbon steel wire rods and shall
conform to the following chemical composition:
Element : % composition
Carbon : 0.50 to 0.85
Manganese : 0.50 to 1.10
Phosphorous : not more than 0.035
Sulphur : not more than 0.045
Silicon : 0.10 to 0.35
Zinc:
The zinc used for galvanizing shall be electrolytic high grades zinc of 99.95%
purity. It shall conform to and satisfy all the requirements of IS 209 -1979.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 42
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
26.7 Tests:
The following type acceptance & routine tests and tests during manufacturing
shall be carried out on the conductor.
Type tests
The following type tests shall be conducted on samples of connection. The
testing charges for the type test shall be charged separately in the prescribed
schedule of the Bid.
Acceptance Tests
All the above tests except test mentioned at (i) shall be carried out on Aluminum
and steel strands after stranding only.
Routine Tests :
a. Check to ensure that the joints are as per specification.
b. Check that there are no cuts, fins etc., on the strands.
c. All acceptance test as mentioned in clause 2.7.3 above to be carried on
each coil.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 43
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
27.2 WORKMANSHIP
All steel strands shall be smooth, uniform and free from all imperfections such as
spills and splits, die marks, scratches, corrosions and kinks after drawing and
also after stranding.
The steel strands shall be hot dip galvanized (and shall have a minimum zinc
coating of 275 gms/sq. m). The zinc coating shall be smooth, continuous of
uniform thickness, free from imperfections and shall withstand three and a half
dips after stranding in strand preece test. The steel wire rod shall be of such
quality and purity that, when drawn to the size of the strands specified and
coated with zinc the finished strands shall be of uniform quality and have the
same properties and characteristic in ASTM designation B498-74.
The steel strands shall be preformed and postformed in order to the prevent
spreading of strands while cutting of composite earth wire. Care shall be taken to
avoid damage to galvanization during performing and postforming operation.
To avoid susceptibility towards wet storage stains (while rust) the finished
material shall be provided with a protective coating of boiled linseed oil.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 44
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
27.4 TOLERANCES
The manufacturing tolerances to the extent of the following limits only shall be
permitted in the diameter of the individual steel strands and any lay length of the
earthwire.
Standard Maximum Minimum
Diameter 3.66 mm 3.75 mm 3.57 mm
Lay length 181 mm 198 mm 165 mm
27.5 MATERIALS
a) STEEL
The steel wire strands shall be drawn from high carbon steel rods shall conform
to the following requirements as to the chemical composition:
Elements : % composition.
Carbon : Not more than 0.55
Manganese : 0.4 to 0.9
Phosphorous : Not more than 0.04
Sulphur : Not more than 0.04
Silicon : 0.15 to 0.35
b) Zinc
The zinc used for galvanizing shall be electrolytic high grade zinc of 99.95%
purify. It shall confirm to and satisfy all the requirement of IS: 209 – 1979
27.7 TESTS
The following type, routine and acceptance tests and tests during manufacturing
shall be carried out on the earthwire.
TYPE TESTS
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 45
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
a) UTS test
b) DC resistance test
ACCEPTANCE TESTS :
ROUTINE TESTS :
a) Check that there are no cuts, fins etc., on the strands
b) Check for correctness of stranding.
The contractor shall offer material for sample selection for type testing. Only after
getting quality assurance programme approved by the owner. The samples for
type testing shall be manufactured strictly in accordance with the quality
assurance programme approved by the owner.
The insulators for suspension and tension strings shall conform to IS: 731,
insulator hardware shall conform to IS: 2486
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 46
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The design of the insulator shall be such that stress due to expansion and
contraction in any part of the insulator shall not lead to deterioration. Ferrotis
parts shall be hot dip galvanized in accordance with the latest edition of IS: 2629.
The zinc used for galvanizing shall be of grade Zn – 99.95 as per IS – 209. The
zinc coating shall be uniform, adherent, smooth, reasonably bright, continuous
and free from imperfections such as flux, ash, rust stains bulky white deposits
and blisters.
Bidder shall make available data on all essential features of design including the
method of assembly of discs and metal parts, number of discs per insulators, the
manner in which mechanical stresses are transmitted through discs to adjacent
parts, provision for meeting expansion stresses, results in corona and thermal
shock tests, recommended working strength and at special design or
arrangement employed to increase life under service conditions.
Insulator hardware shall be of forged steel. Malleable cast iron shall not be
accepted except for insulator disc cap. The surface of hardware must be clean,
smooth, without cuts, abrasion or projections. No part shall be subjected to
excessive localized pressure. The metal parts shall not produce any noise
generating corona under operating conditions. The tension string assemblies
shall be supplied along with suitable turnbuckle sag compensation springs if
required may also be provided.
28.2 Tests:
In accordance with the stipulations under section – 2, the suspensions and
tension strings, insulator discs and hardware shall be subjected to the following
type tests, acceptance tests and routine tests.
a) Dry and wet power frequency voltages withstand test with corona control
rings as per Is – 731.
b) Lightning impulse voltage withstand test (dry) with corona control rings as
per IS – 731.
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 47
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 48
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Samples taken from the zinc ingot shall be chemically analysed as per IS :
209. The purity of zinc shall not be less than 99.95%
The chemical analysis, hardness tests and magnetic particle inspection for
malleable casting will be as per the internationally recognized procedures
for these tests. The sampling will be based on heat number and heat
treatment batch. The details regarding tests will be discussed and
manually agreed to by the contractor and owner in quality assurance
programme.
Samples taken from the zinc ingot shall be chemically analysed as per IS :
209. The purity of zinc shall not be less than 99.95%
The chemical analysis, hardness tests and magnetic particle inspection for
forgings will be as per the internationally recognized procedures for the
tests. The sampling will be based on head number and heat treatment
batch
The details regarding tests will be as discussed and manually agreed to by
the contractor and owner in quality assurance programme.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 49
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The chemical analysis, hardness tests and magnetic particle inspection for
fabricated hardware will be as per internationally recognized procedure for
these tests. The sampling will be based on heat number and heat treatment
batch. The details regarding test will be discussed and mutual and agreed
to by contractor and owner in quality assurance programme.
28.3 PARAMETERS
DISC INSULATORS
INSULATOR STRING
Note : For tension purpose, double insulator strings and for suspension purpose
single suspension insulator string shall be used.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 50
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
This specification is in two parts, part-II and part - III in addition to part-I (general
condition)
Part - III relates to erection of aluminium bus bars with accessories supplied as
per specification in part - II and includes bending, and welding of aluminium
pipes, fixing corona, bells, making expansion joints etc.
The scope of this specification covers the erection of tubular aluminium bus bars
as detailed below:
Erection of 110 KV or 66 KV main bus of 75 mm/ 63 mm, 33KV single main bus
of 50 mm aluminium pipe with rigid cross bus connection to disconnects.
29.1 STANDARDS:
The following points shall be kept in view while submitting the offer:
i. The Y and 'V' tap shall be connected by bolted type clamp at top and
bottom. Through a straight tap of height 1750mm and 1250 mm with 63 and 50
mm aluminium pipe in case of 110 KV and 66KV side bus connectors. The
straight tap shall be connected by bolted type clamps both at top and bottom.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 51
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The materials supplied and the workmanship involved shall be suitable for
operating conditions, which are detailed below
Particulars 110 KV
Normal current to base handled As per normal rating Al. pipes indicated
in annexure
Impulse withstand voltage(KV) 550
Power frequency withstand 230
voltage(KV)
b) Position of post insulator clamps indicating various types i.e., rigid expansion
/ sliding type.
c) Position of welds
d) Cross - section at vital points like welding points, connection of vertical taps
of 66 kV and 33 KV main bus bars, post insulators, clamps points rigid,
expansion and sliding types.
110KV
Main busbars 75mm
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 52
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The requirement for total lengths of various sizes of aluminium pipe is indicated
in section I of volume II. The tubes shall be supplied in convenient lengths so as
to keep wastages to a minimum without diminishing any of the mechanical and
electrical properties. The length of the pipes indicated is based on the drawings
furnished. Any increase in lengths of pipes owing to any practical reasons,
miscalculation will be to the account of the bidder.
The material shall be suitable for operating conditions detailed elsewhere of this
specifications.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 53
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The clamps required are of three types viz. Rigid, sliding and expansion
types
i) RIGID TYPE CLAMPS : Are required to hold the aluminium pipe rigidly
allowing for no lateral movement of pipe. These are required at points marked 'R'
in the layout drawings and shall be suitable for insulator and aluminium pipe. At
all rigid clamp locations, there shall be vertical straight tap connections in case of
110KV, 66KV and 33KV main buses for connecting disconnects respectively.
ii) SLIDING TYPE CLAMPS : Are the ones located in between a rigid clamp
and expansion type clamp, which shall allow for movement of pipes. These are
marked as 'S' in layout drawing. These clamps may be bolted type or plain type
i.e, without bolts. As in case of rigid type clamps, vertical straight line tap
connections are located on sliding clamps also.
iii) EXPANSION TYPE CLAMPS : Are the ones located between two rigid
clamps and marked 'E' in the layout drawing. These clamps are meant for
allowing for expansion of aluminium pipes used for main bus. The expansion
joints so used in the clamps shall be complete in all respects with required
aluminium straps, filler inserts, etc., and should allow for proper expansion of the
portion of aluminium pipes between two rigid clamps.
The tap connections shall be with 63 mm aluminium pipe for 110KV system and
with 50mm aluminium pipe for 66KV.
The height of vertical taps shall be 1750 mm for 110KV system, 1250 mm for
66KV system.
The joints between the main bus and vertical tap and vertical tap to horizontal tap
shalI be made up of suitable clamps, which should conform to the latest edition of
IS-5561.
The main bus shall consists of standard lengths of aluminium pipe joined at
various points by welded joints or expansion joints as the case may be.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 54
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Welded joints to an extent of 10% of the total quantity for each KV class shall be
tested by radio-graphic test to prove the soundness of the weld joints. Further if
desired by the owner, the tenderer shall arrange for the radio-graphic test of
more number of joints for which the unit rates are to be indicated in price
schedule.
The welded joint or the expansion joint shall be complete in all respects with
required number of pipe filler inserts, proper welding etc.
The successful tenderer shall submit the quality assurance plan for the work and
welder qualification for approval. The weld should be cut open to see the quality
of the welds at no extra cost to the purchaser .
29.9 DRAWING
The tenderer should submit drawing in respect of all the components detailed in
clause 1.00 to 5.00 and other essential and necessary components required for
without which the tender will be rejected.
As stated in clause 6.00 of part-1 the tenderer shall submit drawings of various
components for purchaser's approval. The material shall be offered for inspection
only after purchaser's approval is accorded to the drawing.
The drawings of clamps and connectors should be exhaustive i.e, various views
shall be depicted and current rating (Ampacity) mentioned.
29.10 MATERIALS:
The material used for the various pipe joints, connectors shall be of proven tested
quality and workmanship. The composition of alloys used shall be made
available to the purchaser for verification. The bolts and nuts shall conform to IS-
1363- 1967 with latest revisions.
The clamps offered shall be complete in all respect and shall perfectly suit the
required size of aluminium pipes specified in clause 1.00 of part-II.
All ferrous metal parts like bolts, nuts of size l2mm and above shall be hot dip
galvanised and bolt sizes below 12mm may be electro galvanised. The threads
in nuts shall be cut after galvanising and shall be lubricated and greased. All
other threads shall be cut to take care of increase in diameter due to galvanising.
All bolts shall be provided with a lock nut along with fastening nut.
All casting shall be free from blow holes and other casting defects such as cracks
etc.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 55
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The connectors shall have the same electrical characteristics as the associated
aluminium bus bars and, shall be capable of carrying the normal and short time
current rating detailed in clause 5.00 of part-I.
The clamp body shall be of high conductivity aluminium alloy of high strength and
non-corrosive. The aluminium alloy shall be copper free. The bolts and nuts used
shall be of high tensile, non-corrosive galvanic resistant material. Aluminium
alloy, phosphorous bronze or galvanised iron may be used as required by the
clamp design.
Bolting pressure shall be well distributed. The outer surface of the clamp shall be
smooth and free from sharp edges.
29.12 TESTS
Aluminium pipe, associated clamps and corona bell shall be designed for trouble
free operation in the climatic and atmospheric conditions enumerated in the
project data. Hence, the tests and especially the Corona discharge test, Special
features of design to meet the requirement shall be brought out in the tender.
TYPE TESTS:
Tenderer shall furnish the following type test certificates in respect of the
aluminium pipe and accessories.
ACCEPTANCE TESTS:
a) Tensile test.
b) Resistance test.
c) Temperature rise test.
d) Visual and dimensional verification
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 56
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The visual discharge is specified to know the corona effect. Special care shall be
taken to design and manufacture to minimise corona discharge. Corona
discharge shall not be visible from the clamps when the system consisting of pipe
with clamps is energised to phase ground system.
For the purpose of temperature rise and other tests, the current carrying capacity
of various clamps may be reckoned as follows clamps or part thereof in contact
with IPS aluminium pipe of nominal diameter.
a) 75 mm 2000 Amps.
b) 63 mm 1250 Amps.
c) 50 mm 1250 Amps.
d) 38 mm 800 Amps,
The purchaser reserves the right to conduct temperature rise tests at rated
current on any erected portions of the bus works. Total temperature of clamps
more than 85 deg C (temperature rise plus ambient) will not be acceptable.
Clamps which are found to show the usual corona discharge at the rated voltage
will not be acceptable
29.13 SAMPLES
The tenderer shall furnish typical samples of tubular bus bar materials of 500
mm. Minimum length and one unit of each of components like clamps, corona
bell, power connectors, etc., used in the above works, to enable the purchaser to
assess the quality of workmanship of the products.
The workmanship shall be of highest order. The cutting shall be smooth, even
without any burrs on the cut edges. The welding shall be perfect and the
successful tenderer shall take radiographs and furnish the same to the purchaser
to depict the perfect ness of welding,
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 57
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Surface to be welded shall be cleaned thoroughly so that the same are free from
grease, dust and loose particles. Sleeves shall be used for welded joints under
short circuit conditions.
Pure argon gas shall be used for welding. In view of argon gas shield around the
arc, the welding operation shall be shielded from wind that could displace the gas
envelope.
The welding process shall be carried out at the rate of 15-30 cms per minute.
After completion of welding, the surface shall be cleaned.
The ' weld ' shall have an average strength ranging from 120 to 155 KG/cm2.
29.17 TESTS
a) The test is intended for the presence of the cracks, discontinuity in the
welds.
c) Further if the purchaser desires for the radiographic test for more number of
welded joints, the contractor shall arrange for the same.
Test to prove the mechanical strength ie, to withstand 155 KG/ cm2 shall be
conducted on 5% of the welded joints.
1 Nominal size mm 75 63 50 38
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 58
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 59
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
30.1 SCOPE:
This specification covers the design, manufacture, testing & supply of C-Type
wedge boltless connectors ( fired wedge type/ wedge type with bolted
mechanism etc) which are to be used for tation equipments and for connection
between the main bus and auxiliary bus conductor and also for connection to
terminal pads of different station equipments such as circuit breakers, CTs, PTs,
isolators, Lightning Arresters, wave traps etc of different makes. The equipment
required shall be complete with all components which are necessary or usual for
their efficient performance and satisfactory maintenance.
The T & PG connectors shall be cartridge fixed “C” wedge type conforming to
latest version of ANSI-C119.4 (AA) : extra heavy duty class tested. The
connectors shall have maximum contact surface with the conductor, extremely
low and stable contact resistance and minimum power loss. These shall
maintain constant force within the connection for the life of connector/clamp while
compensating for thermal expansion or grip and increased life span.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 60
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
All parts of fittings shall be suitable for use in atmospheric condition indicated
elsewhere in the specification inherently resistant to atmospheric corrosion or be
suitably protected against corrosion both during storage and in service. The
connector shall be capable of withstanding dynamic and thermal stresses without
any damage or deterioration.
The C-Type wedge boltless connectors - latest edition of ANSI C 119.4 - 2004
Standards.
Material:
The C-Type wedge boltless connectors shall be of high strength and high
conductivity aluminium alloy. The same shall be suitable for use on all
combinations of aluminium to aluminium, or aluminium to copper conductors.
Workmanship:
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 61
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The connector consists of tapered “C” shaped member and wedge that is
made of aluminium alloy
The connector should be bolt less and of wedge system.
The “C” member should be provided with built-in spring tension to
maintain constant pressure for a firm electrical contact.
The connector shall be used for multiple combinations of solid/stranded
AAC, AAAC, ACSR, Copper combination etc.
Copper to copper connectors - the “C” member to be composed of
aluminum bronze alloy and the wedge of copper alloy very close to pure
copper.
“C” member wedge shall be factory coated with an inhibitor containing
abrasive particles to help clean the contact surfaces during installation.
The wedge type boltless connectors shall consist of C-member and wedge. The
wedge shall be inserted at a speed (at a speed of 40m./sec approximately in
case of fired wedge type) so as to be effective in abrading all sliding surface and
disrupting surface oxide film to generate large number of contact spot in the
electrical interfaces. The mechanical stresses during the wedge insertion shall
cause plastic deformation of the C-Clamp and shall increase the geometrical
conformation of the clamp to the conductor. An Oxidation inhibitor shall be
applied to the surface thereby elimination of oxidation of metallic surface. The
normal current carrying capacity of clamp shall not be less than the specified in
the specification. If the connectors are to be installed by Powder actuated tool
using cartridges with explosive, valid explosive license issued by the Government
of India/State Government should be posessed.
Clamps shall be corona free and shall carry an overload of at least 20% over the
rated current. The connectors should be easily removable and reusable type.
Reusable means that the connector may be removed from service and installed
again. Prior to reuse, any instructions to be followed for reconditioning the
reusable connector shall be furnished.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 62
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Voltage Voltage
Sl.
Technical Particulars Class Class
No.
66 kV 33 kV
1 Nominal Voltage (KV). 66 33
2 Maximum System Voltage (KV). 72.5 36
3 BIL (Impulse) KV peak. 325 170
Power frequency withstand voltage
4 140 70
(wet) KV rms.
Markings:
For easy identification of the C-Type wedge boltless connectors shall have
markings indicating that the connectors are suitable for station bus
conductor/station equipments/transmission lines.
30.10 INSPECTION
The inspection may be carried out by the purchaser at any stage of manufacture.
The successful bidder shall grant free access to the purchaser's representative at
a reasonable time when the work is in progress. Inspection and acceptance of
any equipment under this specification by the purchaser shall not relieve the
supplier of his obligation of furnishing boltless connector in accordance with the
specification and shall not prevent subsequent rejection if the equipment is found
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 63
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The “C” type wedge boltless connector shall be packed in wooden crates suitable
for vertical / horizontal transport, as the case may be and suitable to withstand
handling during transport and outdoor storage during transit. The supplier shall
be responsible for damage to the equipment during the transit, due to improper
and inadequate packing. The easily damageable materials shall be carefully
packed and marked with the appropriate caution symbols. Any material found
damaged inside the packing cases shall be supplied by the supplier without any
extra cost to the purchaser.
Fixing and Maintenance manuals in English shall be supplied for “C” type wedge
boltless connector one month prior to dispatch of the equipment. The manual
shall be bound volume and shall contain all drawings and information required for
Fixing and Maintenance of the connectors.
Drawings for each item have to be submitted for approval before commencement
of supply. Supplies shall not be commenced before approval of drawings. Non
submission of drawing /receipt of approval shall not be linked with delivery
schedule. Delivery schedule should be adhered to. Final drawings equivalent to
the number of consignees for each item have to be supplied.
The catalogues (in English) describing the items and indicating the
Model/Reference number, Code Name/Across Flat dimension of the
relevant die to be used for compression, conductor sizes and other
relevant details.
Constructional features and material used for components and relevant
technical literature.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 64
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
30.15 TESTS:
All tests shall be conducted in accordance with latest edition of ANSI C 119.4 -
2004 The following shall constitute the tests. Type test certificates of recent
origin (not older than 5 years) for having conducted the tests should be furnished
along with the quotation. In case the test certificates are older than 5 years, then
the contractor shall conduct the same afresh at his own cost.
Type Tests:
a) Failing load test.
b) Electrical resistance test.
c) Heating cycle test.
d) Tensile strength test.
e) Torque strength test
f) Conductor damage test.
g) Short time current rating as per relevant standards.
Acceptance Tests:
a. Tensile strength test.
b. Electrical resistance test.
c. Dimensional check.
Routine Tests:
a. Visual examination.
b. Dimensional verification.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 65
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The “C” type Wedge Boltless connectors offered shall be guaranteed for
satisfactory performance for a period of 24 months from the date of satisfactory
commissioning. The “C” type Wedge Boltless connectors found defective within
the above guarantee period shall be replaced and supplied by the supplier free of
cost within one month from the date of receipt of intimation.
1. Manufacturer's name.
2. Applicable standards.
3. Type.
4. Material of connector.
a. 'C' member
b. Wedge
c. Spring washers (if any)
5. Temperature rise above ambient Temperature
a. At rated current.
b. At 150% of rated current.
6. Rated current
7. Short time current rating.
8. a). Rated terminal load (Kg)
b). Factor of safety.
9. Minimum thickness of any part.
10. weight of clamp complete (Kg)
11. Type test reports
12. OGA drawing
ii) The steel mounting arrangements shall be as shown in the drawing and same
shall be galvanised. The mounting arrangement shall be earthed at two locations
with 8 SWG GI Wire to be supplied by the contractor. Mounting arrangement of
fixtures is to be procured by the contractor.
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 66
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
iii) All lighting fixtures shall be mounted in accordance with the standard
installation practice.
iv) All lighting fixtures shall be assembled, installed and wired. Splices in lighting
circuits shall be avoided. Required size of fuses shall be provided for each light
junction boxes. Contractor after completing the connections to all outlets shall try
out all portions of the lighting system to ensure satisfactory operation.
a) Whether proof out-door type, 'Yard lighting Pillar Box for AC lighting having
the following specifications for EHT sub-stations is to be supplied by the
contractor
b) The box should be made of 2 mm thick Galvanised M.S. Sheet of size 700 x
500 x 150. The box should have hinged type door vermin proof, weather
proof, rubber beeding has to be provided around the door, door of the box
should be provided with panel type lock. The top portion of the box shall be
slanting, so that the rain water will fall away easily.
c) 4 Nos. Galvanised M.S.Flat 50 x 6 mm should be welded to the box with
one No. hole suitable for 5/8" dia bolts to facilitate easy mounting.
d) The contractor shall supply and install junction boxes complete with
terminals as required. The brackets, bolts, nuts, screws etc., required for
erection are also included in the scope of the contractor.
e) Junction boxes having volume less than 1600 cubic centimeters may be
installed without any support other than that resulting from connecting
Conduits where two or more rigid metallic conduits enter and accurately
position the box. Boxes shall be installed so that thie level plumbed and
properly aligned to present a pleasing appearance.
f) Boxes with volumes equal to or greater than 1600 cubic cm, and smaller
boxes terminating on less than two rigid metallic conduits or for other
reasons not rigidly held, shall be adequately supported by auxiliary steel of
standard steel shapes or plates to be fabricated and installed. The
contractor shall perform all drilling, cutting, welding, shimming and bolting
required for attachment of supports.
g) The box should be made of 2 mm thick Galvanised M.S. Sheet of size
750x400x150 mm with hinged type door, vermin proof and weather proof.
Rubber beading has to be provided around the door. Necessary brackets
on the back side of the box should be provided for mounting on the
structures. Doors of the box should be provided with panel type look. The
top portion of the box shall be slanting so that rain water will fall away easily.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 67
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Two rows having 20 Nos. terminals in one and 14 Nos. in other should be
provided in the box.
h) The terminals should be of disconnecting and testing type (Type CDTTS of
'connected make'. Three Nos. holes (Half punched) suitable for 6x2.5
sq.mm Copper cable and 3 Nos. holes (half punched) suitable for 4x2.5
Sq.mm copper cable should be provided at the bottom to take the cables
into the box. Suitable cable glands should be supplied. Terminals in the
Marshalling box should have facility for easy earthing, shorting, isolating and
testing. The following are also required. 2 Sets of Earthing stud of 1/2" dia
with suitable nuts, flat and spring washers are to be provided as shown in
drawing.
For Marshalling boxes for PTs : Ten Nos. (10 Nos.) HRC fuses of 2 amps rating of
M/s. English Electric Co., with neutral link (with Bolts and Nuts) and one No. 3 MCB
(10 amps) (M/s. MDS make).
For Marshalling boxes for CVTs : 6 Nos. HRC Fuses of 2 Amps rating of M/s.
English Electric Co., with neutral link with bolts and nuts.
The marshaling kiosk shall be of out door type suitable for operation in humid, dusty
and tropical atmosphere with seasonal wet, dry and dusty condition as per clause-
6.1 of I.S 5039/1969.The kiosk should be made of 3mm Galvanised M.S Sheet of
size 1200x800x450mm.Each kiosk shall consist of
The terminal blocks shall be provided in vertical formation. They shall be fully
enclosed with removable covers made of barrier moulded integrally. Such block
shall have washer and binding screw for external connection and white marking
strip for ex-circuit identification and moulded plastic cover. All terminals shall be
clearly marked with identification markers.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 68
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
The box shall be provided with self supporting Gavanised M.S. Channel
100x50mm.,welded to the bottom side of the Box and 4 Nos. holes are to be
provided (suitable for 3/4" dia bolts) for fixing to the plinth with galvanised bolts. The
required 4Nos bolts of length 300mm, with galvanised nuts and washers are to be
supplied.
The Kiosk shall be provide with a set of double hinged doors at the front and back.
The doors shall be provided with 2Nos panel locks and 1No.pad lock.It shall have a
door switch operated AC illuminated lamps which gets switched on when door is
opened and gets switched off when closed. Two No. studs shall be provided on
the body for giving earth connection to Marshalling Boxes.
Investigating for location of borewell , drilling 165mm dia. borewell ,fixing suitable 3
phase, 3HP motor, and commissioning of the motor, laying pipe line upto overhead
tank (1000 liters capacity to be installed) on the roof of control house, plumbing, all
the necessary materials etc., complete. The equipment and materials supplied shall
be got approved by the Engineer-in-charge before fixing, samples of these
materials shall be got approved.
a) All installations are made in accordance with the Electricity Supply Act, 1948
and IE rules 1956 which will be inspected by the Executive Engineer and
clearance given.
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 69
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
i) Monitoring of quality of the foundations for the tower pads and transformers in
substations.
ii) that all safety norms during construction are followed to prevent avoidable
accidents during construction.
iii) Handling and placing of the equipment to avoid damage of the equipment and
accidents.
iv) Monitoring whether standard rules are being followed while pulling and
tightening the conductors.
Weekly progress reports showing the actual progress made in the receipt of the
materials by the contractor and in completion of various works shall be regularly
submitted in duplicate by the contractor to the Engineer. The performance
monitoring shall be carried out with the help of computer aided system on MS
project and Excel etc.
The contractor shall guarantee and be entirely responsible for the execution of the
contract in accordance with the general conditions of contract, specifications,
schedules and appendicies. He shall further guarantee and be responsible for
proper erection with in the guaranteed completion and performance periods. The
contractor should give binding certificate necessarily stating that he has considered
supply of all items excluding specified items to be provided by the Employer listed in
the Appendix-II for completion of Substation /Bay’s works. The contractor should
also specify in the binding certificate that he has furnished the additional items with
unit rates & approximate quantities required to complete the work and not covered
in the schedules of bill of quantities. The lumpsum amount shall be quoted for
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 70
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
finished item of work as per Specification of KPTCL. No extra payment over and
above the quoted amount will be entertained. In case any work is not executed
based on site condition suitable amount will be deducted and mutually agreed rates.
b) Internal Walls & Oil paints : 1) Asian 2) Berger 3) ICI 4) Nerolac 5) Dulux 6)
Jenson & Nicholson
7 Electrical works : 1) Fine cab, poly cab, V-guard cables for wiring
and switch board connections.
2) Orient, Khaitan, Usha, Havells make ceiling
and exhaust fans.
3) Osram, Surya for tube lights & incandescent
bulbs
4) Philips / Crompton greaves for decorative
Description Document Number Rev No Page No
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 71
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
Note : This is tentative vendor list. All items will be as per KPTCL approved vendor
list
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 72
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
All the technical deviations from the tender specification shall be listed out by the Bidder
para by para in this schedule. Deviations taken in covering letter, standard terms
and/or body of the Bid but not listed herein will make the Bid liable for rejection as
'Irresponsive'
______________________________________________________________________
______________________________________________________________________
1 2 3 4 5 6
______________________________________________________________________
Certified that above are the only technical deviations from the tender Specification.
Designation : ______________
Date : ______________
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 73
FOR GSS END ETC WORK
105MW SOLAR PV POWER PLANT, KREDAL, KARNATAKA
ANNEXURE-B (BOQ)
TECHNICAL SPECIFICATION
ACME-KR3-00-EE-224-TS-001 00 74
FOR GSS END ETC WORK