Beruflich Dokumente
Kultur Dokumente
Project
Submitted to
Submitted by
Feedback Infrastructure Services Nepal Limited
TABLE OF CONTENTS
1. INTRODUCTION .............................................................................................. - 3 -
Background ................................................................................................. - 3 -
General approach and Objective ................................................................. - 3 -
Reconnaissance Site Visit ............................................................................ - 4 -
2. ALTERNATIVE LAYOUTS .................................................................................. - 6 -
Power House Alternatives ........................................................................... - 7 -
Waterway Alternative.................................................................................. - 7 -
3. OPTIMIZATION ............................................................................................... - 9 -
Assessment of Project Layout ..................................................................... - 9 -
Selection of Powerhouse location ............................................................... - 9 -
Optimization of Power Canal Section .......................................................... - 9 -
Optimization of Penstock Diameter ........................................................... - 10 -
Optimization of Plant Installed Capacity ................................................... - 11 -
Power and Energy estimation.................................................................... - 11 -
4. CONCLUSIONS AND RECOMMENDATIONS......................................................... 44
5. SALIENT FEATURE OF SELECTED ALIGNMENT ................................................... 46
Upper Piluwa-1 Hydroelectric Project
1. Introduction
This report presents the methodology and assumptions considered for the
optimization of the project to determine the optimum cost effective project size
i.e. the Optimum Plant Capacity. The optimization study is conducted to
determine the optimum plant capacity.
The optimization study is carried out taking a range of technically viable
alternative plant capacities. As per available mean monthly river discharge data
and available head, energy calculated at different plant capacities. Project cost
at different capacity is derived by calculating the cost of major items of different
structures involved in the project such as diversion weir, settling basin, water
conveyance system, powerhouse and tailrace and will be presented in feasibility
report. Optimization study includes the sizing and revenues comparison from
different alternatives. The alternative with maximum revenue has been selected
as the optimum project size.
Background
The description of potential alternatives assessed during the feasibility level
study of Upper Piluwa – 1 is portrayed in this report. In reference to these
alternatives, studies were conducted to optimize the plant installed capacity and
water conveyance system of Upper Piluwa – 1.
This project alignment will be situated on the right bank of Piluwa Khola and is
conceptualized as a cascade to Upper Piluwa – 2 Hydropower Project (UP – 2
HP) with tandem operation. This project does not require a separate headwork
since it takes the discharge from the tailrace of UP – 2 HP which is currently
under construction, through the inter connection system and conveyed to the
power canal of the project. Therefore, the capacity of the project depends
directly with the tailrace discharge from the UP – 2 HP. Two possible
powerhouse locations were observed during the site verification study.
capacity in the range of 7.30 MW would be most the feasible output at the
proposed location.
For each alternative layout, Power and Energy were calculated based on design
discharge, net head and assumed efficiencies.Financial analysis based on
different alternatives will be presented in feasibility study report.
2. Alternative Layouts
Right bank of river was selected for the project layout due to its geological and
social conditions. In right bank alternative, four options were studied.
Option 1
Power house 1 option with headrace pipe, surge tank (1) & penstock(1)
Power house 1 option with headrace canal, surge tank (1) & penstock(1)
Option 2
Power house 2 option with headrace canal, surge tank (2) & penstock(2)
Power house 2 option with headrace pipe, surge tank (2) & penstock(2)
Upper Piluwa-I
HEP
Optimization Process
Waterway Alternative
The optimization of plant installed capacity is followed by the optimization of
various water conveying structures, viz. power canal and high pressure conduit
(penstock), in order to determine their economic sections for conveying the
design discharge.
Upper Piluwa-1 Hydroelectric Project
Two different options of waterway was investigated for the selected option i.e.
headrace pipe and canal. Optimization study was carried out between these
options and the best alternative was selected.
Upper Piluwa-1 Hydroelectric Project
3. Optimization
Assessment of Project Layout
The overall layout of UP – 1 HP will be constrained because of its cascade
nature. There is no alternate location option regarding the interconnection with
UP – 2 HP. Nonetheless, as mentioned earlier, the options taken into account
for the powerhouse location of UP – 1 HP will create ample room space to
optimize the layout as it will have significant influence over the installed capacity
and energy generation of the project.
Since the discharge available in the river varies each month, consequently the
net head and the efficiency variations take place. Discharge is one of the prime
factor on which energy revenue is based on. For this study, constant value for
overall efficiency has been taken for calculating power output from the
plant.Based on the net head, turbine discharge and effeciencies and monthly
mean flow, energy production has been calculated and tabulated below and
compared with canal and pipe option. The comparison of annual scenario of the
power and energy generation of the plant is presented in Table 3-1 to 3-
4.Graphical representation of revenue generated from both options is shown in
figure 3-2.
Upper Piluwa-1 Hydroelectric Project
Baishakh 2.52 2.52 2 1.26 89.24% 22.50 202.50 4.5 3.29 0.13 3.15 3.15
Jestha 5.85 5.85 2 1.95 89.24% 22.50 202.50 6.9 5.08 0.20 4.88 2.36 2.52
Asar 10.83 3.89 2 1.95 89.24% 22.50 202.50 6.9 5.25 0.21 5.04 5.04
Shrawan 12.98 3.89 2 1.95 89.24% 22.50 202.50 6.9 5.08 0.20 4.88 4.88
Bhadra 12.83 3.89 2 1.95 89.24% 22.50 202.50 6.9 5.08 0.20 4.88 4.88
Asoj 8.80 3.89 2 1.95 89.24% 22.50 202.50 6.9 5.08 0.20 4.88 4.88
Kartik 4.28 3.89 2 1.95 89.24% 22.50 202.50 6.9 4.92 0.20 4.72 4.72
in Crore
Description Revenue NRs.
Energy, GWh Rate Nrs. NRs.
Wet Tariff Dry Tariff
Dry Energy 13.15 8.4 110460000 11.046
PF 0.71
Annual share of dry
31.70%
energy
Monthly Monthly Monthly
Available Net Net Monthly Avg. Avg. Average
No.of Discharge Overall Headloss Energy Outage(4%)
Month River Turbine Head Avg. Net Dry Wet
Units per Unit Efficiency (m) (GWh) (GWh)
Discharge Discharge (m) Capacity Energy Energy, Energy,
(GWh) (GWh) (GWh)
Baishakh 2.52 2.52 2 1.26 89.24% 3.26 214.29 4.72 3.48 0.14 3.34 3.34
Jestha 5.85 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.38 0.22 5.17 2.50 2.67
Asar 10.83 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.55 0.22 5.33 5.33
Shrawan 12.98 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.38 0.22 5.17 5.17
Bhadra 12.83 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.38 0.22 5.17 5.17
Asoj 8.80 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.38 0.22 5.17 5.17
Kartik 4.28 3.89 2 1.95 89.24% 3.26 214.29 7.30 5.21 0.21 5.00 5.00
Mangshir 2.31 2.31 2 1.16 89.24% 3.26 214.29 4.33 2.99 0.12 2.87 1.38 1.48
Poush 1.60 1.60 1 1.60 89.24% 3.26 214.29 3.00 2.14 0.09 2.06 2.06
Magh 1.27 1.27 1 1.27 89.24% 3.26 214.29 2.38 1.64 0.07 1.57 1.57
Falgun 1.15 1.15 1 1.15 89.24% 3.26 214.29 2.16 1.54 0.06 1.47 1.47
Chaitra 1.24 1.24 1 1.24 89.24% 3.26 214.29 2.32 1.65 0.07 1.59 1.59
45.72 1.83 43.89 13.91 29.98
30
20
Pipe Option
10
Canal Option
0
Dry Wet Total Energy
Energy(Crore) Energy(Crore)
Upper Piluwa-I
HEP
Powerhouse Powerhouse
Option 1 Option 2
1.0 General
Type : Run-of-river, Cascade development of
Upper Piluwa Khola – 2 Hydropower
Project
Source River : Piluwa
State : 1
District : Sankhuwasabha
Municipality : Chainpur, Ward No. 4
Nearest Town : Chainpur Bazaar
Geographical Coordinates
Latitude : 270 17” 00’ N to 270 17” 58’ N
Longitude : 870 20” 56’ E to 870 23” 18’ E
Type of Scheme : Run-of-River
Gross Head : 217.55 m
Net Head : 214.29 m
Design Discharge (Q40.65) : 3.89 m3/s
Installed Capacity : 7.3 MW
Plant Factor : 71%
Net Annual Generation : 43.89 GWh
5.0 Penstock
Material : Steel
Length : 620m
Diameter : 1.7m
6.0 Powerhouse
Type : Surface
Size (L x B x H) :
Type of Turbine : Pelton
Rated Capacity : 2 x 3.65 MW
7.0 Tailrace
Type : Box culvert
Length : 8m
10.0 Generator
Type : Synchronous, Salient pole
Specification : 42000 kVA, 6.6 kV, 50Hz
Power Factor : 0.85
Synchronous Speed : 750 rpm