Beruflich Dokumente
Kultur Dokumente
P. O. BOX 271492
HOUSTON, TEXAS 77277
http://www.profengineering.com
(713) 664-1264
As requested, we are pleased to send you the attached report for the foundation quality of workmanship
inspection performed on the above property. The inspection includes: on-site visual observations of the
foundation construction preparations and installations with the intent of determining the apparent quality of
the foundation and the workmanship related to the construction. This inspection does not include review
of the building design or design of any component of the building either completed or planned as of the
time of the inspection.
We understand the purpose of this inspection was to make visual on-site observations of the workmanship
evident in the construction of the building foundation. As pointed out in the stated purpose of the report, all
of the comments and observations are strictly my opinions, and they may not necessarily agree with other
professionals.
Professional Engineering Inspections, Inc. does not warrant or guarantee the continued performance of
any property inspected beyond the day of inspection. If an extended warranty is desired, it is available
through American Home Shield at 1-800-735-4663 or other similar insurance companies.
This report concludes all obligations related to inspection work provided for the above property for the fee
paid. Thank you for asking PROFESSIONAL ENGINEERING INSPECTIONS, INC. to perform this
inspection work. If you have further questions, please feel free to call on us.
Sincerely yours
Edward Robinson
President
EGR/sl
Attachments
PROFESSIONAL ENGINEERING INSPECTIONS, INC.
P. O. BOX 271492
HOUSTON, TEXAS 77277
http://www.profengineering.com
(713) 664-1264
I. INTRODUCTION
A. Property Description
The property inspected is a house, which will have wood framing, brick veneer and
fiberboard siding, a composition shingle roof, and a post tension concrete slab on
grade foundation.
B. Purpose
The purpose of this inspection was to make visual on-site observations of the
workmanship evident in the construction of the building foundation. The
information will be used as a basis for an opinion of the apparent quality of
workmanship which will be provided in this report. A list of the observed
irregularities and suspected defects will be provided as a part of the report. There
will also be a separate list of some of the most significant irregularities even though
the irregularities may not be very important. Most of the observed irregularities will
be in need of repair or correction to some extent, but it is suggested that the extent
and need for repair be discussed with the general contractor responsible for the
construction of the property. This list of anomalies is not claimed to be the complete
list of irregularities that exist, but a representative list used to form the opinion which
is the basis for this inspection.
C. Scope
On-site visual observations were made of the foundation construction preparations
and installations with the intent of determining the apparent quality of the foundation
and the workmanship related to the construction. This inspection does not include
review of the building design or design of any component of the building either
completed or planned as of the time of the inspection. The design of the building is
considered the responsibility of the builder and/or the engineer or architect who
prepared and approved the plans for construction. There is no intent to determine if
plumbing or other rough- in preparations are properly placed with respect to the
finish components of the building. Placement of rough- in items is the responsibility
of the craftsman and supervisor responsible for the project. This information is
provided for the use of the person to whom this report is addressed and is in no way
intended to be used by a third party, who may have different requirements.
Page 1 of 5
FOUNDATION QUALITY
SANDLOT
II. OPINION
A. Quality of Workmanship
The quality of workmanship indicated in the fabrication of the foundation appears to
be marginally equal to the workmanship found in the foundation of most buildings of
comparable size and price in this area. The number and seriousness of observations
of incomplete, improper, and/or defective workmanship which are listed in this
report are the basis for this opinion.
B. Significant Exceptions
The following exceptions are some of the more significant of the anomalies noted
that have a bearing on my opinion of the quality of workmanship indicated in the
building:
1. The trenches for forming the grade beams were caved in at some locations and
must be cleaned prior to casting the concrete slab. Where soil fills parts of the
trenches, the grade beam dimension will be reduced to an undesirable amount.
Additionally the soil was in contact with the reinforcing.
2. Chairs which support the reinforcing cables were damaged and pushed into the
soil at the pads providing insufficient support for cables. Damaged and
improperly installed cables should be corrected to insure adequate clearances
below the cables which is norma lly a minimum of 1 ½ inches. Reference
Photograph 5
3. There were no supports provided for the top tendons in the grade beams where
they cross perpendicular grade beams. This was resulting in sagging of the top
tendons at these junctions. The post tension institute recommends that these
joints be supported by cross bars or vertical supports to insure straight runs in
the cables. If excessive draping is allowed to occur it may affect the ability to
tension the cables properly. Reference Photograph 10
4. The plumbing for the hall bath at the north side of the foundation was
approximately 12 inches directly behind an anchor point at the edge of the
foundation. The post tension institute recommends that such penetrations be
reinforced or relocated due to the high stress in the concrete which could result
in its failure at the penetration. Reference Photograph 11
III. OBSERVATIONS
The following observations are not claimed to be all the irregularities that existed during
the inspection, but a representative list of observations made that form a basis for the
quality of workmanship opinion:
A. Foundation
2. Drainage at the perimeter of the foundation was very poor, especially at the
following locations: along the south side of the foundation. It is
recommended that the yard grading be accomplished in accordance with the
recommendations contained in the attached Foundation Care Information
sheet.
3. Some debris was observed in the grade beam trenches which must be removed
prior to casting the concrete slab. The debris must be removed before casting
the foundation so that there will be no voids in the concrete sections that are
supposed to be solid.
4. The trenches for forming the grade beams were caved in at some locations and
must be cleaned prior to casting the concrete slab. Where soil fills parts of the
trenches, the grade beam dimension will be reduced to an undesirable amount.
5. There was a significant amount of debris, including pieces of wood, cans, and
soil in the grade beams that must be removed before casting the concrete
foundation. If the debris is left in the trenches, there will be voids and
weaknesses in the concrete slab. Reference Photograph 1
6. The dead-end of a cable was loose at the area of the front porch and needed to
be re-secured to the foundation. Reference Photograph 2
7. The grade beams were caved at many locations at the interior and exterior
grade beams which reduce the dimension of the beams. In some places the soil
had caved and was in contact with the reinforcing cables. There is a need to
remove caved soil and properly position the cables. Reference Photograph 3
8. Wood forming was against a tendon at the grade beam adjacent to the garage
area and supported by a scrap of wood. It is normally desirable for the cables
to be fully encased in the concrete and for the upper tendon to be wired to a
mild steel support to secure it into position. Reference Photograph 4
9. Chairs which support the reinforcing cables were damaged and pus hed into the
soil at the pads providing insufficient support for cables. Damaged and
improperly installed cables should be corrected to insure adequate clearances
below the cables which is normally a minimum of 1 ½ inches. Reference
Photograph 5
10. There were locations where the cables were in contact with the surface of the
plastic underlayment. Locations where this could be observed included at the
east side of the foundation at west of the garage. This appeared to have
occurred because the soil was not properly contoured at these locations.
Reference Photograph 6
FOUNDATION QUALITY
SANDLOT
11. There were locations where the cables were in contact with the surface of the
plastic underlayment. Locations where this could be observed included at the
east side of the foundation at the front of the garage. This appeared to have
occurred because the soil was not properly contoured at these locations.
Reference Photograph 7
12. There were numerous tears in the moisture barrier. These locations should be
repaired prior to placement of concrete. Reference Photograph 8
13. There was a conduit for a pest control system which was installed in contact
with a tendon in the south grade beam and it appeared it was in the zone of
influence of the anchor point. The post tension institute recommends that such
penetration not be placed near an anchor point or that reinforcement be
implemented due to the high stress expected in the concrete in this area.
Reference Photograph 9
14. There were no supports provided for the top tendons in the grade beams where
they cross perpendicular grade beams. This was resulting in sagging of the top
tendons at these junctions. The post tension institute recommends that these
joints be supported by cross bars or vertical supports to insure straight runs in
the cables. If excessive draping is allowed to occur it may affect the ability to
tension the cables properly. Reference Photograph 10
15. There was no provision for a curb at the front porch where it is understood that
wood columns were to be installed. It is desirable to have an anc hor or curb
which will hold the columns off the surface of the concrete to reduce the
potential for it to rot due to becoming frequently wet.
16. The plumbing for the hall bath at the north side of the foundation was
approximately 12 inches directly behind an anchor point at the edge of the
foundation. The post tension institute recommends that such penetrations be
reinforced or relocated due to the high stress in the concrete which could result
in its failure at the penetration. Reference Photograph 11
17. Brick ledge forming was not installed around the entire foundation. It appears
brick was not to be installed at the back of the building. This should be
verified with the builder.
FOUNDATION QUALITY
SANDLOT
PREPARED BY:
Edward Robinson, P. E.
Registered Professional Engineer, #87035
ER/sl
Attachment
The seal appearing on this document was authorized by Edward Robinson, P.E.87035 on 09/26/06. Alteration of
a sealed document without proper notification to the responsible engineer is an offense under the Texas
Engineering Practice Act.
FOUNDATION CARE INFORMATION
Maintenance Recommendations
For Foundations On Expansive Clay Soil
INTRODUCTION
Differential movement of building foundations is a common problem in this area, because of the
highly expansive clay soil and changing weather conditions, and costs owners thousands of dollars
a year in repair bills. As the building ages, it is probable the foundation will continue to
experience differential movement, regardless of how well it was constructed or its present
condition. This differential movement does not stop as buildings become older; older structures
with a history of minimal differential movement have been known to develop foundation problems
in a very short time due to changing conditions at the perimeter of the building foundation.
Page 1 of 2
FOUNDATION CARE
PROFESSIONAL ENGINEERING INSPECTIONS
1. Try to maintain a constant moisture content in the soil around the foundation. Water the
soil evenly and around the entire foundation during extended dry periods. This should
prevent a gap from opening between the soil and foundation edge. However, if a gap does
appear, water frequently (at least daily) around the entire foundation during extended dry
periods (6 to 7 days in the summer). Do not apply water directly into the gap. Instead,
water 1 to 2 feet away from the foundation edge. Some homeowners choose to install a
fully automated foundation watering system to eliminate the need to remember to water. It
is best to add water about three times per day to insure that the applied water has time to
soak into the soil.
2. Cut and cap the roots of any large trees growing closer to the foundation than the mature
height of the trees. The roots from a large tree or several medium size trees can consume
more water from the soil than can be added with a watering system. This will limit the
consumption of water from the soil below the foundation and may prevent excessive
differential settlement and cracks in the structure. It is recommended that a professional
tree expert be used to prevent damage to the trees When a tree grows too close to a
building to allow cutting and capping of the roots, it is advisable to remove the tree or make
special provision for watering the soil below the foundation.
3. Properly grade the soil by filling in low spots and leveling off high spots adjacent to the
foundation so that the surface of the soil slopes gradually away from the building. A
recommended slope is 1 inch per foot for a distance of 3 to 4 feet from the foundation.
4. Control roof water runoff and help prevent soil erosion by using a gutter and downspout
system. This is especially important if a building has no eaves which overhang the walls or
if the eaves are less than 1 foot wide.
5. Water trees and shrubs growing near a building during extended dry periods as they cause
shrinking of the soil due to their high water consumption. Keep in mind that moderate to
large trees consume 50 to 75 gallons of water from the soil every day.
SUMMARY
Remember: the intent of foundation maintenance is to maintain a constant moisture content in the
soil around and below the entire foundation and to prevent soil erosion that can result from water
flowing off the roof or other large flat surfaces near the building.
D. M. Robinson
Registered Professional Engineer, #23598
PROFESSIONAL ENGINEERING INSPECTIONS, INC.
(713) 664-1264
Page 2 of 2
PHOTOGRAPHS September 23, 2006
SANDLOT 11381 Hidden Trails, Houston, Texas
Page 1 of 4
PHOTOGRAPHS September 23, 2006
SANDLOT 11381 Hidden Trails, Houston, Texas
Page 2 of 4
PHOTOGRAPHS September 23, 2006
SANDLOT 11381 Hidden Trails, Houston, Texas
Page 3 of 4
PHOTOGRAPHS September 23, 2006
SANDLOT 11381 Hidden Trails, Houston, Texas
Page 4 of 4