Beruflich Dokumente
Kultur Dokumente
A R T I C L E I N F O A B S T R A C T
Article history:
Received 28 August 2017 The Hawaiian Electric Company intends to procure grid-scale Battery Energy Storage System (“BESS”)
Received in revised form 6 December 2017 capacity. The purpose of this study is to determine whether providing contingency reserve or time-of-day
Accepted 7 December 2017 shifting is of more benefit to the Oahu grid, and to better understand the relationship between BESS size
Available online 23 December 2017 and level of benefit. This is an independent study by Sandia, and is not being used to support the
regulatory case for BESS capacity by Hawaiian Electric. The study team created a production cost model of
Keywords: the Oahu grid using data primarily from the Hawaiian Electric Company. The proposed BESS supplied
Energy storage contingency reserve in one set of runs and time-of-day shifting in another. Supplying contingency reserve
Reserves
led to larger savings than time-of-day energy shifting. Assuming a renewable reserve and a quick-start
Production cost model
reserve, and $15/MMBtu for Low-Sulphur Fuel Oil, the 50-MW/25-MWh, 100-MW/50-MWh, and 150-
Hawaii
MW/75-MWh systems supplying contingency reserve provided, respectively, savings of 9.6, 15.6, and
18.3 million USD over system year 2018. Over the range of fuel prices tested, these cost savings were
found to be directly proportional to the cost of fuel. As the focus is the operational benefit of BESS
capacity, the capacity value of the BESS was not included in benefit calculations.
© 2017 The Authors. Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND
license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
https://doi.org/10.1016/j.est.2017.12.009
2352-152X/© 2017 The Authors. Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344 337
3 4
A discussion of the PLEXOS simulation phases is contained in the user manual In cases with a Quick Start Reserve, we have constrained BESS Contingency
(only available to subscribers) at: https://wiki.energyexemplar.com. Reserve participation to the capacity available in Quick Start Reserve.
338 J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344
reciprocating engines on the Hawaiian Electric system can supply storage volume (at maximum power output) was chosen as it
Quick Start Reserve, with the exception of the Kalaeloa units, matches the Hawaiian Electric storage proposal request of “up to
which are primarily used for baseload generation. 30 minutes” [1].
There is an opportunity cost to specifying a Quick Start Reserve While a 12-h battery (at maximum output) may seem small for
– the units in that reserve will no longer be available to supply peak an Arbitrage application, it should allow the BESS to provide power
power. In order to reduce costs, the system could be operated (less when it is most valuable. It is expected that each additional hour of
reliably) without a Quick Start Reserve and therefore the scenario storage would provide diminishing returns. One caveat here is that
where there is no Quick Start Reserve backing up a Contingency the model will dispatch the battery for the most valuable hour in
Reserve-supplying BESS was also explored. the day, as opposed to 12-h, as the finest time interval in the model is
By 2018, a reserve to compensate for unexpected drops in solar an hour. Therefore, the value of this battery in the time-of-day
and wind production (referred to herein as a “Renewable Reserve”) shifting application is likely to be understated.8
may be required. This reserve would also be on-line reserve that We assume that this BESS will be a lithium-ion battery, as this
can reach nominated output within 10 min and maintain that an established energy storage battery technology and is well-
output for at least 2 h, and can be supplied by any conventional unit suited for the power and storage capacity ratings examined here. A
that is on-line.5 The amount of Renewable Reserve required will 90% round-trip efficiency for the BESS is assumed when providing
depend on both the source of the variable energy and on the Arbitrage. This represents the typical efficiency of a Lithium Ion
amount dispatched. For analysis purposes the formula considered battery system [5].
in this effort is in Eq. (2).6 In this study, the BESS is modeled as a pumped-hydro system,
Renewable Reserve ¼ with the power and storage capacity of the BESS being analyzed.
MINðWindGeneration; 0:5 WindCapacityÞ The battery model is thus two stocks – upper and lower reservoirs
– with flow between them. To pump 90 MWh into the upper
þ MINðUtilityPVGeneration; 0:6 UtilityPVCapacityÞ
reservoir, 100 MWh must be drawn from the grid – yielding the
þ MINðDistributedPVGeneration; 0:2 DistributedPVCapacityÞ required 90% round-trip efficiency. In the Contingency Reserve
ð2Þ case, the battery is not actually activated – it simply remains in
reserve. In the Arbitrage case, the battery is deployed.
In Eq. (2), the actual Renewable Reserve is a function of the
The reason this model's BESS does not actually supply power
actual output, but is capped at 50% of the installed capacity for
when supplying Contingency Reserve is that this is an hourly
wind, 60% for utility PV, and 20% for distributed PV. Given the
model with perfect foresight within a 24-h period. This model
assumptions used for 2018 generation, this comes out to 60 MW
cannot represent things that happen within an hour, such as an
for wind, 90 MW for utility PV, and 80 MW for distributed PV.7
outage at 1:34 pm and spinning reserve immediately being called
To be clear, the model does not allow the BESS to provide
upon to compensate. Also, the model “knows” that a unit will
Renewable Reserve. The hourly model used here is insufficient to
experience a forced outage in, say, hour 15 of a given day, and will
understand how the battery would actually be used to firm wind
dispatch accordingly. The model neither needs a Contingency
and solar generation. Frequent intra-hour discharges of energy
Reserve nor is it able to call upon it. The closest we can come to the
would likely be required to firm variable generation to a forecast.
real world in an hourly production cost model is to specify a
Each time the BESS is used in this way, it would be unavailable for
Contingency Reserve that must be set aside at all times – and never
either Renewable Reserve or Contingency Reserve until it is
activated.
recharged. Without modeling at a finer time scale, it is not possible
to examine the trade-offs involved in using the BESS to supply
3. Data
Renewable Reserve and Contingency Reserve simultaneously. The
only category of reserve the BESS is allowed to provide in this study
The conventional units included in the model, along with their
is therefore Contingency Reserve.
installed capacities, are in Table 1. All units use conventional fuel
At the same time, having a Renewable Reserve in the model is
oil, except for Schofield which will primarily use biodiesel. Both the
important, as it reflects how the system may be operated with
independently-owned dispatchable units and the variable genera-
greater amounts of variable generation. Having larger reserve
tion in the model are listed in Table 2.9
requirements puts more stress on the system. Whether the BESS
Hawaiian Electric provided the following elements of data: unit
serves as Contingency or Renewable Reserve it still functions as a
heat rate curves, fuel type10 and projected cost,11 startup costs (fuel
replacement for spinning reserve, and thus reduces the stress on
and maintenance), minimum and maximum generation points,
the system.
maintenance schedule, and forced outage rate (EFOR). Each unit
BESS capacity and characteristics. A battery size sensitivity was
has its own probability of a forced outage, and each forced outage is
performed in this study, examining 50 MW/25 MWh, 100 MW/
50 MWh, and 150 MW/75 MWh.
The largest capacity was chosen because 150 MW is close to the
8
maximum Contingency Reserve that the BESS in this study could By half-hour battery, what is meant is that the battery has enough storage to
provide, given a net Contingency Reserve requirement of 155 MW. sustain its maximum power rating for half an hour of output. This means that a 100-
MW battery would have 50 MWh of storage. If the model were operating on a half-
The other two sizes were selected to be spaced evenly apart, and to
hourly basis, the battery could be dispatched at 100 MW for half an hour, which
provide a wide enough range for a useful comparison. A 30-min could show more value to the system than the hourly dispatch does. (However, the
battery could be dispatched differently, say at 25 MW for 2 h.)
9
For information on Hawaiian Electric's current generation fleet and their plans
going forward, please see their December 2016 PSIP (Power Supply Improvement
5
For a general discussion of operating reserves for wind power integration, Plan) [12].
10
please see [11]. In these tables, ST stands for Steam Turbine, CT for Combustion Turbine (or gas
6
This Renewable Reserve equation reflects thinking at Hawaiian Electric at the turbine), and RE stands for Reciprocating Engine. Also, LSFO stands for Low Sulphur
time this study was conducted. A newer version was articulated in the December 23, Fuel Oil, Oil for Fuel Oil #2, Bio for Biodiesel, and KALA Oil for the fuel used by the
2016 PSIP. Kalaeloa generator.
7 11
Please see the Hawaii Solar Integration Study [6] for a discussion of how The projected 2018 fuel cost used in the model is (in USD/MMBtu): Coal – 1.93,
different types and amounts of variable generation impact the amount of operating LSFO – 15.18, KALA Oil – 15.69, Fuel Oil – 17.94, and Biodiesel – 34.95. Please note
reserves required. that Oahu LSFO prices on January 1, 2017 were about 9.30 USD/MMBtu.
J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344 339
Table 1 Table 3
Hawaiian Electric Company's dispatchable units in model. Total generation cost savings (in million USD).
Unit Type Fuel Capacity Unit Type Fuel Capacity BESS size Renewable reserves No renewable reserves
Kahe 1 ST LSFO 82 MW Waiau 5 ST LSFO 55 MW Arb CR + QS CR Arb CR + QS CR
Kahe 2 ST LSFO 82 MW Waiau 6 ST LSFO 54 MW
50 MW/25 MWh 2.9 9.6 12.0 3.2 4.8 7.3
Kahe 3 ST LSFO 86 MW Waiau 7 ST LSFO 83 MW
100 MW/50 MWh 4.7 15.6 20.7 4.8 7.1 11.6
Kahe 4 ST LSFO 86 MW Waiau 8 ST LSFO 86 MW
150 MW/75 MWh 5.9 18.3 25.5 5.5 7.5 13.6
Kahe 5 ST LSFO 135 MW Waiau 9 CT Oil 53 MW
Kahe 6 ST LSFO 134 MW Waiau 10 CT Oil 50 MW
CIP CT CT Oil 112 MW Schofield RE Bio 49 MW
12
Reduced unit start costs were responsible for 77% of the $5.9 million in savings
resulting from the use of the 150-MW BESS for Arbitrage. Fig. 2. Total generation cost savings, renewable reserve scenario.
340 J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344
Fig. 3. Difference in total generation cost savings by unit. contours is equal to the required spinning reserve from both the
Contingency Reserve and the Renewable Reserve.
Notable here is that from roughly 2 pm to 9 pm on each of the
lower fuel costs, with about 60% of fuel cost savings due to changes three days Waiau 9 + 10 as well as Schofield are dispatched. The
in generation (less frequent dispatch of marginal units), and 40% decline in solar generation over this period means that conven-
due to improved heat rate (greater efficiency in those units that are tional generation must increase to fill in the void. While the on-line
dispatched). steam turbine units at Kahe and Waiau could generate the needed
The Schofield units operate at roughly the same cost in both power, the system must dispatch additional units to obtain the
cases, but produce 8.3 GWh more power in the 150-MW BESS Case. relatively high level of spinning reserves required.
This is because they were dispatched primarily for reserve in the Fig. 6 illustrates the 150-MW BESS Contingency Reserve Case
Base Case, operating at minimum load – and minimum efficiency. for the same three days. The BESS supplies 150 MW of spinning
In the 150-MW BESS Case, they are used more for peak power, reserve in each hour. Note that Waiau 9 + 10 and Schofield are not
operating at higher loads (and therefore higher efficiency). dispatched over this period. Neither reserves nor power from these
Fig. 4 shows the difference in annual generation by unit units is needed. The system achieves savings by eliminating Waiau
between the two cases in GWh, with positive numbers represent- 9 + 10 starts, not operating these marginal units at partial load
ing an increase (and negative numbers a decrease) in generation (which makes them even less efficient), and by operating the Kahe
from the Base Case. Comparing Figs. 3 and 4, it can be seen that the and Waiau steam turbine units at higher levels, making them more
same units showing the largest cost decreases operate less. efficient.
Tables 4 and 5 provide more insight into how the gas turbines Fig. 7 shows the provision of reserve (which here we define as
and reciprocating engines are being dispatched in each case. Contingency Reserve plus Renewable Reserve) by unit for the Base
In the Base Case, almost all of these units are operating at their Case versus the 150-MW BESS case. Each unit providing reserve in
minimum, as can be seen from their average unit output in Table 4. the Base Case provides a lower amount of reserve in the 150-MW
They seem to be dispatched not for power output, but for spinning case. The BESS itself, not shown on this figure, provides
reserves.13 1,290,000 MWh of reserve in the 150-MW case (averaging out to
However, with the 150-MW BESS case, the picture is much 147 MW of reserve provision in each hour of the year).
different. As shown in Table 5, all of the quick-start units are While the 150-MW BESS providing Contingency Reserve has
dispatched at higher output levels. Schofield's average output is been the main focus in this section, it is also instructive to
near its maximum, reflecting the fact that it is now being used for understand how the BESS operates if instead it operates to provide
power output rather than reserves. The three combustion turbines Arbitrage. Fig. 8 illustrates how the 150-MW BESS providing
are used very little, as one would expect given that they are in a Arbitrage operates over the same three days examined in Figs. 5
quick-start reserve. This lower level of usage, combined with and 6. Over this timeframe, the BESS tends to charge at around
higher set points (and higher efficiencies) when they are used, 11 pm or around noon when solar output is plentiful, and discharge
accounts for much of the savings provided by the BESS providing to help with the evening or morning peaks (when there is little or
Contingency Reserve. no solar output).
After having examined annual operational data, it is useful to Finally, the savings due to the BESS were highly dependent on
study a specific time period for additional insight. Fig. 5 illustrates the fuel price assumed. Model sensitivities were performed with
the Base Case (with Renewable Reserve) for three days, from June the BESS providing both Contingency Reserve (with the Renewable
1–3. The vertical bars show power output by plant, and the solid Reserve and Quick Start Reserve) and Arbitrage (with the
contours at the bottom show the provision of spinning reserve. The Renewable Reserve), reducing liquid fuel costs by 20% and
sum of the vertical bars is equal to the load, and the sum of the solid increasing them by 20%. With the BESS providing Contingency
Reserve, a 20% reduction in liquid fuels prices led to a 20%
reduction in the annual savings, and a 20% increase in liquid fuels
prices led to a 20% increase in the annual savings. With the BESS
13
At the time of the study, 2 MW was the estimated minimum unit capacity at providing Arbitrage, however, a 20% reduction (or increase) in
Schofield. As of May 2017, Hawaiian Electric estimates the minimum capacity per liquid fuels prices led to a 10% reduction (or increase) in annual
unit at Schofield to be 4 MW. The capacity of Schofield to provide spinning reserve,
therefore, may be less than was assumed in this study.
savings.
J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344 341
Table 4
Quick-start units: base case.
Plant Number of units Avg. unit output Max unit capacity Min unit capacity Unit hrs operation Unit hrs above min
Schofield 6 2 8 2 10,205 620
Airport DSG 4 1 2 1 3353 38
Waiau 9 1 12 53 6 1085 671
Waiau 10 1 21 50 6 1600 1596
CIP 1 41 112 41 1009 4
Table 5
Quick-start units: 150-MW BESS case.
Plant Number of units Avg. unit output Max unit capacity Min unit capacity Unit hrs operation Unit hrs above min
Schofield 6 7.6 8 2 3,744 3598
Airport DSG 4 1.4 2 1 2,24 1153
Waiau 9 1 19 53 6 20 20
Waiau 10 1 25 50 6 78 78
CIP 1 66 112 41 270 178
5. Discussion more efficient. The generation from these units will increase. And it
allows the least efficient units to be utilized less, incurring lower
This study has examined one year of operations of the Oahu grid start and fuel costs. When a BESS provides Arbitrage, it operates as
in detail. Understanding this year gives insight into the different a peaker. This allows for conventional peaking units to be started
factors impacting the value of a BESS. less frequently, reducing start costs. It helps to avoid dispatching
In the base case, all dispatchable units provide some level of peaking units at low levels of output, where they are least efficient.
spinning reserve (which is what Contingency Reserve and Using a BESS to provide Contingency Reserve or Arbitrage,
Renewable Reserve actually are) – see Fig. 7. Reserve provision therefore, allows the conventional generation fleet to be dis-
can sometimes be the outcome of economic dispatch. In other patched more efficiently. The amount of savings achieved depend
cases, it must be provided for by deviating from economic dispatch. on how much more efficient the system becomes, as well as on the
Output on efficient units can be decreased to supply headroom. cost of fuel. The more expensive fuel is, the greater the savings
Marginal units can be brought on-line in order to provide the achieved by a given increase in efficiency. It is important to keep in
needed spinning reserve. Or both of these can occur, depending on mind that the efficiency, flexibility, and cost of generation will
what provides the lowest cost. change as new plants are added, old plants retired, and fuel prices
When a BESS provides Contingency Reserve, this allows the change – and that this will have an impact on the level of benefits
most efficient units to operate at full capacity, making them even the BESS provides to the system.
The low BESS storage capacity to power ratio (1:2) limits the extent that Arbitrage value depends on changes in load, the
utility of using the BESS for Arbitrage, where it is used primarily as model's “perfect foresight” may distort the outcome very little, as
a peaker plant. It would be instructive to test larger storage load can generally be predicted with high accuracy.
capacities to determine whether the added benefits outweigh the As variable generation on Oahu increases, it is unclear whether
added costs. At the same time, the Arbitrage savings calculated in providing Contingency Reserve will remain the highest-value
this study do not take into account the capacity value of the BESS application the BESS can perform. Allowing the BESS to firm
system. Adding BESS capacity for Arbitrage provides additional variable generation is an alternative application that should be
peaking capacity, which could allow Hawaiian Electric to defer studied. As the study team examined a year where most power is
adding new generation to deal with peak demand. This additional from conventional generation, and as the model's one-hour time
capacity has a value. If this were taken into account, the value of a resolution did not allow an investigation into how the BESS would
BESS performing Arbitrage would be higher. At the same time, the need to respond in order to firm variable generation, this issue
battery undergoes more cycles when providing Arbitrage as should be kept in mind for a future study. The study team notes,
opposed to Contingency Reserve, shortening its longevity. This however, that as the capacity of variable generation on Oahu
should also be taken into account. continues to increase, the need for both spinning reserve and
At the beginning of each 24-h period, the model has “perfect flexible generation capacity will only increase – both of which
foresight” – it has information as to the load and renewable point to an increase in value in the services provided by a BESS.
generation in each hour of that day. To the extent that Arbitrage The study team also notes that the capital cost of the BESS was
value depends on variable generation output, this could inflate the not considered in this study. This study focuses on the operational
value of BESS Arbitrage provision, as grid operators will not be able benefits of additional BESS capacity. For the reader's benefit,
to forecast variable generation with complete accuracy. To the however, a rough estimate of what a BESS such as this might cost is
1000 USD/kW [5].14
6. Conclusions
14
This estimate does not take into account the expense of transporting the BESS to
Fig. 7. Reserve provision by unit. Hawaii, nor does it take into account any differences in the cost of labor or land.
J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344 343
proposed BESS supplied Contingency Reserve in one set of runs and Over the range of fuel prices tested, the annual savings in
Arbitrage in another. A sensitivity was performed on Contingency Table 3 were found directly proportional to the price of fuel. It is
Reserve, where it was examined with and without a Quick Start important to note that while this study used projected 2018 LSFO
Reserve. pricing of 15.18 USD/MMBtu, Oahu LSFO pricing on January 1, 2017
We examined these cases under two different scenarios: one was about 9.30 USD/MMBtu. This suggests the possibility that 2018
where a Renewable Reserve is required and another where it is not. LSFO pricing will be lower than what was used in this study, which
Our results are in Table 3.15 in turn would mean that the 2018 benefits from using a BESS as
When providing Arbitrage, the BESS is being dispatched to act Contingency Reserve would be lower than the estimates in Table 3.
as a peaking plant, thus reducing the number of unit starts. When At the same time, if LSFO prices go above 15.18 USD/MMBtu in
providing Contingency Reserve, the BESS is never dispatched – future years, benefits from a BESS providing Contingency Reserve
instead, it remains on standby at a full state-of-charge, reducing would likely be higher than those reported in Table 3.
the amount of Contingency Reserve that must be supplied by
spinning reserve.
The most value is obtained by having the BESS serve as 7. Acknowledgements
Contingency Reserve, decreasing the need for spinning reserve and
thereby making conventional unit dispatch more efficient. The We gratefully acknowledge the support of this study's sponsor,
BESS is more valuable when a Renewable Reserve is required the Department of Energy's Energy Storage Program. Led by Dr.
because marginal units must be dispatched more often to provide Imre Gyuk, the Energy Storage Program supports both technical
this additional reserve – and dispatching marginal units increases and analytical work to advance energy storage. The analytical
costs. The BESS supplying Contingency Reserve provides less value work, such as this study, is often done to support a utility in order
when a Quick Start Reserve is required – this is because peaker to provide benefit to both the utility and to the broader community.
plants are required to be in reserve and cannot provide peak power We appreciate the willingness of Hawaiian Electric Company
– even when the system would find it economical for them to do so. personnel to supply us data and help us better understand their
One must consider that the BESS was limited to having a 1:2 system. Victor Bolin, Creighton Liu, Daniel Lum, Ross Sakuda,
energy storage capacity to power ratio in all of the scenarios Kenton Suzuki, and Robert Uyeunten were especially helpful.
studied. A BESS with a larger storage capacity would be more Hawaiian Electric did not participate in the analysis presented
valuable as a peaker plant – and perhaps provide more value than here. The conclusions in this report are not endorsed by the
the provision of Contingency Reserve. At the same time, the Hawaiian Electric Company. This report is an independent study by
Arbitrage savings calculated here do not take into account the Sandia, and has not been/is not being used by Hawaiian Electric to
capacity value of the BESS system. Adding BESS capacity for determine the size of the BESS being procured, to evaluate system
Arbitrage provides additional peaking capacity, which could allow needs, or to support any regulatory filings related to adding BESS
Hawaiian Electric to defer adding new generation to deal with peak capacity. Any errors or omissions are the responsibility of the
demand. This additional capacity has a value. If this were taken into authors alone.
account, the value of a BESS performing Arbitrage would be higher. Sandia National Laboratories is a multimission laboratory
managed and operated by National Technology and Engineering
Solutions of Sandia, LLC., a wholly owned subsidiary of Honeywell
International, Inc., for the U.S. Department of Energy's National
15
In this table, “Arb” means time-of-day shifting through Arbitrage, “CR+QS” Nuclear Security Administration under contract DE-NA-0003525.
means Contingency Reserve together with a Quick Start Reserve, and “CR” means
Contingency Reserve without a Quick Start Reserve.
344 J.F. Ellison et al. / Journal of Energy Storage 15 (2018) 336–344
References [8] E. Kahn, Regulation by simulation: the role of production cost models in
electricity planning and pricing, Op. Res. 43 (3) (1995) 388–398.
[1] Hawaiian Electric Company Request for Proposal (RFP#072114-01) for 60 to [9] M. Carrion, J.M. Arroyo, A computationally efficient mixed-integer linear
200 MW of Energy Storage for Oahu, (2014, May) . (accessed 13.07.16) https:// formulation for the thermal unit commitment problem, IEEE Trans. Power
www.hawaiianelectric.com/clean-energy-hawaii/request-for-proposals- Syst. 21 (3) (2006).
energy-storage-system. [10] D. Shimogawa, Hawaiian Electric Pushes Back Major Energy Storage Plan by a
[2] EIA, Hawaii and Vermont Set High Renewable Portfolio Standard Targets, Year, Pacific Business News, 2015, June.
(2015, June) . http://www.eia.gov/todayinenergy/detail.cfm?id=21852. [11] E. Ela, et al., Evolution of operating reserve determination in wind power
[3] G.M. Masters, Renewable and Efficient Electric Power Systems, John Wiley & integration studies, Power and Energy Society General Meeting, IEEE (2010) 1–
Sons, Inc., Hoboken, NJ, 2004. 8.
[4] P. Denholm, E. Ela, B. Kirby, M. Milligan, The Role of Energy Storage with [12] Hawaiian Electric Company, Power Supply Improvement Plans Update Report,
Renewable Electricity Generation, Tech. Rep., National Renewable Energy (2016, December) . http://selectedpucfilings.hei.com/phoenix.zhtml?
Laboratory, 2010, January. http://www.nrel.gov/docs/fy10osti/47187.pdf. c=101675&p=irol-special-puc-filings.
[5] A.A. Akhil, et al., DOE/EPRI Electricity Storage Handbook in Collaboration With [13] M. Lave, Simulation of Distributed PV in Oahu, HI, Tech. Rep., Sandia National
NRECA, Tech. Rep., Sandia National Laboratories, 2015, Feb, doi:http://dx.doi. Laboratories, 2016, August. http://prod.sandia.gov/sand_doc/2016/167832.
org/10.2172/1170618. http://www.osti.gov/scitech/servlets/purl/1170618. pdf.
[6] K. Eber, D. Corbus, Hawaii Solar Integration Study: Executive Summary, Tech. [14] M. Lave, PV Power all Oahu, (2016, August) . http://prod.sandia.gov/sand_doc/
Rep., National Renewable Energy Laboratory, 2013, June. http://www.nrel.gov/ 2016/167831r.pdf.
docs/fy13osti/57215.pdf. [15] M. Lave, PV Power by Neighborhood, (2016, August) . http://prod.sandia.gov/
[7] J. Ellison, D. Bhatnagar, B. Karlson, Maui Energy Storage Study, Tech. Rep., sand_doc/2016/167830r.pdf.
Sandia National Laboratories, 2012, December, doi:http://dx.doi.org/10.2172/
1088089. http://www.osti.gov/scitech/servlets/purl/1088089.