Sie sind auf Seite 1von 18

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/233315246

Change agents at work: Lessons from Siemens Nixdorf

Article in Journal of Change Management · September 2002


DOI: 10.1080/714042535

CITATIONS READS
16 763

1 author:

Philip A. Dover
Babson College
21 PUBLICATIONS 625 CITATIONS

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Identifying factors for continuous innovation View project

All content following this page was uploaded by Philip A. Dover on 08 September 2016.

The user has requested enhancement of the downloaded file.


Practice papers
Change agents at work: Lessons from
Siemens Nixdorf
Received: 6th August, 2002

Philip A. Dover
is Faculty Director of the School of Executive Education at Babson College, Wellesley, MA,
USA. He has previously served on the faculty at the Amos Tuck School and at IMD and
presently also acts as a visiting professor at Cranfield School of Management in the UK.
He teaches and consults extensively with Fortune 500 companies, mainly in the
technology sector. His major areas of interest lie in corporate entrepreneurship and
strategic market management.

KEYWORDS: culture change, change agents, programme evaluation, prescriptions

ABSTRACT This paper describes a major Change Agent Programme conducted by Siemens
Nixdorf (and later Siemens AG). This programme was part of a larger, sophisticated culture
change initiative. Details of the programme are provided and the benefits accruing to the
company are carefully assessed. It was found that impact should be considered at the levels of
(a) the participant, (b) the business unit and (c) the corporation and that evaluation requires a
longitudinal perspective. A number of lessons are extracted from the analysis — the
requirement for serious senior management commitment, the creation of realistic programme
expectations, providing a road map for post-programme implementation, and so on. Finally,
recommendations are made for future work on this very important topic.

INTRODUCTION Business School on the same Fortune 100


Change is endemic in both private and companies revealed that only 30 per cent of
public lives. For corporations, according change initiatives produced an
to Fast Company, the choice is stark: improvement in bottom-line results that
‘Change — or die’ (Fishman, 1997). And exceeded the company’s cost of capital,
yet, according to the same source, ‘Change: and only 50 per cent led to an improvement
Few can do it, few can sustain it, few can in market share price. As Pascale et al.
survive it’. Moreover, there is substantial (1997) note, ‘This discouraging result was
support for this viewpoint. Fully two-thirds not for lack of trying. On average, each of
of the Fortune 100 — and probably an the companies invested $1bn in change
equally significant proportion of small and programmes over a 15 year period.’
mid-sized companies as well — claim to be
Philip A. Dover in the midst of some type of revamping or These observations are dispiriting, but
Faculty Director, Babson
Executive Education,
major change that is aimed at the behaviour the alternatives to not adjusting to change
Babson College, Wellesley, and skills of hundreds or thousands of are even bleaker. Failure to recognise
MA, USA
people at all levels. Worryingly, research at increasingly powerful drivers of change —
Tel: 11 781 239 5330;
Fax: 11 781 239 5266;
the Harvard rapid technology development, growing
e-mail: dover@babson.edu globalisation of

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243–257 Journal of Change Management 243
Dover

markets, shifting market boundaries, ever- — The kind of change required by most
more demanding customers, and companies is so much more radical and
intensification of direct and indirect uncomfortable than anything met simply
competition — has brought once-powerful by shifts in technology, strategy or
industry icons to their knees. In the Boston structure. As Pascale et al. (1997) note:
area of the US alone, such recent
luminaries as Digital, Prime, Wang and
Polaroid have sadly passed into history. ‘it means a permanent rekindling of
Indeed, their collective demise was felt to individual creativity and responsibility, a
rest in an inability (or unwillingness) to lasting transformation of the company’s
internal and external relationships, an
adjust their culture — the way employees
honest-to-God change in human behaviour
think and act — at least as much as on the job. Revitalisation is not incremental
shortcomings in shifting strategy, process change. Its realizable goal is a discontinuous
or corporate structure. shift in organisational capability’.

This urgent interest in culture change and


corporate change management has In short, the goal is culture change
generated an extensive applied research through the learning of new
literature on the topic. Out of this behaviour and skills.
voluminous database a number of change — Implementation lies at the heart of
management ‘truths’ (findings that are effective change programmes. It is the
repeatedly supported) have emerged. Some CEO or other senior managers who
of the more interesting observations are: provide programme vision and
communicate the rationale for change
and the strategic direction to be adopted
— In order to achieve fundamental change by the organisation. It is, however, the
(often also called revitalisation or regular employees (the doers) who
transformation), employees at every implement the process, putting the detail
level must make committed, imaginative on the big picture. Without the
contributions to organisational success. commitment of these people, no change
The problem with change programmes programme can succeed. There is much
often lies less in programme design and support for the view that change
more in the burden of change resting on operationalisation should be task driven
too few people. — specific tasks designed at each
employee level to contribute to the
— A corollary of this is that employees pursuit of overall change goals.
should be allowed to take more
responsibility for their own destiny
through participation in defining work These four general findings — the need for
objectives, specifying how to achieve employee commitment to change at all
them, and setting stretch targets. levels, the search for more empowerment,
Unfortunately, empowerment is more the learning of new behaviours and skills,
honoured in the breach than in the and the emphasis on task-driven
observance. Senior managers love implementation — raises an important
empowerment in theory but, ultimately, question. If the success of change
the command-and-control model is what programmes depends so much on the goal-
they trust and know best (Argyris, 1998). based actions of large numbers of
committed and motivated employees,

244 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

how can such positive support be actually technology vendor in 1994. The company
generated on the ground? Enter the was created by a 1990 merger between
change agent (CA) or, in McKinsey Nixdorf Computer, an entrepreneurial
parlance, real change leaders (McKinsey minicomputer firm, and the mainframe
deals with organisational change rather computer division of Siemens AG, the
than broader culture change, although German electronics giant. The company
there is clearly a strong association offered a broad range of computer products,
between the two (Katzenbach, 1995)). from personal computers and mainframes to
Although there is some disagreement software and support services. In 1994, the
over the definition of a CA, in this paper company posted $8bn in revenues and
this will be viewed as a person who employed 39,000 people. Despite its size
translates the strategic change vision of and a strong market presence in Europe,
leaders into pragmatic change behaviour. SNI had not posted a profitable quarter
They will be the early adopters — through since the merger. The company had lost
structured learning programmes and other over $350m in fiscal 1994. Over 65 per cent
stimuli — of the new values, actions and of its products were sold in Germany, and
skills required by the company. Through the company had only a weak base in the
this knowledge, they will act as a catalyst growing markets of Asia and North
for the introduction of new ways of doing America. While technological focus was
things across the four corners of the high, SNI was slow to respond to market
corporation. Their goal will be to act as a realities that required more customer
positive virus infecting their host company. responsiveness and less emphasis on large
mainframe systems. In addition, SNI’s
efforts to trim high labour costs were
This paper examines an extraordinarily hampered by strong union pressure and
sophisticated and ambitious Change Agent strict German layoff regulations. Industry
Programme (CAP). Its role within a analysts observed that the company was
broader Culture Change Programme (CCP) constrained by a rigid corporate culture
is assessed, and important lessons are established during the merger. The
drawn for the future design and execution organisational structure was considered too
of CA initiatives. In particular, the ability of bureaucratic in its approach to decision
CAs to act as an effective intermediary in making for the rapidly evolving market.
creating operational impetus for improved
performance through changed behaviour
will be evaluated.
In mid-1994, a decision was made by the
Much of the background description of Chairman of Siemens AG (the 100 per cent
the CAP is taken from cases written at the shareholder of SNI) to bring in a new CEO
Harvard Business School (Kanter, 1996, for Siemens Nixdorf in the search for
1997) and the London Business School profitability. Gerhard Schulmeyer, President
(Ghoshal, 1997). and CEO of the American division of Asea
Brown Boveri (ABB), a Swedish–Swiss
engineering company, was chosen.
THE CHANGE AGENT PROGRAMME Schulmeyer’s goals for SNI were that the
AT SIEMENS NIXDORF company become more customer driven
Siemens Nixdorf Informationssysteme and responsive to the market. Most
(SNI) was the largest European-owned importantly, he was convinced that the
computer manufacturer and information major adjustments

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 245
Dover

Figure 1
Schulmeyer’s
transformation DIRECTION

model
S S B

Y T E

S R H

T U A
C V
E
T I
M U O
S R U
E R

LEARNING

necessary to recreate SNI could only occur underpinned by a continuous learning


alongside a radical change in the corporate process for both individuals and the
culture. He wanted to create an SNI culture organisation itself. A road map (Figure 2)
that enhanced entrepreneurial thinking and was created and published, and execution
team building. He aimed to replace top- set in motion in October 1994.
down procedures with innovative Of particular importance in creating a
leadership that rewarded decision making foundation for change at SNI were the
and risk taking. behavioural and learning components of the
model. On the behavioural side, a set of
To accomplish these goals, Schulmeyer mutually reinforcing initiatives was
initiated a company-wide CCP which had introduced to encourage new ways of acting
three major objectives: and to support the development of new
capabilities. Learning activities were
1 To change the behaviour of managers supported by commitment to a
and employees with a view to achieving comprehensive development programme for
dramatic improvement in performance individuals (including the CAP) as well as
and results. processes to assist organisational learning
2 To change work systems to foster a (eg introduction of an improved
culture of operational excellence. management information system (MIS)).
3 To change processes to emphasise the
customer and to ensure the primacy of
customer service. Behaviour: The Culture Change
Programme
In order to achieve these aims, The mobilisation of the change process
Schulmeyer instigated his own started with the scheduling of four major
transformation model (see Figure 1). change events in Hanover, Germany. The
He calculated that SNI’s radical change first, Hanover I, held in December 1994,
requirements could only be met holistically, was a gathering of selected SNI employees
addressing structure, systems, behaviour with the theme of ‘Giving Employees a
and strategic philosophy, Voice in Defining the New

246 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

Figure 2 Change Siemens Nixdorf Master Schedule Programme


programme road Fiscal Year 95/96 Fiscal Year 96/97
1st quarter 2nd quarter 3rd quarter 4th quarter 1st quarter 2nd quarter 3rd quarter 4th quarter
map
Behavioural capabilities

Culture change initiative Behavioural capabilities

Friday Forum and comm. of practice

Structural capabilities

Fine tuning the organisation


Systems
Systems
Re-engineering/Profit Improvement Programme
Company-wide productivity and quality

Systems Directions/structure/systems

Introduction of new MIS Platform Corporate strategy

Direction/systems

Business strategies and budgeting


Learning

Change agent programme/entrepreneurship development programme/management development programme

Doing/learning Learning/performing

Culture’. Over 300 employees, called set of 300 SNI Opinion Leaders and 75
Opinion Leaders, met with 75 managers, SNI managers teamed up with 54
known as Business Leaders, to agree on customer representatives to develop
changes that were worth striving for at the change ideas and recommendations. An
company. Nineteen topics were identified additional 18 action initiatives were
(eg ‘establishing an environment of generated, such as ‘how to hear the voice
creativity’), followed by brainstorming to of the internal customer’. As with Hanover
translate ideas for change into actions. The I, a Results Fair in January
discussions led to the establishment of 60 1996 presented the status of the work on the
action teams with agendas that required actions identified and assigned during
tangible results within 90 days. A Results Hanover II.
Fair was held in Munich in May 1995, Hanover III, in December 1995, had the
where 12,000 employees were shown what theme of ‘Giving Partners a Voice in
had been accomplished so far on the action Defining the New Culture’. During this
items and what would happen in the future. meeting, SNI worked on strengthening its
partner relationships. In attendance were
350 employees and 40 SNI partners, who
Hanover II, in June 1995, followed the looked for new ways to reinforce and
theme of ‘Giving Customers a Voice in expand the areas in which they worked
Defining the New Culture’. A new together.

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 247
Dover

Hanover IV took place in October consulting firm known for business re-
1996, with a presentation by Schulmeyer engineering. (Although the first programme
on the need to develop a new matrix comprised 13 continuous weeks of study,
organisation. This final event involved subsequent programmes broke down into
decentralising the organisation’s businesses two to three week modules in order to
and associated responsibilities and avoid long periods away from home.
delegating them to some 250 Teaching was conducted at MIT and
‘entrepreneurs’ (Unit Managers) out in Stanford, with site visits arranged to high
the field with full profit-and-loss technology companies in the Boston and
responsibility. Silicon Valley areas.) Each participant
These Hanover meetings were designed undertook a project drawn from a
to help people learn new patterns of previously defined list of the most
behaviour. Instead of the typical important challenges facing the company,
hierarchical distinctions, first names were with the project findings being
the rule, and everyone was free to implemented on the employee’s return to
intervene in the discussions. This SNI. A further post-programme task for the
atmosphere deeply affected participants, employee was to act as a catalyst and
who returned to their day-to-day activities multiplier of change to ensure that the
motivated and fired up with a new sense of culture change initiative would be spread
mission. across the company.
In an effort to disseminate change
information and to stimulate change ideas The high-potential participants were
from throughout the company, a series of selected from the original 300 ‘opinion
Friday Forums was introduced. Whereas the leaders’ invited to Hanover I. The goal of
Hanover meetings were large and one-off the CAP was to build an understanding of
public events, Friday Forums were an business fundamentals and business change
attempt to build a frank and open along three dimensions: customer,
communication environment within the competitiveness and culture. The cost of the
fabric of the organisation. Any topic could instruction was estimated at $100,000 per
be brought to the meetings, from day to day participant, with the ambitious demand that
problems to ‘hot potatoes’ which involved each project generate at least $1m in added
employees from all levels of the company. revenue or saved costs. A key element of the
Information exchanged in the forums was CAP was that each CA was sponsored by
broadcast more widely throughout the two members of management: (1) a
organisation via a fortnightly electronic ‘Business Leader’, who was typically a
mail. In addition to sharing information, senior manager in the division in which the
employees were encouraged to form small CA worked, and who provided funding for
groups to act on issues raised in the the CA’s participation in the programme;
meetings. and (2) an ‘Executive Sponsor’, one of 14
Executive Board members, who was
responsible for the entire division in which
Learning: The Change Agent the CA worked. The CAs discussed and
Programme defined their projects in cooperation with
During Hanover I, Schulmeyer their sponsors. The programme also
introduced the CAP, a programme that intended the sponsors to provide leadership,
allowed 20 employees to go to the US to guidance and support
participate in a 13-week training event
run initially by CSC Index, a

248 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

to the CAs in order to help them achieve within SNI continued as an important goal.
their project and other goals upon return to The development of leadership, business
SNI. The projects spanned a variety of and project management skills grew in
topics from improving innovation at SNI to significance. The projects shifted from
exploring international markets for the being the driving force in the programme to
company. Much of the CAP’s instruction, being an important but not dominant way
including case studies, company visits and for participants to apply their new skills.
coaching was intended to help CAs find The ‘10 3’ return ($100k investment 5 $1m
innovative ways to approach and implement payback) was dropped and replaced by a
their projects. (Two additional educational stretch goal agreed on by the participant
programmes, the Entrepreneurial and his/her Business Leader and Executive
Development Programme and the Sponsor. A study trip to Southeast Asia was
Management Development Programme, added to the programme, to complement the
supported the learning objectives of the time spent in Boston and Silicon Valley.
CAP. The discussion in this paper will be (Although geographic coverage was
restricted to the CAP, because it had such a extended — a module at INSEAD was
high corporate profile and was most closely added in 1999 to add a European
linked with the broader goal of culture perspective — considerable effort was
change.) expended to make it a more cost-effective
programme. Cost per participant dropped
The CAP ran for six years — it was from $100,000 to DM100,000 (about
officially discontinued in late 2000 — in $50,000) when the programme was brought
which time 142 participants graduated as in-house.)
‘CAs’. Although the broad ‘catalyst for
change’ goals remained throughout, the The internal management of the CAP by
operational dynamics shifted over the tenure SNI proved short-lived. In October 1998,
of the programme. In years 2 and 3 of the SNI was fully integrated into the parent
programme, management switched to the company, Siemens AG, and ceased to exist.
consultancy, McKinsey. A heavy emphasis Siemens had become exasperated with the
remained, however, on the projects with the perceived underperformance of its computer
retention of a high level of stress among subsidiary and absorbed all of its activities.
participants. The question was often asked, With this transition, the CCP came to an
‘who has control of the process — end, as did Gerhard Schulmeyer’s
McKinsey or Siemens Nixdorf?’ Indeed, champion’s role. It was decided, however,
towards the end of the third programme, the to continue the CAP under the auspices of
level of discontent of participants grew to a the newly formed division — Information
point where they decided to take over and Communication (I&C) — at Siemens
design of the final module. There was a while retaining the same internal
sense that the project was too dominant with programme team. A strong content
a resultant lack of concern in the programme was delivered in 1999, with
programme design for individual significant individual benefits resulting.
development. Unfortunately, the raison d’etreˆ of
inculcating the whole corporation with
In 1998, substantial changes were made culture change had been lost because most
to the programme. An internal design team senior managers at Siemens showed little
was formed which included three CAs interest in learning from either the
from the previous year’s programme.
Supporting culture change

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 249
Dover

project results or the enhanced skills of 1994–95, the first year of the CCP. Until
participants. Interestingly, one or two Siemens intervened, it remained mildly
business units did continue to encourage the profitable, with reported sales of almost
CAs to act as change catalysts, with positive DM18bn and net income of DM500m
results in terms of both behaviour and in 1998. This performance was
performance. The programme was run again insufficient, however, to convince senior
in 2000, when mid-level managers rather Siemens management that SNI should
than high-potential participants were remain as a stand-alone information
chosen. By this time, the focus had changed technology company. On the ‘softer’
to become more of a leadership excellence side, employee satisfaction surveys
programme. Because of these shifts in the indicated a steady improvement in
environmental and political situation, the morale and confidence over the period
official CAP was terminated at the end of of the CCP. Unstructured observations
2000. indicated that, after a slow start, a
growing number of employees at all
What did SNI — and later Siemens levels of the organisation saw both
— learn from the CAP? What attitudinal personal and institutional benefits from
and behavioural changes, if any, actually changed and more focused values, beliefs
took place within the company? The and attitudes. The take-over by Siemens
remainder of the paper examines these came as a shattering psychological blow
questions. to many SNI personnel, as the CCP
came to an abrupt end with the parent
company showing a marked reluctance
OBSERVATIONS FROM THE CHANGE to consider the culture change initiatives
AGENT PROGRAMME previously undertaken. In truth, SNI was
One of the challenges, and perhaps seen as something of a dilettante —
frustrations, of change initiatives is in privileged, overpaid and a constant drain
isolating reliable measures of effectiveness. on resources — so that there was little
After all, the change programme takes place willingness to adopt their ideas, regardless
in the context of many other mitigating of merit.
internal and external variables (eg varying
market conditions; shifting competitive
forces). Moreover, the CAP took place The change agent experience
within the broader purview of the CCP (at An objective measure of programme
least until the absorption of SNI by outcome is a count of the number of
Siemens). It is useful, therefore, to look participants who remain with the
initially at some outcome indicators from company. Over the six years of the
this latter programme. One can think of programme, 142 ‘graduated’ as CAs. By
‘hard’ and ‘soft’ measures of success. This December 2001 — one year after
is similar to the distinction that has been cessation of the programme — 85 (60
made between ‘hard’ change programmes per cent) remained with the company.
(total quality management, business process Of these, many are now in strategically
re-engineering, etc.) and the more ‘nebulous important positions within Siemens AG.
and soft’ culture change initiatives (eg For those who left, exit interviews
Newman, 1997). revealed that the main reasons were
‘couldn’t find an appropriate post-SNI
In terms of ‘hard’ financial results, SNI position’ and ‘was not being used
produced its first profitable year in properly’. Indeed, a large number left in

250 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

the 1998-99 period, in the immediate cross-functional integration. In addition,


aftermath of the SNI absorption. (Change every effort was made to ensure that
agents contracted to stay with the company faculty fully understood the issues facing
for at least two years after completing the the company. This programme tailoring
programme. A small number of CAs — improved steadily as the programme
never more than 2 per year — chose to evolved, especially when taken over by
leave while still under contract.) The most internal personnel.
popular destination for these leavers was
start-up companies, implying that the — The provision of a truly top-notch
programme had imbued them with an faculty at MIT, Stanford and, later,
entrepreneurial spirit and tolerance of INSEAD. This included such
change. In fact, these CAs were in heavy luminaries as Ed Schein, a world
demand from outside employers, who authority on culture change, Arnaldo
universally viewed the programme in a very Hax, a leading expert on technology
positive light. strategy, Gary Hamel, a guru on
strategic transformation, and Peter
How did the CAs evaluate the Senge, a respected leadership author.
programme? This question will be addressed — The ability to take an international
first, before the broader issue of institutional standpoint on challenges facing the
benefits accruing to SNI/Siemens are modern corporation. This was
discussed. In addition to informally particularly important to SNI, who
monitoring the programme over its duration, sought to shake off their parochial
the author of this paper conducted in-depth German image and replace it with a
interviews with 12 CAs in the Autumn of ‘global’ presence.
2000. Members from each of the first four — The chance for real-time application of
classes were included in the group. holistic learning within the business
Clearly the programme can be assessed projects. This also created layers of
from two major perspectives — the support within the company through the
programme experience itself and the post- involvement of ‘business leaders’ and
programme re-entry into the company. ‘executive sponsors’.
Although programme content and structure — The contribution, beginning in 1997, of a
shifted as time evolved — project strong self-awareness and personal
importance lessened, attention to Europe leadership skills component to the
and Southeast Asia was added to the programme.
original US centricity, the locus of control — The establishment of a tightly knit
shifted from external consultants to internal network of CAs. The intensity of the
personnel, and so on — it was widely programme experience led to the
agreed that it offered a superb learning and creation of strong bonds and a mutually
growth opportunity. Some of the reasons for supportive passion for change that was
this follow. enthusiastically taken back into the
company.
(a) The Change Agent Programme
As a result of this largely positive outcome,
— The delivery of a mini-MBA, almost all participants returned to SNI with
customised to the change needs of SNI: the belief that they had the tools and
This included a strong emphasis on capability to change the culture and
entrepreneurship, leadership and operations of this traditionally conservative
company. It is at this point

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 251
Dover

that cracks begin to appear in the CAP. For programme. This was particularly
all the excitement at the study component, evident when the CAs returned to work
the abiding emotion of CAs on their return and tried to assume a leadership role in
was one of frustration. change initiatives. A certain amount of
jealousy and resistance was to be
(b) Post-programme re-entry expected. The situation at SNI was
exacerbated by some additional
— In many cases, CAs received little considerations. In launching the CAP,
support from senior managers back at Schulmeyer had made it clear that the
the office. This phenomenon manifested future of the company depended, in large
itself in a number of ways. First, CAs part, on these ‘chosen few’. In short,
were often allocated to positions that expectations were very high. Moreover,
differed little, if at all, from their pre- he was deeply and personally involved
programme jobs. Consequently, there in a selection process that appeared to
was limited opportunity to stimulate lack transparency. This led to the
change from positions of weak authority somewhat warped but widespread view
or responsibility. Secondly, there was that participants were ‘anointed’ by the
considerable variance in post- CEO to lead the culture change charge.
programme enthusiasm from project The CAs became known sarcastically as
‘business leaders’ and ‘executive ‘Schulmeyer Kinder’ or ‘Schulmeyer
sponsors’. In business units or Kids’, because they were viewed as
departments where management truly ‘special’ elites designated by the boss. In
embraced the philosophy of the CCP, some cases, they believed their own
some significant progress was made. publicity, going back to the office with
One surrogate measure of change an elevated sense of their own
implementation was perceived project importance and an unrealistic belief in
success. While it is difficult to assess their ability swiftly to encourage change.
financial performance, and project Here again, the situation improved over
outcome depends on more than senior time with much greater transparency and
executive involvement, it was calculated equity being used in participant selection
that 10 to 25 per cent of projects were for the later programmes and a strong
‘successful’. SNI was left with the effort being made to keep CA feet rooted
interesting situation of having isolated firmly on the ground.
areas of change excellence, while other
areas of the company remained largely
unaffected. It should be noted, however, — The post-programme integration of
that this situation improved in the later the CAs back into the company lacked a
years of the programme. Efforts were clearly defined road map. How could
made to ‘train’ senior managers as to they be best used both to communicate
their responsibilities (including and to operationalise what they had
participating in part of the programme) learned? How could they be a
and to create realistic expectations for continuous stimulus to change? These
project implementation. decisions, in fact, were largely left to the
individual CA to make. Little HR
support was forthcoming in the form of
— The CAP initially generated considerable coaching on how to implement ideas
resentment on the part of personnel not and
selected for the

252 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

sensitively assume leadership roles. (c) Change Agent Programme impact


Although the CAs built supportive
informal networks, very few formal — Any programme assessment must start
events were arranged where former with the paradoxical role of Gerhart
participants could get together to seek Schulmeyer. It was his vision and energy
guidance and share experiences. While that took a dysfunctional company and
accepting the need to be somewhat gave it a sense of purpose and direction.
proactive, most CAs desperately needed It was his imagination and
an organisational framework that entrepreneurial spirit that saw the need
outlined a flexible but consistent modus for a both a CCP and an associated CAP
operandi. This shortage of structure, to help facilitate the change process. It
along with senior management’s was his dedication and tireless support
ambivalence, caused many CAs to that led to the design of two of the most
question the true commitment of the sophisticated change programmes
company to genuine cultural change. heretofore seen. But in the end, it is
Things did improve in the 1999–2000 execution that counts. Schulmeyer was
period, when formal post-programme seen as a Godfather, an enlightened
coaching was introduced. leader, a breath of fresh air — CAs
talked of being incredibly galvanised by
his motivational speeches on their role in
Despite these misgivings, most CAs the change process — but he could not
continued to seek ways to contribute guarantee implementation. In fact, his
strongly to positive change within the own missionary zeal may well have
company. Mixed with their sense of clouded his judgment. He failed to
frustration was perhaps a touch of guilt in realise that not all managers shared his
that they had benefited enormously passion, and he therefore relied heavily
personally from the programme, while only on his own personal inspiration rather
achieving a modest institutional impact. than the creation of pedantic but much
There remained a firm desire to ‘give needed operational checkpoints and
something back’ to the company, if only a structures.
clearer road map could be found.

If the CAs were left with mixed — Expectations for change were set too
feelings, what about the broader high. In order to achieve the vision of
institutional reflection on the programme? becoming the ‘European partner of
Although a number of CAs are now using choice among world-class information
their entrepreneurial and leadership skills technology players’, the goal was set to
well in responsible positions, the overall alter the culture to a ‘customer-driven
result from this multi-million dollar ideas factory (where) we encourage
investment would have to be considered entrepreneurship throughout the entire
mixed for the corporation as a whole. Simens Nixdorf network’. The CAs
Why was this? It had visionary leadership, were expected to be a vital component in
a generous budget, a well-planned and this change process. But the difficulties
executed educational programme and and barriers that they confronted have
widespread admiration from external been seen. The more radical the intended
observers. A few major reasons for change, the greater the likelihood of
expectations not being fully met follow. resistance, especially in

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 253
Dover

an inherently conservative culture as It does provide us with some powerful


found in this large German company, lessons, especially on the role of CAs
where many managers could be within the change process. In addition, a
considered ‘uncertainty avoiders’. number of areas for future study are
Change partners needed to be found at suggested.
all levels of the organisation and this the
CAs found hard to do as they strove to
shake-off their ‘exclusive club’ image. KEY LESSONS FROM THE CHANGE
AGENT PROGRAMME
— The CAs were expected to inoculate the
whole of the organisation with their 1. Incorporate change agents into
entrepreneurial ideas and culture change culture change
style. This they intended to do through A CAP — at least of the nature of SNI’s
Friday Forums and other forms of broad — needs to be part of a larger change
communication. In reality, however, management initiative. The CAs can be
their impact — where positively felt — seen as the early adopters or opinion leaders
was mainly at the departmental and in the pursuit of change, replete with a set
business unit level. Here, they were able of skills that encourages entrepreneurial
to assume a leadership role in bringing a thinking and innovative management. But
project to market, in building these efforts must be positioned within a
entrepreneurial teams, and winning the broader change context that has clearly
confidence of close colleagues by articulated vision, goals, strategy and
sharing learned knowledge. Thus change desired cultural values that are continuously
— where it took place — was a largely communicated and updated for all
incremental rather than dramatic employees. Teams play an integral part in
occurrence. As noted earlier, by the time this process (recall the 60 team-based
of the SNI take-over a growing number Action Initiatives that followed Hanover I),
of employees had embraced the with CAs potentially fulfilling an active
requirement for cultural adjustment. This formal or informal role in team
leads to an interesting conclusion. management or direction.
Change Agent Programmes should be
evaluated at three levels: (a) the
individual; (b) the business unit; and (c)
the corporation. It is at the first two 2. Blend programme design with
levels, at least in the short run, where post-programme planning
positive impact can be best expected. It An effective CAP depends on both an
is noteworthy, however, that the outstanding training experience and the
company continues to gain above- clear opportunity for idea implementation
average contributions from old CAs who on return to the workplace. Too often, the
claim that their experience in the former is well designed and executed but far
programme is significantly responsible too little attention is given to the latter. This
for their enhanced performance. was the apparent situation at SNI, although
improvements were evident in the later
programmes. Effective implementation
requires the presence and integration of
many components — an operations road
We are left with a major change experiment map, strong communications assistance for
that produced variable results.

254 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

CAs’ actions, facilitation of networking the ‘future of the organisation’. Most


activities, dedicated senior management companies cultivate a pool of high potential
support, continuous guidance in the individuals who have been earmarked for
transition to a leadership role, the rapid advancement. This group will
transmission of knowledge to peers and generally be young, flexible, hungry for
subordinates. A key question is ‘Who new management knowledge and highly
should assume the responsibility for the receptive to ideas that require considerable
coordination and direction of these cognitive and behavioural adjustment. But
activities?’ Should this be centralised is this enough? The most common refrain
through the Human Resources function or heard in executive development
should it be localised within the programmes is: ‘This is excellent and
appropriate Business Unit? Or should it be thought provoking material. I wish my boss
left to the CAs themselves? It is such could be here to learn from it.’ A familiar
operational decisions that often slip barrier to change is that layer of
through the cracks and result in largely management just below the Board or
unfulfilled CAPs. divisional heads. This group has probably
been at the company for many years, is risk
averse and suspicious of change, often
3. Create realistic programme fearing a diminution of their own
expectations responsibilities and authority. Recognising
It is vital to create realistic expectations for this problem, such managers can be
any CAP. While it is reasonable to position removed or sidelined. Alternatively, they
CAs as catalysts and multipliers of change, can be included as CAs, receiving a tailored
they should also not be seen as ‘walking on educational programme to provide the
water’. There is a real danger that they can change skills required. All too often, this
unwittingly be set up for failure — myopic group is neglected as ‘has beens’, when in
promises from the senior managers who reality there can be a lot of creative (if
instigate the change initiative, inflated sense somewhat buried) talent waiting to be
of self-importance from cosseted CAs, released.
resentment and often downright resistance
from co-workers excluded from the An associated issue is the number of
programme, poor support mechanisms for CAs to be trained. This is a quality versus
implementation activities generate a non- quantity consideration. Change agents
conducive atmosphere for change. Planning must be able to command credibility and
can be greatly aided by this proactive sense respect from their colleagues, yet the
of what can go wrong without carefully dissemination of an entrepreneurial
devised objectives and vigilant control and mindset throughout the organisation
monitoring. demands as many ‘disciples’ as possible.
To overcome this, SNI developed a series
of Entrepreneurial Development
programmes (a five-week project-based
programme, also with active support from
4. Who should be selected? Schulmeyer) that provided training for a
From what ranks of the company will the further 600 high potential employees. This
greatest change stimulus be generated and programme was provided by Babson
therefore where should candidates come College, a leading provider of
from? It is reasonable to argue that this task entrepreneurial education.
should be put in the hands of

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 255
Dover

5. Make change task driven benefits of both past knowledge and an


In the case of SNI, the CA effort was part objective perspective on the company’s
of a company-wide CCP. Questions have challenges. Equally evident is the
been raised, however, as to whether observation that programme management
change is best attained in an incremental should be pulled inside as soon as possible
(eg one business group at a time) rather after launch. It was observed that ‘most
than holistic fashion. Similarly, should companies are overconsulted and
change be a continuous process or be undermanaged’. It is vital to understand that
much more task oriented? Although the the pursuit of institutional change is a
broad culture change philosophy is often radical activity for which responsibility
driven from the centre (through the CEO should not be relinquished to outside forces.
or other very senior executives), actual Moreover, there is always the suspicion that
change must also be a bottom-up consultants — however well intentioned —
phenomenon. While CAs may have a may put their own interests ahead of those
mandate to operate company-wide (eg of the client.
appearing in Friday Forums at SNI), they
are most effective in stimulating new ways
of doing things at a local and highly 7. Establish performance measures
focused level. Indeed, change programmes Finally, there remains the tricky issue of
are energised by quick and very visible how to measure the effectiveness of a CA
‘wins’. The ability, for example, to bring a initiative. As mentioned earlier, one can
new product to market significantly more think in terms of ‘hard’ and ‘soft’ indicators
rapidly while using innovative of success. Another way of looking at it is
cross-functional teams and improving to contrast business targets with cultural
decision-making empowerment at the adjustments. Achieving short-term
point of customer contact can profoundly commercial goals (eg an internal rate of
and positively impact change momentum return on a new product introduction that
within a company. As a corollary, it is exceeds the cost of capital within two
suggested that effective change comes best years) is a necessary but not sufficient
from an integrated and well-articulated measure of CA accomplishment. To be a
series of tasks, each of which attains a true catalyst of change, they must
powerful impetus of its own. Too often contribute significantly to the way people
grandiose change programmes peter out act and think about their work. They must
through lack of focus and the inability to impart their newly acquired knowledge to a
retain the attention of employees who wide and diverse audience. In the SNI case,
perceive the goals as increasingly CAs had not only to achieve positive
amorphous and remote. business results from their projects, but also
to improve the entrepreneurial mindset
within the company through effective team
6. Determine locus of control building and the development of more
Should CAPs (and, for that matter, broader streamlined organisational processes.
culture change projects) be designed and Patience is required to achieve such results,
run by external consultants or should the and these may continue to be observed long
responsibility rest within the company? The after the duration of the programme. As we
SNI experience suggests that there are real have seen, benefits are likely to accrue
merits of external guidance at the initial initially to the
design stages. An established consultancy
has the

256 Journal of Change Management Vol. 3, 3, 243– 257 Henry Stewart Publications 1469-7017 (2003)
Change agents at work

individual, then to the local business witnessed at SNI. This would allow a more
unit, and only finally (if at all) to the scientific assessment of what appears to
corporation as a whole. work and not to work. Linked to this would
be a second proposal — to devise a
template that would, at the very least, pose
CONCLUSIONS a series of questions that companies can
Much has been learned from the design and ask as they put CAPs in place. This would
delivery of the CAP at SNI. The fear of both ensure that future change professionals and
practitioners and researchers is that academics could reap the benefits from
institutional memory quickly dims and that such rich outcomes as those experienced at
important lessons are too easily forgotten, SNI.
others then being destined to repeat the
same mistakes. It is abundantly clear that
devising and managing a truly effective CA
initiative is a complex and demanding task. REFERENCES
The SNI experience established some strong Argyris, C. (1998) ‘Empowerment: The
premises — the need for CA integration into Emperor’s New Clothes’, Harvard Business
a broader culture change effort, the Review, May–June, 98–105.
requirement for serious senior management Fishman, C. (1997) ‘Change’, Fast Company,
April (8), 64–70.
commitment, the benefit of an operational
Ghoshal, S. (1997) Managing Change in the
road map, and so on. It also pointed out
Computer Industry: The Case of Siemens
areas where far less certainty exists — the Nixdorf International, London Business
identification of appropriate CAs, the School, July.
breadth of programme coverage (company Kanter, R. M. (1996) Andy Chew at Siemens
wide or localised?), and the creation of Nixdorf: Change from the Middle, Harvard
realistic expectations remain some of the Business School, Case 9–396–204.
unresolved issues demanding further Kanter, R. M. (1997) The Change Agent
attention. There can be no question, Program at Siemens Nixdorf, Harvard
however, of the pivotal importance of the Business School, Case 9–396–203.
CA in contributing to corporate culture Katzenbach, J. (1995) Real Change Leaders,
change. It is suggested that future applied Random House, New York.
research be directed toward two related Newman, K. (1997) ‘Re-engineering for Service
Quality: The Case of Leicester Royal
activities. The first would be the
Infirmary’, Total Quality Management, 8(5),
development of a database containing 255–264.
details of the design, implementation and Pascale, R., Millemann, M. and Gioja, L.
results from institutional CAPs similar to (1997) ‘Changing the Way We Change’,
that Harvard Business Review, November–
December, 127–139.

Henry Stewart Publications 1469-7017 (2003) Vol. 3, 3, 243– 257 Journal of Change Management 257
Copyright of Journal of Change Management is the property of Routledge and its content
may not be copied or emailed to multiple sites or posted to a listserv without the copyright
holder's express written permission. However, users may print, download, or email articles
for individual use.

View publication stats

Das könnte Ihnen auch gefallen