Sie sind auf Seite 1von 3

June 25, 2018

L1 L2 L3 L4

Bldg. 1 Concrete topping


Plastering outer
wall

Bldg. 2 Skim coat Installation of C-


CHB Laying purlins
Electrical works Dismantling of
(lightings) formworks

Bldg. 3 Dismantling of
formworks

June 26, 2018

L1 L2 L3 L4

Bldg. 1 Plastering outer Dismantling of


wall formworks of lintel
Painting beam

Bldg. 2 CHB laying Skim coat Installation of C-


CHB Laying purlin
Plastering outer Dismantling of
wall formworks of
Painting beams and girders

Bldg. 3 Dismantling of
formworks
June 28, 2018

L1 L2 L3 L4

Bldg. 1 Plastering outer Plastering of Inner


wall and outer walls
Painting

Bldg. 2 Plastering of Plastering of Installation of C-


Exterior walls, Exterior walls, purlin
Installation of Installation of Dismantling of
Door Jamb for Door Jamb for formworks of
beams and girders
CR CR,
Laying out for
plastering of
exterior wall

Bldg. 3 Back-filling,
CHB laying

July 7, 2018

L1 L2 L3 L4

Bldg. 1 Skim coating Pouring of


Installation of concrete mixture
blackboard for lintel beams
Plastering of
rooms

Bldg. 2 CHB Laying of 2


classrooms and
CR

Bldg. 3

July 9, 2018
Bldg. 2 L3
Plastering of CR
Application of Skim coat

Bldg. 2 L4
Installation of formworks and C-bars for lintel beam
Installation of sagrod
CHB laying

Bldg. 1 L4
CHB laying for rooms
Plastering of walls

Das könnte Ihnen auch gefallen