Task ID Task Description Predecessor
Days

A Planning and documentation - 30

Bidding of constructor company,


B construction appliances, and other - 60
project needs

C Deployment of construction needs B 60

Building of underground-to-road
D A 180
connectors

E Hiring of needed crews B 90

F Paving underground foundation B,E 730

G Reinforcing underground B,C 365

Encapsulating underground with


H A,D 365
reinforced fiber glass dome
Installing of underground exhaust
I A,B,C,D,G,H 365
blower fans
Installing bought equipment and
J A,B,C,D,G,H 730
systems

K Deployment of water buoys A,B,C,D,E,F,G,H,J 155

L Deployment of sea life creatures A,B,C,D,G,H,I 365

A,B,C,D,E,F,G,H,I,J
M Systems and equipment check 365
,K,L
A,B,C,D,E,F,G,H,I,J
N Grand opening 1
,K,L,M
A->D->H->I->L->M->N = 30+180+365+365+365+365+1=1671

A->D->H->J->K->M->N = 30+180+365+730+155+365+1=1826

B->C->G->I->L->M->N = 60+60+365+365+365+365+1=1581

B->C->G->J->K->M->N = 60+60+365+730+155+365+1=1736

B->E->F->K->M->N = 60+90+730+155+365+1=1401

Therefore, the critical path is A->D->H->J->K->M->N and the project can


be finished in 1826 days.