PROCEDURAL STEPS

Access transaction by:

Via SAP Standard Menus Logistics  Production-Process  Production Planning  Demand Management
 Planned Independent Requirements  Create / Change / Display
Via Transaction Code MD61 / MD62 / MD63

On screen “Create Planned Independent Requirements: Initial Screen”, enter information in the following
used fields as specified below:

Field Name Description R/O/C User Action and Values Comments


D/N
Planned Section Header
Independe
nt
Requireme
nt for
 Material R Enter relevant Material id or select Select one the radio button
from pull down list. and enter the relevant data
 Product Enter relevant Product group id or in initial screen
Group select from pull down list.
 Reqmts You can enter any combination of
plan letters or numbers – up to 10
number characters.
Plant Key uniquely identifying R Enter relevant Plant id or select
the plant from pull down list.

Plant “1100”
Define Section Header
version
Version Alphanumeric description R By entering one or more version From SOP to Demand
of a demand program, numbers for the demand program, management the default
also known as the you can use the version version is “GP”
(demand) version management function.
number. The system uses the version
number that you enter here as the
default value for items that are to
be created.

Enter “00”
Planning Section Header
www.sap-questions.blogspot.com

User Manual – Training Level 2

DOCUMENT NUMBER: UML2_PP_10_(MD61, MD62, MD63_Maintain Planned Ind Reqmts)_V1.0


PAGE: 2 of 5

TITLE: MD61, MD62, MD63 Maintain Planned Independent Requirements

horizon
From Start of the period of O Enter relevant Start date or select
examination. from pull down list.
To End of the period of O Enter relevant End date or select
examination. from pull down list.
Planning Defines the calendar O Enter relevant calendar period or D
Period periods for entering the select from pull down list.
requirements dates.
(Note: R = Required, O = Optional, C = Conditional, D = Display, N = Not used)

Loading…

 Press “Enter” button to proceed.


www.sap-questions.blogspot.com

User Manual – Training Level 2

DOCUMENT NUMBER: UML2_PP_10_(MD61, MD62, MD63_Maintain Planned Ind Reqmts)_V1.0


PAGE: 3 of 5

TITLE: MD61, MD62, MD63 Maintain Planned Independent Requirements

On screen “Plnd ind. reqmts Create: Planning Table”:

 Select at least one line and click the “Sched. Lines” tab.

On screen “Plnd ind. reqmts Create: Schedule Lines”, enter information in the following used fields as specified
below:
Field Name Description R/O/C User Action and Values Comments
D/N
Sched. Tab
Lines
Indicator: version active R Active indicator controls
whether the demand plan is
relevant to MRP planning.
List Display
Period Defines the calendar R Enter relevant Period indicator “D – for day format like
indicator periods for entering the or select from dropdown list. 31.10.2008”
requirements date
Enter for period indicator “M”. it “M – Month format like
will consider as the 12.2008”
requirement date is at the
beginning of the month
www.sap-questions.blogspot.com

User Manual – Training Level 2

DOCUMENT NUMBER: UML2_PP_10_(MD61, MD62, MD63_Maintain Planned Ind Reqmts)_V1.0


PAGE: 4 of 5

TITLE: MD61, MD62, MD63 Maintain Planned Independent Requirements

Reqmnts Requirements Date or R Enter relevant data or select Period indicator determines
dt. period on/in which the from pull down list. which format of the date is to
planned independent be used
requirement is planned.
Planned The planned quantity R Enter relevant Quantity or Always in Base Unit of
qty determines the quantity select from pull down list. measurement
of a planned independent
requirement for a certain
time or a certain period.
Split This indicator causes the O Enter relevant Period split or Left blank
planned quantity to be select from pull down list.
split up into periods within
the defined intervals.

 Continue to enter requirements as needed.


 Press “Enter” button, and “Save” button.
www.sap-questions.blogspot.com

User Manual – Training Level 2

DOCUMENT NUMBER: UML2_PP_10_(MD61, MD62, MD63_Maintain Planned Ind Reqmts)_V1.0


PAGE: 5 of 5

TITLE: MD61, MD62, MD63 Maintain Planned Independent Requirements

Use MD62 and MD63 to change and display Planned independent requirements.