Office Building Project TRACKING Layout 14-Oct-18 15:16

Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Actual Start Actual Finish Actual Duration BL1 Total Cost 2018 2019
Oct Nov Dec Jan Feb Mar Apr May Jun Jul g
13-Oct-18 22-Jul-19 283d 13-Oct-18 2d $175,300,000 02-Jul-19, Office
Office Build
Building Proje
13-Oct-18 22-Jul-19 283d 13-Oct-18 2d $175,300,000 02-Jul-19, Office
Office Bu
Building Proj
A1000 Start 13-Oct-18 0d 13-Oct-18 0d $0 Start

Earth Work
Wor 13-Oct-18 07-Nov-18 26d 13-Oct-18 1d $36,200,000 05-Nov-18, Earth Work
Access Road 13-Oct-18 07-Nov-18 26d 13-Oct-18 1d $36,200,000 05-Nov-18, Access Road
E1001 Activity 1 13-Oct-18 20-Oct-18 7d 13-Oct-18 1d $5,600,000 Activity 1
E1002 Activity 2 22-Oct-18 07-Nov-18 15d 0d $30,600,000 Activity 2
Civil Work 13-Oct-18 07-Mar-19 146d 15-Oct-18 0d $82,300,000 15-Feb-19, Civil Work
Preparation
Prepara 13-Oct-18 10-Nov-18 29d 15-Oct-18 0d $5,000,000 22-Oct-18, Preparation
C1001 Activity 3 13-Oct-18 10-Nov-18 25d 15-Oct-18 0d $5,000,000 Activity 3
Foundation
Founda 12-Nov-18 08-Jan-19 58d 0d $29,500,000 19-Dec-18, Foundation
C1002 Activity 4 12-Nov-18 15-Dec-18 30d 0d $6,500,000 Activity 4
C1003 Activity 5 17-Dec-18 08-Jan-19 20d 0d $23,000,000 Activity 5
Column and Beam 09-Jan-19 12-Feb-19 35d 0d $40,400,000 23-Jan-19, Column and Beam
C1004 Activity 6 09-Jan-19 25-Jan-19 15d 0d $20,500,000 Activity 6
C1005 Activity 7 26-Jan-19 12-Feb-19 15d 0d $19,900,000 Activity 7
Roof 13-Feb-19 07-Mar-19 23d 0d $7,400,000 15-Feb-19, Roof
C1006 Activity 8 13-Feb-19 07-Mar-19 20d 0d $7,400,000 Activity 8
ME Work 08-Mar-19 13-Apr-19 37d 0d $38,000,000 25-Mar-19, ME Work
HVAC 08-Mar-19 11-Apr-19 35d 0d $13,000,000 22-Mar-19, HVAC
ME10 Activity 10 01-Apr-19 11-Apr-19 10d 0d $5,000,000 Activity 10
ME10 Activity 9 08-Mar-19 30-Mar-19 20d 0d $8,000,000 Activity 9
Fire Fighting
Fig 08-Mar-19 11-Apr-19 35d 0d $10,000,000 22-Mar-19, Fire Fighting
ME10 Activity 11 08-Mar-19 25-Mar-19 15d 0d $5,000,000 Activity 11
ME10 Activity 12 26-Mar-19 11-Apr-19 15d 0d $5,000,000 Activity 12
Cable In
Installation 08-Mar-19 19-Mar-19 12d 0d $5,000,000 27-Feb-19, Cable Installation
ME10 Activity 13 08-Mar-19 19-Mar-19 10d 0d $5,000,000 Activity 13
Lighting 20-Mar-19 13-Apr-19 25d 0d $10,000,000 25-Mar-19, Lighting
ME10 Activity 14 20-Mar-19 27-Mar-19 7d 0d $5,000,000 Activity 14
ME10 Activity 15 28-Mar-19 13-Apr-19 15d 0d $5,000,000 Activity 15
Architect Work 15-Apr-19 22-Jul-19 99d 0d $18,800,000 02-Jul-19, Archit
Ceiling 15-Apr-19 13-May-19 29d 0d $9,400,000 23-Apr-19, Ceiling
AR10 Activity 16 15-Apr-19 25-Apr-19 10d 0d $4,700,000 Activity 16
AR10 Activity 17 26-Apr-19 13-May-19 15d 0d $4,700,000 Activity 17
Painting 14-May-19 11-Jun-19 29d 0d $4,700,000 22-May-19, Painting
AR10 Activity 18 14-May-19 11-Jun-19 25d 0d $4,700,000 Activity 18
Furniture 12-Jun-19 22-Jul-19 41d 0d $4,700,000 02-Jul-19, Furni
AR10 Activity 19 12-Jun-19 22-Jul-19 35d 0d $4,700,000 Activ
Z1000 Finish 22-Jul-19 0d 0d $0 Finish

Primary Baseline Remaining Work Milestone Page 1 of 1 TASK filter: All Activities

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.