Sie sind auf Seite 1von 6

FINAL BILL FOR TOILET WORKS AT ULCI

ABSTRACT OF COST
S.No Descriptions Unit Quantity Rate Amount Remarks
1 Site Clearance and Dismentaling Works
Site Clearance and dismentaling Works all complete LS 1.00 10,000.00
2 Eathwork in Excavation
Excavation in all type soil cu.ft 121.00 30.00 3,630.00
3 Flat Brick Soling
Providing and laying one layer dry brick on flat soling sq.ft 121.00 45.00 5,445.00
4 Plain Cement Concrete
Providing and laying 75 mm PCC of M10 grade sq.ft 121.00 160.00 19,360.00
5 Window/Door
Providing and fixing aluminium casement and fix part window 100x50x1.8mm section I sq.ft 147.00 600.00 88,200.00
6 Partition Works
4" thick Partition work with 10mm thickcement board with GI Framing sq.ft 913.25 350.00 3,19,637.50
7 Plastering/Wall finishing works
Wall Putty sq.ft 2586.50 18.00 46,557.00
Painting Works sq.ft 2586.50 22.00 56,903.00
8 Tile Works
Floor Tile sq.ft 400.00 215.00 86,000.00
Wall Tile sq.ft 1140.00 210.00 2,39,400.00
9 False Ceiling
2'x2' Vinyl touch Gyp-tile Ceiling sq.ft 411.00 120.00 49,320.00
Gypsum False Ceiling sq.ft 56.00 110.00 6,160.00
PART A: 9,30,612.50
II SANITARY WORKS
A Fixtures:
1 Water Closet Set:
Single Piece Water Closet Set set 6.00 12,000.00 72,000.00
2 Wash Basin Set
Below counter Single Wash Basin Set consisting of White Glazed Vitreous China Porcelain mounted
set 2.00 12,500.00 25,000.00
below marble top, basin pillar cock, Bottle Trap, angle Angle and flexible connection.
3 Floor Drain Set:
Floor Drain Set - consisting of uPVC Multi Port Floor Trap and Stainless Steel (SS) Insect Proof Grating
set 8.00 250.00 2,000.00

4 Cold water pipe line and distribution


C-PVC Pipe of CTS 3/4" size (SDR-11) Rft. 252.00 35.00 8,820.00
5 Valves: nos
for 3/4" Ball ValvePipe Line size 4.00 1,200.00 4,800.00

Page 1
S.No Descriptions Unit Quantity Rate Amount Remarks
GM Gate Valves 2.00 1,200.00 2,400.00
Angle Valves 18.00 600.00 10,800.00
6 Pillar/Bib Cocks
Basin Pillar Cock nos 2.00 1,700.00 3,400.00
Short body bidcodk nos 4.00 1,200.00 4,800.00
7 Looking Mirror sets 2.00 6,000.00 12,000.00
Looking Mirror Sets
8 Paper Holder sets 8.00 400.00 3,200.00
9 Towel Rod sets 2.00 500.00 1,000.00
Soil, Waste and Rain Water Drainage Pipe Line (from Toilets/Roof to the ducts and then to Soak
10 pit)
uPVC pipes for Soil Waste, Vent and rain water pipe line having unplastisied poly vinyl chloride

4" Pipe Rft 106.50 250.00 26,625.00


2.5" Rft 106.50 400.00 42,600.00
11 Manholes (450 mm x 450 mm) with Concrete Cover (18" x18") nos 2.00 5000.00 10,000.00
PART B: 2,29,445.00
III ELECTRICAL WORKS
A Light Fixtures
1 Ceiling light/Dome light 8" heavy carrier with led etc all complete set 6.00 850.00 5100.00
2 Wall Lamp with CFL lamp decorative etc all complete set 2.00 850.00 1700.00
B SOCKET, SWITCH JUNCTION BOX (FLUSH TYPE)
Accessories: metal box screws, grips, flexible wire etc all complelte
1 16/6 Amps combined S/socket flush type CPL. Anchor or eqqvt. Etc all complete
2 4 Gang one way switch CPL. Anchor or eqvt. Etc all complete set 4.00 500.00 2000.00
C POINT WIRING set 2.00 300.00 600.00
2x2.5 sq.mm multi strand flexible cu.wire for light & fan point in 1/2" HDPE polythene pipe etc all
m 50.00 32.00 1600.00
complete
D Exhaust Fan nos 4.00 1,200.00 4800.00
PART C: 15,800.00
Total Amount 11,75,857.50
VAT @ 13% 1,52,861.48
Total Amount 13,28,718.98
In Words: NRS Thirteen lakh twenty eight thousand seven hundred eighteen rupees and ninety eight paisa only.

Page 2
Running Bill 01 Measurement Sheet

FINAL BILL FOR TOILET WORKS AT ULCI

Measurement Book
S.No Descriptions Unit Nos Length Breadth Height Quantity Remarks
1 Site Clearance and Dismentaling Works
Site Clearance and dismentaling Works all complete LS 1.00 1.00
Total : 1.00
2 Eathwork in Excavation cu.ft
For Pipe Line 1 71 1 1 71
1 50 1 1 50
Total : 121.00
3 Flat Brick Soling
Providing and laying one layer dry brick on flat soling sq.ft
Upon the Pipe Laying 1 71 1 71
1 50 1 1 50
Total : 121.00
4 Plain Cement Concrete
Providing and laying 75 mm PCC of M10 grade sq.ft
Upon Pipe Laying 1 71.0 1.0 71.0
1 50.0 1.0 50.0
Total : 121.00
5 Window/Door
Providing and fixing aluminium casement and fix part window
5.1 sq.ft
100x50x1.8mm section I
Door 6 2.50 7.000 105.00
2 3.00 7.000 42.00
Total : 147.00
6 Partition Works
4" thick Partition work with 10mm thickcement board with GI
Framing
Longitudianal 3 5.75 9.0 155.25
1 12.00 9.0 108.00
Transverse 2 15.00 9.0 270.00
380.00
Total : 913.25
7 Plastering/Wall finishing works
7.1 Wall Putty Works
Wall Putty sq.ft
Wall 1826.50

Page 11
Running Bill 01 Measurement Sheet

FINAL BILL FOR TOILET WORKS AT ULCI

Measurement Book
S.No Descriptions Unit Nos Length Breadth Height Quantity Remarks
760.00

Total : 2586.50
7.2 Painting Works sq.ft
Wall Painting 1826.50
760.00
Total : 2586.50
8 Tile Works
a Floor Tile sq.ft
Floor Tile 1 200.00 200.00
200.00
Total : 400.00
b Wall Tile sq.ft
Toilet 4 18 5 360.00
Corridor 1 42 5 210.00
570.00
Total : 1140.00
9 False Ceiling
2'x2' Vinyl touch Gyp-tile Ceiling 1 71 5 355.00
Gypsum False Ceiling 1 7 8 56.00 Female Area
Total : 411.00

II SANITARY WORKS
A Fixtures:
1 Water Closet Set:
a. Single Piece Water Closet Set set 6 6.00
3 Wash Basin Set

Below counter Single Wash Basin Set consisting of White Glazed


b. Vitreous China Porcelain mounted below marble top, basin pillar set 3
cock, Bottle Trap, angle Angle and flexible connection.
3.00
4 Floor Drain Set:
Floor Drain Set - consisting of uPVC Multi Port Floor Trap and
set 8
Stainless Steel (SS) Insect Proof Grating 8.00
5 Cold water pipe line and distribution

Page 12
Running Bill 01 Measurement Sheet

FINAL BILL FOR TOILET WORKS AT ULCI

Measurement Book
S.No Descriptions Unit Nos Length Breadth Height Quantity Remarks
C-PVC Pipe of CTS 3/4" size (SDR-11) Rft. 2 126.00 252.00
Total : 252.00
3 Valves:
for 3/4" Ball ValvePipe Line size NOS 4 4
GM Gate Valves NOS 2 2
Angle Valves NOS 18 18
Looking Mirror
Looking Mirror Sets sets 2 2
Paper Holder 0
CI Paper Holder sets 8 8
Towel Rod
CI Towel Rod sets 2 2
Soil, Waste and Rain Water Drainage Pipe Line (from
5
Toilets/Roof to the ducts and then to Soak pit)
uPVC pipes for Soil Waste, Vent and rain water pipe line having
Rft
unplastisied poly vinyl chloride
4" Pipe 1.5 71 106.5
Total : 106.50
2.5" 1.5 71 106.5
Total : 106.50

7 Civil Work
Manholes (450 mm x 450 mm) with Concrete Cover (18"
nos
x18")
Waste water Manhole 1 1
Soil Manhole 1 1
Total : 2.00

III ELECTRICAL WORKS


A Light Fixtures
Ceiling light/Dome light 8" heavy carrier with led etc all
1 set
complete 8 8

Page 13
Running Bill 01 Measurement Sheet

FINAL BILL FOR TOILET WORKS AT ULCI

Measurement Book
S.No Descriptions Unit Nos Length Breadth Height Quantity Remarks
2 Wall Lamp with CFL lamp decorative etc all complete set 3 3
B SOCKET, SWITCH JUNCTION BOX (FLUSH TYPE)
Accessories: metal box screws, grips, flexible wire etc all complelte
16/6 Amps combined S/socket flush type CPL. Anchor or
1 set 5
eqqvt. Etc all complete 5

2 4 Gang one way switch CPL. Anchor or eqvt. Etc all complete set 2
2
Junction box made of metal with cover size 6"x4" etc all
4 set 2
complete 2
C POINT WIRING
2x2.5 sq.mm multi strand flexible cu.wire for light & fan point in
point 18
1/2" HDPE polythene pipe etc all complete 18