PROCEDURE MANUAL
Volume II
Copy No: 00
© No part of the document shall be copied or disclosed without the authorization of the
Chairman and Managing Director, Intercontinental Consultants and Technocrats Pvt. Ltd.
Intercontinental Consultants and
Technocrats Pvt. Ltd.
New Delhi
PROCEDURE MANUAL
VOLUME II
Copy No. : 00
Issue No. : 05 Date : 03 October 2017
Revision No. : 00
DISTRIBUTION LIST
PROCEDURE MANUAL VOLUME II
4 Management Representative 7
HIGHWAY
BRIDGE
SURVEY
4. QSP/8.5.1/Svy/04 Photogrammetry 6
Work Instructions
Issue No. : 05
Doc No : QSP/8.5.1/HW/01 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for providing inputs for preparation of technical / financial
proposal for highway projects.
2.0 Scope
The procedure covers guidelines for preparing inputs, if called for by PC / BD
Division, for preparation of technical / financial proposal.
3.0 Responsibility
HOD (HW) shall be responsible to establish and maintain the procedure.
Nominated coordinator shall be responsible to implement the procedure.
4.0 Procedure
4.1 Planning Risk
Determination of risks and opportunities, meeting the requirements of Clause 6.1 of
the Std ISO 9001:2015 has been done and record maintained in “Risk Register” as
per defined format. ‘Risk Levels’ and ‘Risk Controls’, pertinent inputs for addressal
of the identified risk, have been determined with the help of “Risk Matrix” as per
defined format. Both formats are given Appendix ‘H’ of Quality Manual. The risks
associated with our processes can be of different kinds, for example “Lack of ToR
study and improper briefing about site appreciation to engineer” could be one of the
relevant risk to this procedure.
4.2 HOD (HW) will nominate a Coordinator from within his Division to coordinate
inputs from various Cells.
4.3 In case the PC / BD Division requires input from HW Division for preparing the
Technical Proposal, copy of LOI and TOR will be sent by BD Division based on
which the nature and quantum of works involved and the scope of consultancy
services shall be identified. Comments on TOR if any, shall be sent to BD Division
for obtaining clarification during pre-bid meeting.
4.4 Generally, the following inputs may be provided, if asked for :
Approach and methodology
Schedule of tasks & description of activities
Duration of tasks & activities
Manning schedule for tasks identified
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/01 Date : 03 October 2017
Revision No. : 00
4.5 HOD (HW) shall review the above input data on file before submitting to
BD Division.
5.0 References
TOR
6.0 Records
Retention
Format / Record
By Period
HOD (HW) /
Project File (Only Soft Copy) 1 year
Concerned Coordinator
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
Start
Nomination of Coordinator
No
Yes
Submission of inputs
End
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
2.0 Scope
This procedure specifies requirements for conducting various field surveys, their
studies, working out project details, designs and drawings in the office leading to
compilation of DPR.
3.0 Responsibility
4.0 Procedure
4.3 A project is generally processed through the reconnaissance and inception stage,
feasibility study stage, preliminary project report stage and detailed project report
stage. Various activities in these stages are discussed in the succeeding paragraphs.
4.4.1 Carry out reconnaissance survey of the project site to collect information on :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
Drainage conditions
Condition and extent of the existing facilities and proposed plans for
development
Traffic pattern
Congested areas
Realignment requirements
Requirement of bypasses
Probable locations of toll plazas, bus lay byes, truck parking/lay byes, wayside
amenities, etc.
Collection of available secondary data of the project road from local PWD
office.
4.4.2 Hold a meeting with the client, if required, to brief him on salient features /
requirements and also explain consultant’s approach and methodology, rationale for
selection of traffic survey stations / axle load survey locations, views on specific
aspects / deficiency in the TOR / assignment which became apparent during the
reconnaissance.
4.4.3 TL / PC to prepare a Quality Assurance Plan and an Inception Report and submit to
the client after its review on Format QSP/8.5.1/HW/02:F-02 – Review of Inception
Report and final checking / approval by President / HOD (HW) on Format
QSP/9.0/QMC/13:F-01 – Final Inspection Report. The record of submission to and
approval of client to be maintained on Format QSP/8.5.1/HW/02:F-01 –
Submission / Approval of Reports. Quality Assurance Plan and Inception Report
shall generally contain the following :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
It shall cover all aspects of field studies, investigations, designs and economic
and financial analysis. Procedure for conducting different field studies,
engineering surveys and investigations, designs and documentation activities
are presented as separate sections, e.g. engineering surveys and investigations,
road and pavement investigations, bridges and culverts investigations, design
of bridges and structures, environment and R&R assessment, economic and
financial analysis, drawings and documentation; preparation, checking,
approval and filing of calculations, identification and traceability of project
documents etc. A plan giving the details of personnel responsible for
preparing, checking / verifying various activities forming part of feasibility
study and project preparation, since inception to the completion of work shall
be prepared. The data formats proposed by the Consultants for use in field
studies and investigations shall also be submitted.
Inception Report
- Project appreciation
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
4.5.1 Collect and study all available information, data, reports of the existing facilities
and socio-economic compilations of the influence area. Also collect data regarding
market rates of basic items, availability of labour and labour rates.
4.5.3 Compile inventory of the existing facilities viz. available right of way of the road,
details of cross drainage and other structures, pavement condition, deficiencies in
the road alignment, obligatory points for new alignment, associated nearby
facilities, utilities, land use of area to be acquired (if any) and other important
features of the project road area.
4.5.4 Carry out topographical survey of the existing facilities, cross drainage structures,
realignments, bypasses if any, and / or of the intended project alignment.
4.5.5 Conduct traffic surveys at identified locations, analyze the traffic data and work out
traffic assignment studies and traffic forecast projections.
4.5.6 Conduct all investigations and studies viz. pavement investigations, axle load
surveys, geotechnical studies, soil and material survey along the alignment, testing
of soils and other construction materials, sub-soil explorations at structure locations,
hydrologic and hydraulic studies, pavement evaluation studies, design of C-D works
and structures and availability of construction materials.
4.5.7 Discuss with client and finalize feasible realignments, bypasses, proposals of
widening cross sections and prepare strip plans.
4.5.9 Based on the data collected from investigations and studies, projected traffic volume
and other requirements of the project, work out preliminary design of the pavement,
structures and other facilities.
4.5.10 Prepare analysis of rates, preliminary cost estimates, economic analysis, social and
environmental impact assessment.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
4.5.11 TL / PC to compile draft feasibility study report of the project and furnish
appropriate recommendations to the client. The review of draft feasibility report to
be carried out on Format QSP/8.5.1/HW/02:F-03 – Review of Feasibility Report
(Draft/Final) and final checking / approval by President / HOD (HW) on Format
QSP/9.0/QMC/13:F-01 – Final Inspection Report. The record of submission to and
approval of client to be maintained on Format QSP/8.5.1/HW/02:F-01 –
Submission / Approval of Reports.
4.5.12 Feasibility study report of the project generally contains the following chapters :
Executive summary
Introduction
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
Strip plans
4.5.13 Submit the basic data obtained from the field studies and investigations in a separate
Volume as an Appendix to Feasibility report.
4.5.14 Submit the following documents along with the Feasibility report :
Details of the centre line of the proposed widened highway along with the
existing and proposed right-of-way limits to appreciate the requirements of
land acquisition.
Strip plans showing the position of existing utilities and services indicating
clearly the position of their relocation.
Details for various clearances such as environment, wild life and forest
clearances.
Prepare the utility relocation plans clearly showing existing right-of-way and
pertinent topographic details including buildings, trees, fences and other
installation such as water-mains, telephone, telegraph and electricity poles,
any other common property, environmental / ecological resources and / or
facilities for the public and suggested relocations for submission to the service
departments.
4.5.15 Submit the Final Feasibility report incorporating comments, revisions and
modifications suggested by client within the specified days of receipt of comments
on Draft Feasibility study report. The report shall be reviewed as per format
QSP/8.5.1/HW/02:F-03 – Review of Feasibility Report (Draft/Final) as given at
Para 4.4.11 above.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
4.6.1 Conduct additional topographic survey where necessary and prepare final alignment
plan, profile and cross-sectional details and L-A plans.
4.6.2 Carry out pavement designs with alternate options of pavement for the approved
options, C-D works and other structures, drainage and protective works, road
junctions, etc.
4.6.3 Prepare specifications for all items of works, updated cost of the project with
various alternatives, EIA and social impact report.
4.6.5 Compile Draft Preliminary Project Report. Review the same on Format
QSP/8.5.1/HW/02:F-04 – Review of Preliminary Project Report (Draft/Final) and
its final checking / approval by President / HOD (HW) on format
QSP/9.0/QMC/13:F-01 – Final Inspection Report before submission to Client. The
record of submission to and approval of client to be maintained on Format
QSP/8.5.1/HW/02:F-01 – Submission / Approval of Reports.
4.6.6 The Draft Preliminary Project Report generally contain the following :
Material Report
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 7 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
4.6.7 Submit the basic data obtained from the field studies and investigations and input
data used for the preliminary design in a separate volume as an Appendix to Draft
Preliminary Project Report.
4.6.8 Submit the Final Preliminary Project Report incorporating comments, revisions and
modifications suggested by client within specified days of the receipt of comments
on the draft preliminary project report. The report shall be reviewed as per format
QSP/8.5.1/HW/02:F-04 – Review of Preliminary Project Report (Draft/Final) as
given at Para 4.5.5 above.
4.7.1 Conduct additional topographic survey, if required, together with marking the final
alignment at site. Also conduct additional material survey and investigation, if
required.
4.7.2 Finalize detailed designs and drawings of all highway / road works, structures and
appurtenances in conformity with the design standards and approved alternatives.
4.7.3 Carry out analysis of rates of various items of work and compile detailed cost
estimates, BOQ, contract packaging etc.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 8 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
4.7.4 TL / PC to prepare Draft Detailed Project Report and Contract Documents and
submit to client after its review on Format QSP/8.5.1/HW/02:F-05 – Review of
Detailed Project Report (Draft/Final) and final checking / approval by President /
HOD (HW) on format QSP/9.0/QMC/13:F-01 – Final Inspection Report. The record
of submission to and approval of client to be maintained on Format
QSP/8.5.1/HW/02:F-01 – Submission / Approval of Reports.
4.7.5 The Draft Detailed Project Report generally contains the following :
It presents the project background, social analysis of the project, details of surveys
and investigations carried out, analysis and interpretation of survey and
investigations data, traffic studies and demand forecasts, designs, cost estimates,
environmental aspects, economic and commercial analyses and conclusions. The
report shall include executive summary giving brief account of the findings of the
study and recommendations.
The report shall also include maps, charts and diagrams showing locations and
details of existing features and the essential features of improvement and upgrading.
The basic data obtained from the field studies and investigations and input data used
for the preliminary design shall be submitted in a separate volume as an Appendix
to main report.
It will be in two parts; Part I primarily deals with the design of road features and
pavement composition while Part II deals with the design of bridges and
cross-drainage structures.
The sub-soil exploration report including the complete details of boring done,
results of field and laboratory tests and their analysis, and recommendations on
proposed foundations shall be included as an Appendix to this report.
The detailed design for all features shall be carried out as per the requirements of
the design standards for the project. However, there may be situations wherein it
may not have been possible to strictly adhere to the design standards due to the
existing site conditions, restrictions and other constraints. The report should clearly
bring out the details of these aspects and the variations made in the design
standards.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 9 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
Technical specifications prepared for the proposed project shall be based on the
MORT&H technical specifications for road and bridge works. However, it also
contains additional technical specifications which are not covered by MORT&H
specifications for roads and bridges (latest edition / revision) or amendments to the
specifications provided in this book of specification. It also specifies quality control
norms for the construction of works.
It contains the analysis of rates for all items of works. The details of unit rate of
materials at source, cartage charges, any other applicable charges, labour rates,
machine charges as considered in arriving at unit rates will be included in this
volume.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 10 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
It contains detailed bill of quantities for all items of works including explicit linkage
to the EMP and the RAP.
Volume X : Drawings
All drawings forming part of this volume are good for construction drawings. Plan
and profile and cross-section of drawings are prepared in scale as mentioned in TOR
by client and cover as many kms in 1 sheet as required by client. It contains the
following drawings :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 11 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 12 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/HW/02:F-01
Submission / Approval of Part of Project File
Reports
QSP/8.5.1/HW/02:F-02
HOD (HW) Part of Project File
Review of Inception Report
QSP/8.5.1/HW/02:F-03
Review of Feasibility HOD (HW) Part of Project File
Report (Draft/Final)
QSP/8.5.1/HW/02:F-04
Review of Preliminary HOD (HW) Part of Project File
Project Report (Draft/Final)
QSP/8.5.1/HW/02:F-05
Review of Detailed Project HOD (HW) Part of Project File
Report (Draft/Final)
QSP/8.1/QMC/06:F-01
HOD / TL / PC Part of Project File
Quality Plan
QSP/8.5.1/QMC/10:F-01
HOD (HW) Permanent *
Disk Backup Database
QSP/9.0/QMC/13:F-01
HOD (HW) / TL / PC Part of Project File
Final Inspection Report
Inception Report
HOD (HW) / TL / PC Till completion of project
(Only Soft Copy)
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 13 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
Start
Appointment of PC / TL
Submit to Client Review and Approval Prepare Inception Report Reconnaissance Survey by Key Personnel
Detailed Surveys
Pavement Investigation Topographical Survey Traffic & Transportation Survey Geotechnical and Material
V.C. Survey
Benkelman Beam Deflection GPS Location along Alignment O.D. Survey
Investigation
XYZ Coordinate Junction Survey
Subgrade soil testing
Hydrological Roughness Survey Borrow Area Materials Testing Inventory and
Axle Load Survey
Bridge Inventory Environment and Land Acquisition Investigations LS & CS Condition Survey
and Condition Socio-Economic and Land Pavement Composition Speed Delay Survey Boring at Bridges and high
and Drainage Road Furnitures Willingness to pay Toll Survey Embankment
of Highway and
Survey Studies Records Data Pavement Condition CD Structure
Building / Service etc. VOC Data Aggregate / Material Sourcing
Existing Pavement strength by Strip Plan
Indicative Design Output
and Testing
DCP tests
CD’s Economic Analysis
Financial Analysis
No
Approval by Client
Next Page
Yes
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 14 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/02 Date : 03 October 2017
Revision No. : 00
From Previous
Page
Detailed Design
Geometric Design
Road Design Structures Design
Digital Terrain Model
Preparation
Horizontal Alignment
Vertical Alignment
Pavement Design
Super Elevation Review of Geo-tech CD-Designs Structural Designs
Preparing pavement design scheme
Cross-Sections investigation report Selection of
based on pavement condition survey Retaining Wall
Drainage on bridges & other data and designed plan and profile
Repairing Criteria for
Hydrology of
Road marking plan structures Overlay Design based on BBD and CD structure Drainage
Bridges, CDs Breast Wall
Design of Distress Design of Bridges
Traffic signage plan High Embankment subgrade investigation data Design
and Drainage
Misc. drawings like Design Design of New Carriageway Structure Misc. Furniture
typical layout of bus Life cycle cost analysis for selecting Widening of CD
laybyes, truck the type of pavement Structures
laybyes, toll plaza etc.
No Approval
by Client
Yes Yes
End Approval Prepare Final DPR Approval Review and Approval
by Client by Client
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 15 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/02:F-01 Date : 03 October 2017
Revision No. : 00
1 Inception
2 Feasibility
3 Draft PPR
4 Final PPR
5 Draft DPR
Legend:
7 Final DPR
Planned
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 16 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/02:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
3. Record
Yes No
Development Plans
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 17 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/02:F-03 Date : 03 October 2017
Revision No. : 00
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 18 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/02:F-04 Date : 03 October 2017
Revision No. : 00
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 19 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/02:F-05 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team:
TL / PC
3. Review :
Have following aspects been covered in the report :
Yes No
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 20 of 20
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure to plan and control the design and development of various
elements of a highway.
2.0 Scope
The procedure covers the design and development of the following components of
a highway :
Road Geometrics
Junctions / Interchanges and other Appurtenances
Pavement
High Embankment
Culverts and other Structures
Drainage System
3.0 Responsibility
HOD (HW) shall be responsible to establish and maintain the procedure.
TL / PC / concerned HODs shall be responsible to implement the procedure.
4.0 Procedure
4.1 Design and Development Planning
4.1.1 A design and development plan shall be prepared to include various stages, the
responsibilities for these stages and review, approval and verification appropriate to
each stage. The plan shall be prepared in the Format QSP/8.3/HW/03:F-01 – Design
and Development Plan and updated as the design and development progresses. The
design activities of various elements shall be carried out by the Design Engineers
under guidance of key personnel. Technical interfaces between personnel of the
design team shall be defined in the tabular form given below :
Coordination / Coordination
S. No. Design Stage Remarks
Interface with Issues
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
In accordance with requirements of TOR, the inputs shall be identified for each
design component and shall be reviewed by TL / PC in consultation with concerned
key personnel as per relevant format mentioned against each component. Inputs
required for various component alongwith its source are discussed in succeeding
paragraphs :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
4.2.3 Pavement
The inputs required for different types of pavement are given in the succeeding
paragraphs :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
Annual rainfall and temperature data - Hydrology Cell / Met data from
for the project area web sites
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
Capacity of the existing facilities shall be compared with the projected traffic
volume and need for widening, providing additional carriageways, traffic control
measures etc. shall be determined.
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
The details of service road, etc. shall also be determined. The design shall conform
in general to the provisions and requirements as specified in the latest version of
following codes:
IRC:32, 38, 39, 52, 54, 59, 62, 64, 66, 69, 70, 73, 86, 98, 99, 103, 107
Various characteristics identified for the safe design of road geometrics shall be
checked and approved as per Format QSP/8.3/HW/03:F-02 – Adequacy of Design –
Road Geometrics.
Traffic signs and pavement markings will be designed as per IRC guidelines.
The design shall generally be carried out as per the latest versions of following
codes :
IRC:2, 11, 12, 25, 26, 30, 31, 32, 35, 39, 41, 54, 62, 65, 69, 79, 80, 92, 93, 103
Various characteristics identified for the safe design shall be checked and approved
as per Format QSP/8.3/HW/03:F-03 – Adequacy of Design – Junctions,
Interchanges etc.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
4.3.3 Pavement
The pavement thickness shall be worked out for the cumulative number of
equipment standard axles to be catered for the design life and the subgrade
characteristics using the latest version of the following codes:
IRC:37
IRC:58
IRC:15, IRC:SP:49
Based on the BBD test, after applying the temperature and seasonal corrections,
calculations for mean deflection, standard deviation and characteristic deflection
shall be worked out by the Pavement Engineer. Based on the characteristics
deflections, subgrade strength and pavement condition survey data, the thickness of
overlay shall be worked out using the latest version of the following codes :
IRC:81
4.3.3.4 Various characteristics identified for the safe design of the pavement shall be
checked and approved as per Format QSP/8.3/HW/03:F-04 – Adequacy of Design –
Pavement.
Design of high embankment shall be done with approved computer packages and
correctness of design shall be checked by Geotechnical / Material Engineer.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 7 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
Slope stability analysis for high embankment shall be carried out to ascertain the
embankment’s slope to be recommended. The properties of the soil material for the
embankment shall be as per the design requirement.
The design shall generally conform to the provisions as specified in the latest
version of the following codes :
IRC:36
IRC:75
Various characteristics identified for the safe design of the embankment shall be
checked and approved as per Format QSP/8.3/HW/03:F-05 – Adequacy of Design –
High Embankments.
The design of culverts and other structures shall be carried out by the Highway
Engineer in accordance with the designed standards and / or the standard designs of
culverts. This shall include estimate of design discharge, determination of
waterway and vent height and structural design of foundations, substructure and
superstructure.
The design shall generally conform the provision as specified in the latest version of
the codes:
IRC:SP-13
Various characteristics identified for the safe design shall be checked and approved
as per Format QSP/8.3/HW/03:F-06 – Adequacy of Design – Culverts and other
Structures.
Hydrology Cell shall be responsible for the design of drainage system. The
requirement of roadside drainage linked to the proposed cross-drainage system shall
be worked out for the project road. Adequacy / augmentation of the existing
structures shall be determined from actual requirement at site vis-à-vis collected
data by Highway Engineer / Hydrologist.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 8 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
The designed drainage system shall show size and details of drains, locations of
falls / escapes / outfall points with details of these structures. The drawings for the
same shall be prepared separately.
The design shall generally conform to the provisions as specified in the latest
version of following codes :
IRC:37, 75, 89
Various characteristics identified for the safe design shall be checked and approved
as per Format QSP/8.3/HW/03:F-07 – Adequacy of Design – Drainage System.
4.3.7 Drawings
The drawings for various elements of the highway shall be prepared by the CADD
Section in consultation with the key personnel and TL / PC.
At suitable stages, reviews of various activities have been included in the design and
development planning given in Format QSP/8.3/HW/03:F-01 – Design and
Development Plan. Review shall be carried out for each stage of the project
separately
The design and drawings of various elements of a highway shall be compared with
those of similar structures prepared earlier. In some cases the drawings can be
compared with standard drawings prepared by the MORT&H. The method of
verification and result of verification shall be recorded as per Format
QSP/8.3/HW/03:F-08 – Design Verification for each component of the road
separately.
The design shall be submitted to client for their approval. The client may also carry
out the design verification himself or get it proof checked.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 9 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
Design validation shall be performed to ensure that the resulting product is capable
of meeting specified requirements. Our product being design, approval of the design
by the client shall be treated as its validation.
Based on the comments of client, the design and drawings may be modified,
wherever required after review of comments by the respective key personnel of
design and resubmitted to the client for final approval.
4.8 Flow chart depicting design and development activities is given at Appendix ‘A’.
5.0 References
TOR
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 10 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.3/HW/03:F-02
HOD (HW) /
Adequacy of Design – Road Part of Project File
TL / PC
Geometrics
QSP/8.3/HW/03:F-03
HOD (HW) /
Adequacy of Design – Junctions, Part of Project File
TL / PC
Interchanges etc.
QSP/8.3/HW/03:F-05
HOD (HW) /
Adequacy of Design – High Part of Project File
TL / PC
Embankments
QSP/8.3/HW/03:F-06
HOD (HW) /
Adequacy of Design – Culverts Part of Project File
TL / PC
and other Structures
QSP/8.3/HW/03:F-07
HOD (HW) /
Adequacy of Design – Drainage Part of Project File
TL / PC
System
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 11 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/HW/03 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
DESIGN AND DEVELOPMENT OF HIGHWAYS
Start
Bridge Division
Hydrology Cell
PMG Division
Design Output – Processing of outputs by various Key Personnel with Team Leader / Project Coordinator through CADD Section and its approval
Submission to Client
End
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 12 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-01 Date : 03 October 2017
Revision No. : 00
Responsibility
S. Design and Development Time
Review by Remarks
No. Stages Frame
designation Name
3 (i)
(ii)
(iii)
5 Design Verification
Comments / Approval of
7
Client
8 Design Changes
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 13 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Yes No
Reviewed
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 14 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-02 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 15 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-03 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Yes No
Reviewed
Signature : Date :
Name :
Designation :
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-03 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 17 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-04 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Reviewed
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 18 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-04 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 19 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-05 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Geotechnical Engineer
Reviewed
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 20 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-05 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 21 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-06 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Hydrologist
Yes No
Reviewed
Signature : Date :
Name :
Designation :
Yes No
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-06 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 23 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-07 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC / Highway Engineer
Hydrologist
Yes No
Reviewed
Signature : Date :
Name :
Designation :
Yes No
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 24 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-07 Date : 03 October 2017
Revision No. : 00
Yes No
Approved
Signature : Date :
Name :
Designation :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 25 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/HW/03:F-08 Date : 03 October 2017
Revision No. : 00
DESIGN VERIFICATION
1. Project Title :
2. Team :
3. Verify :
4. Review Remarks (include any problem areas and proposed necessary action)
Verified by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 26 of 26
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for preparation of land acquisition plan and utility location /
relocation plan for highway projects.
2.0 Scope
This procedure cover various aspects involved in preparation of land acquisition
plan and utility location / relocation plan for highway projects.
3.0 Responsibility
HOD (HW) shall be responsible to establish and maintain the procedure.
TL / PC / Land Acquisition Officer shall be responsible to implement the procedure.
4.0 Procedure
4.1 Land Acquisition
4.1.1 The land acquisition plan shall be prepared on the revenue maps (scale 1:3960*)
indicating the following :
Type and category of land use (e.g. irrigated, wet, dry, barren, hilly,
forest, etc.)
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
4.1.3 HOD (HW) / TL / PC shall review the land acquisition plan on file before
submission to the client.
Sewer and drainage lines having gravitational flow shall be laid or shifted at
sufficient depth. These lines shall be laid in the reserve area outside the
carriageway limits.
Storm water drains shall be in the form of open channels and be provided at
the extreme edges of the ROW.
Water supply lines carrying water under pressure shall be provided as far as
possible on one side of the road.
Gas mains and other lines carrying combustible agents shall be laid at one
edge of the ROW and away from the electric cables.
Service ducts shall be provided for optical fibre cables as per requirements.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
Depth of service lines under the road shall be in conformity with the
provisions of the latest version of IRC: 98.
In the longitudinal direction, the utility lines shall be laid parallel to the center-
line of the road.
4.2.6 Accommodation of Utility Lines across a Road
The following requirements shall be kept in mind :
The service line shall cross beneath the road along a line preferably
perpendicular to the road alignment.
The service lines shall be taken through ducts of sufficient size and strength in
order to facilitate future repairs / additions without resorting to fresh digging
of the road.
The installation shall be strong enough to withstand all loads coming on it.
The installation shall be laid in such a manner that there shall be no undue
interference to traffic movement or damage to road pavement.
Lines shall be laid at such depths as to provide adequate cover beneath the
pavement.
To prevent leakage affecting the road, outer casing shall be provided on all
water and oil lines.
The guidelines of utility agencies such as IOCL, GAIL shall be followed while
designing the crossing
4.2.7 Accommodation of Utility Lines across Bridge Structure
The following precautions shall be taken to avoid possibility of any damage to the
bridge and its approaches :
The pipelines shall be supported on the sub-structure of the bridge.
Only seamless pipes with welded joints shall be permitted.
Pipeline on the sub-structure shall be so fixed that it shall be easily accessible
for carrying out its inspection and repairs.
Gas mains and lines carrying combustible material shall be carried out on
independent supports on the riverbed.
Electricity cables and telecom lines carried on the bridge shall be suitably
insulated and carried in protected conduits.
Structural adequacies shall be examined for additional load due to service
lines.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
Underground utility lines once laid along / across the road may require relocation at
a future date. Drawings shall be prepared showing actual location of these utility
lines to facilitate their relocation.
4.2.10 The utility location / relocation plan shall be reviewed by HOD (HW) / TL / PC on
file before its submission to client.
4.2.11 Cost of location / relocation of utilities shall be obtained from the user agencies
after carrying out joint verification.
4.3 Flow charts depicting land acquisition process and utility location / relocation
process are given at Appendix ‘A’ and ‘B’ respectively.
5.0 References
IRC:98
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
Start
Submission to Client
End
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 5 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/04 Date : 03 October 2017
Revision No. : 00
Appendix ‘B’
UTILITY LOCATION / RELOCATION PLAN
Start
Review of Plan
Submission to Client
End
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for preparation of the Final Feasibility cum Preliminary
Design Report for Highway projects to be built with Public-Private Partnership on
Design, Build, Finance and Operate (DBFO) basis.
2.0 Scope
This procedure specifies requirements for conducting various field surveys, their
studies, working out project details, designs and drawings in the office leading to
compilation of the Final Feasibility cum Preliminary Design Report.
3.0 Responsibility
HOD (HW) shall be responsible to establish and maintain the procedure.
PC / TL / concerned HODs shall be responsible to implement the procedure.
4.0 Procedure
4.1 Prepare Quality Plan as per Procedure QSP/8.1/QMC/06 – Planning of Product
Realisation.
4.2 Project is generally processed through the reconnaissance and inception stage, draft
feasibility report stage and final feasibility cum preliminary project report stage.
Various activities in these stages are discussed in the succeeding paragraphs.
Drainage conditions
Condition and extent of the existing facilities and proposed plans for
development
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
Traffic pattern
Congested areas
Realignment requirements
Requirement of bypasses
4.3.3 TL / PC to prepare a Quality Assurance Plan and an Inception Report and submit to
the client after its review on Format QSP/8.5.1/HW/05:F-02 – Review of Inception
Report and final checking / approval by President / HOD (HW) on Format
QSP/9.0/QMC/13:F-01 – Final Inspection Report. The record of submission to and
approval of client to be maintained on Format QSP/8.5.1/HW/05:F-01 –
Submission / Approval of Reports. Quality Assurance Plan and Inception Report
shall generally contain the following :
It shall cover all aspects of field studies, investigations, designs and economic
and financial analysis. Procedure for conducting different field studies,
engineering surveys and investigations, designs and documentation activities
are presented as separate sections, e.g. engineering surveys and investigations,
road and pavement investigations, bridges and culverts investigations, design
of bridges and structures, environment and R&R assessment, economic and
financial analysis, drawings and documentation; preparation, checking,
approval and filing of calculations, identification and traceability of project
documents etc. A plan giving the details of personnel responsible for
preparing, checking / verifying various activities forming part of feasibility
study and project preparation, since inception to the completion of work shall
be prepared. The data formats proposed by the Consultants for use in field
studies and investigations shall also be submitted.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
Inception Report
- Project appreciation.
- Work programme.
4.4.1 Collect and study all available information, data, reports of the existing facilities
and socio-economic compilations of the influence area. Also collect data regarding
market rates of basic items, availability of labour and labour rates.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
4.4.3 Compile inventory of the existing facilities viz. available right of way of the road,
details of cross drainage and other structures, pavement condition, deficiencies in
the road alignment, obligatory points for new alignment, associated nearby
facilities, utilities, land use of area to be acquired (if any) and other important
features of the project road area.
4.4.4 Carry out topographical survey of the existing facilities, cross drainage structures,
realignments, bypasses if any, and / or of the intended project alignment.
4.4.5 Conduct traffic surveys at identified locations, analyze the traffic data, carry out
traffic forecast and also determine tollable traffic and toll revenues.
4.4.6 Conduct all investigations and studies viz. pavement investigations, geotechnical
studies, soil and material survey along the alignment, testing of soils and other
construction materials, sub-soil explorations at structure locations, hydrologic and
hydraulic studies, pavement evaluation studies, design of C-D works and structures
and availability of construction materials.
4.4.7 Conduct Public Consultation, assisted by the local representative of the client and
the local administration, explaining the features of the project, the operational and
safety requirements and manner in which the concerns of the public are addressed.
Subsequently discuss with client and finalize feasible realignments, bypasses,
proposals of widening cross sections and prepare strip plans.
4.4.9 Based on the data collected from investigations and studies, projected traffic volume
and other requirements of the project, work out preliminary design of the pavement,
structures and other facilities.
4.4.10 Prepare analysis of rates, preliminary cost estimates, economic analysis, social and
environmental impact assessment.
4.4.11 Carryout financial analysis of the project to determine its financial viability as a
DBFO project.
4.4.12 TL / PC to compile draft feasibility study report of the project and furnish
appropriate recommendations to the client. The review of draft feasibility report to
be carried out on Format QSP/8.5.1/HW/05:F-03 – Review of Draft Feasibility
Report and final checking / approval by President / HOD (HW) on Format
QSP/9.0/QMC/13:F-01 – Final Inspection Report. The record of submission to and
approval of client to be maintained on Format QSP/8.5.1/HW/05:F-01 –
Submission / Approval of Reports.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
4.4.13 Draft Feasibility study report of the project generally contains the following
chapters :
Executive summary
Introduction
Overview of client’s organization and activities, NHDP programme, project
financing and cost recovery mechanism.
Project description specially the possible alternative project designs (including
realignments / bypasses and technical / engineering alternatives).
Methodology adopted for the feasibility study.
Public consultations including consultations with communities, NGOs, other
stakeholders and government agencies.
Socio-economic profile of the project area.
Design standards to be adopted for the project.
Indicative design and specifications.
Traffic surveys and analysis.
Schematic diagrams (linear chart) indicating but not limited to the following :
- Widening schemes
- Locations of intersections, interchanges, underpasses, overpasses,
bypasses
- Location of service roads
- Location of toll plazas, parking areas, weighing stations, bus bays, rest
areas, if any
- Location of all existing utility services (both over and underground) and
the scheme for their relocation
- Trees to be felled and planted and
- Land acquisition requirements facilitating preparation of schedule for LA
Environmental screening and preliminary environmental assessment.
Social screening and preliminary social assessment (including preliminary
land acquisition / resettlement plan).
Cost estimates (including engineering, environmental, social and management
costs).
Economic and financial analysis for each of the project alternatives.
Conclusions and recommendations.
Strip plans.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 5 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
4.4.14 Submit the basic data obtained from the field studies and investigations in a separate
Volume as an Appendix to the draft Feasibility report.
4.4.15 Submit the following documents along with the draft Feasibility report :
Details of the centre line of the proposed widened highway along with the
existing and proposed right-of-way limits to appreciate the requirements of
land acquisition.
The information concerning the ownership of land to be acquired for the
implementation of the project to be collected from the revenue and other
concerned authorities and presented along with the strip plans.
Strip plans showing the position of existing utilities and services indicating
clearly the position of their relocation.
Details for various clearances such as environment, wild life and forest
clearances.
Separate strip plan showing shifting / relocation of each utility service in
consultation with the concerned local authorities.
Prepare the utility relocation plans clearly showing existing right-of-way and
pertinent topographic details including buildings, trees, fences and other
installation such as water-mains, telephone, telegraph and electricity poles,
any other common property, environmental / ecological resources and / or
facilities for the public and suggested relocations for submission to the service
departments.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 7 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
4.5.6 Submit the basic data obtained from the field studies and investigations and input
data used for the preliminary design in a separate volume as an Appendix to Final
Feasibility cum Preliminary Design Report.
4.5.7 Submit the Final Feasibility cum Preliminary Design Report incorporating
comments, revisions and modifications suggested by client within specified days of
the receipt of comments on the draft feasibility report. Review the same on Format
QSP/8.5.1/HW/05:F-04 – Review of Final Feasibility cum Preliminary Design
Report and its final checking / approval by President / HOD (HW) on format
QSP/9.0/QMC/13:F-01 – Final Inspection Report before submission to Client.
The record of submission to and approval of client to be maintained on Format
QSP/8.5.1/HW/05:F-01 – Submission / Approval of Reports.
4.5.8 Prepare the Schedules (A to V) to the draft concession agreement. Prepare Public
Private Partnership Appraisal Committee (PPPAC) memorandum and check list of
project proposal for PPPAC committee appraisal.
4.5.9 Provide assistance to the Client in the preparation of BOT bid documents; preparing
suitable responses to the bid queries; participate in the pre-bid meeting and assist
the client in preparation of the minutes of the meeting on technical issues; and
finally assist the client in the evaluation of the BOT bids.
4.5.10 Furnish replies to the concessionaire’s queries, if raised by him between the signing
of the agreement and financial closure.
5.0 References
QSP/8.1/QMC/06 – Planning of Product Realisation
QSP/9.0/QMC/13 – Measurement, Analysis & Evaluation of Performance
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 8 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/HW/05:F-01
Submission / Approval of Part of Project File
Reports
QSP/8.5.1/HW/05:F-02
HOD (HW) Part of Project File
Review of Inception Report
QSP/8.5.1/HW/05:F-03
Review of Draft Feasibility HOD (HW) Part of Project File
Report
QSP/8.5.1/HW/05:F-04
Review of Final Feasibility
HOD (HW) Part of Project File
cum Preliminary Design
Report
QSP/8.1/QMC/06:F-01
HOD / TL / PC Part of Project File
Quality Plan
QSP/8.5.1/QMC/10:F-01
HOD (HW) Permanent *
Disk Backup Database
QSP/9.0/QMC/13:F-01
HOD (HW) / TL / PC Part of Project File
Final Inspection Report
Inception Report
HOD (HW) / TL / PC Till completion of project
(Only Soft Copy)
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 9 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
Appointment of PC / TL
Submit to Client Review and Approval Prepare Inception Report Reconnaissance Survey by Key Personnel
Detailed Surveys
Pavement Investigation Topographical Traffic & Transportation Survey Geotechnical and Material
V.C. Survey
GPS Location along Alignment O.D. Survey
Investigation
Benkelman Beam Deflection Subgrade soil testing
Hydrological XYZ Coordinate Junction Survey Inventory and
Axle Load Survey Borrow Area Materials Testing
Bridge Inventory Environment and Land Acquisition Investigations LS & CS Condition Survey
and Condition Socio-Economic and Land
Roughness Survey Speed Delay Survey Boring at Bridges and high
and Drainage Road Furnitures Willingness to pay Toll Survey Embankment
of Highway and
Survey Studies Records Data CD Structure
Pavement Composition Building / Service etc. VOC Data
Aggregate / Material Sourcing
Indicative Design Output
Strip Plan and Testing
Pavement Condition
CD’s Economic Analysis
Financial Analysis
Submit to Client Review and Approval Prepare Draft Feasibility Report Public Consultation
Establish Design Standards and Specifications
Environmental screening and preliminary environmental assessment
No Social screening and preliminary social assessment (including preliminary land acquisition / resettlement plan)
Approval by Client
Formulate Alternate Schemes and present them as linear charts/strip plans, including impact on existing utilities
Next Page Basic preliminary Engineering and Costing
Yes
Initial Economic and Financial Analysis
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 10 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/05 Date : 03 October 2017
Revision No. : 00
From Previous
Page
No Approval by
Client
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 11 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/05:F-01 Date : 03 October 2017
Revision No. : 00
Project Title:
Submission Dates
S. No.
Report Remarks
R0 R1 R2 R3
1 Inception
2 Draft Feasibility
Note: Reasons for time over-runs may be indicated in Remarks column. Legend:
Planned
Actual
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 12 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/05:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
3. Record
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 13 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/05:F-03 Date : 03 October 2017
Revision No. : 00
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 14 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/05:F-04 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team:
TL / PC
3. Review :
Have following aspects been covered in the report :
Yes No
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 15 of 15
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
2.0 Scope
3.0 Responsibility
4.0 Procedure
Pertinent information from the Final Feasibility cum Preliminary Design Report
shall be extracted to furnish information required for various technical schedules
that are integral to the Concession Agreement. Brief details of schedules, where
required, their Annexures and Appendices are given in succeeding paragraph.
Comprises details of the existing condition of the project, through suitable drawings
and description in words, covering the land, buildings, structures and road works
constituting the Site.
Annexure I
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
o Existing Right-of-Way
o The inventory of road, consisting of :
Pavement crust
Truck Laybyes
Busbays
o Inventory of Structures, consisting of :
Annexure II
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
(f) bypasses.
Annexure-I
o Typical cross sections with applicable chainages for each such typical
cross section along the Project Highway
o Right-of-Way details
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
Widening / Rehabilitation
Reconstruction
New construction
Annexure-II
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
Annexure-I
(i) others
Highway patrolling
Ambulances
Cranes
Telecom system.
Annexure-II
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 5 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
Annexure-I
Annexure-II
This schedule sets forth the different Project Milestones and Scheduled Dates for
four / six laning (as applicable) and criteria pertinent to each of the aforesaid
completion stages.
Schedule-H Drawings
This schedule sets forth a broad list of drawings, applicable to the Project Facilities
contemplated for the development of the Project Highway, which the
Concessionaire is required to prepare and submit. These drawings generally include
the following :
Toll plaza layout, toll collection systems and roadway near toll plaza
Control center
Road furniture items including traffic signage, markings, safety barriers etc.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
Pedestrian crossings
Street lighting
In the event a two stage capacity augmentation is applicable and contemplated for
the Project Highway, separate drawings are required to be presented for each of the
two stages of project development.
Schedule-I Tests
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 7 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/06 Date : 03 October 2017
Revision No. : 00
5.0 References
TOR
6.0 Records
Retention
Format / Record
By Period
3 years after
HOD (HW) /
Project File submission of the
TL / PC
Final Report
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 8 of 8
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/07 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for design and drafting using computer aided design
softwares and systems.
2.0 Scope
The procedure covers guidelines and sequence of activities for creating a digital
terrain model of the project road and then integrate that model to produce detailed
design of the road.
3.0 Responsibility
4.0 Procedure
4.1 Each design work station shall be operated by trained Design Engineer.
HOD (HW) / TL / PC / Highway Engineer shall coordinate the activities of Design
Engineers and shall provide first line support.
Collect / import survey data in the design software compatible format such as
dxf, dwg, etc. from the Survey Division.
Send existing and proposed alignment and profile to Water Resources and
Bridge Divisions for design of culverts and bridges respectively.
Based on the accepted design criteria and the horizontal and vertical alignment
(incorporating final deck level of the bridges obtained from Bridge Division),
carriageway designs are processed and then super-elevation is applied to the
carriageway. Widening of carriageway is applicable for single lane and two
lane road on the curve radius less than or equal to 300 m.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/07 Date : 03 October 2017
Revision No. : 00
Design the shoulder of the carriageway and run the earthwork analysis.
Prepare road plan and transfer it on the CADD software for incorporating
bus-bays, truck parking, traffic signs and intersection design.
Transfer final plan and profile to the CADD software for preparation of output
drawings.
Submit plan and profile to the client for comments after review on drawings
by TL / PC / Highway Engineer.
Incorporate comments received from the client, prepare final drawings and
resubmit to the client after review on drawing by TL / PC / Highway Engineer.
4.3 The flow chart showing the CADD process is given at Appendix ‘A’.
5.0 References
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/QMC/10:F-01
HOD (HW) Permanent *
Disk Backup Database
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 2 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/07 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
COMPUTER AIDED DESIGN AND DRAFTING
Start
No
Send to TL /
Highway
Apply Superelevation
Engineer for
approval
Yes
Design Carriageway
Yes
Prepare Long Section Design Service Road and incorporate Drainage Prepare Cross-Section
wherever applicable
Yes
Final Output
End
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
2.0 Scope
3.0 Responsibility
4.0 Procedure
Pertinent information from the Final Feasibility and Detailed Design Report shall be
extracted to furnish information required for the various technical schedules
that are integral to the EPC Agreement. Brief details of schedules, where required,
their Annexures and Appendices are given in succeeding paragraph.
Comprises details of the existing condition of the project, through suitable drawings
and description in words, covering the land, buildings, structures and road works
constituting the Site.
Annexure I
o Existing Right-of-Way
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 1 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Truck Laybyes
Busbays
o Inventory of Structures, consisting of :
Annexure II
The dates on which the authority will provide the right of way to the
contractor on different parts of the site will be mentioned.
Annexure III
Annexure IV
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Appendix A-I
Index map of the project highway will be attached.
Appendix A-II
Chainage wise existing carriageway width will be attached.
Schedule-B Development of the Project Highway
Comprises details of development of the Highway Project i.e. description of 2/4-
laning of the highway.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 3 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Roadside Drainage
Design of Structures
□ Widening / Rehabilitation
□ Reconstruction
□ New construction
Roadside Furniture
Compulsory Afforestation
Hazardous Locations
Change of Scope
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 4 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Annexure-I
(i) others
Highway lighting
Highway Patrol
Ambulances
Cranes
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 5 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Annexure-I
Schedule-I Drawings
This schedule sets forth a broad list of drawings, applicable to the Project Facilities
contemplated for the development of the Project Highway, which the Contractor is
required to prepare and submit. These drawings generally include the following :
This schedule sets forth the different Project Milestones and Scheduled Dates for
two / four laning (as applicable) and criteria pertinent to each of the aforesaid
completion stages.
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 6 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/08 Date : 03 October 2017
Revision No. : 00
Schedule-P Insurance
5.0 References
TOR
MORT&H guidelines
6.0 Records
Retention
Format / Record
By Period
3 years after
HOD (HW) /
Project File submission of the
TL / PC
Final Report
Signature
Designation HOD (Highway) President Management Representative
Prepared by Approved by Issued by Page 7 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
2.0 Scope
The procedure covers determination of design flood discharge and HFL of a river at
road crossing for fixing the road level, to evaluate adequacy of the existing cross
drainage structures, identify new cross drainage works including river training
works.
3.0 Responsibility
4.0 Procedure
Data Responsibility
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 1 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
Keeping in view the type of river stream / canal and the input data available, the
applicability of method / methods given below shall be decided for calculation of
design flood discharge. The codal provisions shall be adhered to as applicable. The
effort shall be made to adopt as many methods as possible to ensure judicious
design discharge values.
Rational method
The flood discharge shall be estimated by the above methods for a return period of
not less than 100 years for bridges and 25 years for culverts. On the above basis,
design discharge shall be arrived at as per CWC, IMD and MORT&H Joint Flood
Estimation Report of different zones, IRC:5 and IRC:SP:13 provisions. In other
cases, the design discharge shall be fixed judiciously giving proper explanation in
support of the adopted design discharge.
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 2 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
The Highest Flood Level (HFL) shall be established and reasons in support of the
adopted values of HFL shall be recorded. HFL shall be checked for corresponding
design discharge as adopted under Paras 4.2 and 4.3 above.
Hydraulic parameters e.g. waterway, fluming, afflux, scour depth etc. for the
existing / proposed bridges and cross drainage structures shall be worked out based
on IRC:5, IRC:SP:13 and other relevant Central Water Commission (CWC) Flood
Estimation Reports.
4.7 Computation
The following data shall be computed :
Afflux
Design discharge
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 3 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
Hydraulic parameters e.g. fluming ratio, scour depth, Froude Number etc.
(abstract of design discharge and hydraulic parameters)
4.10 Record of backup sets of data and report shall be maintained as per format
QSP/8.5.1/QMC/10:F-01 – Disk Backup Database.
5.0 References
TOR
IRC:5 and 89
IRC:SP:13 and 54
MORT&H’s Guidelines
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 4 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/HW/09:F-01
Review of Report on
Hydrological and Hydraulic Part of Project File
Studies for Road Cross Drainage
Structures
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 5 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/09 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
HYDROLOGICAL AND HYDRAULIC STUDIES FOR
ROAD CROSS DRAINAGE STRUCTURES
Start
HOD (HW)
Nominate Hydrologist
Hydrological Details Bridge Details
No
End
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 6 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/09:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
Hydrologist
3. Review
Yes No NA
Flood Conditions
Issue No. : 05
Doc No : QSP/8.5.1/HW/09:F-01 Date : 03 October 2017
Revision No. : 00
Yes No NA
- Empirical method
- Rational method
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 8 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/09:F-01 Date : 03 October 2017
Revision No. : 00
Yes No NA
4. Review Remarks
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 9 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/10 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
2.0 Scope
The procedure covers the requirement of road drainage to side drains and culverts
and preparation of drawings of the drainage system.
3.0 Responsibility
4.0 Procedure
Data Responsibility
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 1 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/10 Date : 03 October 2017
Revision No. : 00
Keeping in view the type of drain and drainage arrangement and the input data
available, the applicability of method / methods given in relevant IRC standard shall
be followed for calculation of design flood discharge. The codal provisions shall be
adhered to as applicable and accordingly afflux shall be fixed.
The High Flood Level (HFL) shall be established on the basis of road gradient and
free length of road draining to the nearest outfall drain through a culvert.
Computation of depth of flow and bed widths for different types of drain –
lined and unlined
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 2 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/10 Date : 03 October 2017
Revision No. : 00
Drainage report and drawings shall be submitted to TL/PC for follow-up action and
shall contain :
Location and type of drains - single / twin drain on either side, median
drainage
4.7 Records of backup sets of data and report shall be maintained as per format
QSP/8.5.1/QMC/10:F-01 – Disk Backup Database.
5.0 References
TOR
Issue No. : 05
Doc No : QSP/8.5.1/HW/10 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/HW/10:F-01
Review of report on
Hydrological and Hydraulic Part of Project File
Studies for Road Side
Drainage System
QSP/8.5.1/QMC/10:F-01
HOD (HW) / TL / PC Permanent*
Disk Backup Database
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 4 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/HW/10 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
HYDROLOGICAL AND HYDRAULIC STUDIES FOR
ROAD SIDE DRAINAGE SYSTEM
Start
HOD (HW)
No
End
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 5 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/HW/10:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
Hydrologist
3. Review
Yes No NA
Culvert inventories for all existing culverts have been
made available.
Design rainfall and runoff data for the area have been
found from rain gauging station from IMD / CWC /
other reports.
Issue No. : 05
Doc No : QSP/8.5.1/HW/10:F-01 Date : 03 October 2017
Revision No. : 00
Yes No NA
Drainage requirement based on existing terrain and road
passing through different area e.g. urban / rural / hilly /
forest / sea / airport etc. has been studied and decision
taken in consultation with TL / PC.
Type of drains (covered / uncovered / lined / unlined
etc.) to be provided have been decided in consultation
with TL / PC.
Long profiles and typical cross-section of road have been
studied for fixing location and layout of drains and their
outfalls.
Outfall points of all drains at culverts / bridges / ponds /
escapes etc. have been decided after due verification at
site and ensuring that the cross drainages are of adequate
capacity.
Bed slopes of drains have been decided as per existing
ground level / proposed road level (both carriageway and
service roads) keeping in view that the invert level of
drain at outfall is above the HFL / bed level of cross
drainage structures.
Conveyance of each type of drain has been calculated
and the carrying capacity of drains have been checked
against design discharge for different stretches.
Velocities are found and checked with permissible
maximum velocity and self cleansing velocity.
Drainage drawings have been prepared in accordance
with design indicating outfalls, escapes, chutes, energy
dissipaters, drainage arrangements for junctions /
medians / super elevated reaches, interchanges / ROB /
underpasses.
4. Review Remarks
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Highways) President Management Representative
Prepared by Approved by Issued by Page 7 of 7
PAVEMENT, MATERIAL &
GEO-TECHNICAL
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for geological and geotechnical investigation required for
engineering design of highways, high embankments, bridges, tunnels and other
structures.
2.0 Scope
3.0 Responsibility
4.0 Procedure
Geological maps of the area and provide background and general information
about geology and geomorphology of the area.
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 1 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
Based on the requirements of TOR/WO and desk studies of available reports, the
Geotechnical Engineer/Geologist in consultation with HOD (PMG) shall plan
geotechnical and geological investigation. Stage-wise investigation, if specified by
the TOR shall be considered for planning & scheduling of investigation. In order to
complete the job within scheduled time frame, he/she shall identify the tasks to be
carried out during various stages of investigation. If necessary, prior to
mobilization, site visit shall be conducted to gather more information on soil
conditions along the alignment, and at location of structures. During the site visit,
previous data, reports and studies if available with the Client shall be collected,
subsequently evaluated and considered in the execution of investigation and
preparation of Inception Report.
Carryout reconnaissance survey of the project site, appraise local geology, rock
formations, slip zone etc.
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 2 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
Identify volcanic eruptions, tectonic movements along the alignment, if any and
describe lithology of the project area.
Carry out detailed geological mapping of the area to observe and make note of
geological features such as type of strata, existence of outcrops, folds, faults,
ground water regime etc. and their influence in the analysis of rock fall and on
the geometry of alignment. Measure dips and strikes of exposed beds and
discontinuities such hat these can be plotted in stereonet.
Detailed study of slopes, tributary valleys, landslides (active & inactive), springs
& seeps, sinkholes and nature of unconsolidated overburden and preparation of
landslide hazard zonation map.
Classification of slope movements into (a) falls, (b) topples ( c) slides rotational
& transitional (d) lateral spreads ( e) flows along with geological &
geomorphological mapping of specified land slide as applicable and analysis of
slopes.
For tunnels, exploratory boreholes shall be drilled for the collection of rock /
soil samples to determine their physical characteristics and confirmation of
geological interpretation. The depth of borehole and direction of drilling shall be
as specified in the TOR or as decided by the Geologist. Test in bore-hole shall
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 3 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
include Standard Penetration Test (SPT) in all type of soil. In addition, insitu
permeability / Lugeon test conforming to IS: 5529, Part I&II may also be carried
out, if specified in the TOR. Geophysical surveys, if required/specified in the
TOR, shall be carried out for the determination of thickness of soil over burden
and bed rock profile.
4.3.3 Laboratory Testing
The following tests shall be conducted on soil and rock samples. Respective codes
are indicated against each type of test:
Direct shear test on non-cohesive soil samples - IS- 2720 Part XIII
Porosity - IS-13030
4.3.4 All geotechnical investigation work in field and in laboratories pertain to bridges
shall be carried out as per guidelines given in IRC-78 and other relevant IS codes
and circulars issued by MORT&H from time to time.
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 4 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
4.3.5 All geotechnical investigation work in field and in laboratory pertaining to high
embankment shall be carried out as per guidelines given in IRC-75 (latest version)
and investigations pertaining to road tunnel shall be as per IRC-SP-91.
4.3.6 Subsoil and geotechnical investigation work may be outsourced, to the firms
empanelled by MORT&H / Client. Such investigation work will be supervised by
competent engineer(s) or trained technician(s) to ensure that the agency has carried
out the works as per TOR requirements and work specification.
4.4 Upon completion of field & laboratory investigations, geological & geotechnical
investigation report shall be prepared together with an assessment of the suitability
of foundation stratum / tunnel support/ high embankment analysis as applicable.
Presentation of data will depend on the method of exploration adopted, the types of
field and laboratory tests conducted, the type of subsoil strata and the extent of data
collected. Generally, the data should be presented in the Format specified in the
TOR / relevant codes and specifications and it should be in the form of a report.
Adequacy of detailed investigations shall be verified by the TL / PC as per check
list given below:
4.6 Backup of the data & report may be taken as per format QSP/8.5.1/QMC/10:F-01 –
Disk Backup Database.
5.0 References
MORT&H Specifications
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 5 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/PMG/01:F-01
Review of Geological Part of Project File
Investigation
QSP/8.5.1/PMG/01:F-02
Review of Geotechnical Part of Project File
Investigation
QSP/8.5.1/QMC/10:F-01
Permanent*
Disk Backup Database
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 6 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
Start
Review Yes
Preparation of
Comments by
Revised Draft Report
HOD, if any
Collection of structure
details & alignment plan Yes No
from Bridges &
Highways Review of
Geotechnical and
Submission of Final Geological Report
Report to TL/PC
No
Follow up for
required inputs End
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 7 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team:
TL / PC / HOD (PMG)
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 8 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/PMG/01:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
HOD (PMG) / TL / PC
Geotechnical Engineer
3. Check List for adequacy of Detailed Investigation :
Yes No
Identification of risk and study of risk mitigation
measures conforming to para 4.2
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 9 of 9
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for carrying out pavement and material investigations for
highway projects to determine engineering characteristics of the subgrade soil,
materials underneath the road pavement and construction materials.
2.0 Scope
3.0 Responsibility
4.0 Procedure
4.1 Planning
Based on the requirements of TOR/WO and desk studies of available reports, the
Material Engineer / Assistant Material Engineer in consultation with HOD (PMG),
shall plan pavement and material investigation. In order to complete the job within
scheduled time frame, he/she shall identify the tasks to be carried out during various
stages of investigation. Requirement of investigation in stages, if specified by the
TOR/WO, shall be considered for planning and scheduling of investigation. If
necessary, prior to mobilization, site visit shall be conducted to gather more
information on soil conditions along the alignment, and through local enquiry
identify the availability of potential sources of selected earth, locally available
materials and other construction materials. During the site visit, previous data,
reports and studies if available with the Client shall be collected and the same will
be evaluated and considered, to the extent applicable, in the execution of
investigation and report preparation.
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 1 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
4.2.1 The following investigations shall be carried out to characterize road bed soil along
the alignment:
Manual excavation of 1 m x 1 m size trial pit to a depth of 1.0 - 1.5 m below the
ground surface or to any other appropriate depth as decided by Material
Engineer, and to such frequency as specified in the TOR/WO. For stretches
involving expansive / problematic soils, the extent and depth of such soils shall
be ascertained by investigation upto the appropriate depth.
In each test pit, record depth and extent of various layers of material strata and
their category / type from visual considerations
Perform field density test using sand replacement method / core cutter method,
if specified in TOR/WO
In each test pit, collect one representative soil sample of about 40 kg from each
stratum encountered. The interval between samples of one soil layer shall be a
maximum of 1 m. A small sealed sample shall also be collected for
determination of natural moisture content.
Perform Dynamic Cone Penetrometer (DCP) test, if specified in TOR/WO, to
500-1000 mm depth below ground or to refusal, whichever comes earlier and to
such frequency as specified in the TOR/WO, to determine in-situ CBR of the
natural soil formation constituting the road bed, which in turn shall be utilized to
determine effective CBR at formation level.
Carry out following laboratory tests on soil samples collected from site to
determine general characteristics of the road bed soil :
Sieve analysis : IS 2720 – Part IV
Natural moisture content :IS 2720 – Part II
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 2 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 3 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
The following laboratory tests shall be carried out on samples collected from
existing subgrade:
The test frequency shall be as specified in the TOR/WO. If test frequencies are not
specified in the TOR/WO, it shall be ensured that each soil type encountered is
tested. For problematic soils, additional tests such as one dimensional consolidation
tests (IS:7720 - Part XV) shall also be carried out.
4.3.2 Deflection Tests
Deflection tests, as specified in TOR/WO shall be carried out as per Client specified
frequencies. The following guidelines shall be used to conduct deflection tests:
For Benkelman beam deflection (BBD) test-IRC:81-1997
For falling weight deflectometer (FWD) test-IRC:115-2014 and IRC:117-2015
The method of deflection test to be adopted for a given project shall be as specified
in the TOR /WO.
4.3.3 Upon completion of field & laboratory investigation, a summary report on the
nature and type of pavement crust and subgrade material encountered in the test pit
shall be prepared together with an assessment of their suitability to function as
respective pavement layer and recommendations of their treatment, where
appropriate.
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
Identification of pond ash/ flyash sources, sources of slag and other innovative
construction materials.
Identification of soil borrow sources for sub-grade and fill material and
collection of representative samples from each source for appropriate
laboratory tests.
4.4.2 Tests on these representative samples would be carried out as per IRC /
MORT&H / BIS or other international codes as applicable to evaluate quality of
materials and to assess suitability for use in the following cases:
Granular material for use in sub-base, drainage blanket and fill behind
abutments, around cross-drainage structures and retaining structures
Crushed stone aggregate for use in pavement layers and in cement concrete for
structures
4.4.3 In general the following tests shall be carried out on soil and quarried stone /
aggregate. The IS codes for these tests are mentioned against the test :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 5 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
4.4.4 Upon completion of field & laboratory investigation, a summary report shall be
prepared together with an assessment of their suitability for use in various
component of road project.
Presentation of data will depend on the method of exploration adopted, the types of
field and laboratory tests conducted, the type of strata and the extent of data
collected. Generally, the data should be presented in the Format specified in the
TOR / relevant codes and specifications and it should be in the form of a report.
Adequacy of detailed investigations for new construction (new alignment/re-
alignment/bypasses, widening areas), existing pavement and construction material
shall be verified by the TL / PC as per check lists given below:
4.6 Backup of the data & report may be taken as per format QSP/8.5.1/QMC/10:F-01 –
Disk Backup Database.
4.7 Flow charts depicting sequence of activities are given at Appendix ‘A’ &
Appendix ‘B’.
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 6 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
5.0 References
TOR/Work Order
MORT&H Specifications
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/PMG/02:F-01
Review of Soil Investigation - Part of Project File
New Construction
QSP/8.5.1/PMG/02:F-02
Review of Investigations - Part of Project File
Existing Pavements
QSP/8.5.1/PMG/02:F-03
Review of Investigation - Part of Project File
Construction Materials
QSP/8.5.1/QMC/10:F-01
Permanent*
Disk Backup Database
Pavement and Materials
Part of DPR
Investigation Report
HOD (PMG) / 3 years after
Project File
TL / PC submission of DPR
* To be reviewed after 5 years
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 7 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PAVEMENT INVESTIGATION PROCEDURE
Start
Carry out following tests & investigation at Carry out following tests & investigation at
TOR/WO specified frequencies : TOR/WO specified frequencies :
Benkelman beam deflection (BBD)/ Falling Excavate trial pit to expose natural soil
weight deflectometer (FWD) test on formation for visual description, soil
existing pavement layering, examination and sample
Pavement composition survey by digging collection
trial pit through existing pavement Collect soil samples for laboratory testing
Collect samples of existing granular crust & Conduct DCP test to determine in-situ CBR
subgrade soil of road-bed soil for a depth of 500-
Conduct field density and DCP test in the 1000mm
subgrade layer Conduct field density test, if specified in
Perform laboratory classification and the TOR
compaction, CBR and other relevant tests Perform laboratory classification,
on collected samples of granular crust and compaction and CBR tests on collected
subgrade samples of road-bed soil
P
Summarize test results and material characteristics
e
r
f
Analyze test results for design input
o
r
m
Review and
Submission of
Report to TL / PC l
a
b
o
End
r
a
Signature t
Designation HOD (PMG) President oManagement Representative
r
Prepared by Approved by Issued by Page 8 of 12
y
c
l
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘B’
Start
End
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 9 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
3. Check List for Adequacy of Investigation:
Yes No
Testing equipment are duly calibrated and these are in
sound condition
4. Review Remarks
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 10 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
4. Review Remarks
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 11 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/PMG/02:F-03 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
TL / PC
3. Check List for Adequacy of Investigation :
Yes No
4. Review Remarks
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (PMG) President Management Representative
Prepared by Approved by Issued by Page 12 of 12
QUANTITY SURVEYING &
CONTRACTS
Issue No. : 05
Doc No : QSP/8.5.1/QS/01 Date : 03 October 2017
Revision No. : 00
PROJECT ESTIMATES
1.0 Purpose
To lay down procedure for preparation of project cost estimates for highway
projects.
2.0 Scope
3.0 Responsibility
4.0 Procedure
In conformity with the TOR, the current market rates of material and labour
prevalent in the project area shall be collected. The borrow area location and quarry
charts shall be prepared to ascertain lead distances. The latest Schedule of Rates of
State PWD, as applicable for the area shall be collected. The minimum wages for
labour as declared by the Ministry of Labour, Government of India or State
Government for the area shall be obtained. The rates of proprietary items shall be
obtained from manufacturers / authorized dealers.
Unit rates for various construction items shall be developed after working out
“analysis of rates” using, in general, the guidelines given in MORT&H standard
data book. The rates are worked out on Format QSP/8.5.1/QS/01:F-01 – “Analysis
of Rates”.
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 1 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/01 Date : 03 October 2017
Revision No. : 00
Issue No. : 05
Doc No : QSP/8.5.1/QS/01 Date : 03 October 2017
Revision No. : 00
4.4 Review
Flow charts depicting the processes of Project Estimates for DPR and BOT projects
are given at Appendix ‘A’ and ‘B’ respectively.
5.0 References
TOR
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/QS/01:F-01
Part of DPR / BOT Project Report
Analysis of Rates
QSP/8.5.1/QS/01:F-02
Part of DPR
Details of Quantities
QSP/8.5.1/QS/01:F-03
Part of DPR
Abstract of Quantities
QSP/8.5.1/QS/01:F-04
Part of DPR / BOT Project Report
Abstract of Cost
QSP/8.5.1/QS/01:F-05
Part of DPR / BOT Project Report
Review of Cost Estimates
Project File 3 years after
HOD (QS) / TL / PC submission of DPR /
BOT Project Report
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 3 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PROJECT ESTIMATES
(For Detailed Project Report)
Start
No Review of
Preliminary
Cost Estimates
Yes
No Review of Detailed
Cost Estimates
Yes
Submit to TL / PC
End
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 4 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘B’
PROJECT ESTIMATES
(For BOT Projects)
Start
No Review of
Preliminary Cost
Estimates
Yes
Submit to TL/PC
End
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 5 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/01:F-01 Date : 03 October 2017
Revision No. : 00
ANALYSIS OF RATES
Project Title :
Reference to
Item
MORT&H Description Unit Quantity Rate Cost Remarks
No.
Specification
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 6 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/01:F-02 Date : 03 October 2017
Revision No. : 00
DETAILS OF QUANTITIES
Project Title :
Item
Description Unit No. Length Breadth Height Quantity
No.
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 7 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/01:F-03 Date : 03 October 2017
Revision No. : 00
ABSTRACT OF QUANTITIES
Project Title :
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 8 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/01:F-04 Date : 03 October 2017
Revision No. : 00
ABSTRACT OF COST
Project Title :
Item
Description Unit Quantity Rate Amount
No.
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 9 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/01:F-05 Date : 03 October 2017
Revision No. : 00
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (QS) President Management Representative
Prepared by Approved by Issued by Page 10 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for preparation of pre-qualification documents and bid
documents for Item Rate / BOT / EPC / Hybrid Annuity Contracts
2.0 Scope
The procedure shall cover identification, analysis of all input data and compilation for
preparation of following contracts documents:
Pre-qualification Documents
Bid documents for Item Rate / BOT / EPC / Hybrid Annuity Contracts.
3.0 Responsibility
HOD (QS) shall be responsible to establish and maintain this procedure.
TL / PC / Contract Engineer shall be responsible to implement this procedure.
4.0 Procedure
4.1 (a) Pre-Qualification (PQ) Documents for Item Rate Contracts
PQ documents shall contain the following details, specific for each procurement, in
conformity with TOR and as prescribed in Standard PQ Documents issued by
MORT&H / WB / ADB from time to time.
Instructions to Applicants.
Qualification Criteria.
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
In some cases the Client may require to abolish the pre-qualification procedure to
save time. In such cases bidders are post qualified on the basis of qualification
documents to be submitted by the bidders along with their bids.
(b) Request for Qualification (RFQ) for BOT/EPC/Hybrid Annuity Contracts
The RFQ shall consist of the following clauses:
1 Introduction.
2 Instructions to Applicants.
3 Criteria for Evaluation
It includes evaluation parameters, Technical capacity and financial information
for purposes of evaluation and details of experience.
4 Fraud and Corrupt Practices.
5 Pre-Application Conference
6 Miscellaneous
4.2 Bid Documents
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 2 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
This section contains the forms for updating and the criteria
to ascertain its qualification.
ii) If the Bidder is post-qualified
This Section contains the forms and the criteria to determine
the qualification of the bidder to perform the Contract.
Section IV - Bidding Forms
This Section contains the Forms which are to be completed by
the Bidder and submitted as part of his Bid.
Section V - Works Requirements
This Section contains the Scope of the Works to be procured
Section VI - General Conditions of Contract
Section VII - Particular Conditions of Contract (PCC) and Appendix to Bid.
Volume IV - Drawings
B. BOT Contract
BOT (Build, operate and Transfer) Contract is the Contract in which the
Concessionaire owns the responsibilities of design and supervise of the Project
highway. The Concessionaire recovers their cost, along with profit, over a period of
time (Concession Period) in which they operate the facility and collect the fee from
the public who make use of the facility. After the Concession period the ownership of
the facility is transferred to the Employer. In BOT the concession agreement shall be
prepared as per guidelines issued by MORT&H. The Concession agreement defines
the scope of the project with precision and predictability in order to enable the
Concessionaire to determine its costs and obligations. The details of these are covered
in different articles and Schedules. The bid Documents shall comprise of 3 volumes
as detailed below:
Volume I - Request for Qualification (RFQ)
Volume II - Request for Proposal (RFP)
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 3 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Schedule-H Drawings
o Control center
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 4 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 5 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
C. EPC Contract
As item rate contract is prone to time and cost overruns therefore EPC mode of
construction has come into practice. In EPC Contacts the Contract Price is a fixed lump
sum amount for construction of the project highway. In this Contract payments are
linked to specified stages of construction as compared to payment for individual items/
units under the item rate contracts. The EPC agreement shall consist of the Agreement
clauses and the schedules.
The bid Documents shall comprise of 3 volumes as detailed below:
Volume I - Request for Qualification (RFQ)
Volume II - Request for Proposal (RFP)
Volume III - EPC Agreement along with associated Schedules
The brief details of the schedule are described below. The Schedule A to D & I shall be
prepared by Highway Division.
Schedule A Site of the Project
Schedule B Development of the Project Highway To be prepared
by Highway
Schedule C Project Facilities Division
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 6 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Schedule-I Drawings
1. Drawings To be prepared by
2. Additional drawings Highway Division
Annex-I: List of Drawings
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 7 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
The brief details of the schedule are described below. The Schedule A to D & H shall be
prepared by Highway Division.
Schedule A Site of the Project
Schedule B Development of the Project To be prepared
by Highway
Schedule C Project Facilities Division
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Schedule H Drawings
1. Drawings To be prepared by
2. Additional drawings Highway Division
Annex-I: List of Drawings
Schedule I Tests
1. Schedule for Tests
2. Tests
4. Completion/Provisional Certificate
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 9 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
7. Divestment Requirements
8. Display of Schedule - K
Annex – I: Repair Rectification of Defects and Deficiencies
ROADS
BRIDGES
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 10 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
6. Operation Period
7. Termination
8. Determination of costs and time
9. Assistance in Dispute resolution
10. Other duties and functions
11. Miscellaneous
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 11 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
4.4 Review
The bid documents prepared (including PQ/RFQ documents) for Item Rate Contract,
BOT Contract, EPC Contract and Hybrid Annuity Contracts shall be reviewed as per
Format No. QSP/8.5.1/QS/02:F-01, QSP/8.5.1/QS/02:F-02, QSP/8.5.1/QS/02:F-03,
QSP/8.5.1/QS/02:F-04 respectively by TL / PC / HOD (QS) before submission to the
Client.
A flow chart depicting the process is given at Appendix ‘A’ and Appendix ‘B’.
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 12 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
5.0 References
TOR
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/QS/02:F-01
Review of Bid Documents for Part of DPR
Item Rate Contracts
QSP/8.5.1/QS/02:F-02
Review of Bid Documents for Part of Report
BOT Contracts
QSP/8.5.1/QS/02:F-03
Review of Bid Documents for Part of Report
EPC Contracts
QSP/8.5.1/QS/02:F-04
Review of Bid Documents for Part of Report
Hybrid Annuity Contracts
3 years after
Project File HOD (QS) / TL / PC
submission of DPR
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 13 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
Start
Study the nature & extent of work and identification of associated risks
& opportunities related to the process and its mitigative measures
No Review of
Prequalification
Document
Yes
Prepare Bid Documents
No Review of Bid
Documents
Yes
Submit to TL / PC
End
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 14 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/QS/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘B’
Start
No Review of Request
for Qualification
Document
Yes
Prepare Bid Documents for BOT /EPC/Hybrid
Annuity Contracts
No Review of Bid
Documents
Yes
Submit to TL / PC
End
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 15 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/02:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
Quantity Surveyor
TL / PC / HOD (QS)
3. Review:
Yes No NA
3.1 Pre-qualification Documents
Are the pre-qualification documents as per requirements of
the TOR? (If not, reasons for the same)
Are the documents in conformity with the standards
pre-qualification documents issued by the funding agency
i.e. MORT&H / WB / ADB? (If not, reasons for the same)
4. Review Remarks
Reviewed by :
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 16 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/02:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
Quantity Surveyor
TL / PC / HOD (QS)
3. Review:
Yes No NA
3.1 Request for Qualification Documents
Is the request for qualification documents as per
requirements of the TOR? (If not, reasons for the same)
4. Review Remarks
Reviewed by :
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 17 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/02:F-03 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
Quantity Surveyor
TL / PC / HOD (QS)
3. Review:
Yes No NA
3.1 Request for Qualification Documents
Is the request for qualification documents as per
requirements of the TOR? (If not, reasons for the same)
3.3 Schedule H
Has Schedule H been checked?
4. Review Remarks
Reviewed by :
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 18 of 19
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/QS/02:F-04 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
Quantity Surveyor
TL / PC / HOD (QS)
3. Review:
Yes No NA
3.1 Request for Qualification Documents
Is the request for qualification documents as per
requirements of the TOR? (If not, reasons for the same)
Are the documents in conformity with the standards
RFQ documents issued by the funding agency i.e.
MORT&H or State PWD? (If not, reasons for the same)
4. Review Remarks
Reviewed by :
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Quantity Surveying & Contracts) President Management Representative
Prepared by Approved by Issued by Page 19 of 19
BRIDGE
Issue No. : 05
Doc No : QSP/8.5.1/Br/01 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for providing inputs to technical and financial proposals for
independent bridge project / bridge as part of highway project.
2.0 Scope
This procedure covers guidelines for preparing inputs, if called for by Project
Coordinator (PC) / BD Division, for preparation of technical / financial proposal for
the following:
Site Appreciation
Approach and Methodology
Tasks involved
Work programme and manning schedule
Comments on TOR for clarifications, if any
Inputs for financial proposal, if required
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 1 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/01 Date : 03 October 2017
Revision No. : 00
4.3 The input shall be reviewed by HOD (Br) on file before its submission to PC / BD
Division.
5.0 References
TOR
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 2 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PRE-AWARD OF WORK : BRIDGE PROJECTS
Start
List of activities involved : List of activities involved: List of activities involved : List of activities involved : List of activities involved :
Study of design standards and
Inception Report Inception Report Study of design standards and Inventory
design philosophy
design philosophy
Feasibility Report Study of GADs Inspection & Condition
Review of bridge designs and
Preliminary Project Report Broad scrutiny of design and Survey
drawings of Design
Detailed Project Report drawings Investigation & Testing
Consultants provided in the
contract To give comments regarding Preparation of Repair &
discrepancies in designs and Rehabilitation Scheme for
To suggest modifications in
drawings or to recommend to distressed bridges.
bridge designs and drawings
as per changed site condition Client for approval if in order
or if found deficient Scrutiny of modified designs
Technical support to field and drawings and to
staff during construction recommend it to Client for
approval
Submission of Inputs
End
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 3 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for preparation of Detailed Project Report (DPR) of
independent bridge project / bridge as part of Highway Project and preparation of
Feasibility cum Preliminary Design Report for BOT / DBFO / EPC projects.
2.0 Scope
This procedure covers identification, preparation and submission of details to TL /
PC for preparation of Detailed Project Report for independent bridge projects /
bridge projects as part of Highway Projects and Feasibility cum Preliminary Design
Report for BOT / DBFO / EPC Projects as follows :
Inception Report
Feasibility Report
Preliminary Project Report
Detailed Project Report
Preparation of Feasibility cum Preliminary Design Report for BOT / DBFO / EPC
and other Project in general shall include :
Inception Report
Draft Feasibility Report
Final Feasibility cum Preliminary Design Report
3.0 Responsibility
HOD (Br) shall be responsible to establish and maintain the procedure.
Nominated Bridge Engineer shall be responsible to implement the procedure.
4.0 Procedure
4.1 Study the TOR, requirements of Client and prepare Quality Plan in case of
independent bridge project only in consultation with HOD (Br) as per Procedure
QSP/8.1/QMC/06 – “Planning of Product Realisation”.
4.2 Prepare an activity development plan identifying the details required for preparation
of various reports including the ground reconnaissance and surveys at each stage.
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 1 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
After approval of inception report, prepare draft feasibility report for bridge portion
based on para 4.2.2 above and get it reviewed by HOD (Br) as per Format
QSP/8.5.1/Br/02:F-02 – “Review of Feasibility Report” and submit to TL / PC.
Thereafter prepare final feasibility report, taking into account comments, received
from Client, if any, get it reviewed by HOD (Br) as per Format
QSP/8.5.1/Br/02:F-02 – “Review of Feasibility Report” and submit to TL / PC.
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
5.0 References
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 4 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/Br/02:F-01
Part of Project File
Review of Inception Report
QSP/8.5.1/Br/02:F-02
Part of Project File
Review of Feasibility Report
QSP/8.5.1/Br/02:F-03
Review of Preliminary Project Report /
Part of Project File
Final Feasibility cum Preliminary Design
Report
QSP/8.5.1/Br/02:F-04
Part of Project File
Review of Detailed Project Report
QSP/8.5.1/QMC/10:F-01
HOD (Br) Permanent*
Disk Backup Database
QSP/8.0/QMC/14:F-01
Final Inspection Report
Part of Project File
(In case of independent bridge project
only)
Till completion of
HOD (Br)
Inception Report Project
(In case of independent bridge project Incharge Central
only) Library / Incharge 2 years
Reprography Cell
All Final Reports of different stages of Till completion of
HOD (Br)
DPR / Final Feasibility cum Preliminary Project
Design Report Incharge Central
(In case of independent bridge project Library / Incharge Permanent*
only) Reprography Cell
Hard Copy : Permanent*
Design Calculations and Drawings HOD (Br)
Soft Copy : Permanent*
3 years after submission
Project File HOD (Br)
of DPR
* To be reviewed after 5 years.
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 5 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
POST AWARD OF WORK – BRIDGE PROJECTS
Start
End
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 6 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Br/02:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
HOD (Br)
Bridge Engineer
Any other specialist
3. Review :
Yes No
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 7 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Br/02:F-02 Date : 03 October 2017
Revision No. : 00
2. Review Team:
HOD (Br)
Bridge Engineer
3. Review :
Yes No
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 8 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Br/02:F-03 Date : 03 October 2017
Revision No. : 00
2. Review Team:
HOD (Br)
Bridge Engineer
Any other specialist
3. Review :
Have following details been included in the report:
Yes No
Client requirements including Statutory and
Regulatory requirements
Technical parameters for bridge work
Details of existing bridges to be Retained / Replaced /
Widened
Span arrangement and type of structure for new
bridges
Preliminary design calculations of bridges
Preliminary General Arrangement Drawings (GAD)
of bridges
Details of distress observed in existing bridges NA
Client comments on Draft Preliminary Project Report
complied
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 9 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Br/02:F-04 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
HOD (Br)
Bridge Engineer
Any other specialist
3. Review :
Have following details been included in the report:
Yes No
Design of bridges has been carried out as per latest IRC codes
of practice
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 10 of 10
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for planning and control of design and development plan of
bridges.
2.0 Scope
This procedure covers detailed design and development of bridges, their review and
verification, for DPR Project required under Procedure QSP/8.5.1/Br/02 – Post
Award of Work – Bridge Projects (Independent Bridge Project / Bridge Project as
part of Highway Project). It also covers detailed design of bridges for
Concessionaire Project under BOT / DBFO Scheme.
3.0 Responsibility
HOD (Br) shall be responsible to establish and maintain the procedure.
4.0 Procedure
4.1 Planning Risk
Determination of risks and opportunities, meeting the requirements of Clause 6.1 of
the Std ISO 9001:2015 has been done and record maintained in “Risk Register” as
per defined format. ‘Risk Levels’ and ‘Risk Controls’, pertinent inputs for addressal
of the identified risk, have been determined with the help of “Risk Matrix” as per
defined format. Both formats are given at Appendix ‘H’ to Quality Manual.
The latest IRC and others applicable codes / standards / manuals shall be used at the
stages of application in the process.
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 1 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
Terms of Reference
Survey Data
Hydrology Report
Coordination / Coordination
S. No. Design Stage Remarks
Interface with Issues
Obtain field data and other required data for design from other Divisions / Sections.
Finalize design input based on the TOR, specific requirements of Client,
statutory and regulatory requirements, applicable Design Codes of Practice /
Manuals and specifications, approved GADs of bridges, topographical survey data,
hydrological and geotechnical investigation report, road alignment, L-section and
X-section of approaches on either side of the bridges. The design input shall be
finalized by nominated Bridge Engineer in consultation with HOD (Br). The review
shall be carried out by Bridge Engineer / HOD (Br) as per Format given in
QSP/8.3/Br/03:F-02 – Review of Design and Development Input.
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 2 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
Prepare detailed design and drawings of various components of bridge as per latest
version of IRC codes of practice and provision of contracts. The list of codes to be
normally used for different components is enclosed as Appendix ‘A’. The design
shall be carried out for all possible load combinations and stipulation made in the
relevant codes. The design output shall be reviewed and approved by Bridge
Engineer / HOD (Br) as per Format QSP/8.3/Br/03:F-03 – Approval of Design and
Development Output.
Review of design at various stages is included in the design and development plan
given at Para 4.2.3 above.
4.6.1 Compare the design and drawings with those of similar structures prepared earlier.
In some cases the drawings of superstructure can be compared with standard
superstructure drawings prepared by the MORT&H / ICT Pvt. Ltd. The method of
verification and result of verification shall be recorded as per Format
QSP/8.3/Br/03:F-04 – Design and Development Verification.
4.6.2 The design shall be submitted to Client for his approval. He may carry out the
design verification himself or engage a Proof Consultant to check the design, if
required.
Design and development validation is performed to ensure that the final design is
capable of meeting specified requirements. Our product being design, approval of
design by the Client shall be treated as its validation.
Based on the comments of Client / Proof Consultant, the design and drawings shall
be modified wherever required. After changes have been reviewed and approved by
HOD (Br), these shall be resubmitted to the client for final approval.
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
5.0 References
6.0 Records
Retention
Format / Record
By Period
QSP/8.3/Br/03:F-01
Part of Project File
Design and Development Plan
QSP/8.3/Br/03:F-02
Review of Design and Part of Project File
Development Input
QSP/8.3/Br/03:F-03
Approval of Design and Part of Project File
Development Output
QSP/8.3/Br/03:F-04
Design and Development Part of Project File
Verification
QSP/8.5.1/QMC/10:F-01
HOD (Br) Permanent *
Disk Backup Database
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 4 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
LIST OF APPLICABLE CODES
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 6 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
(2) MoRT& H Specifications for Roads and Bridge Works 2013 (Fifth Revision)
(3) TOR for Consultancy Contract Agreement
(4) Client’s Requirement in addition to TOR if any
(5) Guidelines and Circulars issued by MoRT&H and NHAI from time to time.
(6) MoRT&H Specifications / Circulars / Other Documents
(7) MoRT&H Pocket Book for Bridge Engineers 2002
(8) Relevant Provisions of IS/BIS/IRS/International Design Codes as applicable
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 7 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.3/Br/03 Date : 03 October 2017
Revision No. : 00
Appendix ‘B’
Start
No Major Yes
Changes
Approval of the Client
No
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 8 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/Br/03:F-01 Date : 03 October 2017
Revision No. : 00
Responsibility
Bridge
6 Submission of Draft DPR HOD (Br)
Engineer
Bridge
9 Submission of Final DPR HOD (Br)
Engineer
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 9 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/Br/03:F-02 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
HOD (Br)
Bridge Engineer
3. Review :
Yes No NA
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 10 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/Br/03:F-03 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Approval Team :
HOD (Br)
Bridge Engineer
3. Verify :
Yes No
Approved by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 11 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.3/Br/03:F-04 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Team :
HOD (Br)
Bridge Engineer
Any other Specialist
3. Verify :
Yes No
Designs satisfy all specified requirements
Verified by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 12 of 12
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/04 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for carrying out Proof Consultancy for the bridge designs &
drawings.
2.0 Scope
The procedure covers approach and methodology for performing the task of Proof
Consultancy for the designs and drawings of bridges prepared by other Design
Consultant / Agency.
3.0 Responsibility
HOD (Br) shall be responsible to establish and maintain the procedure.
4.0 Procedure
4.1 Check and ensure that the documents received from the Client / Design Consultant /
Agency are complete in all respects.
4.4 Prepare comments if any, on the basic design data, design philosophy, design
assumptions of various components of the bridge and GADs and forward the same
to the Design Consultant for clarifications through Client after review by HOD (Br)
on file.
4.5 Study clarifications received from the Design Consultant and verify the design of
each component. The method and result of verification shall be recorded as per
Format QSP/8.5.1/Br/04:F-01 – Review of Proof Consultancy of Bridge Design /
Drawings. Send the corrected design and drawings to the Design Consultant for
correction / modifications.
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 1 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/04 Date : 03 October 2017
Revision No. : 00
4.6 Examine modified design and drawings received from the Design Consultant to see
that all comments raised have been duly incorporated. All the documents shall be
finally checked by HOD (Br) before dispatch to client for his approval.
5.0 References
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/Br/04:F-01
Review of Proof Consultancy Part of Project File
of Bridge Design / Drawings
QSP/8.5.1/QMC/10:F-01
HOD (Br) Permanent*
Disk Backup Database
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 2 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/04 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PROOF CONSULTANCY OF BRIDGE DESIGNS & DRAWINGS
Start
Award of work
Submission to Client
Approval by Client
End
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 3 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Br/04:F-01 Date : 03 October 2017
Revision No. : 00
1. Project Title :
2. Review Team :
HOD (Br)
Bridge Engineer
3. Review :
Yes No
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 4 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/05 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for carrying out inspection and testing of bridges and
preparing repair and rehabilitation scheme as an independent bridge rehabilitation
project.
2.0 Scope
3.0 Responsibility
4.0 Procedure
4.1 Study the TOR, requirement of client, scope of work and time schedule to carry out
the services.
4.2 Obtain following data / records to the extent possible from the client / other sources,
otherwise collect by inspection and site assessment as per IRC:SP:18:
Hydrology reports
Issue No. : 05
Doc No : QSP/8.5.1/Br/05 Date : 03 October 2017
Revision No. : 00
4.3 Study the above documents to familiarize with the details of structure and assess the
type of distresses observed and their severity and to identify bridges needing special
repair and rehabilitation measures.
4.4 Carry out detailed visual inspection of each bridge as per guidelines given in
IRC:SP:35 (updated) “Guidelines for Inspection and Maintenance of Bridges”.
Condition of bridges shall be assessed by visual inspection using conventional
standard tools and the bridges requiring special inspection, repair and rehabilitation
shall be identified.
4.5 After examining the details collected and assessment of the extent of severity of
distresses, carry out detailed investigation / documentation of distresses of affected
part by advanced techniques, equipments supported by non-destructive tests / partial
non-destructive tests of the affected portion as per site requirements to assess likely
causes of distresses for bridges identified for special inspection, repair and
rehabilitation.
4.6 Based on site inspection, investigation and test results, prepare repair rehabilitation
scheme as per provisions of IRC:SP:40 (updated) “Guidelines on Techniques for
Strengthening / Rehabilitation of Bridges”.
4.7 Prepare detailed report on repair and rehabilitation of structure, which shall include
repair proposals, design / drawings of distressed components and cost estimate. The
design shall be carried out as per Procedure QSP/8.3/Br/03 - Design and
Development Plan of Bridges and the cost estimate prepared by Quantity Surveying
& Contracts Division.
4.8 The repair and rehabilitation project report shall be finally reviewed by
HOD (Br) as per Format QSP/9.0/QMC/13:F-01 - Final Inspection Report and
approved by President on file before submission to the client for approval.
5.0 References
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 2 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/05 Date : 03 October 2017
Revision No. : 00
6.0 Records
Retention
Format / Record
By Period
QSP/9.0/QMC/13:F-01
Part of Project File
Final Inspection Report
QSP/8.5.1/QMC/10:F-01
HOD (Br) Permanent *
Disk Backup Database
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 3 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Br/05 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
REPAIR AND REHABILITATION OF BRIDGES
Start
Award of Work
End
Signature
Designation HOD (Bridge) President Management Representative
Prepared by Approved by Issued by Page 4 of 4
SURVEY
4. QSP/8.5.1/Svy/04 Photogrammetry 6
Work Instructions
Issue No. : 05
Doc No : QSP/8.5.1/Svy/01 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for providing topographical survey and GIS inputs for
preparation of technical / financial proposals.
2.0 Scope
3.0 Responsibility
4.0 Procedure
4.1 Receive copy of TOR and necessary relevant information from PC / BD Division
for preparing technical and financial proposal related to topographical survey and
GIS component of the TOR
4.2 Obtain any additional information / clarifications of the client received during pre-
bid meeting, site visit report if available.
4.3 Senior Surveyor nominated by HOD (Svy) / HOD (Svy) shall study the TOR and
identify relevant scope of survey work, which may include quantum of various
survey tasks, viz.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/01 Date : 03 October 2017
Revision No. : 00
Requirement of data, drawing outputs (soft and hard copies), records and
reports.
4.4 HOD will assess the in-house availability of survey resources versus the
requirements of resources as per the TOR and finalize associates / hiring of
resources and their inputs, if required, in consultation with PC / President.
4.5 Nominated Senior Surveyor / HOD (Svy) shall prepare approach and methodology
and Comments on TOR, if any, to be included in the technical proposal. The
proposal shall include methodology of establishment of control points and carrying
out detailed topographical survey and type of survey instruments (e.g. GPS, Total
Station, Auto / Digital Level, LiDAR system) to be used to meet the accuracy
requirement of output stipulated in TOR.
4.6 HOD will also assess if any GIS and Photogrammetry work is involved in the
proposal (RFP) and will accordingly prepare pre-bid queries (if any), technical
approach & methodology and cost estimation considering volume of work, project
duration, man-power, qualification of Key expert, cost of procurement of satellite
image (if required), field survey etc.
4.7 Nominated Senior Surveyor / HOD (Svy) shall estimate requirements of manpower,
instruments, equipment, transport, accommodation, etc. and work out cost estimates
for conducting topographical survey and all relevant components within the
timeframe as given in the TOR. Time required for mobilization and final processing
of data will be judicially included.
4.8 The input shall be reviewed by HOD and submitted to PC / BD Division for
incorporation in the technical / financial proposal.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/01 Date : 03 October 2017
Revision No. : 00
5.0 References
TOR
IRC Codes
Any specific instructions issued by the MORT&H, NHAI or any other
authority, on the subject.
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/01 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PRE-AWARD OF WORK – TOPOGRAPHICAL SURVEY & GIS
Start
Yes
Appreciation of project
No
Is in-house capability Finalize associates and their inputs
adequate?
Yes
Submit Inputs
End
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 4 of 4
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/02 Date : 03 October 2017
Revision No. : 00
TOPOGRAPHICAL SURVEY
1.0 Purpose
2.0 Scope
It includes general system procedure for carrying out detailed topographical surveys
after award of work.
3.0 Responsibility
4.0 Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/02 Date : 03 October 2017
Revision No. : 00
Ensure that action has been taken by BD / PC about approval of CVs of all the
Surveyors / Senior Surveyor by client, if required.
Issue broad outline plan for execution of survey tasks and move plan to Senior
Surveyor.
4.3 All personnel of survey team shall initiate the process of mobilization by submitting
online request for movement which will be recommended by HOD(Survey) and
finally approved by the concerned President.
Identify project location on Google Earth and explore suitable camping place
and terrain conditions for deployment of survey teams.
Initiate the process to procure GTS Bench Marks from Survey of India
through proper channel if necessary.
Collect maps, data and all other relevant records and carry out reconnaissance
of the project area so as to apprise himself with the terrain for execution of the
survey tasks.
Locate GTS BMs on the ground as per description received from survey of
India or the client and ensure that proper mark has been traced on ground.
Make arrangements for casting of cement concrete pillars and other materials,
as required.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 5
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/02 Date : 03 October 2017
Revision No. : 00
Ensure that control network is established using GPS as per Work Instruction
WI/Svy/02/01 – Control Work for Field Surveys Using GNSS Receivers. He
shall prepare technical report on GPS survey giving details about preparatory
work, instruments used, methodology, data processing and projection system
used and any other information necessary for describing the approach and
methodology for the GPS control work.
Ensure that additional supplementary control points all along the alignment are
established by carrying out traverse using Total Station / GPS as per Work
Instruction WI/Svy/02/02 – Traverse Control Using Total Station / GPS.
- Ensure that proper requisite software for downloading of data from Total
Station is available in the computer.
- Check completeness of all details, contours and heights and ensure that
sufficient data is available to develop Digital Terrain Model.
Send progress reports and other reports to HOD (Svy) / TL including request
for the additional resources, if required.
4.5 HOD (Svy) shall monitor progress of field work and provision for additional
resources, if required, in consultation with President.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 5
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/02 Date : 03 October 2017
Revision No. : 00
4.6 Senior Surveyor shall ensure completion of additional survey requirements, as may
be obtained from Team Leader / Design Team and arrange to supply final survey
data in desired format to the design team or the Team Leader, as required. He shall
submit the draft technical report on topographical survey and other reports to
HOD (Svy) and Team Leader as required.
4.7 The field survey team shall return to Corporate Office and deposit all instruments
and shall be debriefed by HOD (Svy).
5.0 References
TOR
IRC Codes
Any specific instructions issued by the concerned Ministry and NHAI or any
other authority.
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 4 of 5
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/02 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
TOPOGRAPHICAL SURVEY
Start
Construction Supervision
DPR
Yes No
Is outsourcing Are resources
advisable? available?
Move to site in consultation with
HDO (Adm)
Quantify task to be Yes
No
outsourced
Project requirement Finalize personnel and instruments in Surveyor to support the TL in activities as
coordination with President / TL assigned
End
Finalize execution program of survey work
in consultation with President / TL
Monitoring progress of work and provision of Ascertain and carryout additional field survey for
additional resources by HOD / TL in consultation hydrology, bridges, bypasses, junctions, etc.
with President
End
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 5 of 5
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down procedure for development of GIS database and variety of base maps
for feasibility studies and preparation of detailed project reports of various
infrastructure projects
2.0 Scope
3.0 Responsibility
4.0 Procedure
4.1 General
Team Leader / HOD shall nominate Project In-charge who shall collect the
copy of the TOR of the concerned project and study scope of work. GIS need
shall be assessed in terms of quantum & type of GIS work involved.
Project in-charge will discuss the methodology with HOD to carry out specific
GIS tasks and requirement of Remote Sensing (Satellite Imagery/ Aerial
Photographs) data for preparation of base map/updating of Survey of India
map sheets.
Project In-charge shall coordinate with other divisions regarding data, earlier
project reports, maps, hardware/software, and will have consultation with
other experts, wherever required.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03 Date : 03 October 2017
Revision No. : 00
The Project In-charge shall discuss existing resources e.g. software/ hardware,
man power with HOD / President to seek appropriate allocation for additional
resources, if required.
Project In-charge shall assess the requirements of field visit for GCP
collection and ground verification of land use and/or primary and secondary
data collection. Project In-Charge shall study and discuss with HOD the data
processing and deliverable standards to be used to meet the requirements of
the TOR such as Map projection for geo-referencing, database design,
cartographic symbols, map scale, technical reports and file format etc.
4.3 Data Types used for the development of GIS database & Mapping
Following data types are usually collected or procured from respective agencies and
used as input for the development of GIS database and preparation of relevant base
maps.
Other departments’ specific maps (e.g. forest map, soil map, geological map,
water resources map, administrative boundaries map, etc.)
Open source data such as Google earth based satellite images and maps can be
used for feasibility study.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03 Date : 03 October 2017
Revision No. : 00
4.4 Data Processing for the development of GIS database & mapping
In order to create GIS database and preparation of base map, generally following
activities are involved.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03 Date : 03 October 2017
Revision No. : 00
Divisions
Environment &
Transportation
Infrastructure
Metro Allied
Railways &
GIS layers/ thematic maps required across the
Traffic &
Highway
Services
Urban
Social
departments
6.0 Records
Retention
Format / Record
By Period
QSP/8.5.1/Svy/03:F-01
HOD (Svy) Part of Report File
Review of Report – GIS
Report File HOD (Svy) 1 years
Final GIS Output Data (Soft Copy) GIS Expert 3 years
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 5 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
USE OF GEOGRAPHIC INFORMATION SYSTEM IN PROJECT
HOD Project In-charge
Start Planning
GIS need assessment in line with project requirement
Identification of spatial and non-spatial data and their sources e.g.
satellite imageries, Aerial Photographs, Topographical Maps, other
Receipt of ToR maps for input
Review of existing resources e.g. manpower, hardware and software etc.
Coordinate with other associate division regarding earlier study, report
and other data in connection with assigned project
Finalize standards regarding GIS software, database, file format, scale
etc
Input
Review of Report Collection of GIS input for the project area from the concerned government
and private agencies, e.g.
Satellite Imageries
Topographical Maps
Yes Total station survey, DGPS survey data
Satisfactory? Other department specific maps e.g. revenue or cadastral map, forest map,
soil map, geological map, water resources map, administrative boundary
map etc
No
Deliverables
Vector and Raster Geodatabase/ Shape files/kml
Maps and Drawings in both Digital and Hardcopy form
Technical Reports
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 6 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Svy/03:F-01 Date : 03 October 2017
Revision No. : 00
REVIEW OF REPORT
GIS
1. Project Title :
2. Review Team :
HOD (Svy)
TL / Project In-charge
3. Check List:
Yes No NA
Identification of geographical extent of the study area
and demarcation of area of interest
Review of all GIS related earlier studies and spatial data
(maps / imageries) and documentation of the related
study area
Collection of data :
Topographical maps
Satellite imageries
Aerial Photographs
Other ancillary maps
GPS / DGPS data
Review of Hardware / Software
Processing of the spatial data: geo-referencing,
geodatabase creation, thematic layer generation,
attribute attachment, etc.
Submission of Inception Report
GIS based analysis / modeling and mapping as required
Deliverables : hardcopy / softcopy of the final GIS
data / maps and Reports
4. Remarks
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 7 of 7
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04 Date : 03 October 2017
Revision No. : 00
PHOTOGRAMMETRY
1.0 General
Photogrammetry is the art, science and technology of obtaining reliable information
about the properties of the earth surface and its objects along with relevant
measurements and interpretation using remotely sensed data without physical
contact with the object.
2.0 Purpose
To lay down procedure for conducting the Photogrammetry Survey to generate
Digital Elevation Model (DEM) and Ortho Photo images of the Area of Interest
using Stereo images.
3.0 Scope
The procedure covers guidelines and procedure to carry out the photogrammetric
survey after award of the work.
4.0 Responsibility
HOD (Svy) and nominated Photogrammetric expert shall be responsible to establish
and maintain the procedure.
5.0 Procedure
HOD (Svy) shall nominate Photogrammetry Expert who will conduct/supervise the
work.
5.1 Image Data Collection
HOD/nominated Photogrammetry expert will collect the TOR of the project and
examine for any photogrammetric survey requirements and initiate the process to
procurement of relevant images. If, as per the TOR, the stereo images are to be
provided by the client, act accordingly to collect adequate data to meet the project
requirements. Usually Indian Satellite CartSat-1 stereo data with 2.5m resolution is
used in most of the green field or high hills bound infrastructure projects. There are
other high resolution stereo data also available from foreign satellites which can be
procured where high accuracy is desired.
5.2 Quality Check of Input Stereo Data
The Stereo data consist of fore (BandF) and aft (BandA) imagery along with RPC
data and metadata. Prior to process the data, the following data quality specification
are examined :
The overlap between BandF and BandA should be greater than 90%
Cloud content should be less that 10%
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04 Date : 03 October 2017
Revision No. : 00
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04 Date : 03 October 2017
Revision No. : 00
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04 Date : 03 October 2017
Revision No. : 00
Retention
Format / Record
By Period
QSP/8.5.1/Svy/04:F-01
HOD (Svy) Part of Report File
Review of Report – Photogrammetry
9.0 Deliverables
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 4 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Procedure
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04 Date : 03 October 2017
Revision No. : 00
Appendix ‘A’
PHOTOGRAMMETRY
Start
Quality Control
Yes RMSE of residuals No
<0.50 times the
pixel size
Quality Control
Terrain Editing (TE) DEM/DTM and (Spikes, floating and digging
(Mass points + Break lines) Contour Generation mass points, break lines)
Digital Ortho
Image Generation
Image Enhancement,
Seam line feathering
End
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 5 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Format
Issue No. : 05
Doc No : QSP/8.5.1/Svy/04:F-01 Date : 03 October 2017
Revision No. : 00
REVIEW OF REPORT
Photogrammetry
1. Project Title :
2. Review Team :
HOD (Svy)
TL / Project In-charge
3. Check List :
Yes No NA
Identification of geographical extent of the study area
and demarcation of area of interest
Review of all earlier relevant studies and spatial data
(maps/imageries) and documentation of the study area
Reviewed by
Signature :
Name :
Designation :
Date :
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 6 of 6
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/01 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down work instruction for establishment of network of control points using
Global Navigational Satellite System (GNSS) receivers.
2.0 Scope
This covers guidelines for establishment of network of control points required for
subsequent detailed topographical surveys using GNSS.
3.0 Responsibility
HOD (Svy) shall be responsible to establish and maintain the work instruction.
Designated Surveyor / Senior Surveyor shall be responsible to implement the work
instruction.
4.0 Procedure
4.1 Study the requirements for GNSS control points for subsequent topographical
surveys for the project. Control points at an interval of 5 to 10 km are sufficient to
establish subsequent control stations by traverse using Total Station / GNSS,
otherwise as per requirement of TOR or as required by the client.
4.2 Plan broad network of control points to be established to cover the entire project
area. Reference station is usually a national control point established by National
Survey Agency having highly accurate coordinates. However, in the absence of any
national control point in the project area, a suitable local reference station may be
established. Observations on local reference station will be recorded for sufficiently
long period ranging from 2 to 6 hours depending upon GNSS specifications and
processed suitably to achieve more refined positional accuracy on WGS 84
reference ellipsoid. Based on reference station, the coordinates of the other stations
will be calculated using the differential GNSS observations. Time of observations
for each station shall be followed as per the manual of the GNSS receiver or as
specified in the TOR.
4.3 Ensure casting of proper size of reference pillars, as per the TOR or IRC code,
required for the project. The control stations normally consist of cement concrete
pillars with an iron nail in the centre, embedded in the concrete.
4.4 Carry out reconnaissance of the area and select suitable sites for fixing of cement
concrete pillars. These should be on positions such that there is a clear view to the
satellites in the sky and are not very far off from the project area to be surveyed.
Ensure that all these pillars are properly marked with unique number and
description and location recorded so that these control points can be accessed easily.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/01 Date : 03 October 2017
Revision No. : 00
4.5 Ensure proper GNSS observation procedure is followed at each station, as per
instruction manuals provided with the instrument.
4.6 In case these pillars are to be connected to National Coordinate System, contact the
Project Team Leader and get the coordinates of the national control points and
include these points in network of control points for observations. Generally one
control station at the beginning, one in the middle and one at the end of the road
stretch will be required to transform the observed GNSS coordinates system to
national coordinate system. Otherwise, reference datum as per instrument manual
(normally WGS - 84) will be used for control work.
4.7 All observations recorded during the day must be downloaded on the computer and
processed for calculation of all base lines measured. Ensure that ambiguity is
automatically resolved in base line computation, otherwise observations will be
repeated next day.
4.8 Select a suitable projection system as per TOR requirements to transform spherical
coordinates (latitude and longitude) into X, Y coordinates for subsequent Total
Station survey, as may be necessary for the area of work.
4.9 Normally ellipsoidal heights given by GNSS observations are not to be used for
project survey work. For precise work, all these pillars are to be connected to the
nearest Great Trigonometric Survey (GTS) bench marks using Auto / Digital Levels
as per instructions laid down in Work Instruction WI/Svy/02/03 – Levelling for
Topographical Surveys Using Auto / Digital Levels.
4.10 Utilize GNSS control data for further field work and prepare lists of control points
and descriptions to be incorporated in the draft technical report for topographical
survey as required in QSP/8.5.1/Svy/02 –Topographical Survey.
5.0 References
Instrument Manuals
6.0 Records
Retention
Format / Record
By Period
Descriptions and Coordinates of Part of draft survey
HOD (Svy)
GNSS Control Points report
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/02 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down work instruction for carrying out traverse using Total Station / GNSS.
2.0 Scope
This covers guidelines for supplementing survey control by Total Station / GNSS.
3.0 Responsibility
HOD (Svy) shall be responsible to establish and maintain the work instruction.
4.0 Procedure
4.1 Ensure that Total Station/GNSS receiver is in complete working condition and
battery fully charged.
4.2 Get description and coordinates of all primary control points fixed by GNSS survey
or any other method. Projection system used for GNSS control points / reference
control points should be ascertained.
4.3 Assess the requirements of secondary control for subsequent detailed topographic
survey. These are normally intermediate stations between GNSS control station and
should be inter-visible so that detailed survey can be carried out expeditiously.
These traverse control points shall be provided at 100 to 300 m apart or as terrain
permits. These control points are to be uniquely numbered and description recorded
for subsequent use.
4.4 Normally distance and angle method will be used for traverse observations if using
Total Station. In case of GNSS, differential GNSS receivers will be used in fast
static mode by recording signals by the receivers for 5 to 10 minutes for each base
line of 100 m to 300 m.
4.5 Ensure that all secondary control points are connected by traverse and closed on to
GNSS or any reference control points. All traverse data is required to be adjusted in
the field office and adjusted coordinates used for subsequent topographic survey.
Ensure desired accuracy of adjustment, otherwise observations of the traverse lines
are to be repeated.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/02 Date : 03 October 2017
Revision No. : 00
4.6 Provide elevation for these secondary control points using Auto / Digital Levels or
Total Stations as may be relevant to the task.
4.7 Utilize traverse control data for detailed field survey and prepare list of traverse
control points and their description (chainage etc. in case of linear projects) to be
incorporated in the draft technical report for topographical survey as required in
QSP/8.5.1/Svy/02 – Topographical Survey.
5.0 References
Instrument Manuals
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/03 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down work instruction for carrying out levelling for topographical survey
using Auto / Digital Level.
2.0 Scope
This covers guidelines for establishment of levels using Auto / Digital Levels for
various projects.
3.0 Responsibility
HOD (Svy) shall be responsible to establish and maintain the work instruction.
4.0 Procedure
4.1 Obtain detailed description and elevations (RL) of GTS / reference Bench Marks
(BMs) as may be available in the areas of survey. Based on these references (BMs),
the subsequent control level network, Temporary Bench Marks (TBMs) shall be
established in the area of work.
4.2 Normally all the three wire readings on the levelling staff will be read and double
levelling resorted to between reference BMs. The agreement of BMs level
difference between two reference bench marks should be better than 12 mm x k,
where k is distance between reference Bench Marks in km.
4.3 In case Auto Level is used for carrying out levelling, all observations of the
levelling staff readings shall be entered properly in the proforma in ink and all
computations for calculations of RLs shall be carried out the same day. All
computation of RLs in the level book shall be checked preferably by another
Surveyor before finalizing it. However, no manual recording is involved in case of
Digital Levels.
4.4 Ensure that all RLs of BMs are adjusted with reference BMs and adjusted values
only are used for subsequent surveys.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/03 Date : 03 October 2017
Revision No. : 00
4.5 Prepare short descriptions alongwith RLs for all the BMs to be used for subsequent
surveys. These shall be preferably checked by the Incharge survey team before
giving to Surveyors for detailed survey.
4.6 Assess requirements of providing levels using Auto / Digital Level, if any, for
longitudinal sections, cross-sections and other topographical points, as required in
the TOR / technical proposal / IRC codes. Generally these depend on the type of
terrain and the specific requirement of the project. Levelling for establishment for
RLs for longitudinal sections, cross-sections and other topographical points shall be
carried out, based on nearest BMs.
4.7 Ensure that all computations are carried out in the field itself and verified in the
terrain model developed in the computer and ambiguities, if any, resolved in the
field itself.
4.8 Study the contract agreement / technical proposal to find out any specific
requirement of level control (BMs) in the area of the project. Senior Surveyor will
deploy suitable survey team for establishment of these bench mark pillars, as to
meet the requirement of TOR.
4.9 Utilize level data for further field work and prepare list of BMs and their description
to be incorporated in the draft technical report for topographical survey as required
in QSP/8.5.1/Svy/02 – Topographical Survey.
5.0 References
Instrument Manuals
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 2
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/04 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down work instruction for carrying out topographic surveys for details using
Total Station / Lidar.
2.0 Scope
This covers guidelines for survey of topographical details using Total Station / Lidar
System.
3.0 Responsibility
HOD (Svy) shall be responsible to establish and maintain the work instruction.
4.0 Procedure
4.1 Collect list of coordinates and description of all the GNSS and traverse control
points falling in the area allotted for carrying out survey for details.
4.2 Collect information about the corridor to be surveyed from Senior Surveyor / TL /
TOR.
4.3 Ensure proper functioning of the Total Station and check that the battery is fully
charged.
4.4 Decide feature codes for various topographical features prevailing in the area of
work before starting the detailed topographical survey.
4.5 Based on the grid coordinates of survey control network, carry out detailed
topographical survey to pick up x, y & z coordinates of all the physical features
within the area of work (corridor) as per the requirement of TOR, using Total
Station / GNSS Receivers in RTK mode or LiDAR system.
Issue No. : 05
Doc No : WI/Svy/02/04 Date : 03 October 2017
Revision No. : 00
The following general objects are surveyed/digitised using either of the techniques
(conventional survey using Total Station or Lidar survey. Certain hidden objects
such as culvert details etc. which are not visible to the Lidar system are usually
surveyed by using Total station.
All types of roads, rails, culverts, bridges, ROBs, RUBs, canals, rivers, drains,
ditches, ponds, buildings, structures, power and transmission lines, km stones
along roads / railway lines / canals etc.
All details about inner and outer boundaries of religious places / important
structures falling within corridor for survey.
All details within a radius of 100 m (or more as required by design team) of
the junctions of all important roads like state and national highways are to be
surveyed.
4.7 Decide the density of ground points required to be picked up for longitudinal section
and cross sections survey depending on the terrain, so that proper digital terrain
model is created for design purposes, keeping the requirements of TOR in view.
Sufficient numbers of height points are required to depict properly the topography
of the terrain to develop proper contours, L-section and cross-section.
4.8 Collect names of important buildings, villages, destination of roads, rivers, canals
and railway lines including land use on both sides of the road.
4.9 Survey all trees falling in the corridor having girth specified in the TOR with proper
classification based on girth.
4.10 Ensure that all additional survey requirements for hydrology and bridges have been
carried out as desired, including deck level, soffit level and bed level of the bridges
and height of point marked by hydrology team to represent HFL of the river.
4.11 Ensure that all data surveyed is down loaded on the computer in the field. Inform
the data processor about any new feature added to the pre-defined feature library
and any other relevant information about his field survey data.
4.12 Senior surveyor will examine the field survey data for its completeness in all
respects and inform the Surveyor for any missing details to be re-surveyed.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/04 Date : 03 October 2017
Revision No. : 00
5.0 References
Instrument Manuals
6.0 Records
Nil
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/05 Date : 03 October 2017
Revision No. : 00
1.0 Purpose
To lay down work instruction for processing survey data collected in the field for
topographical surveys.
2.0 Scope
This covers guidelines for data processing in the field for topographical surveys.
3.0 Responsibility
HOD (Svy) shall be responsible to establish and maintain the work instruction.
4.0 Procedure
4.1.1 Ensure that all the requisite software for data downloading from survey equipment
like Total Stations/GNSS Receivers/Digital Level etc. and software for data
processing for desired output are loaded on to the computer and all necessary
precautions against probable virus attack are taken.
4.1.2 All survey data collected by Total Station shall be downloaded in the computer
using appropriate software, depending upon the format of the Total Station/data
recording device. It may be required to convert this data to a format acceptable to
the data processing software by changing the format or editing some header lines
etc.
4.1.3 Make proper feature library to include and define proper symbology to each feature
type for clear distinction between different features.
4.1.4 View the model to verify that all the data as required has been surveyed and make
necessary amendments to remove any visible discrepancies. Also check whether all
line features have been joined properly and verify all details for completeness and
missing details to be noted for corrections or re-survey. Ensure that strings for
continuous features are properly connected, especially at junctions of roads, bridges,
rivers, culverts etc.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 1 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/05 Date : 03 October 2017
Revision No. : 00
4.1.5 Examine all the height points (utilizing contours, longitudinal section, cross-section
etc.) to achieve a true representation of the terrain. Examine the model
systematically for any odd or redundant height with field records. If required, these
heights may be re-surveyed and model examined later.
4.2 Processing Point Cloud data collected through Mobile Lidar System
4.2.1 Point cloud data and corresponding panoramic images collected using Mobile /
Static Lidar systems will be suitable processed to generate 3D Model of the project
corridor and digitize all ground objects on proper layers using appropriate point
cloud data processing software.
4.2.2 Ensure that point cloud data collected through Lidar mapping system has been
preprocessed to define proper trajectory of the path travelled by the vehicle
4.2.3 Ensure minimum GNSS outage while scanning and take adequate remedial action to
safeguard against errors introduced due to GNSS outage by providing additional
ground control.
4.2.4 Digitize all relevant ground features in the corridor using 3D model generated from
point cloud and panoramic images draped over it using proper feature codes and
symbology exactly as done in the process of conventional data processing.
4.2.5 Certain gaps in the Mobile Lidar survey data may be noticed in the region not
directly visible to the scanner such as below the culverts & Bridges or any other
object obstructing the view. Such gaps will be identified and surveyed using
conventional survey methods using Total Station and supplemented to Lidar Survey
data.
4.2.6 Survey data collected through Mobile Lidar survey and conventional methods will
be combined to form seamless data of the project corridor and generate 3D model of
the area of interest.
4.3 Prepare hard copy output of the model. Ensure that all available descriptive
remarks, suitable marginal items, references, suitable texts etc. are incorporated.
This shall be checked / verified by the In-charge survey team to ensure that it
matches with ground and meets all the requirements of TOR.
4.7 Ensure that all corrections (insertions and deletions) marked in the verified hard
copy by Senior Surveyor have been incorporated and the final terrain data is
complete in all respect including descriptive text.
4.8 After completing all the tasks, supply the data to design team in the desired format,
in phases, as required by Design Team / TL.
4.9 Supply soft copy of final data to HOD (Svy) after completion of field survey.
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 2 of 3
Intercontinental Consultants & Technocrats (P) Ltd. Work Instruction
Issue No. : 05
Doc No : WI/Svy/02/05 Date : 03 October 2017
Revision No. : 00
5.0 References
Instrument Manuals
6.0 Records
Retention
Format / Record
By Period
Signature
Designation HOD (Survey & GIS) President Management Representative
Prepared by Approved by Issued by Page 3 of 3