COMMISSIONING INSPECTION SHEET

SETE ENERGY SAUDIA FOR INDUSTRIAL PROJECTS LTD.

QUALITY CONTROL DEPARTMENT CONTRACT NO. 7200012306 - INSTALLATION OF


48,000 M³/DAY INDUSTRIAL WASTE WATER
Site Acceptance Testing (S.A.T) TREATMENT PLANT

INSPECTION CHEKLIST: 2nd DAF air compressor vessel

1.0] ITEM DESCRIPTION: 2nd DAF air compressor

1.1] Construction Category : 1.2] Process Location/Component ID No :

1.3] Contractor : 1.4] Documents Defining Quality Requirements :

Not
2.0] ITEM ACCEPT REJECT
Applicable

A- GENERAL :
(i) Review required Material Specifications and condition for the equipment
(ii) To the Item: Recording of items Received, Spares Received and checking for that
equipment model, type and source check.
B- OVERALL EXAMINATION :
(i) Examination of system Materials, and check for certificates for F.A.T for the equipment.
(ii) Check for transportation Damage caused or storage damage for Complete
system and parts.
C-INSTALLATION AND ASSEMBLY
(i) Installation according to the submitted document / Drawing in the
Corresponding Drawing p&I.D No.( 12306-PP-A1-140 for Deoiling Pressure vessel,
and 12306-PP-A1-140 for secondary Pressure vessels ).

(ii) Vessel orientation agrees with construction drawings.

(iii) Check if the Vessels are properly installed ( anchor bolts, secured a

and grouting properly placed) .

(iv) Check for Accessibility for vessels, devices and valves .

(v) Support brackets and clips for piping, ladders, platforms, etc.,

have been properly installed.

(vi) Check for Suitability of flanges, facings, and gaskets for service conditions.

(vii) Check that the Vessel nameplate has been installed.

(viii) Check that the Connecting piping and valves have been installed on the vessel

(included all instrument devices according to the drawing).

(ix) Check to confirm that vessel is free of all loose debris or standing water.

(x) Check that the water nozzles installed properly and internly cleaned.

(x) Check that the earthing of the vessel was connected properly.

REV. No. 0 - 10/17/2018 SETE-CIS-IWTP-II-**** PAGE NO. 1


COMMISSIONING INSPECTION SHEET

SETE ENERGY SAUDIA FOR INDUSTRIAL PROJECTS LTD.

QUALITY CONTROL DEPARTMENT CONTRACT NO. 7200012306 - INSTALLATION OF


48,000 M³/DAY INDUSTRIAL WASTE WATER
Site Acceptance Testing (S.A.T) TREATMENT PLANT

INSPECTION CHEKLIST: 2nd DAF air compressor vessel

1.0] ITEM DESCRIPTION: 2nd DAF air compressor

1.1] Construction Category : 1.2] Process Location/Component ID No :

1.3] Contractor : 1.4] Documents Defining Quality Requirements :

Not
2.0] ITEM ACCEPT REJECT
Applicable

D-OPERATION
(i) check for performance of the equipment against the designed specifications.
(ii) check data sheet and corresponding test results from running equipment on site.

3.0] DESCRIPTION OF DEFICIENCIES NOTED :

4.0] ACTION TAKEN ON NOTES DEFICIENCIES :

SUB-CONTRACTOR
CHECKED BY: PREPARED BY SETE QA/QC MARAFIQ
QA/QC

NAME:

SIGNATURE:

DATE:

REV. No. 0 - 10/17/2018 SETE-CIS-IWTP-II-**** PAGE NO. 2