LIST OF QC INSPECTION FORM FOR MECHANICAL

TANJUNG JATI B, BOILER OF BOP

No. Form No. Description Remarks No. Form No. Description Remarks

1 F 1-1 Insulation Report IR

2 F 1-2 Painting Inspection Report PIR

3 F 1-3 Welding Inspection Report WIR

4 F 1-4 Anti Corrosive Coating Inspection Report ACR

5 F 1-5 Alignment Inspection Report AIR

6 F 1-6 Elevation & Levelling Report ELR

7 F 1-7 Internal Cleaning Report CIR

8 F 1-8 Pressure Test Report PTR

9 F 1-9 Punch List (Final Inspection) PL

10 F 1-10 Foundation Inspection Report FIR

11 F 2-1 Column/Verticality Report CVR


Elevation Inspection Report (Padding
12 F 2-2 EIR
Plate)
13 F 2-3 Grouting Inspection Report GIR

14 F 2-4 Bolt Tightening Report BTR

15 F 2-5 Leak Test Report LTR

16 F 2-6 Dimensional Inspection Report DIR

17 F 2-7 Fit-up Inspection Report FUR


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)
OWNER : PT.CENTRAL JAVA POWER REPORT NO. : R-EQU-EIR -008
CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE :
SUBJECT : PADDING Plate (TRESTLE C 104 ) REF. DWG NO.: F558S-T0204 REV-C
AREA : trestle C 104 PSS NO. : 322

SKETCH

COAL CRUSHER TT 107

C411 C410 C409 C408 C407 C406 C405


1 5 5
Top Elev. of Padding

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE

Notes.

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)
OWNER : PT.CENTRAL JAVA POWER REPORT NO. :
CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE :
SUBJECT : REF. DWG NO. :
AREA : PSS NO. :

E L E V A T I O N (mm)
NO. POSITION RESULT
Design Actual Dev. N
1 0
2 0 1 2 3

3 0
8 4
4 0
5
7 6 5
6

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24
Notes.

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)
OWNER : PT.CENTRAL JAVA POWER REPORT NO. : R-EQU-EIR-009
CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE :
SUBJECT : PADDING PLATE TRESTLE C-105B REF. DWG NO.: f 558S-T0205-02
AREA : TRESTLE C-105B PSS NO. : 322

SKETCH
NORTH SIDE

STACK RECL-B TT 104

C 5-b

C 5-a

6 1
5 14 3 2 1
6
Top Elev. of Padding

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE

Notes.

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E EQU EIR 013


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 12-Apr-10
SUBJECT : PADDING PLATE OF CRUSHER BUILDING REF. DWG NO.: F 558 S -T 0110 -01 REV 11
AREA : CRUSHER BUILDING PSS NO. : 322

SKETCH

CH -E 1 2

CH 4 3
-D

CH
-C
Top Elev. of Padding
CH -B

CH -A

CH -1 CH -2 CH -3 CH -4 CH -5

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
4300 4300
4300 4300
4300 4300
4300 4300
4300 4300
4300 4300
4300 43OO
4300 4300
Notes.

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
FIELD INSPECTION REPORT
Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)
OWNER : PT.CENTRAL JAVA POWER REPORT NO. : R -EQU -EIR -
CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : MAY 24 .2010
SUBJECT : PADDING PLATE OF TRESTLE C 105 A REF. DWG NO. : F 558 S- T0205 -01
AREA : COAL TRESTLE C 105 A (south side ) PSS NO. : 322

SKETCH

SOUTH SIDE

STACK RECL- A TT 106

C 5-D

C 5-a

C-508 C-509 C-510 C-511 C-512 C-513 C-514 1 2

4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE

Notes.

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -75


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : may 31 ,2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
131 A 1 3750 1 3749 -1 129 A 1 3750 1 3749 -1
2 3750 2 3748 -2 2 3750 2 3752 2
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3748 -2 4 3750 4 3748 -2

131 B 1 3750 1 3748 -2 129 B 1 3750 1 3751 1


2 3750 2 3748 -2 2 3750 2 3748 -2
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3748 -2 4 3750 4 3748 -2

130 A 1 3750 1 3749 -1 128 A 1 3750 1 3747 -3


2 3750 2 3748.5 -1.5 2 3750 2 3752 2
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3750 0 4 3750 4 3748 -2

130 B 1 3750 1 3748 -2 128 B 1 3750 1 3748 -2


2 3750 2 3751.5 1.5 2 3750 2 3749 -1
3 3750 3 3754 4 3 3750 3 3749 -1
4 3750 4 3747 -3 4 3750 4 3749 -1
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -75


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : may 31 ,2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
127 A 1 3750 1 3748 -2 125 A 1 3750 1 3748 -2
2 3750 2 3747 -3 2 3750 2 3747 -3
3 3750 3 3748 -2 3 3750 3 3748 -2
4 3750 4 3748.5 -1.5 4 3750 4 3753 3

127 B 1 3750 1 3748.5 -1.5 125 B 1 3750 1 3747 -3


2 3750 2 3748 -2 2 3750 2 3748 -2
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3748 -2 4 3750 4 3749 -1

126 A 1 3750 1 3747 -3 124 A 1 3750 1 3754 4


2 3750 2 3751 1 2 3750 2 3749 -1
3 3750 3 3748 -2 3 3750 3 3748 -2
4 3750 4 3748 -2 4 3750 4 3753 3

126 B 1 3750 1 3749 -1 124 B 1 3750 1 3753 3


2 3750 2 3747 -3 2 3750 2 3748 -2
3 3750 3 3748 -2 3 3750 3 3747 -3
4 3750 4 3748.5 -1.5 4 3750 4 3750 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -75


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : may 31 ,2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
123 A 1 3750 1 3752 2 121 A 1 3750 1 3753 3
2 3750 2 3748 -2 2 3750 2 3747 -3
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3753 3 4 3750 4 3752 2

123 B 1 3750 1 3753 3 121 B 1 3750 1 3752 2


2 3750 2 3750 0 2 3750 2 3749 -1
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3752 2 4 3750 4 3752 2

122 A 1 3750 1 3753 3 120 A 1 3750 1 3751 1


2 3750 2 3748 -2 2 3750 2 3748 -2
3 3750 3 3747 -3 3 3750 3 3749 -1
4 3750 4 3753 3 4 3750 4 3751 1

122 B 1 3750 1 3754 4 120 B 1 3750 1 3752 2


2 3750 2 3748 -2 2 3750 2 3748 -2
3 3750 3 3749 -1 3 3750 3 3749 -1
4 3750 4 3753 3 4 3750 4 3752 2
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR 75


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : may 31 ,2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

MAX.
ELEVATION MAX. ELEVATION
POINT DEV. POINT DEV. TOLERANC
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL
E
119 A 1 3750 1 3751 1 117 A 1 3750 1 3750 0
2 3750 2 3749 -1 2 3750 2 3749 -1
3 3750 3 3748 -2 3 3750 3 3748 -2
4 3750 4 3751 1 4 3750 4 3754 4

119 B 1 3750 1 3751 1 117 B 1 3750 1 3751 1


2 3750 2 3747 -3 2 3750 2 3748 -2
3 3750 3 3747 -3 3 3750 3 3747 -3
4 3750 4 3750 0 4 3750 4 3750 0

118 A 1 3750 1 3754 4 116 A 1 3750 1 3748 -2


2 3750 2 3749 -1 2 3750 2 3747 -3
3 3750 3 3748 -2 3 3750 3 3748 -2
4 3750 4 3754 4 4 3750 4 3750 0

118 B 1 3750 1 3753 3 116 B 1 3750 1 3750 0


2 3750 2 3747 -3 2 3750 2 3747 -3
3 3750 3 3749 -1 3 3750 3 3748 -2
4 3750 4 3754 4 4 3750 4 3750 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR - 77


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : june, 03 2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322
page (1 of 2)
SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
115 A 1 3750 1 3749 -1 113 A 1 3750 1 3751 1
2 3750 2 3749 -1 2 3750 2 3751 1
3 3750 3 3749 -1 3 3750 3 3752 2
4 3750 4 3749 -1 4 3750 4 3750.5 0.5

115 B 1 3750 1 3749 -1 113 B 1 3750 1 3748 -2


2 3750 2 3749 -1 2 3750 2 3752 2
3 3750 3 3749 -1 3 3750 3 3752 2
4 3750 4 3749 -1 4 3750 4 3753 3

114 A 1 3750 1 3749 -1 112 A 1 3750 1 3750.5 0.5


2 3750 2 3749 -1 2 3750 2 3750.5 0.5
3 3750 3 3750 0 3 3750 3 3750 0
4 3750 4 3749 -1 4 3750 4 3750.5 0.5

114 B 1 3750 1 3749 -1 112 B 1 3750 1 3752 2


2 3750 2 3749 -1 2 3750 2 3750 0
3 3750 3 3749 -1 3 3750 3 3752 2
4 3750 4 3748 -2 4 3750 4 3750 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR 77


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : june, 03 2010
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322
page (2 of 2)
SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
111 A 1 3750 1 3751 1 109 A 1 3750 1 3746 -4
2 3750 2 3752 2 2 3750 2 3746 -4
3 3750 3 3753 3 3 3750 3 3746 -4
4 3750 4 3751 1 4 3750 4 3746 -4

111 B 1 3750 1 3750 0 109 B 1 3750 1 3746 -4


2 3750 2 3750 0 2 3750 2 3746 -4
3 3750 3 3750 0 3 3750 3 3746 -4
4 3750 4 3749 -1 4 3750 4 3746 -4

110 A 1 3750 1 3744 -6


2 3750 2 3745 -5
3 3750 3 3744 -6
4 3750 4 3745 -5

110 B 1 3750 1 3749 -1


2 3750 2 3750 0
3 3750 3 3750 0
4 3750 4 3750 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)
OWNER : PT.CENTRAL JAVA POWER REPORT NO. : R-EQU-EIR -008
CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 11-Jun-10
SUBJECT : PADDING PLATE COALTRESTLE CT-107 REF. DWG NO.: F558S-T0204 REV-C
AREA : TRESTLE C-107 B PSS NO. : 322
SKETCH

COAL CRUSHER TT 107

C701 C702 C703 C704 C705 C706 C707 Top Elev. of Padding
1 5 5

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1
2
C701 A C701 A
3
4

1
2
C701 B C701 B
3
4

1
2
C702 A C701 A
3
4

1
2
C702 B C701 B
3
4

1
2
C703 A C701 A
3
4

1
2
C703 B C701 B
3
4
Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -101


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 24-Jun-10
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
108A 1 1 106 A 1 1
2 2 2 2
3750 3747 -3 3750 3748 -2
3 3 3 3
4 4 4 4

108 B 1 1 106 B 1 1
2 2 2 2
3750 3749 -1 3750 3750 0
3 3 3 3
4 4 4 4

107 A 1 1 105 A 1 1
2 2 2 2
3750 3748 -2 3750 3752 2
3 3 3 3
4 4 4 4

107 B 1 1 105 B 1 1
2 2 2 2
3750 3749 -1 3750 3751 1
3 3 3 3
4 4 4 4
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -102


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 24-Jun-10
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
104 A 1 1 102 A 1 4000 1 4001 1
2 2 2 4000 2 4000 0
3750 3748 -2
3 3 3 4000 3 4001 1
4 4 4 4000 4 3999 -1

104 B 1 1 102 B 1 4000 1 4000 0


2 2 2 4000 2 4001 1
3750 3748 -2
3 3 3 4000 3 4001 1
4 4 4 4000 4 4000 0

103 A 1 3750 1 3747 -3 101 A 1 4000 1 3998 -2


2 3750 2 3751 1 2 4000 2 3998 -2
3 3750 3 3749 -1 3 4000 3 3999 -1
4 3750 4 3751 1 4 4000 4 3998 -2

103 B 1 3750 1 3752 2 101 B 1 4000 1 3998 -2


2 3750 2 3748 -2 2 4000 2 3999 -1
3 3750 3 3750 0 3 4000 3 3998 -2
4 3750 4 3749 -1 4 4000 4 3998 -2
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR - 103


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 24-Jun-10
SUBJECT : PADDING PLATE OF TRESTLE C 101 REF. DWG NO. : f-558 S-T0201-01 REV 11
AREA : JETTY1 COAL TRESTLE C 101 PSS NO. : 322

SKETCH
Column 7 29

N
B

A
6

1 2
Top Elev. of Padding
### 4 3

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
100 A 1 4000 1 3999 -1 098 A 1 4000 1 3999 -1
2 4000 2 4000 0 2 4000 2 3999 -1
3 4000 3 3999 -1 3 4000 3 4000 0
4 4000 4 3999 -1 4 4000 4 3999 -1

100 B 1 4000 1 3999 -1 098 B 1 4000 1 3999 -1


2 4000 2 3999 -1 2 4000 2 4000 0
3 4000 3 3999 -1 3 4000 3 4000 0
4 4000 4 3999 -1 4 4000 4 3999 -1

099 A 1 4000 1 3999 -1


2 4000 2 3998 -2
3 4000 3 3999 -1
4 4000 4 3999 -1

099 B 1 4000 1 3999 -1


2 4000 2 3998 -2
3 4000 3 3999 -1
4 4000 4 3999 -1
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


FIELD INSPECTION REPORT
Tanjung Jati "B" Coal-Fired 2x660 MW

WELDING INSPECTION REPORT (WIR)

OWNER : PT. CENTRAL JAVA POWER REPORT NO. : R-EQU-WIR-080


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 22-Jul-10
SUBJECT : WELD JOINT OF PORTAL REF. DWG NO. : GSU0702. Erc.0
AREA : JETTY SHIP UNLOADER PSS NO. : 321

Result
Line No Joint No Welder Stamp Process Thickness Diameter
Accepted Rejected
FW 01 SCED W-168 12 - Accepted -
SMAW
FW 02 SCED W-172 10 - Accepted -
A
FW 03 SCED W-169 12 - Accepted -
SMAW
FW 04 SCED W-167 10 - Accepted -

FW 01 SCED W-169 12 - Accepted -


SMAW
FW 02 SCED W-168 10 - Accepted -
B
FW 03 SCED W-167 12 - Accepted -
SMAW
FW 04 SCED W-166 10 - Accepted -

NOTE:

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by,
PT. Truba Jaya Engineering SCED BVI
F1-3

SCED
R)

R-EQU-WIR-080
22-Jul-10
GSU0702. Erc.0109-19 rev.0
321

Remarks

Reviewed / Approved by,


Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -158


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 18-Aug-10
SUBJECT : PADDING PLATE OF TRESTLE C 108 REF. DWG NO. : F5585-T0208-01, F5585-T0208-11E-14E
AREA : COAL TRESTLE C-108 PSS NO. : 322

SKETCH
Z1
Column Z1 Z5
Z2
Z3 N
1 2 -1 Z3
1 2 -2 Z4
4 3 1 2
TT-107 4 1 2 Z5
3
4 1
3 2
4 1 2
3
1 2 4
1 3 4
B
2 3 B
4 1 2
3 4 1 2
3 1 2
4 3 4 1 2
1 2 3
4
### 3
4
Top Elev. of Padding 4300
4 3 3 A

A
ELEVATION MAX. ELEVATION MAX.
POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 4300 1 4301 1 1 4300 1 4301 1
2 4300 2 4301 1 2 4300 2 4301 1
Z-1 A Z-3-1A
3 4300 3 4301 1 3 4300 3 4301 1
4 4300 4 4301 1 4 4300 4 4301 1

1 4300 1 4301 1 1 4300 1 4300 0


2 4300 2 4301 1 2 4300 2 4300 0
Z-1 B Z-3-1B
3 4300 3 4301 1 3 4300 3 4300 0
4 4300 4 4301 1 4 4300 4 4300 0

1 4300 1 4302 2 1 4300 1 4300 0


2 4300 2 4301 1 2 4300 2 4302 2
Z-2 A Z-3-2A
3 4300 3 4302 2 3 4300 3 4301 1
4 4300 4 4301 1 4 4300 4 4300 0

1 4300 1 4300 0 1 4300 1 4300 0


2 4300 2 4301 1 2 4300 2 4300 0
Z-2 B Z-3-2B
3 4300 3 4300 0 3 4300 3 4300 0
4 4300 4 4299 -1 4 4300 4 4300 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -159


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 18-Aug-10
SUBJECT : PADDING PLATE OF TRESTLE C 108 REF. DWG NO. : F5585-T0208-01, F5585-T0208-11E-14E
AREA : COAL TRESTLE C-108 PSS NO. : 322

SKETCH
Z1
Column Z1 Z5
Z2
Z3 N
1 2 -1 Z3
1 2 -2 Z4
4 3 1 2
TT-107 4 1 2 Z5
3
4 1
3 2
4 1 2
3
1 2 4
1 3 4
B
2 3 B
4 1 2
3 4 1 2
3 1 2
4 3 4 1 2
1 2 3
4
### 3
4
Top Elev. of Padding 4300
4 3 3 A

A
ELEVATION MAX. ELEVATION MAX.
POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 4300 1 4301 1
2 4300 2 4301 1
Z-4 A
3 4300 3 4300 0
4 4300 4 4301 1

1 4300 1 4300 0
2 4300 2 4301 1
Z-4 B
3 4300 3 4301 1
4 4300 4 4300 0

1 4300 1 4300 0
2 4300 2 4300 0
Z-5 A
3 4300 3 4300 0
4 4300 4 4300 0

1 4300 1 4301 1
2 4300 2 4301 1
Z-5 B
3 4300 3 4301 1
4 4300 4 4301 1
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -160


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 19-Aug-10
SUBJECT : PADDING PLATE OF TRESTLE C 108 REF. DWG NO. : F5585-T0208-01, F5585-T0208-11E-14E
AREA : COAL TRESTLE C-108 PSS NO. : 322

SKETCH
Z6
Column Z6 Z 10
Z7 N
C-10 Z8
1
8 A4 /B Z9
2 1
3
Z 10-1 Z 10-2
1 4
2
4 2 3 1
1 4
3 2
B 4 2 3 1 B
1 4
3 2
4 3 1 1 2 2
12 4 4 3 3
3
1 2 4
2
### 3 1 1 2 2
4 3 Top Elev. of Padding 4300 4 4 3 3
A

A
ELEVATION MAX. ELEVATION MAX.
POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 4300 1 4300 1 4300 1 4300 0
2 4300 2 4300 2 4300 2 4301 1
Z6A Z8A
3 4300 3 4300 3 4300 3 4300 0
4 4300 4 4300 4 4300 4 4301 1

1 4300 1 4300 1 4300 1 4300 0


2 4300 2 4300 2 4300 2 4301 1
Z6B Z8B
3 4300 3 4300 3 4300 3 4301 1
4 4300 4 4300 4 4300 4 4301 1

1 4300 1 4301 1 1 4300 1 4301 1


2 4300 2 4302 2 2 4300 2 4300 0
Z7A Z9A
3 4300 3 4301 1 3 4300 3 4300 0
4 4300 4 4300 0 4 4300 4 4300 0

1 4300 1 4302 2 1 4300 1 4300 0


2 4300 2 4301 1 2 4300 2 4300 0
Z7B Z9B
3 4300 3 4302 2 3 4300 3 4300 0
4 4300 4 4300 0 4 4300 4 4301 1
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -161


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 19-Aug-10
SUBJECT : PADDING PLATE OF TRESTLE C 108 REF. DWG NO. : F5585-T0208-01, F5585-T0208-11E-14E
AREA : COAL TRESTLE C-108 PSS NO. : 322

SKETCH
Z6
Column Z6 Z 10
Z7 N
C-10 Z8
1
8 A4 /B Z9
2 1
3
Z 10-1 Z 10-2
1 4
2
4 2 3 1
1 4
3 2
B 4 2 3 1 B
1 4
3 2
4 3 1 1 2 2
12 4 4 3 3
3
1 2 4
2
### 3 1 1 2 2
4 3 Top Elev. of Padding 4300 4 4 3 3
A

A
ELEVATION MAX. ELEVATION MAX.
POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 4300 1 4300 0
2 4300 2 4300 0
Z 10-1 A
3 4300 3 4300 0
4 4300 4 4300 0

1 4300 1 4300 0
2 4300 2 4300 0
Z 10-1 B
3 4300 3 4300 0
4 4300 4 4300 0

1 4300 1 4300 0
2 4300 2 4299 -1
Z 10-2 A
3 4300 3 4301 1
4 4300 4 4300 0

1 4300 1 4301 1
2 4300 2 4300 0
Z 10-2 B
3 4300 3 4300 0
4 4300 4 4300 0
Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR - 206


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 27-Sep-10
SUBJECT : PADDING PLATE OF TRESTLE C 106 REF. DWG NO. : F5585-M0206-11E/12E/13E
AREA : COAL TRESTLE C-106A/B PSS NO. : 322

SKETCH
Column C601 C609
1
1
1 2 N
4 2
2 1 1 1 1 1 1 1
4 3
1
3 B
2 2 2 2 2 2 2
2
1
C.601 C.602 C.603 C.604 C.605 C.606 C.607 C.608 C.609
2
3
1 2
1 1 1 1 1 1 1
1 2 4 1 A
4 3 1 2 2 2 2 2 2 2
4 2
2 4 3
### 3
Top Elev. of Padding 4300
A

ELEVATION MAX. ELEVATION MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 4300 1 4300 0 1 4300 1 4300 0
C601A C606A
2 4300 2 4301 1 2 4300 2 4300 0
1 4300 1 4299 -1 1 4300 1 4300 0
C601B C606B
2 4300 2 4299 -1 2 4300 2 4299 -1
1 4300 1 4299 -1 1 4300 1 4300 0
C602A
2 4300 2 4300 0 2 4300 2 4300 0
C607A
1 4300 1 4300 0 1 4300 1 4298 -2
C602B
2 4300 2 4299 -1 2 4300 2 4299 -1
1 4300 1 4300 0 1 4300 1 4299 -1
C603A
2 4300 2 4301 1 2 4300 2 4299 -1
C607B
1 4300 3 4300 0 1 4300 3 4299 -1
C603B
2 4300 4 4298 -2 2 4300 4 4299 -1
1 4300 1 4300 0 1 4300 1 4298 -2
C604A
2 4300 2 4300 0 2 4300 2 4300 0
C608A
1 4300 1 4300 0 1 4300 1 4300 0
C604B
2 4300 2 4298 -2 2 4300 4 4300 0
1 4300 1 4300 0 1 4300 1 4298 -2
2 4300 2 4300 0 2 4300 2 4299.5 -0.5
C605A C608B
3 4300 3 4300 0 3 4300 3 4299 -1
4 4300 4 4300 0 4 4300 4 4298 -2
1 4300 1 4300 0 1 4300 1 4299.5 -0.5
C609A
2 4300 2 4300 0 2 4300 2 4298 -2
C605B
3 4300 3 4299 -1 3 4300 3 4299 -1
C609B
4 4300 4 4299 -1 4 4300 4 4299 -1

Notes

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,
PT. Truba Jaya Engineering SCED BVI Owner's / Engineer
F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR -281


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 10-Jan-11
SUBJECT : PADDING PLATE OF TRESTLE C 109 NO(901-904) REF. DWG NO. : F5585-T0209-01
AREA : COAL TRESTLE C-109 PSS NO. : 322

SKETCH Column C.901 C.904


1
N
1 1 1 2

C
1 2 2 2 2 4 3

B
4 3
C.904 C.903 C.902 C.901

A
1 1 2
1 1

B 3
4
A
2 2 2
###
Top Elev. of Padding 5300

ELEVATION MAX. CENTER LINE MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 5300 1 5302 2
A 2315 A 2315 0
2 5300 2 5302 2
C901B C901
3 5300 3 5301 1
B 2315 B 2315 0
4 5300 4 5302 2
1 5300 1 5301 1
A 2315 A 2315 0
2 5300 2 5301 1
C901C C902
3 5300 3 5301 1
B 2315 B 2315 0
4 5300 4 5301 1
1 5300 1 5300 0
C902B A 2315 A 2324 +9
2 5300 2 5300 0
C903
1 5300 1 5301 1
C902C B 2315 B 2306 -9
2 5300 2 5301 1
1 5300 1 5301 1
C903B A 2315 A 2315 0
2 5300 2 5301 1
C904
1 5300 1 5300 0
C903C B 2315 B 2315 0
2 5300 2 5301 1
1 5300 1 5299 -1
C904B
2 5300 2 5300 0
1 5300 1 5299 -1
C904C
2 5300 2 5299 -1

Notes : For centerline on foundation no.C903 can be adjusting when erection time, And directly check on structure

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,

PT. Truba Jaya Engineering SCED BVI Owner's / Engineer


F2-2

FIELD INSPECTION REPORT


Tanjung Jati "B" Coal-Fired 2x660 MW
SCED
ELEVATION INSPECTION REPORT (EIR)

OWNER : PT.CENTRAL JAVA POWER REPORT NO. : E -EQU -EIR - 282


CLIENT : SUMITOMO CORPORATION ERECTION DIVISION DATE : 14-Jan-11
SUBJECT : PADDING PLATE OF TRESTLE C 109 NO.C-907 REF. DWG NO. : F5585-T0209-01
AREA : COAL TRESTLE C-109 PSS NO. : 322

SKETCH Column C.901 C.904


N
1 1 1 1 2

C
1 2 2 2 2 4 3

B
4 3
C.907 C.903 C.902 C.901

A
1 1 2
1 1

A B 3
2 2 2 4
###
Top Elev. of Padding 5300

ELEVATION MAX. CENTER LINE MAX.


POINT DEV. POINT DEV.
NO PLAN NO ACTUAL TOLERANCE NO PLAN NO ACTUAL TOLERANCE
1 5300 1 5297.5 2.5 A 2315 A 2315 0
C907C C907
2 5300 2 5298 2 B 2315 B 2315 0

3 5300 3 5298 2
C907B
4 5300 4 5298 2

Notes :

Prepared & Inspected by, Witnessed / Approved by, Witnessed / Approved by, Reviewed / Approved by,