Sie sind auf Seite 1von 8

This article has been accepted for publication in a future issue of this journal, but has not been

fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
1

Power Testing of Pre-Insertion Resistors:


Limitations and Solution
Helmut Heiermeier, Member, IEEE, and Rosy Balaram Raysaha

 (separation of arcing contacts), the PIR switch will open


Abstract—Pre-Insertion Resistors (PIR) are used in followed by the interrupter. During “closing” operation, the
combination with circuit breakers to absorb switching transients pre-strike in PIR switch must occur before it happens in the
and come into effect during the “closing” operation of the interrupter. Depending on the design, PIR switch may remain
breaker. It is mainly used for rated voltages equal to or higher
fully closed during normal operation. In a series PIR
than 420 kV for line lengths above 200 km. Although it is an
important component, power testing of complete PIR is very configuration (fig. 1b), the PIR switch is in series with the
complicated and not well-defined. Therefore, an attempt has been interrupter but in parallel with the resistor stack. It can be seen
made in this paper to provide alternative test methods for power from table 1 that different configurations experience different
testing of PIR without compromising on its important stresses. Depending upon GIS bay layout, the series PIR
parameters. Due to high energy requirement and limitations of configuration might use less space and could be less expensive
the test laboratory, a multipart testing of PIR is necessary to
than shunt PIR configuration.
prove its thermal capability and dielectric behavior. Before
proceeding with the complete PIR test, the critical parameters of There are several literatures available on the usage of PIR
PIR like Mechanical Insertion Time (MIT), Rate of Decay of for mitigation of switching overvoltages [5], [6], [7], [8], [9],
Dielectric Strength (RDDS) of interrupter and PIR switch, etc., [10], [11], [12], [13]. An alternative to PIR is “Controlled
should be verified by testing. These test procedures are also Switching” [13], [14], which is especially used for
explained in detail along with a method to theoretically evaluate applications like reducing inrush current in transformers and
Electrical Insertion Time (EIT) for different network conditions. overvoltages during capacitive switching. However, recent
The series PIR configuration for metal enclosed SF6 system has advances in PIR technology [11], [12] have also made it
been considered in this paper.
equally efficient for the latter applications keeping it cost
competitive with a relatively simple design. In addition,
Index Terms— electrical insertion time, mechanical insertion
time, pre-strike, RDDS, series PIR, shunt PIR, thermal energy literature is available on the replacement of PIR by pre-
insertion reactors [13] and also by surge arrestors [15], [16].
However, PIR continues to remain a reliable solution [2], [11]
I. INTRODUCTION and its performance needs to be confirmed by testing. The
amount of literature available on PIR testing is very limited

P RE-INSERTION Resistors (PIR) are used in combination


with Circuit Breakers (CB) to absorb switching transients
and come into effect during the “closing” operation of the
[17], [18] and even in international standards [18], no detailed
test procedure is mentioned. The power testing of complete
PIR is very complicated and less defined as compared to other
breaker [1], [2], [3], [4]. PIR consists of a resistor stack and a power tests for circuit breakers [18]. Therefore, an attempt has
switch, which will be called PIR switch in this paper. been made in this paper to explain in detail the test procedure
Depending upon the position of the PIR switch with respect to of PIR since power testing of PIR requires special methods
the interrupting chamber/CB, there can be a series or a parallel and considerations. These test procedures need to take into
PIR configuration. Series PIR configuration is widely used in account the different stresses (based upon PIR configuration)
Dead Tank Breakers (DTB) and Gas Insulated Switchgear that will occur under various network conditions. Due to all
(GIS) while parallel PIR configuration is widely used in Live these factors, the power testing of PIR will finally result in a
Tank Breakers (LTB). Basically, both configurations can be multipart testing.
used in DTB and GIS, depends upon bay layout, cost, etc.
In parallel/shunt PIR configuration (fig. 1a), the PIR switch
is in series with the resistor stack and both are in parallel with
the interrupter. The interrupter operation follows the PIR
switch operation, i.e., during “closing” operation (first (a) Parallel PIR (b) Series PIR
mechanical arcing contact touch), the PIR switch will close Fig. 1. Schematic of PIR configuration
followed by the interrupter and during “opening” operation

Helmut Heiermeier is with ABB Switzerland, CH-5401 Baden, Fabrikstrasse 13,


II. COMPARISON OF PIR ENERGY FOR DIFFERENT NETWORK
(email: helmut.heiermeier@ch.abb.com) CONDITIONS
Rosy B. Raysaha is with ABB India, Maneja, Vadodara - 390013, Gujarat.
(email: rosy.raysaha@in.abb.com) For PIR, there is a minimum “Electrical Insertion Time”
(EIT) specified, which is defined by network conditions. The

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
2

resulting energy forms the basis for PIR dimensioning and


hence, is of prime importance. The maximum EIT, as well as, TABLE 1. Comparison of series and shunt PIR
number of operations is limited by the energy capability of the Switch Parallel PIR configuration Series PIR configuration
condition Interrupter PIR Interrupter PIR switch
resistor stack itself. Various network conditions have to be switch
considered to determine the most critical case for defining the “Close” closes last closes closes first closes last
resistor stack. For a given rated voltage and resistance, the operation and closes first and closes and
energy to be absorbed by PIR is defined by the Rate of Decay against full and closes against closes
short circuit against resistor against full
of Dielectric Strength (RDDS) of interrupter and PIR switch, current resistor current short
as well as, Mechanical Insertion Time (MIT). current circuit
In fig. 2, a series PIR configuration has been considered as current
an example with interrupter closing on Out-of-Phase (OoP) “Open” extinguishes opens extinguishes opens after
operation the short prior to the short interrupting
condition, i.e., it pre-strikes at the voltage peak which is 2 p.u.
circuit the circuit process of
(where 1 p.u. is peak phase voltage). In these figures, rectified current interrupter current the
voltage is plotted only for ease of calculation. The figure will interrupter
be explained in detail in section IV A. The MIT is defined as Closed must carry no must carry must carry
position nominal nominal nominal nominal
the time delay between the first mechanical arcing contact
current current to current current
touch of interrupter and PIR switch as shown in fig. 2a. The be carried
intersection of interrupter RDDS with source wave shows the Open must must must must
pre-strike instant in interrupter while the intersection of PIR position withstand withstand withstand withstand
RDDS with the voltage drop across PIR gives the pre-strike full full full max.
dielectric dielectric dielectric voltage
instant in PIR. The difference between these two pre-strike ratings ratings ratings drop across
instant gives EIT, i.e., the time for which the PIR will be resistor
inserted in the circuit. Fig. 2b shows the current through the during
interrupter and PIR after the respective switches are closed, operation
During PIR need to withstand the energy (heat), as well as, the
whereas the cumulative PIR energy is shown in fig. 2c. The operation dielectric stress along the resistor blocks
simulation is carried out using Alternative Transient Program
(ATP) and the simulation details will be explained in section
IVA.
A. Possible Network Conditions
Based upon network conditions, the maximum PIR energy
will be determined, which will then decide the dimension of
the resistor stack.
1) Closing against 100% Terminal Fault (TF)
This is a condition where highest short circuit current will
be provided by the network. However, the applied voltage will
be the nominal system voltage. Depending on the making
angle of the first switching device, this will lead to a different
energy input to the resistor stack. The probability of
occurrence of this stress during service is very low.
2) Closing against Out-of-Phase (OoP) Fig. 2. CB closing on OoP condition (series PIR) (a) Ucb and Upir represents
This condition is related to the highest voltage stress across voltage across interrupter and resistor respectively after corresponding
switches are closed, RDDS_cb is RDDS of interrupter, RDDS_pir is RDDS of
either the resistor stack or interrupter (depends upon PIR PIR (b) Ipir and Icb represents current through resistor and interrupter
configuration), which may lead to longest EIT. The respectively after PIR switch is closed (c) Cumulative PIR energy
probability of occurrence of this stress during service is also
very low.
3) Closing against Pre-Charged Line (PCL) B. Comparison of Stress for Different Network Conditions
This condition will produce high voltage stress for the For comparison, calculations have been performed for a
resistor stack, as well as, for the switching devices. Since in series PIR configuration with interrupter closing at different
this case, the PIR energy is related to the length of the line and network conditions. The results are given in table 2 and it
its natural capacitance, it will be comparatively low. The shows the different stresses occurring across PIR switch based
probability of occurrence of this stress in service is high since on the following ratings as an example:
this is a normal switching operation for a line circuit breaker. rated network voltage (Ur): 420 kV (r.m.s, line-to-line)
rated short circuit current (Ir): 63 kA (r.m.s,)
This condition can produce voltage stress higher than OoP
rated frequency (f): 60 Hz
since while closing on to a PCL, if a single phase fault occurs
DC time constant (): 45 ms
then the total voltage appearing across PIR switch in the
MIT : 10 ms
healthy phases can go up to 2.4 p.u. (for neutral grounded
RDDS of interrupter: -100 kV/ms
system). RDDS of PIR: -130 kV/ms

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
3

PIR resistance: 425  current), the voltage drop across the resistor will reduce. This
Line length: 591 km may result in different EIT for a given MIT and hence, may
Line capacitance: 4.38 µF lead to different PIR energy as shown in fig. 4 depending upon
switching condition. This means that testing of PIR in such
TABLE 2. Comparison of stress across PIR switch based on rated conditions laboratories may confirm its behavior for values which are
Interrupter Source CB pre- Max. voltage Energy EIT
closing on peak strike across PIR much lower than the actual scenario. Hence, such stand-alone
voltage voltage contacts tests cannot be relied upon and therefore, to confirm the PIR
(kV) (kV) (kV) (MJ) (ms) behavior, both from dielectric and thermal point of view,
100%TF 514 514 514 4 13.6 multipart testing is needed. However, before undergoing
actual tests, critical parameters of PIR which determines its
OoP 686 686 681 7 14.3
energy should be verified through testing and this will be
PCL with discussed in the next section.
line at +343 343 686 600 1.3 15.5
kV peak
III. VERIFICATION OF CRITICAL PARAMETERS FOR PIR
ENERGY
Additional calculations have been performed by taking into
The critical parameters needed for evaluation of PIR energy
account the available power of testing laboratory for different
network conditions, which are interrupter closing on: irrespective of any network conditions are: RDDS of
i) 100 % Terminal Fault (TF) with kpp = 1.5 interrupter and PIR switch, as well as, MIT. These parameters
ii) Out-of-Phase condition (OoP) with kpp = 2 should be verified by individual testing before proceeding
iii) Pre-Charged line (PCL) with kpp = 1 with complete PIR testing. This is necessary because if any of
where, kpp is first pole to clear factor. these parameters have values different from the calculated,
then PIR energy may exceed its limit, leading to destruction of
resistor discs. The MIT can be easily verified through testing
and therefore, is generally specified by the customer.
The other important parameter is the RDDS of both
interrupter and PIR switch whose verification by testing is a
little complicated. Although, they are dependent on the closing
speed of the interrupter, there will be some tolerance on the
RDDS value even for a given closing speed. If the RDDS
value is beyond this range, then the calculated PIR energy may
exceed its limit, leading to destruction of resistor discs. In
addition, theoretically calculated RDDS will be slightly
different from the practical scenario due to following reasons:
i) actual surface finish of active conductors might be different
or worse than that considered in theoretical analysis
Fig. 3. Max. Voltage stress across PIR switch ii) the influence of particle contamination is not considered in
theoretical analysis
iii) In gas (SF6) circuit breakers, there will be overpressure or
under pressure regions created during the movement of arcing
contacts, which will influence the breakdown value in those
regions
iv) Dimensional tolerance of the conductors
Therefore, theoretically calculated RDDS must be verified by
testing. This is valid for both PIR switch, as well as,
interrupter.
There are several methods of evaluating the RDDS through
testing and they are broadly classified into static and dynamic
methods. In the Static method, the arcing contacts are moved
to a desired contact position and then a voltage is applied high
enough to lead to a voltage breakdown between the contacts.
This method has to be repeated several times in order to get
Fig. 4. Comparison of PIR energy the curve for all possible voltage condition and polarities.
Several dynamic methods are known to determine the
It is seen from fig. 3 that depending on the available power RDDS. The easiest method is just to close against an applied
of the testing laboratory, the voltage drop across the resistor power frequency voltage. This method, however, will not lead
will change. With lower available power (lower short circuit to a complete RDDS since the device will prestrike only in a
certain region of the RDDS. The second method consists of

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
4

closing against an applied D.C. voltage. If the D.C. voltage 343 kV is shown in fig. 7. The source peak voltage Vp
can be adjusted in small steps then a complete RDDS may be applied was calculated by using (1). The source impedance Zs,
reachable. The third method is to apply a voltage pulse of high resistance Rs and inductance Ls was calculated by using (2),
frequency depending on contact position. This method will (3) and (4) respectively. The capacitance of line shown in fig.
also lead to a complete RDDS but requires more complicated 7 was calculated by using (6).
test procedures and triggering devices [19].
In either method, the contact position at which the
breakdown occurs between the arcing contacts should be
noted along with the time needed to reach that contact
position. The above steps are repeated for different voltage
levels to get a curve of breakdown voltage versus time. The
most linear portion of the curve should be used to evaluate the
RDDS, which will be in “kV/ms”. Fig. 5. Circuit for closing on OoP and 100 % TF

IV. MULTIPART TESTING PROCEDURE OF PIR


Once the critical parameters needed for PIR energy are
verified, the actual capability of PIR, i.e., PIR energy rating,
should be confirmed by testing for worst network condition.
This basically consists of the proof of the thermal capacity
(required EIT) of the resistor stack and dielectric withstand
capability of the PIR switch. Testing of the complete PIR
along with interrupter is impossible due to the amount of Fig. 6. Schematic of actual circuit for closing on OoP
power needed to perform such tests. Therefore, the only
possible way to show evidence is a combination of
calculations and power tests, which is the proposed multipart
testing method of PIR. The different steps involved in
multipart testing are explained in sections A to D, which
should be compiled to give a complete picture of the whole
device.
A. Determination of EIT and PIR Energy Fig. 7. Circuit for closing on PCL at 343 kV
The EIT needs to be calculated for different network
conditions in order to determine the maximum PIR energy. V p  k pp U r 2/3
For a given MIT, resistance and RDDS of both interrupter and (1)
PIR switch, the EIT depends on the making/pre-strike instant where, Ur is the rated line-to-line (root mean square) voltage.
of the interrupter (series PIR) and power of the network.
However, this EIT cannot be tested, as will be explained in the
following sections, but only calculated. In this paper,
Zs  V
p
 2 I
r

calculations and results have been shown for a series PIR (2)
configuration as an example. The simulations are carried out where, Ir is the rated (root mean square) short circuit current.
in ATP wherein the interrupter is made to pre-strike at voltage
peak under different network conditions, which are listed in
section II B. Similar calculations can be carried out for
Rs  Z
s
1 X  s
R
s
2
interrupter pre-striking at different voltages but has not been (3)
shown in this paper. The main reason being that most where, (Xs/Rs) was calculated by using (5).
customers demand for interrupter closing on voltage peak.
Additional calculations have been done by considering the Ls   R
available source power of testing laboratories and the (4)
calculated source resistance and inductance are given in table
3 whereas EIT and PIR energy are shown in table 4 X R  2 f 
corresponding to comment column “Test Lab. 1” and “Test s s
Lab. 2. (5)
The circuit for closing on OoP and 100 % TF is shown in where, f is source frequency

 r kc   3 I c 
fig. 5. The actual scenario for closing on OoP is shown in fig.
6 wherein two sources at 180 degree out-of-phase will be Xc  U
present. However, for simplicity of calculation, a single source (6)
has been considered in ATP with source peak of same where, Ic = 400 A and kc = 1.4 as per [18].
magnitude without affecting the accuracy of the results. The In fig. 5, fig. 6 and fig. 7, the switches S1 and S2 represent
ATP circuit for closing on PCL (represented by capacitor C) at interrupter and PIR switch respectively, whereas R represents

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
5

PIR resistance. The closing of S1 and S2 represent making proves the PIR behavior for an energy level, which is lower
instant in interrupter and PIR switch, respectively. The results than the actual network condition. Since the energy involved
for interrupter closing on OoP, 100 % TF and PCL at 343 kV in actual network condition (Case-1, Case-4 and Case-6 in
is shown in fig. 2, fig. 8 and fig. 9 respectively. In these table 3) is very high, no testing laboratory can simulate such
figures, rectified voltage is plotted only for ease of calculation. conditions. Hence, a multipart testing of PIR becomes
The PIR energy is calculated in two steps and as an example, necessary such that’s its thermal, as well as, dielectric
it will be explained for the network condition shown in fig. 8. behavior is proven for conditions similar to actual scenario.
In the first step, the EIT is calculated as shown in fig. 8a. The
interrupter is made to close at 1 p.u, (peak phase voltage),
Table 3. List of cases for EIT and PIR energy calculation in ATP
which is shown by the intersection of RDDS_cb with voltage
drop across interrupter Ucb. Then the pre-strike instant in PIR
is calculated by the intersection of RDDS_pir and voltage drop
across resistor Upir. In the second step, as shown in fig. 8b, the
PIR switch is closed at the PIR pre-strike instant to calculate
the total PIR energy, which is plotted in fig. 8c.

Table 4. EIT and PIR energy calculation in ATP for CB closing at voltage
peak

Fig. 8. CB closing on 100 % TF (Series PIR) (a) Ucb and Upir represents
voltage across interrupter and resistor respectively after corresponding
switches are closed, RDDS_cb is RDDS of interrupter, RDDS_pir is RDDS of
PIR (b) Ipir and Icb represents current through resistor and interrupter
respectively after PIR switch is closed (c) Cumulative PIR energy

Table 5. Comparison of EIT and PIR energy versus making instant of


interrupter using source model of Case-4 from table 3

Fig. 9. CB closing on Pre-Charged Line at 343 kV (Series PIR) (a) Ucb and
Upir represents voltage across interrupter and resistor respectively after
corresponding switches are closed, RDDS_cb is RDDS of interrupter,
RDDS_pir is RDDS of PIR (b) Ipir and Icb represents current through resistor B. Determination of Critical Condition for PIR
and interrupter respectively after PIR switch is closed (c) Cumulative PIR
energy For a given design of interrupter and PIR, the maximum
PIR energy is decided by the network condition. It is observed
The calculated PIR energy for all the cases considered is from table 4 that maximum PIR energy occurs for closing on
given in table 4. It can be observed from these results that OoP (Case-4) and the minimum PIR energy occurs for closing
when the available source power of the testing laboratory is on PCL with 343 kV (Case-6). In addition, it is seen that
lower than the required value (lower short circuit current), it maximum EIT need not always correspond to maximum PIR
results in lower voltage drop across resistor compared to the energy. For example, comparison of case-1, case-4 and case-6
actual network condition. Thus, testing in such laboratories from table 4 shows that maximum EIT of 15.5 ms occurs

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
6

when interrupter closes on PCL whereas maximum PIR test is very less, the thermal stability of the resistor stack is not
energy occurs when interrupter closes on OoP condition. This an issue.
is because PIR energy depends not only on EIT but also on the The calculations for closing on PCL explained in section
maximum voltage drop across the resistor. Here the maximum IV A was based on a line without shunt compensation. In case
voltage drop across resistor occurs when interrupter closes on of a shunt compensated line, a higher overvoltage may be seen
OoP condition. However, for a given network condition, MIT, by the interrupter or PIR switch depending upon PIR
RDDS and available power of testing laboratory, maximum configuration. However, as can be observed from the results in
EIT will correspond to maximum PIR energy as can be seen table 4, the energy requirement for PIR is defined by OoP and
from table 5. not by closing on PCL. Nevertheless, EIT and dielectric stress
Further, for a given network condition, the maximum PIR across PIR switch/interrupter should be checked in such
energy will depend upon the making instant of the interrupter. situations.
This is because the making instant of the interrupter will not
C. Test of Pre-Arcing Behavior of PIR Switch
only decide the EIT but also the maximum voltage drop across
the resistor. As an example, the variation of EIT and PIR Based on the design (series or shunt PIR configuration),
energy with respect to the making instant of interrupter is PIR switch will experience a pre-arc with full short circuit
given in table 5 using source model of Case-4 from table 3. current or with resistor current. Both conditions need to be
The making instant of the interrupter is given in column 1 and shown and evaluated. Depending on the available power and
is represented as “Per Unit (p.u.)” at which the interrupter pre- voltage output of the test laboratory, it may be possible to
strikes. The voltage across interrupter arcing contacts during perform the closing operations with resistor current (in case of
pre-strike is given in column 2. It can be observed that the shunt PIR configuration) in a direct test circuit. The closing
maximum EIT and PIR energy need not correspond to with full short circuit current (in case of series PIR
interrupter pre-strike at peak, which is 2 p.u. in this case. Here configuration) together with required applied voltage is not
the maximum EIT and PIR energy, which is 14.8 ms and 7.75 possible to be performed in a direct test circuit. In such cases,
MJ respectively, occurs when interrupter closes at 1.9 p.u. it is necessary to perform this test using synthetic test methods
This majorly depends on MIT, as well as, individual RDDS [20].
value. After the performed making operations, the dielectric
The most critical case for the resistor stack (means withstand capability of the PIR arcing contact gap (i.e., PIR
maximum energy and voltage drop) thus needs to be switch in fully open position) should be verified. For a series
determined from the definition of test values. Type testing of PIR configuration, it is enough to check this gap with a
the complete breaker, however, comprises the following test maximum voltage of 2 p.u. This is due to the fact that when
[18]: both interrupter and PIR switch are in complete open position,
1) 100% Terminal Fault Switching the dielectric stress, if any, will always occur across
This test will include one closing operation under full interrupter first since the PIR switch is shunted by the resistor
prestrike, where the interrupter will pre-strike at voltage peak as shown in fig. 1b. Further, the 2 p.u. will always occur
(for shunt configuration, PIR switch will close at voltage in a relatively shortened PIR switch gap since the PIR contacts
peak). The second closing operation will be made at voltage will travel some distance during the time when the resistor is
zero wherein the aim is to have current with highest inserted in the circuit. For shunt PIR configuration, the test
asymmetry and peak magnitude. voltage should be as per the value mentioned in [18] i.e.,
2) Out-of-Phase Switching dielectric integrity test values (80 or 90 % of switching
This test will include only one closing operation under full impulse). This is due to the fact that PIR switch is in parallel
prestrike, where the breaker will pre-strike at voltage peak (for to interrupter and hence, in open position, same voltage will
shunt configuration, PIR switch will close at voltage peak). be seen by both interrupter and PIR switch as shown in fig. 1a.
Testing for such conditions in laboratory generally includes D. Test of Resistor Stack
applying 2 p.u. (1 p.u. = peak phase voltage) on one side of the
breaker, as shown in fig. 5. Since this network condition The resistor stack will experience a high thermal stress
within a very short time when closing against OoP or TF. This
involves maximum PIR energy, the resistor discs need
withstand capability has to be proven by means of testing. It is
minimum cooling time (typically some hours) depending upon
often not possible to test the complete resistor stack due to
the thermal time constant of the disc material.
lack of power in test laboratories. In addition, only direct tests
3) Pre-Charged Line Switching
This test is not required by [18] since CB has to undergo a and no synthetic tests are possible because voltage, as well as,
large number of operations (whether C1/C2 class CB) during power must be supplied at the same time by a single source
only. Therefore, one possibility to perform such tests is by
capacitive switching tests and this will lead to an abnormally
considering only a part of the complete resistor stack (pro-rata
high PIR energy in a short time for which the PIR is not
section).
designed. However, as explained in section IIA, this network
The main aim of this test is to stress a part of the resistor
condition may lead to a maximum voltage stress across the
interrupter and should therefore, be verified through testing. stack as it would be when performing a test on the complete
The interrupter will close at voltage peak (for shunt stack. This means that the energy input, as well as, the time in
which the required energy input is needed should correspond
configuration, PIR will close at voltage peak). Depending
to that of a direct test. In order to do so, attention needs to be
upon customer requirement, there may be demand for more
given to the available short circuit power since this defines the
than one closing operations. Since the energy involved in this

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
7

corresponding voltage drop across the resistor as shown in One way to overcome this problem is by testing the resistor
table 4. It is recommended to perform calculations by varying stack itself, mounted on its own structure. In this case,
the closing instant over the whole half wave of the source in energization of PIR and by-passing of PIR will then have to be
order to find the maximum PIR energy as shown in table 5. done by means of auxiliary breakers. In order to do so, it is
In situations where the available test voltage of the absolutely necessary to use very precise auxiliary breakers and
laboratory is less than the required voltage, the test should be furthermore, RDDS of the used auxiliary breakers must be
performed exactly known. This is explained in fig. 11a wherein the
with a reduced number of resistor discs since it is not possible RDDS of PIR switch no longer plays any role. Here the EIT is
to do the test with the complete breaker. The reason for this is increased to 17.3 ms to get PIR energy of 3.5 MJ and this is
that the MIT is not changeable and will therefore, lead to a achieved with the help of auxiliary breakers. Also in situations
completely different EIT and hence, different PIR energy. As where the test laboratory is able to supply the full voltage but
an example, such a case has been shown in fig. 10, wherein only limited power, i.e., lower short circuit current, the EIT
the test laboratory has only 50% of the voltage needed to close should be increased by means of auxiliary breaker in order to
on actual OoP condition (case-4 of table 4). Since only 50% of achieve the required PIR energy.
the rated voltage is available, only half of the resistor stack is Another important aspect is the test arrangement itself,
considered so that 50 % of PIR energy should be tested, which which should be as close as possible to the real conditions of
is 3.5 MJ (half of PIR energy needed for case-4 of table 4). the circuit breaker. Special considerations should be given to
However, with the given RDDS and MIT, the outcome of such the heat transfer from the resistor blocks to the surrounding
a test would result in lower PIR energy of 2.7 MJ with EIT of metallic parts since these parts may acts as a heat sink. Of
13.5 ms. course, the test should be performed in an atmosphere with
normal operating condition. For example, testing of PIR inside
SF6 breakers should be performed with SF6 gas at required
pressure. In addition, special attention must be paid to the
dielectric condition during test if the resistor blocks are in
close vicinity of conductive parts and therefore, dielectrically
stressed. Also, in case of testing with pro-rata section, special
care must be taken for the decision about the length of the
resistor stack in order to be as close as possible to the original
assembly.

V. INFLUENCE OF TOLERANCE ON PIR STRESS


The most important aspect of PIR design is to make sure
that the EIT should be within limits in order not to exceed the
Fig. 10. CB closing against 50% OoP condition (Series PIR) (a) Ucb and Upir energy rating of the resistor disc. The tolerances of the
represents voltage across interrupter and resistor respectively after following parameters majorly influences MIT, which decides
corresponding switches are closed, RDDS_cb is RDDS of interrupter,
RDDS_pir is RDDS of PIR (b) Ipir and Icb represents current through resistor
EIT:
and interrupter respectively after PIR switch is closed (c) Cumulative PIR i) Closing speed
energy ii) Drive condition (in case of hydraulic drive, there may be
several lock-out conditions which will define the closing
speed)
iii) Dimensional tolerance
iv) RDDS of interrupter and PIR switch
Also, the measured MIT of a breaker may vary within the
production tolerances. Therefore, to evaluate the range of MIT
for a given breaker design, a rigorous tolerance chain
calculation should be done of the complete circuit breaker
including PIR. Out of the various methods used for tolerance
chain calculation like linear, non-linear, production weight,
etc., whichever is applicable, the method that gives the
maximum or worst tolerance should be considered. This will
then decide the range of MIT and hence, EIT needed for PIR
energy calculation.
An alternative method to approximately take into account
Fig. 11. CB closing on OoP with increased EIT (Series PIR) (a) Ucb and Upir the effect of the above tolerances on PIR energy is the
represents voltage across interrupter and resistor respectively after
corresponding switches are closed, RDDS_cb is RDDS of interrupter (b) Ipir following: For a given RDDS of interrupter and PIR switch,
and Icb represents current through resistor and interrupter respectively after calculate EIT and PIR energy with different MIT values for
PIR switch is closed (c) Cumulative PIR energy the worst network condition (for example, closing on OoP).
The analytical method to do so is explained in section IVA

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRD.2016.2519604, IEEE
Transactions on Power Delivery
8

and the calculations should begin with the nominal value of [11] N. Mccord, J. Rostron, T. Speas and F. Therby, “Comparison of short
and long term use of synchronous control versus closing resistot
MIT and must be done for both, higher and lower MIT values. switching methods for capacitor switching”, CIGRE, A3-303, 2014.
In any case, the calculated maximum energy per disc should [12] Jingxuan Hu, Bruno Bisewski, Dudley Maki and Michael B. Marz.
not exceed the limits specified by the resistor disc (2011, June). Mitigation of voltage drop using pre-insertion resistor
during large transformer energization in a weak system: Simulation
manufacturer.
and field verification. International Conference on Power Systems
Transients (IPST2011), 14-17 June 2011, Delft, Netherlands
VI. CONCLUSION [Online], pp. 1-7
[13] CIGRE-305, “Guide for Application of IEC 62271-100 and IEC 62271-
PIR is an important component of power system, however, 1: Part 2 Making and Breaking Tests”, Working Group A3.11, Oct.
complete testing of PIR is very complicated and less defined. 2006.
This is due to the large amount of power involved and limited [14] Dan Goldsworthy, Tom Roseburg, Demetrios Tziouvaras and Jeff Pope.
(2008, April). Controlled switching of HVAC circuit breakers:
capability of testing laboratory. Therefore, a multipart testing Application examples and benefits. Presented at 61st Annual
method for PIR is proposed and consists of the following in conference for protective relay engineers, 1-3 April 2008,
the College Station, TX [Online], pp. 1-17.
given sequence: [15] Legate, A.C., Brunke, J.H., Ray, J.J., and Yasuda, E.J. (1988, January).
Elimination of closing resistors on EHV circuit breakers. IEEE Trans.
1) Verification of critical parameters (MIT & RDDS) by On
testing which determines PIR energy Power Delivery. [Online]. 3(1), pp. 223–231.
2) Calculation of maximum PIR energy and EIT deciding [16] Jinliang He, Chen Li, Jun Hu, Rong Zeng, and Jun Yuan (2012, July).
worse network condition to be tested Elimination of closing resistors for breakers in 1000-kV UHV system by
surge arrestors. IEEE Trans. On Power Delivery. [Online]. 27(4),
3) Calculation of new EIT and resistor stack length needed for pp. 2168–2175.
equivalent PIR testing based upon available source power of [17] Jun Chen, Yun Wang, Jun Lu, Bo Zhang, Ling Ruan and Yong-qin
test laboratory Wang. (2011, March). Development of a novel circuit breaker closing
4) Testing of new EIT and equivalent PIR energy resistance instrument. Power & Energy Engineering Conference
(APPEEC), 25-28 March 2011 Asia-Pacific, [Online], pp. 1–3.
5) Testing of “pre-arcing” behavior of PIR switch [18] High Voltage Switchgear and Controlgear Part 100: Alternating-
6) Testing of dielectric withstand capability of PIR switch. Current Circuit Breakers, IEC 62271-100, Ed. 2.1, 2012-09.
A detailed procedure has been presented for the evaluation [19] Helmut Heiermeier. (2015, June). Testing of reactor switching for
of the most critical parameters of PIR along with an UHV circuit breakers. IEEE Trans. On Power Delivery. [Online].
30(3), pp. 1172–1178.
explanation of all the above test procedures. This enables the [20] High Voltage Switchgear and Controlgear Part 101: Synthetic Testing,
user to judge about the application of PIR, possible limitations IEC 62271-101, Ed. 2.0, 2012-10.
of PIR testing or needed action with regard to operating
conditions. Helmut Heiermeier was born in Hamm
Germany in 1956. He studied electro
REFERENCES technique with focus on energy technique
[1] Mirsad Kapetonovic, High Voltage Circuit Breakers. Sarajewo: DTB at University Gesamthochschule
Mahir Sokolija, 2011, ETF - Faculty of Electrical Engineering, Paderborn in Germany. He joined
University of Sarajevo (Bosnia and Herzegovina). BBC/ABB Switzerland in 1981 as
[2] Ruben D. Garzon, “Switching Overvoltages,” in High Voltage Circuit
Breakers: Design & Applications, 2nd Ed., CRC Press, 2002, pp. 107- development Eng. for high voltage circuit
128. breaker. During this time he led several
[3] Heinz-Helmut Schramm, Schalten im Hochspannungsnetz, Germany. development projects and was involved
[4] Lou van der Sluis, Transients in Power Systems, John Wiley & Sons in the evaluation of circuit breaker related problems in service.
Ltd., England, June 2001.
[5] K. Hirasawa, K. Hirata and S. Suganomata. (1971, March). Switching He is involved in several international working groups such as
Surge and Insulation Coordination of EHV Power Circuit Breaker. IEEE IEC MT 36 (IEC 62271-100),MT28 ( IEC 62271-101),IEC
Trans. On Power Apparatus and Systems. [Online]. 90(2), pp. 682 – 62271-310, IEEE, C37.04,06,09. He is the chair of the IEEE
692. PC 37.010 (circuit breaker application guide). Presently he is a
[6] Thoren, H.B. (1971, May). Reduction of switching overvoltages in EHV
and UHV systems. IEEE Trans. On Power Apparatus and Systems. Senior Principal Eng for breaker development.
[Online]. 90(3), pp. 1321 – 1326.
[7] Konkel, H.E., Legate, A.C., and Ramberg, H.C. (1977, March). Limiting Rosy B. Raysaha was born in Mumbai,
switching surge overvoltages with conventional power circuit breakers. India in 1981. She is an electrical engineer
IEEE Trans. On Power Apparatus and Systems. [Online]. 96(2), pp.
535–542. and obtained her Ph.D in Electrical Engg.
[8] Hedman, D.E., Johnson, I.B., Titus, C. H., and Wilson, D.D. (1964, (High Voltage Engg.) from Dept. of
December). Switching of Extra-High-Voltage circuits II-Surge reduction Electrical Engg., Indian Institute of
with circuit-breaker resistors. IEEE Trans. On Power Apparatus and Science (IISc), Bangalore in 2011. She
Systems. [Online]. 83(12), pp. 1196–1205.
[9] Faria Da Silva, F., Bak, C.L., Guomundsdottir, U.S., Wiechowski, W. has been working on GIS product line
and Knardrupgard, M.R. (2009, July). Use of a pre-insertion resistor to since then and joined ABB India in Nov.
minimize zero-missing phenomenon and switching overvoltages. 2012 in High Voltage Technology Centre.
Power & Energy Society General Meeting, July 26-30, 2009. During this time, she has led the project for 420 kV GIS PIR
PES’09. IEEE PES [Online], pp. 1–7.
[10] Eman A. Awad, Ebrahim A. Badran and Fathi M. H. Youssef. (2014, on which a Patent has been approved. At present, she is a
October). Mitigation of temporary overvoltages in weak grids connected R&D Engineer majorly involved with PIR and circuit breaker
to DFIG-based wind farms. Journal of Electrical Systems. [Online]. development for GIS.
10(4), pp. 431–444.

0885-8977 (c) 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.

Das könnte Ihnen auch gefallen