Beruflich Dokumente
Kultur Dokumente
III. RESULTS
A. Constant Load-Voltage profile study
The network is sectionalised into three different zones. Each
zones has a different load profile. Voltage sensitivity study is
then performed for each of these zones. The voltage profile of
the 13 nodes in the simulated 13-bus network is depicted in
Fig. 4. In this case no PV generation is considered for any of
the network nodes. It can be seen from Fig. 4 that all network Fig. 5. Voltage profile of modified 13-Bus with high PV penetration in
DIgSILENT.
nodes are operating within normal range (i.e between 0.85 pu
to 1.1 [1],[2].) while the load is assumed being the maximum
amount and constant. By way of comparison, the voltage The most important point in each of these plots is that the
profile given in Fig. 5, when PV generation is connected to voltage rise happens after the power flows reversely in the
the network. Most of the 13-bus nodes experience voltage rise network and the current at the head bus starts to be injected
to the values that are more than 1.1 pu. in opposite direction into the higher voltage network. Table
II depicts that before and after, PV units come into service,
B. Simplified load profile in three different network zones-
massive changes in bus voltages occur.
voltage profile study
In this case considering the actual nature of load profile, C. Real case industrial load profile-voltage profile study
especially in LV and MV distribution system, simplified and In the last two case studies in order to take a more accurate
general changes have been considered for loads while the PV step the real Australian industrial and residential load profiles
generation is assumed to be constant. Table I gives the voltage of NSW region, a typical summer day of January is considered
levels of load points for different loads during one day, for as an input load profile of each node spot in separate cases.
two conditions; with and without PV generation. Three outputs Figs. 9 and 10 depict these real load profiles respectively which
obtained by DIGSILENT are depicted in Figs. 6-8. Each figure are utilized from real field work studies [7],[8]. The general
shows the voltage trend due to five different load changes. The trend of load changes are applied to the maximum load level
five different step changes in the load of each customer are in percentages of the load peak values. table III. has classified
simulated as 100%, 75%, 50% and 10% of the peak amount these two load profiles in percentages, separately. These load
of load in each bus. Once again, the 13-Bus network has been profiles are simulated one by one in DIgSILENT. Scales and
sectionalised into three different zones A, B and C which have are applied to the modified 13-Bus network each considered
similar general behaviour. as typical residential and industrial loads. In case study 3,
Fig. 12. Voltage at point 652, before and after PV penetration with residential
load profile.
Fig. 11. Industrial simulated load profile upon a real case study.
Fig. 14. Voltage at point 634, before and after PV penetration with
Residential load profile.
V. CONCLUSION