Sie sind auf Seite 1von 81

CONSULTANT

EMPLOYER CONTRACTOR

GRAPHIC of WEATHER
Civil Works For Construction of Karian Multipurpose DAM
Month May 2015
Date
Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
00 : 00 - 01 : 00
01 : 00 - 02 : 00
02 : 00 - 03 : 00
03 : 00 - 04 : 00
04 : 00 - 05 : 00
05 : 00 - 06 : 00
06 : 00 - 07 : 00
07 : 00 - 08 : 00
08 : 00 - 09 : 00
09 : 00 - 10 : 00
10 : 00 - 11 : 00
11 : 00 - 12 : 00
12 : 00 - 13 : 00
13 : 00 - 14 : 00
14 : 00 - 15 : 00
15 : 00 - 16 : 00
16 : 00 - 17 : 00
17 : 00 - 18 : 00
18 : 00 - 19 : 00
19 : 00 - 20 : 00
20 : 00 - 21 : 00
21 : 00 - 22 : 00
22 : 00 - 23 : 00
23 : 00 - 24 : 00
Rain 0
Drizzle 0
Total
Cloudy 0
Sunny

Remark Rain/Hujan Drizzle/Gerimis Cloudy/Berawan Sunny/Cerah


REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfa
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industria
PT. Yala Persada Angkasa

GRAPHIC WEATHER

18.00

17.00

16.00

15.00

14.00

13.00

12.00

11.00

10.00

9.00

8.00
24

08

16

Keterangan : ( MARCH
Remark :

Checked by the Engineer Submitted by the


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Con
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persa

Contractor
Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

IC WEATHER

Keterangan : ( MARCH )

Hujan
Gerimis
Berawan
Cerah
Submitted by the Contractor
PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan  
- Contractor : KYERYONG - YALA, JO.
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
- Date : April 29th 2014 PT. Yala Persada Angkasa

SUMMARY OF LABORATORY TEST


JOB MIX DESIGN AGGREGATE BASE CLASS-A
NO EXAMINATION UNIT RESULT SPECIFICATION REMARK
I Gradation
1 1/2" % 100.00 100.00
1" % 83.09 79 - 85
3/8" % 54.72 44 - 58
#4 % 45.88 29 - 44
# 10 % 37.41 17 - 30
# 40 % 18.70 7 - 17
# 200 % 6.03 2-8
II Atterberg Limit
- Liquid Limit 0 - 25
- Plastic Limit
- Indeks Plasticity NP 0-6
- Product Plasticity Index Times
Max. 25
Percentage Passing # 200
III Compaction Method Modified
- Max. Dry Density gr/cc 2.170
- Opt. Moisture Content % 8.25
CBR at 100 % Max Dry Density
IV % 96.00 Min 90
after 4 days soaking
V Specific Gravity gr/cc 2.804
VI Soft Fragments % 1.29 Max 5
VII Fracture Face % 100.00 Max 100
VIII Abration % 34.26 Max. 40
Remark : From Quarry Kayu Tanam III (LMKP Production)

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa
Andi Sadriansyah, ST.
Quality Engineer Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 16 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

COMPACTION TEST
Aditional Water Water Content beginning are = 1.05%
Additional water % 3% 5% 7% 9% 11%
Additional water cc 180 300 420 540 660
COMPACTION DATA
Wt. wet soil + mould Gram 9,550 9,588 9,735 9,892 9,850
Weight of mould Gram 5,065 5,065 5,065 5,065 5,065
Weight of wet soil Gram 4,485 4,523 4,670 4,827 4,785
Volume of mould Cc 2,049
Wet unit weight Gr/Cc 2.189 2.207 2.279 2.356 2.335
Dry unit weight Gr/Cc 2.085 2.096 2.137 2.176 2.104
{ gd /(100+w) } x100

MOISTURE CONTENT
Wt. wet soil + tare Gram 184.7 210.1 230.1 197.6 235.8 263.9 182.1 207.6 239.2 226.2
Wt. dry soil + tare Gram 178.6 202.7 221.6 190.3 225.1 250.8 172.4 196.2 219.6 211.3
Weight of tare Gram 54.3 55.4 58.3 55.9 59.7 59.8 56.0 57.5 59.4 59.3
Weight of water Cc 6.1 7.4 8.5 7.3 10.7 13.1 9.7 11.4 19.6 14.9
Weight of dry soil Gr/Cc 124.3 147.3 163.3 134.4 165.4 191.0 116.4 138.7 160.2 152.0
Moisture content Gr/Cc 4.91 5.02 5.21 5.43 6.47 6.86 8.33 8.22 12.23 9.80
Moisture content Gr/Cc 4.97 5.32 6.66 8.28 11.02

2.500
Dry Unit Weight (gD)

2.400

2.300
2.170 gr/cc
2.200

2.100

2.000
8.25 %

1.900

1.800

1.700

1.600

1.500
3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00
Moisture Content (%)
1.500
3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00
Moisture Content (%)

Result :
Moisture Content Optimum = 8.25 %
g D max = 2.170 t/m3
Checked by the Engineer Submitted by the Contractor
DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 20 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

COMPACTION AND C.B.R GRAPH

2.5 2

2.4
Dry Unit Weight (gD)

2.3 2

2.2 2

2.17
2.1 2

2 2

96.00 %
1.9 1
8.25 %

1.8 1

1.7 1

1.6 1

1.5 1

3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 20 30 40 50 60 70 80 90 100 110

Moisture Content (%) CBR (%)

Result : Specfic Grafity = 2.804 t/m3


Moisture Content Optimum = 8.25 %
g D max = 2.170 t/m3
CBR = 96.00 %
Remark :

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa
Andespa Hedison, ST.
Lab. Technician Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 16 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

CALIFORNIA BEARING RATIO (CBR) TEST


BLOW 65 x
Before After
Date 16-Feb-15 17-Feb-15 18-Feb-15 19-Feb-15 20-Feb-15 Wt. of soil + mould gr 11,415 11,467
Time 9.00 9.00 9.00 9.00 9.00 Wt. of mould gr 6,550 6,550
Reading 0 0 0 0 0 Wt. of wet soil gr 4,865 4,917
Sweling 0 0 0 0 0 Volume of mould cm3 2,117.9 2,117.9
Wet unit weight gr/cm3 2.297 2.322
Factor of Calibration (k) = 33.18 lb = 15.05 kg Dry unit weight gr/cm 3
2.174 2.179
Penetration Reading Load (kg)
( mm ) Minute Up Down Up Down
0.318 1/4 11.0 165.6 7000
0.635 1/2 23.0 346.2
1.270 1 45.0 677.3 6500

1.905 1 1/2 98.0 1474.9


6000
2.540 2 148.0 2227.5
3.810 3 221.0 3326.1
5500
5.080 4 342.0 5147.3
7.620 6 364.0 5478.4
5000
10.160 8
12.700 10
Load (lb)

4500

4000
WATER CONTENT Before After
Wt. of wet soil + tare 216.2 258.2 225.9 232.6 3500
Wt. of dry soil + tare 207.3 247.8 215.5 221.7
Weight of tare 54.8 57.5 55.4 55.9 3000
Weight of water 1-2 8.9 10.4 10.4 10.9
Weight of dry soil 2-3 152.5 190.3 160.1 165.8 2500
Water Content % 5.8 5.5 6.5 6.6
Average 5.7 6.5 2000

CBR Value 1500


CBR
0.1 " 0.2 "
1000
Up 2250.0 x 100 4350.0 x 100
3000 4500
500
= 75.00 = 96.67
Average 96.67
0
Down - x 100 - x 100 0 0.1 0.2 0.3 0.4 0.5
3000 4500
Penetration (in)
0
0 0.1 0.2 0.3 0.4 0.5

Penetration (in)
= - = -

Remark :

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 16 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

CALIFORNIA BEARING RATIO (CBR) TEST


BLOW 35 x
Before After
Date 16-Feb-15 17-Feb-15 18-Feb-15 19-Feb-15 20-Feb-15 Wt. of soil + mould gr 10,833 10,890
Time 9.00 9.00 9.00 9.00 9.00 Wt. of mould gr 6,465 6,465
Reading 0 0 0 0 0 Wt. of wet soil gr 4,368 4,425
Sweling 0 0 0 0 0 Volume of mould cm3 2,125.2 2,125.2
Wet unit weight gr/cm3 2.055 2.082
Factor of Calibration (k) = 33.18 lb = 15.05 kg Dry unit weight gr/cm3 1.912 1.944
Penetration Reading Load (kg)
( mm ) Minute Up Down Up Down 5000
0.318 1/4 5.0 75.3
0.635 1/2 13.0 195.7
1.270 1 34.0 511.7 4500
1.905 1 1/2 71.0 1068.6
2.540 2 92.0 1384.6
4000
3.810 3 156.0 2347.9
5.080 4 223.0 3356.2
7.620 6 247.0 3717.5 3500
10.160 8
Load (lb)

12.700 10
3000

WATER CONTENT Before After


2500
Wt. of wet soil + tare 315.2 335.0 192.8 250.2
Wt. of dry soil + tare 298.1 315.1 183.7 237.8
Weight of tare 59.4 59.7 57.5 59.4 2000
Weight of water 1-2 17.1 19.9 9.1 12.4
Weight of dry soil 2-3 238.7 255.4 126.2 178.4
Water Content % 7.2 7.8 7.2 7.0 1500
7.5 7.1

1000
CBR Value
CBR
0.1 " 0.2 "
Up 1550.0 x 100 2950.0 x 100 500
3000 4500
= 51.67 = 65.56
Average 65.56 0
Down - x 100 - x 100 0 0.1 0.2 0.3 0.4 0.5
3000 4500 Penetration (in)
= - = -
0 0.1 0.2 0.3 0.4 0.5

Penetration (in)

Remark :

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control

REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project
SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014
- Date : April 29th 2014 CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 16 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

CALIFORNIA BEARING RATIO (CBR) TEST


BLOW 10 x
After Before
Date 16-Feb-15 17-Feb-15 18-Feb-15 19-Feb-15 20-Feb-15 Wt. of soil + mould gr 10,732 10,800
Time 9.00 9.00 9.00 9.00 9.00 Wt. of mould gr 6,600 6,600
Reading 0 0 0 0 0 Wt. of wet soil gr 4,132 4,200
Sweling 0 0 0 0 0 Volume of mould cm3 2,139.0 2,139.0
Wet unit weight gr/cm3 1.932 1.964
Factor of Calibration (k) = 33.18 lb = 15.05 kg Dry unit weight gr/cm3 1.814 1.823
Penetration Reading Load (kg)
( mm ) Minute Up Down Up Down
0.318 1/4 4.0 60.2 4000
0.635 1/2 12.0 180.6
1.270 1 35.0 526.8
1.905 1 1/2 44.0 662.2 3500
2.540 2 63.0 948.2
3.810 3 85.0 1279.3
5.080 4 102.0 1535.1
3000
7.620 6 117.0 1760.9
10.160 8
12.700 10
Load (lb)

2500

WATER CONTENT Before After


Wt. of wet soil + tare 310.0 260.3 408.1 399.1 2000
Wt. of dry soil + tare 294.6 247.7 382.5 374.8
Weight of tare 55.9 55.4 54.8 54.8
Weight of water 1-2 15.4 12.6 25.6 24.3
1500
2000

1500
Weight of dry soil 2-3 238.7 192.3 327.7 320.0
Water Content % 6.5 6.6 7.8 7.6
6.5 7.7
1000
CBR Value
CBR
0.1 " 0.2 "
Up 900.0 x 100 1500.0 x 100 500
3000 4500
= 30.00 = 33.33
Average 33.33
0
Down - x 100 - x 100
0 0.1 0.2 0.3 0.4 0.5
3000 4500
Penetration (in)
= - = -

Remark :

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation W
PT. Perentjana Djaya and Hasfarm Dian Konsu
- Contractor : KYERYONG - YALA, JO.
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO
- Date : April 29th 2014
PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 6 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

TEST of CONSISTENCY ATTERBERG

LIQUID LIMIT (LL) PLASTIC LIMIT


Blow
Number of tare
Wt. wet soil + tare
Wt. dry soil + tare
Weight of tare
Weight of water
NP
Weight of dry soil
Moisture content
Average

45
Moisture Content (%)

40

35

30

25
NP
20
LL PL PI NOTE :

15
Sample with cond
- Real
10 - Sieve / Not Siev
10 15 20 25 30 35 40 45

Blow

Remark :
Checked by the Engineer Submitted by the Contractor
DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan       
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

: Andespa Hedison, ST.

STENCY ATTERBERG

PLASTIC LIMIT (PL)

Sample with condition

- Sieve / Not Sieve


PT. Kyeryong Construction Industrial Co. Ltd.
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in Assosiation With
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
- Date : April 29th 2014 PT. Yala Persada Angkasa
LOCATION : Laboratorium Project DATE : 6 February 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

SPESIFIC GRAVITY AND ABSORPTION TEST (AASHTO T 85-81)


FOR COARSE AGGREGATE 1 2
RETAINED # No. 4 (Percentage %) 54.12
WEIGHT OF SAMPLE OVEN DRY IN AIR A 3,567 3,792
WEIGHT OF SAMPLE SATURATED SURFACE DRY IN AIR B 3,736 3,961
WEIGHT OF SAMPLE IN WATER C 2,282 2,507
A 2.453 2.608
BULK SPESIFIC GRAFITY (OVEN DRY BASIS)
B-C AV 2.531
B 2.569 2.724
BULK SPESIFIC GRAFITY (S.S.D. BASIS)
B-C AV 2.647
A 2.776 2.951
APPARENT SPECIFIC GRAFITY
A- C AV 2.863
B -A 4.738 4.457
ABSORPTION x 100
A AV 4.597
FOR FINE AGGREGATE 1 2
PASSING # No. 4 (Percentage %) 45.88
WEIGHT OF SAMPLE OVEN DRY IN AIR A 485.0 484.1
WEIGHT OF FLASK FILLED WITH WATER TO CALIBRATION B 664.5 697.0
WEIGHT OF FLASK + WATER + SAMPLE TO CALIBRATION C 972.0 1004.2
WEIGHT OF SAMPLE SATURATED SURFACE DRY IN AIR D 500 500
A 2.519 2.511
BULK SPESIFIC GRAFITY (OVEN DRY BASIS)
B+500-C AV 2.515
500 2.597 2.593
BULK SPESIFIC GRAFITY SATURATED SURFACE DRY
B+500-C AV 2.595
A 2.732 2.737
APPARENT SPECIFIC GRAFITY
B +A- C AV 2.734
500 - A 3.093 3.284
ABSORPTION x 100
A AV 3.189
MAIN SPECIFIC GRAFITY (COMBINED)
BULK SPESIFIC GRAFITY (OVEN DRY BASIS) gr/cm3 2.524
BULK SPESIFIC GRAFITY SATURATED SURFACE DRY gr/cm3 2.623
APPARENT SPECIFIC GRAFITY gr/cm3 2.804
ABSORPTION % 3.951
REMARKS

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa
Andespa Hedison, ST.
Lab. Technician Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial C
- Date : April 29th 2014 PT. Yala Persada Angkasa

SOFT FRAGMENTS
( AASHTO T-112-81 / SNI 03 -4141-1996 )
LOCATION : Laboratorium Project DATE
MATERIAL : Aggregate Base Class A TESTED BY
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY
Retained # No. 4 (G) =
Passing # No. 4 (H) =

SIEVE SIZE PROSENTASE of


SIEVE OF SAMPLE WEIGHT of SAMPLE WEIGHT of SAMPLE WEIGHT of LOSS
WEIGHT FROM LOSS
WITH PROSENTASE BEFORE TEST AFTER TEST SAMPLE
SAMPLE

NO
D
A B C D=B-C E= X 100
PASSING RETAINED B

I II I II I II I II I II

1 1 1/2 " (38,10 mm) 100.00 100.00 0 0 0 0 0 0 0.00 0.00


2 1 1/2 " (38,10 mm) 3/4 " (19,10 mm) 83.09 83.09 3000 3000 2997.4 2997.4 2.6 2.6 0.09 0.09
3 3/4 " (19,10 mm) 3/8" (9,50 mm) 54.72 54.72 2000 2000 1992.4 1992.4 7.6 7.6 0.38 0.38
4 3/8" (9,50 mm) # 4 (4,75 mm) 45.88 45.88 1000 1000 990.6 990.6 9.4 9.4 0.94 0.94
AMOUNT OF CLAY LUMPS AND FRIABLE PARTICLES IN COARSE AGGREGATE (I)
5 # 4 (4,75 mm) # 16 (1,18 mm) 37.41 37.41 500 500 473.7 473.7 26.3 26.3 5.26 5.26
AMOUNT OF CLAY LUMPS AND FRIABLE PARTICLES IN FINE AGGREGATE (J)
TOTAL = (G x I) + (H x J)

REMARKS

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Ind
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan       
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

RAGMENTS
81 / SNI 03 -4141-1996 )
: 6 February 2015
: Kanif Setiady
: Andespa Hedison, ST.
54.12%
45.88%
AVERAGE
PROSENTASE of
WEIGHT
( CORECCTION BY
LOSS SAMPLE
PROSENTASE )
AxE
F= 100

I II

0.00 0.00
0.07 0.07
0.21 0.21
0.43 0.43
0.71 0.71
1.97 1.97
1.97 1.97
1.29 1.29
1.29

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULT


- Province : West Sumatera DOHWA Engineering, Co.L
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Ha
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Indu
- Date : April 29th 2014 PT. Yala Persada Angkasa

FRACTURE FACE

LOCATION : Laboratorium Project DATE


MATERIAL : Aggregate Base Class A TESTED BY
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY

No. Description I

1 Weight of Dry Sample (Retained sieve No. 4) 2,015.1

2 Weight of Sample Fracture Face 2,015.1

3 Prosentase Fracture Fase % 100.0

4 Prosentase Fracture Fase (Average) % 100.0

Remark :

Checked by the Engineer Submitted by the Contrac


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Constructio
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angk

Andespa Hedison, ST.


Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan       
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

RACTURE FACE

: 6 February 2015
: Kanif Setiady
: Andespa Hedison, ST.

II III

2,046.3

2,046.3

100.0

100.0 %

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


DOHWA Engineering, Co.Ltd in Assosiation With
- Province : West Sumatera
PT. Perentjana Djaya and Hasfarm Dian Konsultan
- Contractor : KYERYONG - YALA, JO.
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
- Date : April 29th 2014 PT. Yala Persada Angkasa

UNIT WEIGHT
LOCATION : Laboratorium Project DATE : 00 January 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hedison, ST.

No. Description Gram Gram Gram

I II III

1 Weight of Container + Sample

2 Weight of Container

3 Weight of Sample (1-2)

4 Volume of Container

5 Unit Weight (3/4)


Gr/cm3
Avarage Unit Weight
REMARKS

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Industrial Co. Ltd.
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Engineer Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSUL


- Province : West Sumatera DOHWA Engineering, Co.L
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and H
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Ind
- Date : April 29th 2014
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE
MATERIAL : Coarse Aggregate 30-40 mm TESTED BY
Quarry : Quarry Kayu Tanam III (LMKP Production) CHECKED BY
WEIGHT OF SAMPLE I : 5,121.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative
Standart Opening Weight Ret Average Aggregat Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams
3 in 76.2
2 in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 0.0
1 in 25,4 2,309.0 2,309.0 45.09 54.91 56.21 2,450.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 2,723.3 5,032.3 98.27 1.73 2.05 3,180.6
No. 4 4,76 7.4 5,039.7 98.41 1.59 1.78 22.8
No. 8 2.38
No. 10 2,00 5.5 5,045.2 98.52 1.48 1.63 11.1
No. 16 1.181
No. 30 0.59
No. 40 0,425 14.4 5,059.6 98.80 1.20 1.33 18.7
No. 50 0.300
No. 100 0.150
No. 200 0,074 45.4 5,105.0 99.69 0.31 0.46 49.1
PASS No. 200

100
Passing ( % )

80

60

40

20

0
0.01 0.1 1 10
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10

Sieve Size ( mm )
Remark :

Checked by the Engineer Submitted


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyery
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yal

Andespa H
Lab. Technician Quality Co
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

VE ANALYSIS
: 08 - 10 Novemebr 2014
: Kanif Setiady
: Andespa Hedison, ST.
WEIGHT OF SAMPLE II : 5,767.0 Gr

Cumulative

Retained % Ret % Passing

0.0 0.00 100.00


2,450.0 42.48 57.52

5,630.6 97.63 2.37


5,653.4 98.03 1.97

5,664.5 98.22 1.78

5,683.2 98.55 1.45

5,732.3 99.40 0.60

1 10 100
1 10 25.4 38.1 100

Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSU


- Province : West Sumatera DOHWA Engineering, Co
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction In
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE
MATERIAL : Coarse Aggregate 19-30 mm TESTED BY
Quarry : Quarry Kayu Tanam III (LMKP Production) CHECKED BY
WEIGHT OF SAMPLE I : 3,351.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative
Standart Opening Weight Ret Average Aggregat Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams
3 in 76.2
2 in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 0.0
1 in 25,4 229.9 229.9 6.86 93.14 94.00 160.7
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 3,063.0 3,292.9 98.27 1.73 1.70 2,918.0
No. 4 4,76 14.5 3,307.4 98.70 1.30 1.38 6.5
No. 8 2.38
No. 10 2,00 3.1 3,310.5 98.79 1.21 1.26 4.8
No. 16 1.181
No. 30 0.59
No. 40 0,425 2.9 3,313.4 98.88 1.12 1.11 6.8
No. 50 0.300
No. 100 0.150
No. 200 0,074 18.3 3,331.7 99.42 0.58 0.49 21.6
PASS No. 200

100
Passing ( % )

80

60

40

20

0
0.01 0.1 1 10
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10

Sieve Size ( mm )
Remark :

Checked by the Engineer Submitted


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyery
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yal

Andespa H
Lab. Technician Quality Co
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

VE ANALYSIS
: 08 - 10 Novemebr 2014
: Kanif Setiady
: Andespa Hedison, ST.
WEIGHT OF SAMPLE II : 3,131.0 Gr

Cumulative

Retained % Ret % Passing

0.0 0.00 100.00


160.7 5.13 94.87

3,078.7 98.33 1.67


3,085.2 98.54 1.46

3,090.0 98.69 1.31

3,096.8 98.91 1.09

3,118.4 99.60 0.40

1 10 100
1 10 25.4 38.1 100

Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSU


- Province : West Sumatera DOHWA Engineering, Co
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction In
- Date : April 29th 2014
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE
MATERIAL : Coarse Aggregate 13-19 mm TESTED BY
Quarry : Quarry Kayu Tanam III (LMKP Production) CHECKED BY
WEIGHT OF SAMPLE I : 2,556.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative
Standart Opening Weight Ret Average Aggregat Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams
3 in 76.2
2 in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 0.0
1 in 25,4 0.0 0.0 0.00 100.00 100.00 0.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 1,933.6 1,933.6 75.65 24.35 26.00 1,761.2
No. 4 4,76 560.5 2,494.1 97.58 2.42 2.57 606.8
No. 8 2.38
No. 10 2,00 11.5 2,505.6 98.03 1.97 2.11 11.5
No. 16 1.181
No. 30 0.59
No. 40 0,425 10.2 2,515.8 98.43 1.57 1.66 12.0
No. 50 0.300
No. 100 0.150
No. 200 0,074 26.6 2,542.4 99.47 0.53 0.57 27.9
PASS No. 200

100
Passing ( % )

80

60

40

20

0
0.01 0.1 1 10
Sieve Size ( mm )
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10
Sieve Size ( mm )
Remark :

Checked by the Engineer Submitted


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyery
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Ya

Andespa H
Lab. Technician Quality Co
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

VE ANALYSIS
: 08 - 10 Novemebr 2014
: Kanif Setiady
: Andespa Hedison, ST.
WEIGHT OF SAMPLE II : 2,434.0 Gr

Cumulative

Retained % Ret % Passing

0.0 0.00 100.00


0.0 0.00 100.00

1,761.2 72.36 27.64


2,368.0 97.29 2.71

2,379.5 97.76 2.24

2,391.5 98.25 1.75

2,419.4 99.40 0.60

1 10 100
Sieve Size ( mm )
1 10 25.4 38.1 100
Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSU


- Province : West Sumatera DOHWA Engineering, Co
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction In
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE
MATERIAL : Medium Aggregate 5-13 mm TESTED BY
Quarry : Quarry Kayu Tanam III (LMKP Production) CHECKED BY
WEIGHT OF SAMPLE I : 1,451.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative
Standart Opening Weight Ret Average Aggregat Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams
3 in 76.2
2 in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 0.0
1 in 25,4 0.0 0.0 0.00 100.00 100.00 0.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 64.9 64.9 4.47 95.53 95.90 54.3
No. 4 4,76 869.4 934.3 64.39 35.61 35.54 886.0
No. 8 2.38
No. 10 2,00 429.8 1,364.1 94.01 5.99 6.12 425.6
No. 16 1.181
No. 30 0.59
No. 40 0,425 29.2 1,393.3 96.02 3.98 4.14 28.4
No. 50 0.300
No. 100 0.150
No. 200 0,074 30.8 1,424.1 98.15 1.85 2.01 31.2
PASS No. 200

100
Passing ( % )

80

60

40

20

0
0.01 0.1 1 10
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10

Sieve Size ( mm )
Remark :

Checked by the Engineer Submitted


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyery
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yal

Andespa H
Lab. Technician Quality Co
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

VE ANALYSIS
: 08 - 10 Novemebr 2014
: Kanif Setiady
: Andespa Hedison, ST.
WEIGHT OF SAMPLE II : 1,457.0 Gr

Cumulative

Retained % Ret % Passing

0.0 0.00 100.00


0.0 0.00 100.00

54.3 3.73 96.27


940.3 64.54 35.46

1,365.9 93.75 6.25

1,394.3 95.70 4.30

1,425.5 97.84 2.16

1 10 100
1 10 25.4 38.1 100

Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSU


- Province : West Sumatera DOHWA Engineering, Co
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction In
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE
MATERIAL : Fine Aggregate 0-5 mm (Stone Dust) TESTED BY
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY
WEIGHT OF SAMPLE I : 1,466.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative
Standart Opening Weight Ret Average Aggregat Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams
3 in 76.2
2 in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 0.0
1 in 25,4 0.0 0.0 0.00 100.00 100.00 0.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 0.0 0.0 0.00 100.00 100.00 0.0
No. 4 4,76 73.6 73.6 5.02 94.98 94.84 79.9
No. 8 2.38
No. 10 2,00 319.0 392.6 26.78 73.22 73.30 320.8
No. 16 1.181
No. 30 0.59
No. 40 0,425 617.5 1,010.1 68.90 31.10 31.19 633.5
No. 50 0.300
No. 100 0.150
No. 200 0,074 314.3 1,324.4 90.34 9.66 9.77 322.1
PASS No. 200
100
Passing ( % )

80

60

40

20

0
0.01 0.1 1 10
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10

Sieve Size ( mm )

Remark :

Checked by the Engineer Submitted


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyery
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yal

Andespa H
Lab. Technician Quality Co
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

VE ANALYSIS
: 08 - 10 Novemebr 2014
: Kanif Setiady
: Andespa Hedison, ST.
WEIGHT OF SAMPLE II : 1,505.0 Gr

Cumulative

Retained % Ret % Passing

0.0 0.00 100.00


0.0 0.00 100.00

0.0 0.00 100.00


79.9 5.31 94.69

400.7 26.62 73.38

1,034.2 68.72 31.28

1,356.3 90.12 9.88

1 10 100
1 10 25.4 38.1 100

Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
PT. Perentjana Djaya and Hasfarm
- Contractor : KYERYONG - YALA, JO.
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial
- Date : April 29th 2014
PT. Yala Persada Angkasa

SIEVE ANALYSIS COMBINED


AASTHO T, 27 - 82
AGGREGATE BASE CLASS A
Original Gradation
Seive Designation Specification
CA I CA II CA III MA FA
Combined
30-40 mm 19-30 mm 13-19 mm 5-13 mm 0-10 mm
No. Size Lower
35% 10% 10% 15% 30%

1 1/2in 38.100 100.00 100.00 100.00 100.00 100.00 100.00 100


1 in 25.400 56.21 94.00 100.00 100.00 100.00 84.08 79
3/8 in 9.520 2.05 1.70 26.00 95.90 100.00 47.87 44
No. 4 4.760 1.78 1.38 2.57 35.54 94.84 34.80 29
No. 10 2.000 1.63 1.26 2.11 6.12 73.30 23.81 17
No. 40 0.425 1.33 1.11 1.66 4.14 31.19 10.72 7
No. 200 0.075 0.46 0.49 0.57 2.01 9.77 3.50 2

100
Passing ( % )

80

60

Control Point (Upper)


40

20
Control Point (Lower)

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10 25.4
Sieve Size ( mm )

REMARK :

Checked by the Engineer Submitted by the Contracto


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angka
Andespa Hedison, ST.
Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan       
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

NALYSIS COMBINED
AASTHO T, 27 - 82
EGATE BASE CLASS A

Specification
Center
Upper

100 100
85 82
58 51
44 36.5
30 23.5
17 12
8 5

nt (Upper)

Control Point (Lower)

1 10 25.4 38.1 100


Sieve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa
Andespa Hedison, ST.
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfar
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industria
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE : 26 Maret 2015
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hediso
WEIGHT OF SAMPLE I : 14,293.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative Cu
Standart Opening Weight Ret Average Aggregate Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams Retained
###in 76.2
###in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 100 0.0 0.0
1 in 25,4 2,525.0 2,525.0 17.67 82.33 83.09 79 - 85 2,227.0 2,227.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 3,969.0 6,494.0 45.43 54.57 54.72 44 - 58 3,993.0 6,220.0
No. 4 4,76 1,236.0 7,730.0 54.08 45.92 45.88 29 - 44 1,245.0 7,465.0
No. 8 2.38
No. 10 2,00 1,212.0 8,942.0 62.56 37.44 37.41 17 - 30 1,165.0 8,630.0
No. 16 1.181
No. 30 0.59
No. 40 0,425 2,708.0 11,650.0 81.51 18.49 18.70 7 - 17 2,545.0 11,175.0
No. 50 0.300
No. 100 0.150
No. 200 0,074 1,715.0 13,365.0 93.51 6.49 6.03 2-8 1,841.0 13,016.0
PASS. NO.200

100
Passing ( % )

80

60
Control Point (Upper)

40

Control Point (Lower)


20
Control Point (Lower)
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10 25.4 38.1

Sieve Size ( mm )

Remark :

Checked by the Engineer Submitted by the C


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Con
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persad

Andespa Hedison
Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

E ANALYSIS
: 26 Maret 2015
: Kanif Setiady
: Andespa Hedison, ST.
13,782.0 Gr

Cumulative

% Ret % Passing

0.00 100.00
16.16 83.84

45.13 54.87
54.16 45.84

62.62 37.38

81.08 18.92

94.44 5.56

er)

Control Point (Lower)


Control Point (Lower)

1 10 38.1 100

eve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfar
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industria
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE : 6 April 2015
MATERIAL : Aggregate Base Class - A TESTED BY : Kanif Setiady
: STA 0 + 300/R ( LMKP Production) CHECKED BY : Andespa Hediso
WEIGHT OF SAMPLE I : 13,200.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative Cu
Standart Opening Weight Ret Average Aggregate Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams Retained
###in 76.2
###in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 100 0.0 0.0
1 in 25,4 2,071.0 2,071.0 15.69 84.31 84.91 79 - 85 1,910.0 1,910.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 2,868.0 4,939.0 37.42 62.58 63.69 44 - 58 2,730.0 4,640.0
No. 4 4,76 1,975.0 6,914.0 52.38 47.62 48.03 29 - 44 2,155.0 6,795.0
No. 8 2.38
No. 10 2,00 1,915.0 8,829.0 66.89 33.11 33.28 17 - 30 1,975.0 8,770.0
No. 16 1.181
No. 30 0.59
No. 40 0,425 2,172.0 11,001.0 83.34 16.66 16.56 7 - 17 2,238.0 11,008.0
No. 50 0.300
No. 100 0.150
No. 200 0,074 1,466.0 12,467.0 94.45 5.55 5.36 2-8 1,488.0 12,496.0
PASS. NO.200

100
Passing ( % )

80

60
Control Point (Upper)

40

Control Point (Lower)


20
Control Point (Lower)
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10 25.4 38.1

Sieve Size ( mm )

Remark :

Checked by the Engineer Submitted by the C


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Con
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persad

Andespa Hedison
Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

E ANALYSIS
: 6 April 2015
: Kanif Setiady
: Andespa Hedison, ST.
13,178.0 Gr

Cumulative

% Ret % Passing

0.00 100.00
14.49 85.51

35.21 64.79
51.56 48.44

66.55 33.45

83.53 16.47

94.82 5.18

er)

Control Point (Lower)


Control Point (Lower)

1 10 38.1 100

eve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT


- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfar
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
- Date : April 29th 2014 Kyeryong Construction Industria
PT. Yala Persada Angkasa

SIEVE ANALYSIS
LOCATION : Laboratorium Project DATE :
MATERIAL : Aggregate Base Class A TESTED BY : Kanif Setiady
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY : Andespa Hediso
WEIGHT OF SAMPLE I : 11,368.0 Gr WEIGHT OF SAMPLE II :
US Sieve Individu Spec Individu
Cumulative Cu
Standart Opening Weight Ret Average Aggregate Weight Ret
Sieve (in) mm Grams Retained % Ret % Passing Grams Retained
###in 76.2
###in 50.8
1 1/2 in 38,1 0.0 0.0 0.00 100.00 100.00 100 0.0 0.0
1 in 25,4 2,888.0 2,888.0 25.40 74.60 74.60 79 - 85 2,888.0 2,888.0
3/4 in 19,1
1/2 in 12,7
3/8 in 9,52 3,206.0 6,094.0 53.61 46.39 46.39 44 - 58 3,206.0 6,094.0
No. 4 4,76 678.0 6,772.0 59.57 40.43 40.43 29 - 44 678.0 6,772.0
No. 8 2.38
No. 10 2,00 1,137.0 7,909.0 69.57 30.43 30.43 17 - 30 1,137.0 7,909.0
No. 16 1.181
No. 30 0.59
No. 40 0,425 1,989.0 9,898.0 87.07 12.93 12.93 7 - 17 1,989.0 9,898.0
No. 50 0.300
No. 100 0.150
No. 200 0,074 1,437.0 11,335.0 99.71 0.29 0.29 2-8 1,437.0 11,335.0
PASS. NO.200

100
Passing ( % )

80

60
Control Point (Upper)

40

Control Point (Lower)


20
Control Point (Lower)
20

0
0.01 0.074 0.1 0.425 1 2.00 4.76 9.52
10 25.4 38.1

Sieve Size ( mm )

Remark :

Checked by the Engineer Submitted by the C


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Con
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persad

Andespa Hedison
Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

E ANALYSIS

: Kanif Setiady
: Andespa Hedison, ST.
11,368.0 Gr

Cumulative

% Ret % Passing

0.00 100.00
25.40 74.60

53.61 46.39
59.57 40.43

69.57 30.43

87.07 12.93

99.71 0.29

er)

Control Point (Lower)


Control Point (Lower)

1 10 38.1 100

eve Size ( mm )

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CON


DOHWA Engineering,
- Province : West Sumatera
PT. Perentjana Djaya an
- Contractor : KYERYONG - YALA, JO.
CONTRACTOR
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014
Kyeryong Construction
- Date : April 29th 2014 PT. Yala Persada Angka

LOS ANGELES ABRASION LOSS TEST

Location : Laboratorium Project Date Testing


Material : Aggregate Base Class A Tested by
: Quarry Kayu Tanam III (LMKP Production) Checked by

GRADING : TYPE A

SAMPLE
PASSED RETAINED I
Before (A) After (B) Befor
3" 2 1/2 "
2 1/2 " 1 1/2 "
1 1/2 " 1" 1,250.2 1,25
1" 3/4 " 1,250.5 1,24
3/4 " 1/2 " 1,250.3 1,25
1/2 " 3/8 " 1,250.1 1,24
3/8 " 1/4 "
1/4 " No. 4
No. 4 No. 8
TOTAL WEIGHT 5,001.1 5,00
TOTAL WEIGHT SIEVE No. 12 RETAINED 3,259.1

I Before Weight (A) = 5,001.1 gram II Before Weight (A) =


After Weight (B) = 3,259.1 gram After Weight (B) =
Abrasion Weight = 1,742.0 gram Abrasion Weight =
A - B A -
% Abrasion = x 100% % Abrasion =
A A

5,001.1 - 3,259.1 5,003.7 -


% Abrasion = x 100% % Abrasion =
5,001.1 5,003.7
= 34.83 % = 33.69 %

34.83 + 33.69
Average % Abrasion =
Average % Abrasion =
2
= 34.26 %
Remark : Stone from Quarry Kayu Tanam III

Checked by the Engineer Submitted by the C


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Con
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persad

Andespa Hedison
Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan            
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

LES ABRASION LOSS TEST

: 18 Januari 2015
: Kanif Setiady
: Andespa Hedison, ST.

SAMPLE
II
Before (A) After (B)

1,256.1
1,249.6
1,250.8
1,247.2

5,003.7
3,317.8

5,003.7 gram
3,317.8 gram
1,685.9 gram
B
x 100%

3,317.8
x 100%
5,003.7
Submitted by the Contractor
PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Quality Control
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS
- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSULTANT
- Province : West Sumatera DOHWA Engineering, Co.Ltd in A
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya and Hasfarm
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction Industrial C
- Date : April 29th 2014 PT. Yala Persada Angkasa

SOFT FRAGMENTS
( AASHTO T-112-81 / SNI 03 -4141-1996 )
LOCATION : Laboratorium Project DATE
MATERIAL : Aggregate Base Class A TESTED BY
: Quarry Kayu Tanam III (LMKP Production) CHECKED BY
Retained # No. 4 (G) =
Passing # No. 4 (H) =

SIEVE SIZE PROSENTASE of


SIEVE OF SAMPLE WEIGHT of SAMPLE WEIGHT of SAMPLE WEIGHT of LOSS
WEIGHT FROM LOSS
WITH PROSENTASE BEFORE TEST AFTER TEST SAMPLE
SAMPLE

NO
D
A B C D=B-C E= X 100
PASSING RETAINED B

I II I II I II I II I II

1 1 1/2 " (38,10 mm) 100.00 100.00 0 0 0 0 0 0 0.00 0.00


2 1 1/2 " (38,10 mm) 3/4 " (19,10 mm) 83.09 83.09 3000 3000 2997.4 2997.4 2.6 2.6 0.09 0.09
3 3/4 " (19,10 mm) 3/8" (9,50 mm) 54.72 54.72 2000 2000 1992.4 1992.4 7.6 7.6 0.38 0.38
4 3/8" (9,50 mm) # 4 (4,75 mm) 45.88 45.88 1000 1000 990.6 990.6 9.4 9.4 0.94 0.94
AMOUNT OF CLAY LUMPS AND FRIABLE PARTICLES IN COARSE AGGREGATE (I)
5 # 4 (4,75 mm) # 16 (1,18 mm) 37.41 37.41 500 500 473.7 473.7 26.3 26.3 5.26 5.26
AMOUNT OF CLAY LUMPS AND FRIABLE PARTICLES IN FINE AGGREGATE (J)
TOTAL = (G x I) + (H x J)

REMARKS

Checked by the Engineer Submitted by the Contractor


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Construction Ind
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persada Angkasa

Andespa Hedison, ST.


Lab. Technician Quality Control
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan       
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

RAGMENTS
81 / SNI 03 -4141-1996 )
: 6 February 2015
: Kanif Setiady
: Andespa Hedison, ST.
54.12%
45.88%
AVERAGE
PROSENTASE of
WEIGHT
( CORECCTION BY
LOSS SAMPLE
PROSENTASE )
AxE
F= 100

I II

0.00 0.00
0.07 0.07
0.21 0.21
0.43 0.43
0.71 0.71
1.97 1.97
1.97 1.97
1.29 1.29
1.29

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF HIGHWAYS

- Project : Padang Bypass Capacity Expansion Project SUPERVISION CONSU


- Province : West Sumatera DOHWA Engineering, Co
- Contractor : KYERYONG - YALA, JO. PT. Perentjana Djaya an
- Contract No. : Ku.08.08/KTR.06.PPK/12/PJNJI/V/2014 CONTRACTOR
Kyeryong Construction I
- Date : April 29th 2014
PT. Yala Persada Angkas

GRAPHIC WEATHER

18.00

17.00

16.00

15.00

14.00

13.00

12.00

11.00

10.00

9.00

8.00
24

16
16

Explanation : (

Remark :

Checked by the Engineer Submitted by the


DOHWA Engineering Co. Ltd., in Assosiation with PT. Kyeryong Co
PT. Perentjana Djaja and Hasfarm Dian Konsultan JO PT. Yala Persa

Consultant Contractor
SUPERVISION CONSULTANT
DOHWA Engineering, Co.Ltd in Assosiation With
PT. Perentjana Djaya and Hasfarm Dian Konsultan                  
CONTRACTOR
Kyeryong Construction Industrial Co., Ltd. (JO)
PT. Yala Persada Angkasa

PHIC WEATHER

18.00

17.00

16.00

15.00

14.00

13.00

12.00

11.00

10.00

9.00

8.00
08

16
16

Explanation : ( March )

Rain Hujan
Drizzle Gerimis
Cloudy Berawan
Sunny Cerah

Submitted by the Contractor


PT. Kyeryong Construction Industrial Co. Ltd.
JO PT. Yala Persada Angkasa

Contractor
18.00

17.00

16.00

15.00

14.00

13.00

12.00

11.00

10.00

9.00

8.00
24

08

16
08
EMPLOYER CONSULTANT CONTRACTOR

GRAPHIC of WEATHER
Civil Works For Construction of Karian Multipurpose DAM
Month April 2015
Date
Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
00 : 00 - 01 : 00
01 : 00 - 02 : 00
02 : 00 - 03 : 00
03 : 00 - 04 : 00
04 : 00 - 05 : 00
05 : 00 - 06 : 00
06 : 00 - 07 : 00
07 : 00 - 08 : 00
08 : 00 - 09 : 00
09 : 00 - 10 : 00
10 : 00 - 11 : 00
11 : 00 - 12 : 00
12 : 00 - 13 : 00
13 : 00 - 14 : 00
14 : 00 - 15 : 00
15 : 00 - 16 : 00
16 : 00 - 17 : 00
17 : 00 - 18 : 00
18 : 00 - 19 : 00
19 : 00 - 20 : 00
20 : 00 - 21 : 00
21 : 00 - 22 : 00
22 : 00 - 23 : 00
23 : 00 - 24 : 00
Rain 0
Drizzle 0
Total
Cloudy 0
Sunny

Remark Rain/Hujan Drizzle/Gerimis Cloudy/Berawan Sunny/Cerah

Das könnte Ihnen auch gefallen