Beruflich Dokumente
Kultur Dokumente
PROJECT CATEGORY :
FROM OWNER
MINIMUM REQUIREMENT
Description No. Needed
Dump Truck 2
Bagger Mixer 1
Concrete Vibrator 1
Welding Machine 1
Plate Compactor 1
Bar Cutter 1
Service Vehicle 1
Handtools 10
TOTAL 100.00%
B. INDIRECT COST
1. Overhead, Contingency, Miscellaneous
(12.0% of A1 to A4)
2. Profit (8.0% of A1 to A4)
3. Comprehensive All Risk Insurance
4. VAT (5% of A and B)
SUB-TOTAL (CONTRACT COST)
I. ESTIMATED GOVERNMENT EXPENDITURES
Preliminary Detailed Engineering (3.5%)
1. Engineering & Administrative Supervision
(3.5% of Estimated Project Cost/Allocation)
2. ROW/Site Acquisition
3. Soil Exploration
SUB-TOTAL (CONTRACT COST)
II. CONTINGENCIES / RESERVES
1. Physical (Up to 5% of the Estimated Contract Cost)
PROPOSED WORK
Unit QTY Direct Cost Unit Cost
months 7.00 182,000.00 26,000.00
38,263,190.39
38,263,190.39
4,515,649.65
3,030,444.68
2,290,464.24
48,099,748.96
1,750,000.00
150,000.00
1,900,000.00
49,999,748.96
50,000,000.00
NAME / LOCATION OF PROJECT
PROJECT CATEGORY :
FROM VBC
MINIMUM REQUIREMENT
Description No. Needed
Dump Truck
Bagger Mixer
Concrete Vibrator
Welding Machine
Plate Compactor
Bar Cutter
Service Vehicle
Handtools
TOTAL 0.00%
B. INDIRECT COST
1. Overhead, Contingency, Miscellaneous
(12.0% of A1 to A4)
2. Profit (8.0% of A1 to A4)
3. Comprehensive All Risk Insurance
4. VAT (5% of A and B)
SUB-TOTAL (CONTRACT COST)
I. ESTIMATED GOVERNMENT EXPENDITURES
Preliminary Detailed Engineering (3.5%)
1. Engineering & Administrative Supervision
(3.5% of Estimated Project Cost/Allocation)
2. ROW/Site Acquisition
3. Soil Exploration
SUB-TOTAL (CONTRACT COST)
II. CONTINGENCIES / RESERVES
1. Physical (Up to 5% of the Estimated Contract Cost)
PROPOSED WORK
Unit QTY Direct Cost Unit Cost
months -
set -
months -
lot -
m3 -
m3 -
m3 -
m3 -
m3 -
kgs -
kgs -
lot -
m2 -
m2 -
m2 -
m2 -
m -
m -
m -
m2 -
m2 -
lot -
lot -
lot -
lot -
-
-
-
50,000,000.00
NAME / LOCATION OF PROJECT
PROJECT CATEGORY :
FROM OWNER
MINIMUM REQUIREMENT
Description No. Needed
Dump Truck 2
Bagger Mixer 1
Concrete Vibrator 1
Welding Machine 1
Plate Compactor 1
Bar Cutter 1
Service Vehicle 1
Handtools 10
1003 (1) a1 Ceiling (Fiber Cement Board, 4.5mm thk on Metal Frame) 3.47%
1003 (2) b1 Wall (Fiber Cement Board, 6.0mm thk on Metal Frame) 1.01%
TOTAL 100.00%
B. INDIRECT COST
1. Overhead, Contingency, Miscellaneous
(12.0% of A1 to A4)
2. Profit (8.0% of A1 to A4)
3. Comprehensive All Risk Insurance
4. VAT (5% of A and B)
SUB-TOTAL (CONTRACT COST)
I. ESTIMATED GOVERNMENT EXPENDITURES
Preliminary Detailed Engineering (3.5%)
1. Engineering & Administrative Supervision
(3.5% of Estimated Project Cost/Allocation)
2. ROW/Site Acquisition
3. Soil Exploration
SUB-TOTAL (CONTRACT COST)
II. CONTINGENCIES / RESERVES
1. Physical (Up to 5% of the Estimated Contract Cost)
PROPOSED WORK
Unit QTY Direct Cost Unit Cost
months 6.00 156,000.00 26,000.00
-
NAME / LOCATION OF PROJECT
PROJECT CATEGORY :
FROM VBC
MINIMUM REQUIREMENT
Description No. Needed
Dump Truck
Bagger Mixer
Concrete Vibrator
Welding Machine
Plate Compactor
Bar Cutter
Service Vehicle
Handtools
1003 (1) a1 Ceiling (Fiber Cement Board, 4.5mm thk on Metal Frame)
1003 (2) b1 Wall (Fiber Cement Board, 6.0mm thk on Metal Frame)
TOTAL
B. INDIRECT COST
1. Overhead, Contingency, Miscellaneous
(12.0% of A1 to A4)
2. Profit (8.0% of A1 to A4)
3. Comprehensive All Risk Insurance
4. VAT (5% of A and B)
SUB-TOTAL (CONTRACT COST)
I. ESTIMATED GOVERNMENT EXPENDITURES
Preliminary Detailed Engineering (3.5%)
1. Engineering & Administrative Supervision
(3.5% of Estimated Project Cost/Allocation)
2. ROW/Site Acquisition
3. Soil Exploration
SUB-TOTAL (CONTRACT COST)
II. CONTINGENCIES / RESERVES
1. Physical (Up to 5% of the Estimated Contract Cost)
PROPOSED WORK
Unit QTY Direct Cost Unit Cost
months -
set -
months -
lot -
m3 -
m3 -
m3 -
m3 -
m3 -
kgs -
kgs -
lot -
m2 -
m2 -
m2 -
m2 -
m -
sets -
sets -
m2 -
m2 -
set -
m2 -
m -
m -
m -
m2 -
m2 -
m2 -
m2 -
m2 -
m2 -
m2 -
m2 -
m2 -
-
-
-
-
50,000,000.00