Beruflich Dokumente
Kultur Dokumente
Stability
Presented by :
Ishan Banerjee
Associate Manager , Technology and Innovation
Smarter
Sterlite Network
Power Solutions
Core Purpose and Values
Separators 1:
Smarter Network Solutions
Outline
1. Problems at grid level
7. Proposal
Problems at Grid Level
RENEWABLE INTERMITTENCY EXCESS GENERATION
Renewable sources are unpredictable by nature and produce The current electric grid is an inefficient system that wastes
daily variability in output along with sudden ramping issues significant amounts of the electricity it produces
THE SOLUTION-
BESS
TIME OF USE
POWER QUALITY
Mismatch between the peak output of solar generation and peak
Inadequate power quality, frequency imbalance, voltage and load demand
current harmonics, excess reactive power
765 kV
400 kV
33 kV
Tertiary rated
for 5MW
continuous
5 Nos , 1 MVA BESS,
Output : 430 V, 1200
Amps
Mode of operation
Charging :
When frequency is above 50.05 Hz, the BESS will operate in charging mode till the
batteries are fully charged
Discharging :
When frequency is less than 49.9 Hz, the BESS will operate in discharging mode till the
batteries are fully discharged
( The above is just an illustration which can be changed / programmed and many other
logics can be added.)
Business Model Canvas
KEY KEY VALUE CUSTOMER CUSTOMER
PARTNERS ACTIVITIES PROPOSITIONS RELATIONSHIPS SEGMENTS
• Battery
• Inverter • Detailed Load Analysis of B2B with WRLDC to tackle the • WRLDC
the identified Load Centers key pain areas-
• Control System of WRLDC • Energy storage as • Frequency Deviation
• O&M • Approvals an Ancillary service • Voltage Control
• System Integrator • Installation and O&M solution to WRLDC • Over/Under Injection/Drawl
• Assured frequency
KEY
RESOURCES
response capacity
CHANNELS
(MW and MWH)
based
• Bhopal & Dhule S/S- Land • BOOM model
• Availability of substation
for easy integration
CAPEX + OPEX + Finance Availability based tariff proposed (similar to transmission tariff)
• Actively feed and get active & reactive power to/ from the grid as per grid voltage and frequency deviation
• Assist the traditional power system to respond the frequency / voltage-adjustment instructions quickly and improve the
grid stability
• Solve the grid stability problems high penetration of new energy access and guarantee the new energy grid-connection
safety
Indian Proposed Storage Projects- 2017
Storage (Flywheel)
1. NLC India Ltd. Project
Location: Attampahad, Portblair, A&N Islands
• 20 MW(AC) grid interactive solar PV Power Project integrated with a minimum of 6 MWHr Battery Energy Storage System with a 6
MW Power Conversion System to mitigate and smoothen the solar power output fed into the grid with associated 33 KV Power
System complete for grid interconnection at the take-off points.
• 100 MW (2x 50 MW Solar PV Projects having 5MW/2.5MWh BESS on Build Own Operate (BOO) basis. The minimum energy
rating of the battery shall be 2.5 MWh, which the Proposed BESS shall support the grid at rated power output for 30 Minutes.
• 200 MW (4x 50 MW Solar PV Projects having 5MW/2.5MWh BESS on Build Own Operate (BOO) basis. The minimum energy
rating of the battery shall be 2.5 MWh, which the Proposed BESS shall support the grid at rated power output for 30 Minutes.
Source : SECI Tenders
Key Highlights of WRLDC
Has highest Installed Capacity compared to all region i.e. ~ 108 GW as on 31.03.2016. It is 36% of all India Installed capacity of 302 GW.
CAGR over a decade is 11.84% Storage (Flywheel)
Total Renewable installed capacity was 15315 MW as on 31.03.2016. RES energy capacity growth was 19.69% compared to the year
2014-15.
Total capacity of 6875 MW added in this year including central, state & IPPs
Has highest nos (68 Nos) of 765 kV lines out of which 19 Nos of 765 kV lines added in this year. Total Transmission lines of 6913 ckt km
including 765 kV & 400 kV added in 2015-16
System frequency in IEGC band (49.9-50.05) improved from 52.78% in 2014-15 to 66.73% of time in 2015-16. Average frequency was
49.99 Hz
Maximum Demand of 49938 MW achieved on 19.10.2015 at 1500 hours. CAGR in Maximum Demand met over a decade is 6.51%
Recorded Maximum Energy consumption of 1131 Mus on 20.10.2015. Average energy consumption increased by 6.3% compared to 2014-
15
Total 3276 Nos intra-regional & inter-regional STOA transactions of 11835 Mus energy approved in this year
DSM charges collected and disbursed Rs. 1720 Cr in 2015-16 against Rs. 2207 Cr in 2014-15. Weekly Max DSM bill- 89.5 Cr in the week
31.08.2015 to 6.09.2015
3500 3409
3000
2465
2500 2362 2304
2207
2101
2000
1720 DSM Charges INR (in Crores)
500
0
2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16