MANUAL
TABLE OF CONTENTS
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance
ProcessingNotification Create (General) – IW21
1. Double click IW21 – Notification Create (General)
2. Information step:
Field Name Field Description
Notification type Key that enables notifications to be differentiated and grouped according to
notification category, notification origin and other criteria.
Notification Number that identifies the notification.
5. Information step:
Field Name Field Description
Notification short text Short description of the contents of a notification.
System status for Key which records the condition of the notification or the execution of a
notification function for the notification.
User status for Field displaying user status
notification
Functional location Label that uniquely identifies a functional location.
Equipment Number by which a piece of equipment can be clearly identified.
Assembly Number which uniquely identifies an assembly.
Code group - coding Key for the code group that contains the codes for coding the notification.
Note:
d) strategy plan,
There are various icons and tabs which assist us in analyzing the object
information details for instance;
d) Display object , by clicking this icon, you will be able to display the object
e) Maintenance items , by clicking this tab, we will be able to
view the maintenance items for the object.
This screen gives you an indication of the notifications raised against the
equipment. You are also able to see if the fault you are reporting has been
raised before or not.
8. Click Continue
Malfunction end Date of day on which the problem was solved, or on which the malfunction
ended
Malfunctn End (Time) Time at which the malfunction ended, or at which the problem was solved
Breakdown Indicator that informs you when a machine has broken down
Note:
Note:
The number ranges for notifications are linked to the Notification Types.
14. Note down the notification number from the message bar.
Notification number ……………………………………….
You will now update the item details relating to the damage to equipment.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance
ProcessingNotificationChange – IW22
1. Double click IW22 –Notification Change
2. Information step:
Field Name Field Description
Notification Number that identifies the notification.
Note:
Normally, the last notification you worked on defaults If you want to change that
particular notification, click Enter to proceed. If you want to change different
notification, enter the number of the notification to be changed and click Enter.
Note:
If you are a maintenance planner, you can create an Order from this notification
screen by clicking Create adjacent to the Order field. (
5. Click .
6. Click
Write the message to send to the responsible Engineer, and Enter the recipient.
7. Click
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance
ProcessingNotificationList EditingChange – IW28
1. Double click IW28 –List Editing - Change
2. Information step:
Field Name Field Description
Notification Status Specifies whether notifications or orders which have the status "outstanding"
“Outstanding” should be selected..
Notification Status Specifies whether or not notifications with the status "postponed" should be
“Postponed” selected.
Notification Status “In Specifies whether notifications or orders with the status "In process" should
process” be selected.
Notification Status Specifies whether notifications or orders with the status "Completed" should
“completed” be selected.
Notification type Key that enables notifications to be differentiated and grouped according to
notification category, notification origin and other criteria.
Status included Status which a maintenance notification should have for selection. This
system selects only those PM notifications which have this status and which
also fulfill all the other selection criteria you have entered.
Status excluded Status which a maintenance notification should not have for selection. The
system selects only those PM notifications which do not have this status and
which fulfill all the other selection criteria you have entered.
Main work center Key which uniquely identifies the responsible work center for this technical
object.
Plant for work center Plant in which the main work center that has been entered is to be found.
Planner group Key that uniquely identifies the planner group in Customer Service or Plant
Maintenance.
Maintenance plant Number which clearly identifies a maintenance plant.
Note:
There are various selection parameters available. Choose the parameters that
best suit your requirements.
4. Click Execute
5. Information step:
Field Name Field Description
Notification Number that identifies the notification.
Notif.date Date at which the notification was created.
Note:
You can manipulate this list by selecting various icons for example;
a) You can view the details of a particular notification by selecting the line item
for that notification and clicking Details .
c) You can generate an order by highlighting the line item of the notification to
be linked to the order and clicking Generateorder .
d) You can complete a notification by highlighting the line item of the notification
to be completed and clicking Complete .
e) You can filter the list by clicking the Set filter icon.
f) You can change the layout of the list by clicking the Change report/layout
icon.
Note:
You can change the report layout by highlighting the column you need to display
or the column you do not need to display and clicking on show selected fields
and hide selected fields respectively.
7. Scroll down the Column Set and select the Main work centercolumn
8. Click Show selected fields to move the Main work center to the
DisplayedColumns.
Note:
Note:
Note:
Note:
Every time you will run this report you will find your defined layout because you
defined it as a user specific layout.
14. Click the Notif.date column and click Set filter to determine values for filter
criteria.
Note:
The “List of Notifications” is now shown based on the filter values you
entered.
You may need to scroll down the screen to view other notifications depending
on the size of your notification list.
17. Scroll to the left of the screen and select a Line item for the Notification you
created in the exercise (Create Notification – IW21) and click Details
The system displays the message “Do you want to specify a new dates”
Note:
The system displays the message “Execution date reset according to priority”
Note:
The column for the selected line that has been saved is updated with a tick
INSTRUCTIONS
2. Information step:
Note:
Normally, the last notification you worked on defaults. Also the order type
associated with that notification. If you want to create order for that particular
notification, click Enter to proceed. If you want to change a different notification,
enter the number of the notification to be changed and the order type click
Enter.
5. Information step:
In cost evaluations, for example, total costs or number of orders for each
technical object, you can classify data according to maintenance activity
type.
Activity types describe the activity produced by a cost center and are
measured in units of time or quantity.
7. Click Enter
9. Information step:
Note:
The first operation short text is defaulted from the order description in the
header section.
Note:
You can change the control key of operations already existed from “PM01”
plant maintenance internal operation to “PM03” plant maintenance
external operation
Note:
The system displays the message “Calculation Executed” to inform you that
Work is calculated since calculation key is defaulted as “Calculate Work”
The Control Key is defaulted as PM01 for internal processing. In case you
need external processing you will use control keys PM02 or PM03 as will be
explained later in this training manual
Note:
Analyze the material to be required for this work. It can be stock or non stock
items.
Click onList to see the part lists with reference to the equipment.
(Note: Parts list can be seen once you maintain the material number in the
construction type field in the equipment master).
The system displays the message “Costs were determined: See cost overview”
Note:
Click Calculate to calculate the planned costs; we can see the actual costs
after order confirmation;
The system status will be allocated with “PRC – Pre-costed” status inwork
order
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
SCENARIO
You now need to plan internal operations and assign people to operations by using the
capacities in the assigned work centers. You will also plan the sequence of operations.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderIW32 –Change
Note:
Normally, the last order you worked on defaults. If you want to work on that
particular order, click Enter to proceed. If you want to d work on a different
order, enter the number of the order you want and click Enter.
3. Click Enter
5. Information step:
Note:
You can select the internal button at bottom of screen to show more details
about assigning the person who will perform this operation
9. Click Save
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderIW32 –Change
Note:
Normally, the last order you worked on defaults. If you want to work on that
particular order, click Enter to proceed. If you want to d work on a different
order, enter the number of the order you want and click Enter.
3. Click Enter
Note:
You have assigned three operations to your maintenance order. Any component
you want to add to your order should be assigned to one of these operations.
6. Information step:
9. Click Material by Material Type to search for material using material type.
The system displays the message “Enter operation number and sequence” to assign
this component to which operation
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
*SCENARIO
The maintenance order has been created; you need to change the work order to assign
non -stock material to it.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderIW32 –Change
3. Click Enter
Note:
You can write a short description for the non-stock item or enter the component
number with the item category N “Non-stock items” which we will use in this
work order
You can enter non stock item number. If division type is “RR” Reorder on
Request” then automatically the item category will be picked up as “N” Non
stock items
Here we will enter a description for the material, unit of measure, item category,
operation code, material group, unloading point, and price of the material which
we will include in the work order
5. Information step:
ReqmtQty Required quantity that we want to request to be included in the work order
IC Item category which will differentiate between stock item and non-stock item
7. Click Enter
The system displays the message “Enter operation number and sequence” to assign
this component to which operation
8. Exercise step: update the following fields:
Field Name Values
Operation 0020
9. Click Continue
Note:
In case of there is contract with a specific vendor and you need to purchase
these material with reference to this contract you should enter the contract
number in agreement filed
In other cases you can simply enter text description for the material you need to
purchase or enter
14. Click Purch. To display the purchasing data copied from the
contract.
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
19. Click Purch. To display the purchasing data copied from the
contract.
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
SCENARIO
The maintenance order has been created; you need to change the work order to assign
external services which can be supplied by external vendor like consultancy partner or
external maintenance technician to provide the operation.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderIW32 –Change
Note:
Normally, the last order you worked on defaults. If you want to work on that
particular order, click Enter to proceed. If you want to d work on a different
order, enter the number of the order you want and click Enter.
3. Click Enter
Note:
You can change the control key of operations already existed from “PM01”
plant maintenance internal operation to “pM03” plant maintenance
external operation
5. Information step:
7. Click Continue
8. Click Confirm
11. Select the line item by a single click on the grey button to the left of it and click
sub tab External or double click on the operation 0040
Quantity 1
UOM EA
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
SCENARIO
Maintenance engineer should print shop papers in order to send it to operations and the
work center that will carry out the work.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderIW32–Change
2. Information step:
Note:
Normally, the last order you worked on defaults. If you want to work on that
particular order, click Enter to proceed. If you want to do work on a different
order, enter the number of the order you want and click Enter.
4. Click Enter
6. Information step:
Note:
You need to contact your System Administration to inquire your output device in
your location.
Note:
Note:
Now your order is printed and you are ready to execute your maintenance
activities.
The system will take you out of the order header screen.
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
You use the individual time confirmation primarily if you want to enter detailed time
confirmations for individual operations and splits (several operations), and only
occasionally enter additional data, such as materials used or information about damage.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance
ProcessingCompletion ConfirmationEntryIndividual Time Confirmation –
IW41
1. Double click IW41 – Individual Time Confirmation
2. Information step:
Field Name Field Description
Confirmation Number used to identify an operation in the confirmation.
Operation/Activity Determines in which order the operations of a sequence are carried out.
number
Sub operation Determines in which order the sub-operations of an operation are listed.
Capacity category Key which describes capacity in more detail. The capacity category enables
you to determine whether it is machine or labor capacity.
Split number This is the split number for the time confirmation
If alternative labels exist for a functional location, you can define in your user
profile which label should be displayed in this field.
Equipment Number by which a piece of equipment can be clearly identified.
Note:
If only one operation exists for the maintenance order the Create PM Order
Confirmation: Actual Data screen is displayed.
4. Click Enter .
Note:
The order specified on the previous screen with all its operations and planned
working hours is displayed. You can select the operation that is complete and
do the confirmation for it.
5. Information step:
Field Name Field Description
Confirmation Indicator shows you if you have created or cancelled a confirmation for the
created/cancelled operation, while you were editing the data.
The indicator is flagged even if you have called the details screen but you
have not made any entries.
Operation/Activity Determines in which order the operations of a sequence are carried out.
number
Split indicator Indicator indicating that a capacity category is split up into individual
capacities.
Work center Key identifying the work center.
Plant Key uniquely identifying a plant.
Work involved in the Amount of work involved in performing the activity.
activity
Unit Unit for work.
Operation short text Describes the operation or sub-operation.
Actual work Total work carried out for this operation or activity (PS).
6. Select the Operation/Activity number 0010 line item for the operation to be
confirmed.
Note:
The planned hours defaults in the Actual Work field. This should be changed to
the actual hours worked on the operation.
If this is not the final confirmation, hours worked can be entered and can be
updated at a later stage as work progresses on the operation. When a final
confirmation is done, the “Final Confirmation, No Remain. Work and Clear
Open Res” check boxes should be ticked.
This indicates there is no more work to be done on the operation and also if
there are any reservations that are open against the operation they should be
closed automatically. This will release the reserved materials which will become
available again.
8. Information step:
Field Name Field Description
Confirmation Number used to identify an operation in the confirmation.
Personnel number Personnel number of the person to whom the confirmed data relates.
Wage type Key which specifies the wage type (for example, piecework wage or
premium wage). The wage type is used as a criterion for calculating the
wage or salary of an employee.
The value from the work center is the default in the routing.
Activity type Key identifying an activity type for the confirmation.
Posting date Date on which the confirmation is posted.
Final confirmation Specifies what sort of confirmation is to be automatically proposed.
No remaining work Indicator showing that no further work is expected for this operation.
Accounting indicator Key that uniquely identifies the accounting indicator.
Clear open reservation Indicator specifying that with a final confirmation, the indicator "delivery
completed" is set for all open reservations that are assigned to the
confirmed operation.
Remaining work Value for the expected amount of work that still needs to be done.
Actual duration The amount of time (duration) that was worked.
Reason Via this key you can specify why a confirmed value deviates from a planned
value (for example due to scrap, or due to an operating error).
Confirmation text Confirmation text
Note:
When you exceed the planned hours, the system displays the message “Actual
duration + remaining duration deviates by more than XXX% from schd”
Click Enter to by pass this message.
The system displays the message “Number of confirmations saved for order
XXXXXXXXXX: X”.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance
ProcessingCompletion ConfirmationEntryCollective Time
ConfirmationWith Selection – IW48
1. Double click IW48 – With Selection
Confirmation using operation list: Selection of Order Operations
2. Information step:
Field Name Field Description
Work Center Key identifying the work center.
If you select this field, the system only selects the operations from service and
maintenance orders.
Collective time Entry of data on the entry screen for the collective time confirmation.
confirmation
If you flag this field, the system enters the result of the selection directly on the
entry screen for the collective time confirmation.
4. Click Execute
Note:
On this screen, there are various icons and tabs that can be used to manipulate
your data for instance;
a) You can select all the line items for confirmation by clicking Select All icon.
b) You can deselect all the line items for confirmation by clicking Deselect All
icon.
c) You can propose all actual data for confirmation by clicking the Proposeall
actual data tab.
5. Information step:
Field Name Field Description
Confirmation Number used to identify an operation in the confirmation.
Order Number which identifies an order within a client.
Operation/Activity number Determines in which order the operations of a sequence are carried out.
Actual Work Value for the amount of work that has accumulated since the last
confirmation.
Unit Unit for work.
Final confirmation Specifies what sort of confirmation is to be automatically proposed.
Clear reservation Indicator specifying that with a final confirmation, the indicator "delivery
completed" is set for all open reservations that are assigned to the
confirmed operation.
No remaining work Indicator showing that no further work is expected for this operation.
Work center Identifies the work center, at which the operation is confirmed.
Actual duration The amount of time (duration) that was worked.
Cause Via this key you can specify why a confirmed value deviates from a
planned value (for example due to scrap, or due to an operating error).
Confirmation text Confirmation text
Operation short text Describes the operation or sub-operation..
Note:
You can enter the actual data on this screen or click Actual Data to go to the
detail confirmation. For this exercise, we are going to enter the actual data on
this screen.
Note:
When you exceed the planned hours, the system displays the message “Actual
duration + remaining duration deviates by more than XXX% from schd”
Click Enter to by pass this message.
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 100 of 122
USER TRAINING MANUAL
Corrective Maintenance
SCENARIO
After the completion of external service performed by the vendor / contractor,
maintenance engineer will create a service entry sheet in the system.
This is essential since Finance (accounts payable) will validate the vendor's invoice
against the purchase order and also against the confirmed service entry sheet.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
Completion ConfirmationML81N – Services
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 101 of 122
USER TRAINING MANUAL
Corrective Maintenance
3. Information step:
Field Name Field Description
Purchase Order Service purchase order for which you need to create a service entry sheet.
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 102 of 122
USER TRAINING MANUAL
Corrective Maintenance
5. Click Continue
Note:
You can display the purchase order by clicking on Show purchase order
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 103 of 122
USER TRAINING MANUAL
Corrective Maintenance
7. Information step:
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 104 of 122
USER TRAINING MANUAL
Corrective Maintenance
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 105 of 122
USER TRAINING MANUAL
Corrective Maintenance
13. Click Select All to select all items in the purchase order
14. ClickAdopt Services to copy selected services into service entry sheet
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 106 of 122
USER TRAINING MANUAL
Corrective Maintenance
Note:
In some cases you may encounter the “Entry Sheet XXXXXXXXXX” pop up
screen as shown below;
If you have it just click yes and the service entry sheet will be saved
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 107 of 122
USER TRAINING MANUAL
Corrective Maintenance
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 108 of 122
USER TRAINING MANUAL
Corrective Maintenance
SCENARIO
Maintenance engineer wants to accept (or confirm) a saved service entry sheet.
This is essential since Finance (accounts payable) will validate the vendor's invoice
against the purchase order and also against the confirmed service entry sheet. They are
unable to pay the vendor unless the service entry sheet is confirmed.
You will now confirm (accept) the service entry sheet created already.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
Completion ConfirmationML81N – Services
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 109 of 122
USER TRAINING MANUAL
Corrective Maintenance
Note:
Normally, the last service entry sheet you worked on defaults. If you want to
change that particular service entry sheet, click Change / Display to
proceed. If you want to change a different service entry sheet, double click on
the service entry sheet on the Purchase Orders/Entry Sheets are to the left.
Note:
You can approve any other service entry sheet by clicking OtherPurchase.
Order then enter the number of service entry sheet you
want to approve.
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 110 of 122
USER TRAINING MANUAL
Corrective Maintenance
Note:
4. Click Save
Note:
In some cases you may encounter the “Entry Sheet XXXXXXXXXX” pop up
screen as shown below;
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 111 of 122
USER TRAINING MANUAL
Corrective Maintenance
If you have it just click yes and the service entry sheet will be saved
The system displays the message “Service entry sheet saved, acceptance
document XXXXXXXXXX posted”
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 112 of 122
USER TRAINING MANUAL
Corrective Maintenance
It is only when this status is reached that Controlling staff can run settlement of the work
orders to ensure that the maintenance costs are charged to the correct cost centers.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
Order IW32 – Change
1. Double clickIW32 -Change
3. Click Enter
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 113 of 122
USER TRAINING MANUAL
Corrective Maintenance
4. Click
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 114 of 122
USER TRAINING MANUAL
Corrective Maintenance
5. Click Continue
Note:
The system will automatically take current system date and time for
confirmation.
You can change the date as well as the time if they actually differ.
The Complete notifctns check box is ticked by default. When ticked the
notification for the order will automatically be completed when the order is
completed. If not ticked, you will have to go to the notification and complete it
separately.
The system displays the message “Order XXXXXXXXXX saved with notification
XXXXXXXXXX”
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 115 of 122
USER TRAINING MANUAL
Corrective Maintenance
Note 1:
Once you complete the previous step user status will change automatically
from11 RDTC Ready to TECO to 12 MTCL Maintenance Close
Note 2:
Once the order is set for technically complete you will see the status is assigned
as “TECO- Technically completed”.
The system will give a warning message, if by any chance the task in the
notification is not completed when you are setting the order as technically
complete.
After the work order is set for technically completed, even in change mode it is
only displayed (no changes can be made)
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 116 of 122
USER TRAINING MANUAL
Corrective Maintenance
SCENARIO
Sometimes you want to know how many PM orders have been created in a particular
time period and what the planned cost is.
INSTRUCTIONS
Follow the Menu Path: Logistics Plant Maintenance Maintenance Processing
OrderOrderList IW38–Change
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 117 of 122
USER TRAINING MANUAL
Corrective Maintenance
2. Information step:
Note:
According to how you need to run this report, choose which field in the exercise
step you need to use
Note:
If your work requires generating certain reports on a frequent basis, you can
save your time by defaulting the fields you need using Variant
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 118 of 122
USER TRAINING MANUAL
Corrective Maintenance
4. Click Execute
Note:
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 119 of 122
USER TRAINING MANUAL
Corrective Maintenance
Details
Set filter
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 120 of 122
USER TRAINING MANUAL
Corrective Maintenance
Note:
You can change the report mode from display to change mode by clicking
Change < - > Display
USER TRAINING MANUALPM – Corrective Maintenance Version 1.0 Page 121 of 122
USER TRAINING MANUAL
Corrective Maintenance
9. Click Back