Sie sind auf Seite 1von 6

Method Statement No: A008-MS-MECH-014 Issue: A0

Al RushaidConstruction Co., Ltd.

AL RUSHAID CONSTRUCTION CO. LTD.

Method Statement

Project – JUPC ETHYLENE PLANT PROJECT

Document Title:

Method Statement For Loading Of Coalescing Media

APPROVED FOR CPL BY:


Reviewed by Approved by
Rev. No.
DISCIPLINE SAFETY QA / QC FEM CM

A0
ARCC/EE/ ISSUE STATUS

A0 Issued for Approval MT Magno


Issue
Issue or Revision Description Origin By Date Checked By Date Approved By Date
Rev.

Method Statement for Loading of Coalescer Media Page 1 of 6


Method Statement No: A008-MS-MECH-014 Issue: A0
Al RushaidConstruction Co., Ltd.

TABLE OF CONTENTS

Page

1 PURPOSE 3

2 SCOPE 3

3 REFERENCE DOCUMENTS 3

4 MANPOWER 3

5 TOOLS AND EQUIPMENT 3

6 METHODS AND PROCEDURES 4

7 QUALITY CONTROL 5

8 SAFETY PRECAUTIONS 5

9 ATTACHMENT 6

Notes:
1.0 The latest revised documents shall always be used.
2.0 Any conflict between this method statement and the CPL procedure, the CPL procedure shall
be followed.

Method Statement for Loading of Coalescer Media Page 2 of 6


Method Statement No: A008-MS-MECH-014 Issue: A0
Al RushaidConstruction Co., Ltd.

1.0 PURPOSE

This method statement will serve as a minimum guideline to carry out and complete the
loading of coalescing media for Primary and Secondary Coalescers.

2.0 SCOPE

This procedure will cover loading of coalescing media for Primary Coalescers: V-
1161A, V-1161B, V-1161C, V1161D; and Secondary Coalescer: V-1162. The coalescers
are situated in DOX skids.

3.0 REFERENCE DOCUMENTS

3.1 Vendor Drawings of Primary and Secondary Coalescers.

3.2 NATCO Start, Maintenece, and Operating Manual

3.3 MS, ITP and Other Applicable Procedures


 A008-ITP-MR-001 ITP for Materials Receiving Inspection

4.0 MANPOWER

A mechanical foreman will control and coordinate the over-all activity for loading of
coalescer media for Primary and Secondary Coalescers. The basic crew will consist but not
limited to as follows:
 Media Loaders
 Rigger
 Scaffolders
 Helpers

5.0 TOOLS AND EQUIPMENT

Tools and equipment shall be made available to support continuous work. Tools and
equipment shall include but not limited to as follows:

5.1 Tools and Jigs


a) Socket wrenches f) A-frames
b) Hammer / spud wrenches g) Gap /feeler gauge
c) Bevel gage h) Hi-Lo gauge
d) Steel square i) Chainblocks
e) Straight edge j) Pipe

5.2 Equipment
a) Mobile crane (telescopic type) f) Crane
b) Water Pump
c) Air compressors
d) Water truck
e) Ventillating Fans
Method Statement for Loading of Coalescer Media Page 3 of 6
Method Statement No: A008-MS-MECH-014 Issue: A0
Al RushaidConstruction Co., Ltd.

6.0 METHODS AND PROCEDURES

6.1 Receipt of Coalescing media

6.1.1 For the amount of coalescing media to be loaded, refer to Table 1 and 2 of
pages 18/51 on the attach NATCO Startup, Maintenance, and Operating
Manual.

6.1.2 Deliver materials to staging area. Material shall be sufficient, at most, for 3
days loading works.

6.1.3 Store materials with sufficient dunnage and cover at staging area.

6.1.4 For Materials Receiving Inspection, Refer to A008-ITP-MR-001

6.2 Preparatory Works

6.2.1 Confirm by way of Work Transfer Sheet that coalescing loading can
proceed.

6.2.2 Isolate the Primary Coalescer and Secondary Coalescer for media loading.
Refer to manufacturer’s recommendation which vavle(s) to close, and what
blinds to rotate to close position. Check and confirm isolation

6.2.3 Make ready any permanent platforms on manhole openings to serve as


access for entry and pouring of media. Provide scaffolding for access if
permanent platforms are not available.

6.2.4 Install ventilating fan at openings that will not be reach by media.

6.3 Loading of Coalescing Media

6.3.1 Follow closely the manufacturers method of loading the media. For
loading sequence, refer to paragraph V of attach NATCO Startup,
Maintenance, and Operating Instructions; pages 13/51 to 18/51.

6.3.2 For Primary Coalescer the media are poured and layered from bottom as
follows:
 ¾” x ½” Gravel
 ½” x ¼” Gravel
 ¼” x 1/8” Gravel
 # 16 Garnet
 # 36 Garnet
 # 1.5 Anthracite Coal
For relative depth or height of layers refer to Fig 1 page 16/51; NATCO
Startup, Maintenance, and Operating Instruction

Method Statement for Loading of Coalescer Media Page 4 of 6


Method Statement No: A008-MS-MECH-014 Issue: A0
Al RushaidConstruction Co., Ltd.

6.3.3 For Secondary Coalescer the media are poured and layered from bottom
as follows:
 ¾” x ½” Gravel
 ½” x ¼” Gravel
 ¼” x 1/8” Gravel
 # 16 Garnet
 Activated Carbon
For relative depth or height of layers refer to Fig 2 page 17/51; NATCO
Startup, Maintenance, and Operating Instruction

6.3.4 As per manufacturer instruction, pre-backwash of coalescers is required.


Get approval from proponent when to pre-backwash. Refer to last
paragraph of page 15/51 of NATCO Startup, Maintenance, and Operating
Instruction for pre-backwash operation.

7.0 QUALITY CONTROL

7.1 ARCC QC Inspector will be assigned to attend to the quality control and quality
assurance requirement of this work.

7.2 All documents attesting to the acceptability of the work will be produced by
ARCC QC Inspector and submit to CPL/United for review and approval. Refer
to ITP-XXX

8.0 SAFETY PRECAUTIONS

8.1 Obtain the approval of the work permit from the concerned CPL/JUPC
Department before starting any work.

8.2 Fire watchers shall be at work area whenever there is hot work.

8.3 All electrical tools shall be checked and color-coded.

8.4 Continuous monitoring and inspection shall be implemented to detect and


correct unsafe practices while performing the work activities.

8.5 Provide warning sign and sufficient barricade on working area and only assigned
personnel will be allowed in the area.

8.6 Welding location shall be enclosed with wind barrier and provided with non-
asbestos fire blanket to prevent spread of any welding sparks.

8.7 Safety Officer shall monitor the work activities to help and to protect all assigned
workers against exposure to safety hazards. He shall ensure that Personnel
Protection Equipment (PPE’s) are supplied and used and comply with
CPL/JUPC applicable general instruction and standards.

Method Statement for Loading of Coalescer Media Page 5 of 6


Method Statement No: A008-MS-MECH-014 Issue: A0
Al RushaidConstruction Co., Ltd.

8.8 Safety harness with double lanyards shall be used all the time when working at
elevated temporary platforms.

8.9 Manlift users shall be trained and certified to operate and use the equipment.

9.0 ATTACHMENTS

Attachment A NATCO Startup, Maintenance, and Operating Instruction

Attachment B Job Hazard Risk Analysis

Method Statement for Loading of Coalescer Media Page 6 of 6