Sie sind auf Seite 1von 7

ELECI 101

Question no (1). NEC Article_________ covers the use, installation and


construction specification for rigid metal conduit (RMC) and associated fittings.
Ans: - (a) NEC Article 358 (b) NEC Article 350 (c) NEC Article 344 (d) NEC Article 310

Question no (2).-Conduit can have no more than________in a single run between pull
points.

Ans: - (a) 180 degree bends (b) 270 degree bends (c) 360 degree bends (d) 90 degree
bends.

Question no (3).____________________________a conducting connection, either


intentional or accidental, which connects and electrical circuit to the earth or to some
conducting body that serves in place of the earth.

Ans:- (a) Grounded (b) Ground fault (c) Ground (d) Ground conductor.

Question no (4).-Why seal conduit system are applicable for installation in Class I
.Division 1 and 2 location.

Ans: - If sparks, arcs, or high temperatures could be present in enclosures containing


electrical equipment. The seals will minimize the spread of gases, vapors, and prevent
the passage of flame from one part of the electrical system to another. They will also
prevent an explosion in enclosure from traveling through the conduit or cables to other
locations, causing additional fires or explosions.

Question no (5).-What is NEMA, NFPA, CSA & ANSI.


Ans: - National Electrical Manufacturers Association

NFPA: - National Fire Protection Association.

CSA: - Canadian Standards Association.

ANSI: - American National Standards Institute.


ELECI 102

Question no (1). If the resistance of 1 cmil-ft of copper at 23⁰C is 10.5, what is the
resistance of 500 feet of copper wire with a diameter of .292?
Ans:- (a)1 ohms (b).0635 ohms (c) below 1 ohms (d) .0615 ohms (e) none of them.

Question no (2). Wiring at terminal blocks required to be identified by the use of


Ans;-(a) Adhesive type markers.(b)Wrap around type(c)Hand written type
(d) none of them.

Question no (3). What is the minimum acceptable size of power cable below
600V?
Ans;-(a) 2.5mm²(b) 4mm² (c) 6mm² (d) 2.5mm²

Question no (4). What maximum percentage of filling required cross-sectional


area of the raceway for three conductors as per Chapter 9, Table 1, of the NEC?
Ans;-(a) 53 percent (b) 31 percent c) 31 percent (d) 40 percent.

Question no (5). What is the basic formula used to determine the voltage drop?
Explain in brief.
2xLxRxI
Ans;- 𝑉𝐷 =
1000

VD= voltage drop (Base on conductor temperature of 75⁰C)

L=one-way length of circuit (ft)

R=Conductor resistance in ohms per thousand feet (from chapter9, table 8)

I= load current (amperes)


ELECI 111

Question no (1). What is area classification?

Ans: - Classified areas are locations that have a high risk of fire or explosion due to
volatile gases in the surrounding atmosphere or vicinity. These areas are divided
into different classes, divisions, and groups.

Question no (2). A location where ignitable concentrations of flammable gases


or vapors can exist under normal operating conditions.

Ans: - (a) Class I division II (b) Class I division I (c) Class II division II (d) Class II division I

Question no (3). (a) Seals minimize the flow of gas/vapors and prevent flame
from passing through conduit. They must be installed.

Ans: - (a) Within 12 inch of boundaries and enclosures that contain arcing devices.

(b)Within 18 inch of boundaries and enclosures that contain arcing devices.

(c)Within 32 inch of boundaries and enclosures that contain arcing devices.

(d)Within 48 inch of boundaries and enclosures that contain arcing devices.

Question no (4). A seal requires;

(a) Seal fitting (b) one or more plugs (c) conduit fitting (d) Vent plug
(e) One or two fiber dams (f) Sealing compound.

Ans:- (1) a,b,c,d (2) b,c,d.e (3) a,b,e,f (4) a,c,d,f (5) None of them.

Question no (5). Do not replace the pouring plug on the Seal fitting for at least
_______ hours after pouring to allow for proper drying and curing. The compound
will set up quickly if it is hot, slower if it is cold.
Ans:- (a) twenty four hours (b) twelve hours (c) Eight hours (d) Minimum two days.

ELECI 115

Question no (1). What is UPS system?


The most important use of batteries in industries is for systems that provide backup
power when the primary power fails. These systems are called uninterruptible power
supply system. Can require a large number of batteries

Or
A device that provides battery backup when the electrical power fails or drops to an
unacceptable voltage level. Small UPS systems provide power for a few minutes;
enough to power down the computer in an orderly manner, while larger systems have
enough battery for several hours.

Question no (2). ____________ in certain atmospheric concentrations


may be flammable and explosive. For this reason no smoking or open
flames are allowed in battery rooms or near batteries.

Ans: - (a) Oxygen (b) Hydrogen (c) Nitrogen (d) Sulfur dioxides.

Question no (3). A primary battery is used only for discharge. It converts

Ans:-(a) Chemical energy into Electrical energy.(b)Thermal energy to


Electrical energy(c)Gas energy to Electrical energy (d) none of them.

Question no (4). There must be a minimum working space of at least


______ in front of each battery rack or enclosure.

Ans: - (a) 1.5meter (b) 1meter (c) 2meter (d) 0.5meter.


Question no (5). A __Hydrometer is an instrument used for determining
the specific gravity of the electrolyte.

ELECI 108

Question no (1).What is creepage distance?

Ans: - The distance between the end of the cable and the point where the
conductor shields is removed.

Question no (2). Define DC High Potential Test?

Ans: - High potential test is a procedure for testing new and used cable. The test
voltage test set .The test provides a means of increasing the test voltage in small
increments allowing voltage and current indications to be read precisely .The behavioral
characteristics of the leakage current are evaluated to determine the condition of the
cable, specifically the insulation.

Question no (3).Mechanical (compression) connectors are used to make


_______

Ans :-( a) Supports and termination. (b) Splice and supports (c) Splice and
termination (d) none of them.

Question no (4).The medium voltage range is considerd ____________

Ans: - 5to 25kV (b) Above 30kV(c) 2kV to 45kV (d) 5kV to 35kV

Question no (5). The spacing of duct banks is done in accordance with the
______

Ans: - (a) NEC, Article 300(b) NEC, Article 250(c) NEC, Article 314(d) NEC, Article
310
ELECI 113

Question no (1). What do you mean by fuse?


Ans: - An electrical device that can interrupt the flow of electrical current when it is
overloaded.

Question no (2). `Which type of enclosure required for protection against


specified weather hazard & Suitable for use outdoors location?

Ans:- (a) NEMA Type 1 (b) NEMA Type 3(c) NEMA Type 3R(d) NEMA
Type 5

Question no (3). Heavy duty switches are rated __________

Ans: - (a) 30A through 1200A (b) 600A through 1200A(c) 800A through
1000A

(d) None of them,

Question no (4).What information generally found in the name plate of


disconnect switch?

Ans: - (a) Manufacture’s name or trademark


(b) Manufacturer’s type or identification number
(c) NEMA designation.
(d) Rated maximum voltage
(e) Amperage rating

Question no (5). How much DC voltage applied for safety switches are
rated at 600volts or less before placing the equipment in service?

(a) 500V DC (b) 250V DC (c) 300V DC (d) none of them.

Das könnte Ihnen auch gefallen