Beruflich Dokumente
Kultur Dokumente
TRUE OR FALSE
1. The DOT is considering two proposals for a bridge replacement project. One
alternative is a steel girder structure. The other is a concrete beam structure.
Using the information below determine which structure is the most cost effec-
tive. Both structures have a 50-year life. Use a discount rate of 7% and per-
form an alternative analysis using 4%.
Steel Alternative
Concrete Alternative
Existing Process
Process/Product A
Process/Product B
Existing Program
Determine the most economical solution(s). The team may change the
assumptions based on their variables/parameters.
Answer: Existing program as is.
5. The builder is considering three options for a technique improvement for the
labor portion of the project. The original case shown below is to continue us-
ing the existing labor methods to produce . The other two alternatives
use the value team's recommendation using the following assumptions to po-
tentially improve the labor methods to produce . Using the informa-
tion below determine which alternative is the most cost effective. The labor
method has a 4-year life. Use a discount rate of 7% to perform an alternative
analysis.
Existing Operation
1. The team leader should prepare the plan, draft an agenda, identify infor-
mation needed by the team, and prepare a budget during a pre-study
phase.
Answer: True
2. The team leader helps the owner determine who should be on the team.
Answer: True
3. The team leader should make sure that everyone attending the study has
signed the sign-in sheet.
Answer: True
4. Ideas can be generated by brainstorming on each function taken from the
FAST diagram.
Answer: True
5. The job plan will not work without the team leaders involvement.
Answer: True
6. Constraints are determined early in the job plan.
Answer: True
7. A FAST diagram can be cost loaded.
Answer: True
8. The term "value," as it relates to the field of value improvement is deter-
mined by: (circle correct letter)
a. The manufacturer
b. The buyer
c. The seller
d. The value engineer
e. The design engineer
9. The team should adjust the cost estimate upwards if the team determines
that items of scope are not included in the original estimates.
Answer: True
Answer: No
16. If the basic function of an elevator is to carry goods/people. What is an
answer when we ask "why does the elevator carry goods/people?"
Answer: To increase productivity.
17. Given: there are two types of FAST diagrams: technically-oriented and
customer-oriented. Development of each diagram can identify the basic
function and critical path functions.
Answer: Yes
Cost Model
Office building 50,000 gross square feet (sf)
ITEM Cost Worth
Basic bldg. 47.12/sf 35.80/sf
Site work 4.91 4.00
Gen. &spec
Conditions 6.42 6.00
Structural 4.64 4.75
Foundation 2.91 2.50
Structural 1.73 2.25
Architectural 14.95 9.25
Ext. wall and roof 9.59 5.00
Int. const. 3.29 2.50
Int. finishes 2.07 1.75
Mechanical 10.98 7.80
Electrical 5.22 4.00
22. What is the value index for plumbing if each fixture is worth $675?
(99 fixtures, cost = $83,500)
Answer VI = C/W 843/675 = 1.25
23. If the value index for HVAC is 0.79, how much is HVAC worth per ton?
(cost = $204,000, 13 ton)
Answer VI = C/W 204,000/13 = 15,692/ton, VI = C/W, 0.79
=15,692/W=19,864/ton