VVVMC RING ROAD

ROB STRUCTURAL QUANTITIES


Nalasopara
detail survey charges
geotechnical investigation charges
detailed design charges
item n l b d qty unit
PILE
500 64 15 960 rmt 188.4
1000 12 20 240 rmt 188.4
500 40 15 600 rmt 117.75 lift+stair
494.55

PILE CAP
lift +stair 4 9 9 1 324
for abutment 4 12 2 1 96
for pier 2 6.2 3.7 1.5 68.82
488.82 m3
pier 2 5 2 7.5 150 m3
abutment 4 11.7 1 7.5 351 m3
pier cap 2 11.7 2 2.5 117 m3
abutment cap 2 11.7 1 0.3 7.02 m3
dirt wall 2 11.7 0.3 1.3 9.126 m3
deck slab
railway portion 2 48 11.7 0.3 336.96
additional track
336.96 m3
walkway railing wall 2 48 0.15 1 14.4 m3
approach slab 2 48 12 0.3 345.6 m3
tmt reinforcement
pile 494.55
pile cap 488.82
pier 150
abutment 351
pier cap 117
abutment cap 7.02
dirt wall 9.126
deck slab 336.96
walkway railing wall 14.4
approach slab 345.6
total 2314.476 90 208.3028 MT
structural steel
GIRDER
30m span
top plate 12 24 0.6 0.025 4.3 34
web 12 24 1.2 0.025 8.6 68
btm plate 12 24 0.6 0.025 4.3 34
18m span
top plate 12 30 0.6 0.04 8.6 68
web 12 30 2.2 0.032 25.3 199
btm plate 12 30 0.6 0.04 8.6 68
total 470
gussete plate 24
gr total 494 MT
bearing 48 4 192 MT