Environmental Engineering – II
Dr.Amir Farooq
INVERT LEVEL:
SIGNIFICANCE:
Sewers must be laid at a particular slope to attain self
cleansing velocities. The required slope (while laying the
sewers) is achieved through calculations of invert levels.
INVERT LEVEL CALCULATIONS
W = CωB2
Where;
W = CωB2
Where;
Where;
Load Factor:
Fig: Method of bedding concrete pipes and load factors applicable to strength
SEWER BEDDINGS IN LAHORE (WASA)
1) Excavation
2) Bracing
3) Dewatering
4) Pipe Installation/Laying
5) Backfilling
6) Construction of Appurtenances
1) Excavation
Locate the centre line of the trench.
Excavate according to size of the trench and required gradient.
Start Excavation and construction preferably from end point.
Excavation is relatively easy from the starting
Depth increases as work proceeds (Deep excavation &
Dewatering)
Increases probabilities of run off of contractors.
2) Bracing
3) Dewatering
Required, If GWT is above the bottom of the trench.
Sheeting, bracing and pumping for de-watering) .
4) Pipe laying Laying of pipes Old method