CONTRACT NO : 010/SP/DIR/XI/2015
JOB NO : 781502
DOC NO : GGCP-00-P0-PR-013-PP
REV :2
DISTRIBUTION ORDER
CONSTRUCTION MANAGER
PROCUREMENT MANAGER
SHE MANAGER
QC MANAGER
CHIEF ENGINEERING
Page 2 of 16
JOB NO : 781502
REV :2
TABLE OF CONTENT
1. INTRODUCTION
Page 3 of 16
JOB NO : 781502
REV :2
1. INTRODUCTION
1.1. Scope
This procedure covers general requirements for ESD Dry Test Procedure as a part of pre-
commissioning procedure for Gresik Gas Cogeneration Plant (GGCP).This function is to makesure
the ESD system covering from the input element (push button local and remote) to the toll activation
(ESD valve, EDP valve, motor trip, equipment trip, etc.) is well functioning
1.2. Definition
The following words shall have the meaning indicated when used herein:
Owner : PT. PUPUK INDONESIA ENERGI
Consultant PMC : TRACTEBEL ENGINEERING S.A. &PT. CONNUSA ENERGINDO
Contractor : PT. PP (Persero) Tbk. – DIVISI EPC
Engineering Consultant : PT. REKAYASA ENGINEERING
Vendor/Subcontractor : The party that manufactures or supplies equipment and services to
perform the duties specified by the Owner or Contractor
1.4. Abbreviations
The following abbreviations are used within this document:
GGCP Gresik Gas Cogeneration Plant
EPC Engineering Procurement Construction
ESD Emergency Shutdown
XV On-off valve
Page 4 of 16
JOB NO : 781502
REV :2
: By Contractor
Preparing Detail
Review
procedure : By Owner
Application for
Instrument test
Execution work:
1. Preliminary check: Review document, pre
hocked Equipment
2. ESD dry-test procedure
Page 5 of 16
JOB NO : 781502
REV :2
Before conducting ESD dry run test, the running status of all mechanical motor related with ESD shall be
simulated at Operator Console PCS. For Gas Turbine Generator (GTG), close isolation valve fuel gas and
reset ESD valve from fuel gas system for GTG simulation on running status condition.
ESD dry run test shall be conducted from ESD push button at Control Room. Activation of ESD push
button from Control Room can be done by operator to activate ESD. ESD dry run test from ESD push
button at Control Room shall be conducted as following:
1. Simulate all mechanical motors (including air fin cooler motor) and turbine to running condition.
2. Reset all ESD valves from ESD panel. Ensure no alarm or warning on ESD panel at Control
Room.
3. Ensure all personnel who will do witness, near to the valve I equipment which will be witnessed.
Two or more Commissioning engineer should be standby at control room and MCC room.
4. Witnessed shall be executed total output of ESD.
5. Confirmation from all personnel at plant area about each valve position based on operating
condition and light indicator of each equipment t h a t will be witnessed on operating condition
also (simulating without operating equipment)..
6. Activate ESD by pushing ESD push button (ESD-001) at Control Room.
7. Confirm all alarms appear in ESD panel at Control Room.
8. Confirm all ESD valves (12-SDV-701) close and all equipment trip, appropriate with Safety
Interlock System.
9. Confirm Gas Turbine Generator trip. Confirm back feeding f rom Am urea II PKG or SS UBB
PKG automatically start after GTG trip. By check 20kV MV Switchgear (outgoing breaker must
stay closed).
10. Confirm Package boiler trip (03-ESD-201& 03-ESD-202).
11. Confirm HRSG trip (02-ESD-101 & 02-ESD-102)
Page 6 of 16
JOB NO : 781502
REV :2
5. WITNESS
Witness and approval shall be made in the presence of Owner's, PMC Consultant’s and Contractor’s
inspectors.
Page 7 of 16
JOB NO : 781502
REV :2
Page 8 of 16
JOB NO : 781502
REV :2
Date Issued :
To : PT. PI Energi
We would like to have your presence for ESD dry run test according to the following schedules
Date/Time :
Location :
Note :
Signature,
Page 9 of 16
JOB NO : 781502
REV :2
Page 10 of 16
JOB NO : 781502
REV :2
Page 11 of 16
JOB NO : 781502
REV :2
Page 12 of 16
JOB NO : 781502
REV :2
Page 13 of 16
JOB NO : 781502
REV :2
Page 14 of 16
JOB NO : 781502
REV :2
Page 15 of 16
JOB NO : 781502
REV :2
Page 16 of 16