PROJECT HSE RISK REGISTER

Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

Ite Activity Sub-Activity/ Hazards Consequence Likelihood Initial Proposed Risk Treatment (Controls) Consequence Likelihood Revise Responsibility
m Task Risk d Risk
No Score Score

1 HDPE PIPE Laying of Entrapment 5 5 25 Operator trained to the Approved as 2 2 4 Site Engineer
HYDRO Pipes, per the Construction Regulations.
TEST due to fall/
Vehicles should never be
EXTENSIO roll of pipe. overloaded. Loads should be evenly
N OF  Operators distributed, secured and not
PAEW direct field protruding beyond the sides or back
PIPE LINE of the vehicle.
NETWORK
of vision
obscured by  Reverse beeper, flashing beacon,
mirrors fitted
load leading
 Defective skids removed
to contact immediately from the line.
with other  Heavy duty gloves to be worn by
persons or operatives handling skids.
plant.  All engines guards and covers to
 Failure of be in position and secured.
Windows, lights, mirrors to be kept
lifting
clean at all times
equipment.  The cab floor to be kept clean and
Inadequate free from any obstacles which may
supervision. affect the safe operation of the
 Untrained Machine.
Operatives  Ground workers to wear Hi
Visibility Vests at all times and Hard-
Use of Hats.
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

mobile  Warning signs will be erected to


phones by alert pedestrians of
operators. Unloading/Loading Operations. 
Traffic management must be in
Displaceme place where loading/unloading is
nt of load being carried out on public roads.
Person  Loads to be tipped only on suitably
being struck level ground to prevent overturning
of skip.
by
suspended
pipe causing
serious
injury of
harm.
Defective
and broken
skids
causing
crushing of
limbs of
entrapment
of body

2 Working at Heat Stress Personal 5 5 25 Adequate supply of cool 2 2 4 Site Engineer


PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

Extreme De- injury drinking water


temperature hydration Workers undergone training
Exhaustion on heat stress
Follow the summer working
time schedule
Rotation of workers
Develop, communicate and
communicate the heat stress
plan for all workers.
Heat Stress topic shall be
included in the daily TBTs.
Provide heat stress awareness.

3 Use Vibration 4 4 16 Appropriate equipment should be 2 2 4 Site Engineer


pneumatic used. Daily inspection of the
jackhamme Noise equipment uses suitable gloves to
r to break. Dust reduce vibration in hand/fingers-
P.P.E., Proper maintenance,
Rotation of Staff, Use ear defender.
4 Use of Electrocutio 5 5 25 Ensure grinding/cutting machine is 2 2 4 Site Engineer
Electrical n hazard double insulated, in good repair,
tools. inspected confirmed ok before use.
Cables, plugs and socket must be
of correct rating industrial type,
free of defects. Electrical connection
by competent authorized electrical
person.
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

5 Work in Potential 5 5 25 Competent Supervisor to adopt and 2 2 4 Site Engineer


Confined Exposure of implement procedure approved for
Space personnel to entry and work in confined.
hazardous
atmosphere Permit to work system shall be
such as implemented
oxygen
deficiency, An Emergency response procedure
potential for and readiness to implement when
asphyxiation required.
or toxic gas
e.g. Co, H2S All persons for task must have
etc. with completed confined space training.
significant Controls must be discussed in pre-
health task tool box meeting.
impact.
Other Ensure adequate and close
hazards such supervision.
as; Poor
lighting, Standby person/ hole watch must
Restricted be trained and competent
Access &
egress.
6 Loading & Poor manual 5 4 20 Ensure proper manual handling / 2 2 4 Site Engineer
Off- handling or lifting technique. As much as
Loading/ lifting possible, ensure use of mechanical
Transportati technique, lifting aid for heavy loads. Where
on of resulting in manual lifting cannot be avoided,
Materials manual ensure adequate number of
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

handling persons in relation to load mass.


related Provide and enforce use of
injuries to adequate PPE.
workers.

7 Lifting Equipment 5 4 20 Crane erection only by the 2 2 4 Site Engineer


Operation & Lifting authorized personnel.
Lifting equipment inspected.
gear failure. Operator shall inspect the crane
Pinch point as per daily check list.
and struck Verification of the safe lifting
by the capacity of equipment, tools &
tackles should be done before
load/equip
taking in use.
ment Respect the SWL of the
Fall and equipment, tools & tackles
damage of lifting tools & tackles.
materials Rigger will perform visual
inspection of all lifting tools &
and tackles before usage.
equipment Lifting to be carried out as per
Fall of the approved lifting plan and
counter rigging study.
Guarding of all moving parts
weights including
Drawing in
into the
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

moving
parts
Toppling of
crane.
8 Unauthoris Unauthorised entry to the working 2 4
 Personal 5 4 20 2 Site Engineer
ed Access area to be reported to site
injury management.
 All barriers to be replaced to
secure access

9 Slips, Trips Cuts and 5 4 20 Workplace tidiness maintained by 2 2 4 Site Engineer


& Falls cleaning up during work, at end of
bruises day to avoid slips and trips – Clean
Laceration. as you go.
Serious  Vigilance from employees as to the
bodily injury dangers from slips trips and falls.
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

10 Noise Impact on 5 4 20 Ensure selection of equipment in 2 2 4 Site Engineer


hearing. optimum state. Carryout routine
Hearing preventive maintenance to keep
loss equipment in best state. Carryout
(operator Noise survey and classification;
helper) put signs at high noise zones
with recommendation of controls
such as use of hearing protection
PPE. Where required, put noise
screen in place around noisy
equipment/ work area in line with
best practice. Discourage
equipment being left
11 Vibration Vibration 3 4 12 Ensure equipment is in excellent 2 2 4 Site Engineer
from related state. Rotation of operation
equipment ailment, among two competent operators
numbness. to reduce vibration exposure
(Operator hazard. Use of gloves PPE for
helper) handling.
PROJECT HSE RISK REGISTER
Name of the Project Booster Pump Station with Potable and Process Water Network for MISCO Review Records
Location of the Project Oman, Suhar Port/MISCO Review Date Review Date
Date of Risk Assessment Started 25 SEPT 2018 26-09-2018 25-03-2019
Risk Assessment Carried Out by Tafseel Azimi HSE Engineer/Manager
Scope of Risk Assessment HDPE PIPE HYDRO TEST EXTENSION OF PAEW PIPE LINE NETWORK

12 Use of Cuts, 3 4 12 Ensure proper selection of tools. 2 2 4 Site Engineer


defective abrasion, Inspect tools before use.
tools/ bruise
wrong use injury to
of tools operator,
helper