Sie sind auf Seite 1von 7

Contents Question Corner

 Definition of estimating
 Types of Estimation 1. How much do you like 
architecture? 
 Taking Quantities 2. How much do you like 
your bike or car?
Estimation for Architecture   Accuracy in estimation
3. How much do you like 
Students  Units of Measurement your mom or dad?
 Method of estimating 4. How much space do you 
require to park a car, build a 
 Details of Measurement  house or a shop?
and calculation of 
Quantities

Find the answers 
on your own!

Definition of estimating 1.  Detailed Estimate 5.  Sub-Estimate

Estimate is a document that gives the quantities


of different works, the rates and the expenditure 6.  Annual Maintenance Estimate
2.  Approximate / Rough /
anticipated in a project. Preliminary Estimate

Estimation or Estimating is the process of 7.  Repair Estimate


calculating the quantities and costs of various 3.  Revised Estimate
items of works involved in a project

8.  Complete Estimate
4.  Supplementary Estimate
3 4

1
Detailed Estimate Revised Estimate
 This estimate gives item-wise  When any major change or
quantities of works, rates and alteration is made in the plan
item-wise cost anticipated. / structural arrangement

 When the estimated cost is


likely to exceed by more
Approximate / Rough / than 5% during execution.
Preliminary Estimate
Supplementary Estimate
 This estimate is prepared by
any rough method to get the  During execution of work, it
approx. cost of construction. may be necessary to do a few
extra items of work which
were not included in the
original estimate.

5 6

Sub-Estimate Repair Estimate Complete Estimate


 In the main estimate lump-sum This estimate includes in addition
In addition to periodical to the cost of construction,
provisions are made as a % of maintenance repairs are to be
construction cost to works like carried out for the damaged
electrification, sanitary & water  The cost of land, the expenses
parts of a structure such as
supply, interior decoration, Annual Maintenance towards surveying, preparation of
leveling etc.  Replacement of roof sheets, drawings, getting the approval,
Estimate
 Before taking up these minor decayed wooden items, legal assistance, registration of
works separate sub-estimates  Maintenance works such as corroded steel items, pipes, documents, payment of taxes,
are being prepared for each painting, cleaning, servicing of wires, switches etc supervision charges, insurance,
and every item in detail electrical equipment's, etc. are
to be carried out periodically. providing safety devices etc..
 Repairs for the cracked roofs,
 For such expenditures annual walls, sunshades, shelves etc
maintenance estimates are
prepared  Renewal of broken glass /
window shutters

7 8

2
Trade System
Taking Quantities (Quantity Surveying) In the trade system, the 
measurements are recorded 
Technique of computing the quantities of various trade by trade. For e.g) 
works involved in a project by any standard method. “brickwork” is a trade in the 
construction of a building Group System

In the group system, 
Systems of taking quantities measurements are recorded 
item by item.
a) Trade System
b) Group System

9 10

Importance of Inaccuracy in
What estimates are made in projects?
accurate estimates estimates is caused
1. If estimate is due to
1. Time estimates are used in scheduling
work, assigning resources and determining exceeded it becomes  Omission of items
delivery dates.
difficult to explain, to
 Changes in design
2. Cost estimates are used for budgeting. account and arrange
 Improper rates
3. Cost and benefit estimates are used in for additional money
cost/benefit analysis to determine the
 Incorrect calculation 
overall viability of a project. methods

11 12

3
Dimensions shall be
0.01 metre i.e) 1 cm
measured to the
UNITS OF MEASUREMENTS METHODS OF
MEASUREMENTS nearest….
 Metric system, based on IS : 1200
 Item-wise finished item of work

 Including materials, labour,


transport, fabrication, hoisting,
tools, machinery, overheads

 Dimensions in the sequence of


length, breadth and height or 0.01 cu m i.e) 0.1 cu ft
depth or thickness
0.01 sq m i.e) 0.1 sq ft

13 14

Quintal Kg
CU M SQ M M No.  Rolled steel joist,  Supply of stiff paint,
Channels, Steel explosives for blasting
 Earthwork  Surface dressing  String course, drip  Cutting of trees reinforcement..
course, coping
 Excavation  Jali work  Door & window /
 Cornice sanitary fittings Litre Bags
 Brickwork  Lime conc in roof
 Pargetting  Ornamental pillar  Supply of varnish, oil…  Supply of cement – bags
 R.C.C  D.P.C. chimney caps, base, of 50 Kg each
 Half-brick work flower brackets..
 Supply of timber  Brick edging
 Thin partition wall  Fixing of glass
 Lime concrete  Iron railing panes or
 Cement  Stone slab in roof  Barbed wire fence windows % nos. Tonne
Concrete
 Trestle, crates …  Supply of bricks..  Supply of bitumen, tar etc.
 Expansion,
construction joints  Painting furniture

cm Sq cm
 Welding of rails, steel,  Cutting of angles, tees,
trusses, rods etc. plate etc.
15 16

4
DETAILS OF MEASUREMENT FORM

Item No. Description No. Length Breadth Height or Quantity


or Depth Necessity of Approximate Estimates
Particulars
Preparing detailed estimates consumes a lot of 
time and manpower.

ABSTRACT OF ESTIMATE FORM Hence, Approximate estimates are prepared first 


for any project for enabling the client to decide 
Item No. Description or Quantity Unit Rate Amount
whether the project can be taken up or not.
Particulars

17 18

METHODS OF APPROXIMATE ESTIMATION

a) Service unit method or Unit cost method
b) Plinth area method
c) Carpet area method
d) Cube rate method
e) Typical bay method
f) Rough Quantity method
S.No Building Type Service Unit
1 Hostel Student
2 Hospital Bed
3 Hotel Room
4 School Class room
19 20

5
21 22

Rough Method

The approximate quantities of different items are worked 
out based on main items of work only and the cost is 
estimated assuming suitable rates.

METHODS OF MEASUREMENT
 Centre line method
 Long wall short wall method

23 24

6
Centre line method for rectangular areas Centre line method for Cross walled areas
This method calculates the total length of the walls in the building & 
multiplies it by width and depth or height to get the total quantity.
0.3m
0.3m

4.3m c/c

5.3m c/c
0.3m 5.0m x 4.0m clear 0.3m 0.3m 0.3m

0.3m
0.3m
5.3m c/c
9.6m c/c
Total length of wall = (2 long walls + 2 short walls)c/c
Total length of wall = (2 long walls + 3 short walls)c/c 
– 2 x (0.5width of the wall)c/c

25 26

Centre line method Long wall & short wall method
This method calculates the total  This method is sometimes 
length of the walls in the  referred as out‐to‐out and 
building and multiplies the same  in‐to‐in method. 
by width and depth or height to 
LONG   WALL (L)
get the total quantity.
SHORT WALL (B)

SHORT WALL (B)

LONG   WALL (L)
Area = (2 Long walls + 2 short
walls ) X width of the wall

27

Das könnte Ihnen auch gefallen