Part A ( Main Villa Remedial Works)

Sl. Description Action Date Remarks


No
1 Contract Agreement issued to - - Completed
IKA
2 Specification (Draft) Priya/IKA - Comment sent,
Pending from IKA
3 IFC Specification IKA Pending
4 Design Drawing IKA - Received
Micropile (BDF)
1 Quotation from BDF - - Received
(Preliminary )
2 Final Quotation Awaited BDF Pending
3 Design submission BDF Pending
4 Piling Method Statement - - Received &
including Risk Assessment submitted to IKA
5 Works Program (Piling Works) BDF Pending
6 LPO Nass Purchase Pending
Dept.
7 Preparatory Works to start piling Nass Site Team - To plan.
works
NASS Contracting
1 Site Visit - - -
2 Work Programme BM Pending
3 Site mobilization Plan PM/BM Pending
4 Resource planning BM Pending
5 Temporary Protection /Isolation BM/Site Team Pending
6 General Method Statement BM Pending
7 Budget Preparation BM Pending
Al Retaj – Client’s Representative

1 Appoint Project Coordination


2 Removal of Finishes & Fixtures

Part B (Soil Improvement of Internal Swimming pool)

1 Quotation from IKA IKA Pending


2 LPO to IKA IKA Pending
3 Design from IKA IKA On going