Sie sind auf Seite 1von 11

Proceedings of Bridge Engineering 2 Conference 2010

April 2010, University of Bath, Bath, UK

A CRITICAL ANALYSIS OF THE VICARIA ARCH BRIDGE YESTE,


ALBACETE, SPAIN.
D. M. Quirke1
1
Undergraduate Student – University of Bath

Abstract: This paper examines the deceptive structural function, aesthetics and interesting construction
technique of the Vicaria Arch Bridge, Yeste, Albacete, Spain. British standards are used for the analysis of the
loads acting on the bridge and Fritz Leonhardt‟s ten rules, from his renowned work „Bridges‟ are used to
consider the aesthetic qualities of the bridge.

Keywords: Vicaria Bridge, Weathering Steel, Self compacting concrete, Arch.

1 Introduction

La Vicaria Arch Bridge (See Fig. 1) spans the Rio


Segura (River Segura) roughly 20km southwest of
where it meets Embalse de la Fuensanta (Reservoir of
Fuensanta), near Yeste in the province of Albacete,
Spain. The bridge was designed by Ferrovial-Agromán,
who claim to be “one of the world‟s leading private
developers of transport infrastructure”, to enable a new
route between Yeste, Letur and the neighbouring area
to the east, to offer an alternative to heading north and
around the reservoir and over the dam at the reservoir
(see Fig. 2), saving roughly 50 minutes. The design
was led by Santiago Perez-Fadón, José Emilio Herroro
and Luis Martín-Tereso as Technical Director, Head of
Civil Engineering and Project Manager respectively for Figure 2: Previous route across reservoir/river.
Ferrovial. It was actually the dam owner who decided
to commission a symbolic bridge that required La Vicaria Bridge is a tied through arch, where the
minimum maintenance possible, to address the arches are hollow weathering steel sections filled with
separation and extended route to local inhabitants self-compacting concrete spanning 168 metres with a
caused by the building of the dam back in 1932 and the 48 metre rise. The bridge‟s total length is 258 metres,
bridge now retraces a road present before the dam and consisting of two approach spans of 20 and 25 metres
reservoir were present. either side of the main 168 metre span (see Fig. 3)

Figure 3: Elevation overall dimensions.

The construction of the bridge began in August


2005 and was built and ready to be load tested by
Figure 1: Vicaria Arch Bridge. September 2007. The bridges 11 metre wide deck
consists of two lanes for traffic, one in each direction
1 and two pedestrian walkways either side of the bridge.
Mr. Daniel Michael Quirke – dmq20@bath.ac.uk
2 Aesthetics deck has a constant depth of 1m and the arches‟ depths
vary from 1.2m to 2.4m, and therefore always have a
The design and aesthetic appeal of this bridge are greater depth than the arch. This does not however take
not revolutionary, as arches are one of the oldest into account the visual affect of the parapets. Despite
structural forms used to enable greater spans and this looking at Fig. 1, the arch definitely comes across
according to Jean M. Muller “Instinctively one would as the dominant feature.
say that an arch bridge is one in which form follows
function” [1] this is due to the fact that the arch that 2.1.3 Order
experiences no bending under a constant uniformly Order in the structure is created by the hangers and
distributed load (udl), is a parabolic one, which is the cross-braces particularly noticeable when crossing the
shape a chain will find naturally if hung from its two bridge, rather than looking at it from far.
ends, therefore an arch is used due to its function rather
than elegant form, which can be seen as a bonus. 2.1.4 Refinement and colour
The aesthetical analysis of the bridge shall be done Detailing was taken very seriously on the bridge,
so in accordance with Fritz Leonhardt‟s ten rules, from such that he finer details, like the hanger connections
his renowned work „Bridges‟. were hidden in both the deck and arch.
Looking at the bridge it is not immediately
obvious that the arches are tied, due to the fact that the 2.1.5 Integration with the environment
arches carry on past the deck to the ground, rather than The key reason weathering steel was used as a
having a vertical support at either end of the arch. finish on this structure, was due to the requirement for
Unlike the Apollo Bridge, Bratislava, Slovakia, where minimal maintenance, however its natural earthy tones
it is quite obvious that the deck is tied due to the fact also happen to compliment its surroundings along with
that the supports at either end of the arch are vertical its flowing nature which also suits the environment.
(see Fig. 4). Therefore the Vicaria Bridge could be The flowing nature of the bridge comes about due to
deemed to be not structurally honest; however this also the fact that the bridge is an arch, which is a natural
gives the structure a flowing continuity not present in shape itself.
most tied arch bridges with vertical supports. The
advantages of doing this are that there are no large 2.1.6 Character
horizontal forces in the ground that the foundations Character is a very subjective value to quantify,
must carry if the arch was not tied and the improved however the Vicaria Arch Bridge, seems to have a
aesthetics, however the curved supports beneath the certain understated yet refined character about it.
deck must carry the vertical load to the foundation,
which induces a moment in the foundation, as the 2.1.7 Complexity and surface texture
points where the bridge is being supported is not From looking at the bridge it seems very simple to
directly above the foundation. understand how the bridge is working, however as we
know the bridges function is not as first meets the eye,
however as the aesthetics are being considered, then it
must be said that the bridge does have a certain
simplicity about it.

2.1.9 Summary of aesthetics


The form of the bridge is not revolutionary,
however it is effective and works well in the
environment in which it is located, it is also highly
efficient and elegant in doing so, hence why it is so
slender.
Figure 4: Apollo tied arch bridge.
3 Foundations and Geotechnics
2.1 Leonhardt Fritz Analysis
After an extensive geotechnical survey it was
2.1.1 Fulfilment of function found that the rock base was limestone, however the
The bridge clearly serves its function, due to the rocky base of the west bank required consolidation
fact that it is still standing, however just not as one around the abutment, which is closed to prevent land
would intitially imagine looking at it. The bridge also sliding in from the front side, alternatively the
has a slender, but safe look about. abutment on the east bank is almost completely
underground and open. The concrete bases in which
2.1.2 Proportions the arches are anchored are reinforced by 28 high
Leonhardt stated that the arch should be the strength steel bars that run from the concrete in the
dominant feature on an arch bridge, by ensuring that it arches to that of the foundations ( see Fig. 9) , and the
is of greater thickness than the deck, which it is as the smallest of the concrete bases is 6m×7m×5m.
4 Structural Design

The structural precedent of this bridge obviously


comes from many arch bridges that have come before,
despite this the bridge is fairly unique in it‟s structural
function, as looking at it one would immediately think
that it is an untied through arch where the foundations
take all of the horizontal and vertical force, whereas it
is actually a tied arch cantilevered off the banks at
either end. Fig. 5 shows how a conventional tied and
untied through arch bridge look and work, and how the
Vicaria actually acts despite looking like a
conventional untied through arch. The arch of a
conventional untied arch bridge continues all the way
to the foundations such that the foundations must
restrain the arches thrust in both the horizontal and
vertical directions, this is often avoided as foundations
Figure 6: Arch Section.
capable of dealing with horizontal forces can be
expensive especially if poor geotechnical conditions
The bridge piers are “Y” shaped reinforced
are present. The arch of a conventional tied arch bridge
concrete (see Fig. 7) and were cast in situ. There are
stops at the deck with vertical supports at either end,
two piers at either end of the bridge located 20m from
the arches only require vertical restraint and no
the abutment where the deck starts and a further 25m
horizontal restraint as the horizontal component of the
along at the beginning of the arches (see Fig. 3), they
arches thrust is restrained by the deck, therefore
vary in height due to the sloping nature of the valley in
meaning the deck is acting in tension. Finally the
which the bridge sits, however the supports at the
Vicaria arch bridge looks like an untied arch bridge,
beggining of the arch are 24.3m in height. The deck is
due to the fact that the arches continue all the way to
connected to the piers, through the transverse beams
the ground, however the arch is tied into the deck and
which are box sections at the piers, rather than
there is therefore only a vertical force at either end of
“I”sections elsewhere along the deck.
the arch, which must be carried to the foundations by
the inclined members that appear to be a continuation
of the arches, however these are not directly above the
foundations and therefore induce a moment as well as a
vertical force in the foundations. This unconventioanl
function was largely driven by choices made in order
to construct the bridge which shall be explained in the
next section.
The Bridge‟s main structure is two, two pinned
arches inclined 10° from the vertical into the centre of
the Bridge, where they are horizontally braced to each
other by 6 beams of a similiar outer section as the main
arches. The arches are actually polygons consisting of
63 hollow weathering steel box sections each roughly
3m long, welded together and filled with HM-35 self-
compacting concrete, meaning it has a characteristic
strength of 35 Mpa. The hollow sections are formed of
four folded metal sheets welded at their edges, have a Figure 7: “Y” shaped reinforced concrete piers.
constant width of 1.2m and depth that varies from 1.2m
in the central 100m to 2.4m at the arches ends, as All in all the bridge is an efficient one, with a span
shown in Fig. 6. The arches are anchored at their ends to deck depth ratio of 134, however the deck depth
into the reinforced concrete bases. does not include the parapets as they serve no
The deck, which is a reinforced concrete slab with structural purpose unlike in a through truss for
two 1m deep steel U-section beams longitudinally at instance. The efficiency of the bridge shall be
it‟s edges, connected transversely every 3m by I considered in greater depth in the structural analysis
beams, is suspended from the deck by 85mm mild steel section of this report.
cables wrapped in mortar filled polyethylene sheet in
plane with the arch roughly every 9m.
i. ii. iii.

Figure 5: Arch Force Distributions, Conventional untied arch (i), Conventional tied arch (ii), Vicaria arch (iii).

5 Construction done by diverting the water, using drains, passing both


the reservoir and dam, as the Segura water board also
Traditionally speaking the efficiency of arches, has used this opportunity to carry out works on the dam
been countered by the difficulty of constructing them, itself. Once the reservoir was empty a temporary work
due to the fact that an arch cannot support itself until platform was built on the reservoir bed.
the crown at its centre is in place, therefore requiring Firstly the longitudinal and transverse beams
significant formwork to support the arches until this of the deck that lie between the arches were welded
point, this however has changed in modern times, with together on the temporary work platform and restrained
the development of building methods, such as every 9m by supports on the temporary works
cantilevering and rotating. Despite this these are both platform. The wethering steel box sections of the arch
quite complex with slender, inclined arches and were then welded together into sets of six to form
falseworks and cranes were deemed to be troublesome, roughly 18m sections and falsework tower were
due to the remoteness of the site and 60m working assembled every 18m at the location of every other
height over the reservoir bed respectively, as it was hanger. Once the 18m sections were ready and towers
also decided that the reservoir would have to be empty assembled, the assembly begun from the outside into
for the construction process. Therefore it was decided the centre, by welding the outer most sections of the
that the bridge would be constructed as 3 independent arch to the deck with structural braces whilst the
structures in tandem. These being a cantilever structure section were leant against the first towers. Working
on either side of the bridge, which were constructed in inwards the next sections were then provisionally
their final position and consisted of the ground works, bolted to the previous sections and placed on the
arch below the deck and deck up to the point that the following towers, until the whole arch was formed at
arch and deck crossed. The third of these independent which point all joints were welded. Finally the six
structures being the tied arch itself, which was cross braces were welded into place at the location of
constructed on the reservoir bed and encompassed the all the formwork towers, allowing the formwork towers
section of the arch above the deck and the section of to be removed.
deck that fell inside the arch. Once the construction of The hangers were then put into place and
all three structures was complete the tied arch was then tightened until the catenary of the deck induced by it‟s
hydraulically jacked up into position and welded to the own deadweight was no more.
two cantilever structures, Fig. 8 shows the arch being
jacked into position. This approach limited the 5.2 Approach span and arch cantilever construction
cantilevering, amount of falsework required and both
the number and size of cranes required. Firstly the approach spans were constructed by
craning the longitudinal and transverse steel of the
deck, which had already been welded together, into
place, with the road level abutments at one end and
piers at the other. Then the transverse box sections
positioned above the piers were filled with concrete,
the precast slabs of the deck were laid, allowing the
decks reinforcement to be placed and the rest of the
slab to be cast in situ. The guy lines at the abutment
were then tightened, therefore securing the deck.
The box sections for the cantilevered section of the
arch were assembled on the reservoir bed, before being
craned onto the arch foundation, where they were then
fixed to the 28 bars in the foundation (see Fig. 9). Once
Figure 8: Tied arch being jacked up into posistion. this had all been done a brace was posistioned and
welded into place inbetween the two cantilevered
5.1 Tied Arch Construction sections of arch at either end of the bridge.

As previously mentioned the reservoir had to be


empty to enable the construction of the bridge, this was
Once the approach span and cantilevered sections
were constrcuted the longitudinal and transvers steel of
the section of deck between the approach span and the
tied arch could be craned into posistion, by firstly
lowering and joining the rear end to the approach span
and then resting the other end on the brace between the
two cantilevers (see Fig. 10).

Figure 12: Two jack jacking one end of the arch (left).
Figure 13: Steel stop being compressed between tied
arch and deck on cantilevered structure (right).
5.5 Concrete casting in the arches and deck

The final stage of construction was to cast all the


concrete in the structure. Due to the slenderness of the
arches it was decided that they could not be vibrated
and that self-compacting concrete would have to be
Figure 9: Arch foundations and fixing steel (left). used. It was not possible to cast an arch in one day, due
Figure 10: Posistioning section of deck (right). to local limitations in concrete production. The arches
were therefore cast in two non consecutive day long
5.3 Jacking periods, to ensure the first days casting was set before
the second begun, to minimise the pressure acting on
Once all the previous parts were constructed, four the arch box section. This also meant that the concrete
hydraulic jacks could be set up, two on both of the supply could be dealt with by two local production
cantilevered structures at either end of the tied arch. plants, located one hour from the site. Once the arches
The tied arch was then connected to the jacks by had been cast the precast slab could then be positioned
hoisting cables and the tied arch was then jacked up on the deck, allowing the reinforcement to be placed
into place. The whole jacking process was and the rest of the slab to be cast in situ from the centre
computerised to ensure the process ran smootly (see outwards.
Fig. 11 and Fig. 12).
6 Loading
5.4 Joining the whole structure together
All bridges must bear the same combinations of
At this point the three independent structures had dead, superimposed dead, and live loads along with
to be welded together, whilst still being held in place wind, creep and temperature effects and therefore must
by the hoisting cables and guy-lines. The welding at be considered for the Vicaria Arch Bridge. BS5400-
each bank could not be done in tandem and each banks 2:2006 [2] shall be used to calculate the loads
welding took a week. During which time the bridge experienced by the Vicaria Arch Bridge. Table 1 shows
was moving a lot, due to thermal effects, which was the load combination specified in clause 4.4 [2] that are
not an issue until it came to welding the final joints; as applicable for highway bridges and therefore this
all joints up to this point were relatively free to move bridge. This report shall not be considering Bearing
to the required position. This problem was overcome Friction or Secondary Live Loads, therefore only Load
by positioning steel stops, as seen in Fig. 13, in the combination 1, 2 and 3 shall be considered.
joint that was due to be the last welded at the time of
hoisting. Therefore allowing the guy-lines to be Load Combinations
severed at the opposite end and abutment to be released 1 2 3 4 5
during the joining process, which released the tensile Permanent Dead Load     
forces holding the structure in place, which in turn Primary Live Load    
Load Types

compressed the steel stops where they came to lie ( see Secondary Live Load 
Fig. 13), enabling the final welds to be completed. Wind Load 
Erection  
Temperature 
Bearing Friction 
Table 1: Clause 4.4 [2] load combination.
Figure 11: Schematic of the whole jacking process and forces present during the jacking process.
Once all of this had been established, it was then
6.1 Permanent Dead Loads possible to calculate that 2838m3 of the regular
concrete in the structure was in the deck, which is quite
6.1.1 Structural Dead Load simply 1m×11m×258m. On the assumption that the
The permanent dead load of the structure is its distribution of mild steel is the same as of that of the
self-weight. Section 2 of [3] tells us the following concrete throughout the structure, then there would be
information featured in table 2. roughly 220 × 103 kg in the deck, however there is also
the transverse beams every 3m to account for and it
Material Volume or Mass shall therefore be assumed that 300 × 10 3 kg of the
3
Weathering Steel 890 × 10 kg steel in the structure is in the deck. All of which plus
Mild Steel 480 × 103 kg the assumptions that all of the load is distributed
Regular Concrete 6150 m3 evenly around the whole of the deck and that concrete
Self-compacting Concrete 600 m3 has a density of 2400 kg/m3, leads to a values of 24
Table 2: Structural materials of bridge. kN/m2 of deck for concrete and 2 kN/m2 of deck for
steel.
Unfortunately there seems to be no source stating
the thickness of the hollow weathering steel box 6.1.2 Superimposed Dead Load
sections or longitudinal beams that run along the edge The superimposed dead load consists of all the
of the deck, which are the only weathering steel in the other permanent loads that do not serve a structural
structure. It is however possible to calculate the total function on the bridge. For this bridge that will just be
length of weathering steel box sections in each arch, the bridge surfacing and street furniture accounting for
which is roughly 200m. From knowing this and the the hand rails and so forth. We shall assume the bridge
amount of self compacting concrete in each arch it is surface is 100mm thick asphalt all over which account
possible to calculate that there is an average of 1.5m 3 for the road and pedestrian walkway surfacing, with
of concrete in every metre of arch. This in turn gives a the same 2400 kg/m3 density as concrete and
depth of 1580mm and total steel perimeter of 6140mm conservatively that the street furnishing contribute
for the average hollow weathering steel section. Finally 0.5kN/m2 to the whole surface of the bridge.
if it is assumed that all of the weathering steel in the
structure has a constant thickness of 30mm, then the Bridge Surfacing
weathering steel of the arches weighs 630 × 103 kg of 2400 kg/m3 × 0.1m × 1m × 1m = 240kg/m2
the total 890 × 103 kg of weathering steel in the = 2.4kN/m2
structure, and the longitudinal beams of the deck weigh
260× 103 kg, with a section as detailed in Fig. 14. 6.2 Primary Live Loads

6.2.1 Primary Vehicular Live Loads


The vehicular live loads that the Vicaria arch
bridge shall be checked for are those due to HA and
HB loading, specified in clauses 6.2 and 6.3 [2]
respectively. Where clause 6.1 [2] states HA represents
normal traffic and HB represents abnormal vehicle unit
loading.
The UDL per notional lane due to HA Loading is
calculated below in Eq. (1).

(1)

As the carriageway width is 7m and therefore less


Figure 14: Longitudinal U-beam section (mm). than 7.6m the maximum number of notional lanes is 2
page 172 [4], meaning the total load for the
carriageway is 41.32kN/m and that the knife edge load
(KEL) should be taken as 120kN per notional lane in (8)
accordance with clause 6.2.2 [2].
It could well be that this bridge has been designed
to deal with the kind of loading that can be expected (9)
due to HB vehicles, however it is highly unlikely due
to the fact that the bridge was designed and built to
improve local economy where abnormal vehicles Finally the nominal longitudinal wind load, PL, can
requiring police escort would not be expected, is be calculated using Eq. (12) by firstly calculating the
relatively small in terms of carriageway width and nominal longitudinal wind load on the superstructure,
there are alternate routes available, therefore HB PLS, and the nominal longitudinal wind load on the live
loading will not be considered in this paper. load, PLL, using Eqs. (10 and 11) respectively. Eqs. (10,
11 and 12) can all be found under clause 5.3.4 [2].
6.2.2 Pedestrian and Cyclist Loads
As the loaded length is in excess of 36m, Eq. 3 (10)
must be used to calculate the nominal pedestrian live
load; however Eq. 2 must be used first to calculate k,
clause 6.5.1.1 [2]. (11)

(2)
(12)
(3)

There are two 1.75m pedestrian walkways on Any unstated values can either be found or
either side of the bridge, which therefore contribute calculated from equations stated within clause 5.3 [2].
6.83kN/m to the total live load of the bridge. Now that all wind loads have been calculated they can
now be combined in accordance with clause 5.3.6 [2],
6.3 Wind Loading table 3 below shows these combinations.

The method and Eq. (4) used for calculating the


maximum wind gust speed, Vd, are set out in clause Load Loads and Worst Case
5.3.2 [2]. For this method the site hourly mean wind Combination Factors Result (kN)
speed Vb is required and having looked at the National a Pt 1216.38
Meteorological Institute‟s forecast for Yeste [5] it has b Pt ± Pv 2680.91
conservatively been taken to be 25m/s. Before being c PL 393.1
able to calculate Vd the gust factor, Sg, and site hourly d 0.5Pt + PL ± 0.5Pv 1733.56
mean wind speed, Vs, must be calculated using Eq. (5) Table 3: Wind Load Combinations.
and Eq. (6) respectively, which can both be found in
clause 5.3.2 [2], alongside all the other values needed 6.4 Temperature Effects
for the equations.
When the temperature any bridge experiences
(5) increases or decrease, it expands or contracts
respectively, however the surrounding area in which it
is located does not do the same. This generally
(6) speaking results in an increase in compression or
decrease in tension within the structure, depending how
the structure is working, if expansion occurs.
(4) Alternately if the structure contracts compression
decreases or tension increases, once again depending
how the structure is working. Fortunately pot bearings
Using the maximum wind gust speed, Vd, it was
and an expansion joint were fitted at one end of the
then possible to calculate the dynamic pressure head, q,
bridge, which allow for these temperature changes, by
which can be found using Eq. (7) as the wind load
allowing one end of the bridge to move rather than
offers no relief and only an additional load, clause
imparting a smaller or larger load at the abutments and
5.3.3 [2]. Calculating q enables the nominal transverse
in turn back into the structure itself. Despite this
wind load, Pt, and the nominal vertical wind load, Pv, to
bearings and expansion joints require maintenance to
be calculated with Eqs. (8 and 9) respectively. Both
ensure they do not get stuck and prevent the bridge
can also be found under clause 5.3 [2].
moving and variations due to temperature still must be
checked to ensure they are within a respectable
(7) amount.
The method set out in clause 5.4 [2], requires Load ULS SLS
effective bridge temperatures for design purposes to be Dead (kN/m) 326.7 286
derived from figures also featured in the clause, Superimposed Dead (kN/m) 51.6 36.2
however these are unfortunately not available for Vehicular HA UDL (kN/m) 62.0 49.6
Spain, so conservative values have been taken [6]. As Vehicular HA KEL (kN) 180 144
shown in Table 4, alongside the effective temperatures Pedestrian and Cyclist (kN/m) 10.2 6.8
derived from Tables 10 and 11[2]. Table 6: Design loads for load combination 1.

Load
Assumed shade Effective Bridge Limit
Load Combinations
air Temperature Temperature State
1 2 3
Minimum -6.2 °C -8 °C Ultimate 1.05 1.05 1.05
Maximum 35.6 °C 50 °C Steel
Service 1.00 1.00 1.00
Table 4: Assumed and Effective Bridge Temperatures. Dead
Ultimate 1.15 1.15 1.15
Concrete
Service 1.00 1.00 1.00
The coefficient of thermal expansion for steel and Ultimate 1.75 1.75 1.75
concrete, αS and αC, shall both be taken to be 12×10-6 Super Surfacing
Service 1.20 1.20 1.20
from page 190 [4]. So if the outside temperature where -imposed
Ultimate 1.20 1.20 1.20
the bridge is located is assumed to be 20°C, then Dead Other
Service 1.00 1.00 1.00
maximum variations the bridge will experience are
30°C and -28°C. Eq. 13 below is used for calculating Ultimate - 1.10 -
Wind
the strains due to temperature effects. Service - 1.00 -
Ultimate - - 1.30
Temperature
(13) Service - - 1.00
Vehicular Ultimate 1.50 1.25 1.25
All of which result in strains of 360μ and -336μ in HA Service 1.20 1.00 1.00
both the steel and concrete, the extensions these Ultimate 1.50 1.25 1.25
Pedestrian and Cyclist
induced in the main structural elements can be seen in Service 1.00 1.00 1.00
Table 5, where positive values represent an increase Table 7: Relevant γfL values for load combinations.
and negative represent a reduction in length.
7 Structural Analysis
Assumed shade air
Temperature It would be possible to check every aspect of this
-6.2 °C 35.6 °C bridge with every load case, however for the sake of
Deck, 258m -86.7 mm 92.88 mm this paper the key aspects shall be considered with the
Arch, 200m -67.2 mm 72 mm ULS load case of load combination.
Longest Hanger, 24m -8.1 mm 8.6 mm
Table 5: Expansion and contraction due to temperature. 7.1 Tied Arch Analysis

From looking at these values it is safe to say that The main structural component of this bridge is the
the expansion joint and bearings could deal with such tied arch central span. The worse case loading for an
temperature effects. The other elements that must arch is one half to be fully loaded and minimally
withstand the temperature effects without bearings or loaded in the other, which for this bridge is the total
expansion joints, would only be subject to nominal ULS dead load (189.2 kN/m per arch) being applied to
stresses of 72N/mm2 and -67.2N/mm2 in the steel and the whole arch and the total ULS live load (36.1 kN/m
10.8N/mm2 in the concrete, which can only bear per arch) being applied just to one half, as shown in
compression, meaning all tension would have to be Fig. 15, where the arch is being considered
carried in the steel of the structure and would therefore independently. The load arrangement results in a
also be fine under the temperature effects. maximum moment occurring at a quarter way into the
span.
6.5 Design Load 36.1 kN/m
In reality all load combinations would be Live Load, Wlive
189.2 kN/m
considered, however for this paper only load
combination 1 has been. Table 6 below shows the
design loads for load combination 1, all of which were Dead Load, Wdead
calculated in accordance with the partial load factors,
γfL, found in Table 1 [2]; Table 7 includes the relevant
values from Table 1 [2] for load combination 2 and 3
also. Figure 15: Arch critical load diagram.
As a constant UDL, such as the dead load shown 7.2 Moments in Foundations
above, induces no moment in an arch it is reasonable to
model the arch as shown below in Fig. 16 and assume Assuming that a maximum UDL, Wlive+dead, of 225
the redistribution of the live load, also as shown in Fig. kN/m acts along each side of the deck then Eq. 16 can
16. be used to calculate the maximum load each cantilever
Wlive must experience.

(16)

If each cantilever experiences 21.7MN at the


Wlive/2 bridge deck then the concrete base in which the arch
sits a perpendicular distance of 25m away, must
Wlive/2 therefore experience 543 MNm. Fig. 18 shows the
reactions acting on a concrete base and the centre of
rotation.
Mmax

Figure 16: Arch loading, redistribution and bending.

The bending moment for a ½ load arch can then be


calculated using Eq. 14.

(14)

This value can then be multiplied by γf3, which for


ULS calculations is 1.1 and accounts for errors in
analysis, to give a maximum bending moment of
17512 kNm.
The arches second moment of area must now be
Figure 18: Forces acting on concrete base.
calculated, so that that the stresses in the arch induced
by the maximum moment can be calculated, to ensure
As the smallest concrete base is 6m×7m×5m, the
that it is within an acceptable limit. Assuming that the
minimum possible load that one of the concrete bases
steel section of the arch is perfectly rectangular with
can impart is 5MN at a distance of 3.5m from the
plate thickness of 30mm, the average depth as
centre of rotation, therefore only offering 17.6 MNm of
previously calculated to be 1580mm is applicable and
moment resistance. Which therefore tells us that the
the breadth is 1200mm, then the second moment of
concrete bases rely on the weight of the soil plus the
area for the steel section of the arch is 0.061m4. This
embedment of high strength steel into the soil to resist
then enables the stress in the outer most fibres of the
the moments induced, due to the force carried from the
steel to be calculated using Eq. 15.
top of the cantilever structures.

(15) 8 Serviceability

Comparing this to a factored design strength of Seeing as the bridge is not of the highest profile it
238N/mm2 (characteristic yield strength of is not continuously monitored, however in light of the
275N/mm2), which is fairly conservative, the section fact that it bears the ultimate limit state loading fairly
proves strong enough to bear the worse case loading. comprehensively, which in reality is almost definitely
Fig. 17 shows the actual load test of the bridge, where not going to occur, then it should also fair even better
one half is fully loaded with haulage lorries and the under the serviceability limit state. Despite this the
other half is empty. bridge is accessed annually by inspecting the key
connections for damage or corrosion and by also
checking the tension in the hangers to ensure that the
dead weight of the deck is being transferred to the arch,
as it should be to ensure a gradual failure of the
structure does not occur.

Figure 17: Load test to induced critical moment.


9 Natural Frequency reservoirs banks before being floated into place if
craning it into place off the reservoir bank was not
The natural frequency of a bridge is a very desirable, like was done on the Apollo bridge (see Fig.
important feature, as if it matches that of the wind, the 4). Despite this if this approach were to have been
bridge will oscillate, with potentially fatal results and taken then the visual aspect and flowing nature would
catasphropic failure of the bridge, most notably as appealing or striking.
Tacoma Narrows. The millennium bridge also had
problems with the natural frequency; however this was 13 Conclusion
induced by the users walking in rhythm, rather than the
wind. As well as fear of failure oscillating bridges are Despite not being of significant size or profile, the
also undesirable for the bridge users‟ comfort. Eq. 17 Vicaria Arch Bridge is a very interesting and an
can be used to get a rough idea of the bridges natural effective one largely due to its unusual structural
frequency, ωn. function, driven by an interesting construction method
and aesthetic desires, due to it rare weathering steel
(17) finish, which suits the earthy tones of its surrounding
supremely well and also due to the fact that it serves
For this bridge ωn came out to be roughly 7.4Hz, the age old brief of reuniting two communities, that
which is acceptable, as if it is any less than 5Hz it have been divided since the construction of the dam
could be prone to oscillations in the wind. and reservoir in 1932, excellently. Finally most general
information discussed in this report was found in a
10 Creep report produced by Ferrovial-Agromán [3].

Due the location of the bridge and potential for the References
water level to rise fairly high up the arches, water
tightness was of paramount important during their [1] National Research Council (U.S.), Bridge
welding process, due to this the moisture loss and aesthetics around the world [online] available
therefore shrinkage of the concrete in the issues is not a from:
significant issue for the bridge. Creep is also of very http://books.google.co.uk/books?id=9nxWh68
little concern for the same reason. ut3AC&pg=PA18&lpg=PA18&dq=Instinctiv
ely+one+would+say+that+an+arch+bridge+is
11 Durability and Vandalism +one+in+which+form+follows+function”&so
urce=bl&ots=VjBWnsKiZd&sig=Oiar91wpx
At the time of writing this paper the bridge had KpeN53zcL8g5jCM5nc&hl=en&ei=gt-
been open for less than four years, and it is therefore uTd2XPMnDswb92s3hDA&sa=X&oi=book_
fairly difficult to judge the Durability of the bridge. result&ct=result&resnum=1&sqi=2&ved=0C
Despite this the bridge shows no signs of vandalism or BYQ6AEwAA#v=onepage&q=Instinctively%
problems with its durability. The maintenance of the 20one%20would%20say%20that%20an%20ar
bearings will be of key importance to the durability of ch%20bridge%20is%20one%20in%20which
the bridge, due to the fact that the bridge is in Spain %20form%20follows%20function”&f=false
and therefore can experience hot days and also fairly [Accessed 29th March 2011].
mild nights, giving a fairly significant daily variation.
Despite all this one of the criteria for the bridge was [2] BS5400-2: 2006. 2006. Steel, concrete and
that a minimum amount of maintenance should be composite bridges – Part 2: Specification for
required and for this reason, it should be expected that loads. British Standards Institute.
durability should not be an issue even with very little
maintenance, where many decisions were influenced [3] Ferrovial-Agromán, PUENTE ARCO MIXTO
by this such as the fact that the arch-deck connection DE LA VICARIA SOBRE EL EMBALSE
was designed to ensure bridge adaptability during DE LA FUENSANTA [online] available
construction and throughout its service life and use of from:
weathering steel. http://e-
ache.com/modules/ache/ficheros/Realizacione
12 Suggested Improvements s/Obra91.pdf
[accessed 18th march 2011]
Due to the fact that the luxury of draining the
water away from the reservoir was possible, the [4] Ibell, T. Bridge Engineering, Department of
bridges function could have been made far more simple Architecture and Civil Engineering,
by constructing two vertical piers at either end of the University of Bath.
arch with very little difficulty, this would greatly
simplify the structural function of the bridge, and then [5] Agencia Estatal de Meteorología [online]
if need be the arch could be constructed on the available from:
http://www.aemet.es/es/portada [accessed
10th April 2011]

[6] Agencia Estatal de Meteorología [online]


available from:
http://www.aemet.es/es/elclima/datosclimatol
ogicos/efemerides_extremos?o=1387&o=817
5&m=13&v=VMX&v=PND%2CPDV%2CP
DT%2CPMD%2CPMA%2CPMB%2CVMX
%2CTMX%2CTMMA%2CTMmB%2CTMA
%2CTMB%2CTmn [accessed 13th April
2011]

Das könnte Ihnen auch gefallen