It has been a public knowledge that Agusan del Sur is often visited by
continuous heavy rains throughout the year that partially or totally damage crops,
infrastructures and even claim lives of Agusanon, that makes us fully aware of the
Province’s vulnerability to floods, landslides and earthquakes.
With this PDRRM Plan, Agusan del Sur has now a roadmap towards disaster
resiliency. This plan details the specific interventions, projects and activities to
effectively and efficiently reduce and manage the impacts of hazards affecting the
lives and properties of our constituents.
1
ACRONYMS AND ABBREVIATION
2
18. DOH- Department of Health
3
36. PRC- Philippine Red Cross
4
53. BFP- Bureau of Fire Protection
5
70. AHA- ASEAN Humanitarian Assistance
6
DEFINITION OF TERMS:
(c) "Civil Defense" - disaster preparedness and prevention activities, other than
military actions, geared towards the reduction of loss of life and property brought
about by natural and human-induced disasters. Civil Defense may also be referred to
as Civil Protection.
(d) "Civil Society Organizations" or "CSOs" - non-state actors whose alms are neither
to generate profits nor to seek governing power. CSOs unite people to advance shared
goals and interests. They have a presence in public life, expressing the interests and
values of their members or others, and are based on social, ethical, cultural, scientific,
religious or philanthropic and other considerations. CSOs include non-government
organizations (NGOs), professional associations, foundations, independent research
institutes, community-based organizations (CBOs), faith-based organizations,
people's organizations, social movements, and labor unions.
(e) "Climate Change" - a change in climate that can' be identified by changes in the
mean and/or variability of its properties and that persists for an extended period
typically decades or longer, whether due to natural variability or as a result of human
activity.
7
of disaster risks in order to reduce their vulnerabilities and enhance their capacities,
and where the people are at the heart of decision-making and implementation of
disaster risk reduction and management activities.
(j) "Disaster Mitigation" - the lessening or limitation of the adverse impacts of hazards
and related disasters. Mitigation measures include but not limited to the engineering
techniques and hazard-resistant construction but includes as well as improved
environmental policies and programs and public awareness.
8
analysis of disaster risk, and good linkages with early warning systems, and includes
such activities as contingency planning, stockpiling of equipment and supplies, the
development of arrangements for coordination, evacuation and public information,
and associated training and field exercises. These must be supported by formal
institutional, legal and budgetary capacities.
(I) "Disaster Prevention" - the outright avoidance of adverse impacts of hazards and
related disasters. It expresses the concept and intention to completely avoid potential
adverse impacts through action taken in advance such as construction of dams or
embankments that eliminate flood risks, land-use regulations that do not permit any
settlement' in high-risk zones, and seismic engineering designs that ensure the
survival and function of a critical building in any likely earthquake.
(m) "Disaster Response" - the provision of emergency services and public assistance
during or immediately after a disaster in order to save lives, reduce health impacts,
ensure public safety and meet the basic subsistence needs of the people affected.
Disaster response is predominantly focused on Immediate and short-term needs and
is sometimes called "disaster relief".
(n) "Disaster Risk" - the potential disaster losses in lives, health status, livelihood,
assets and services, which could occur to a particular community or a Society over
some specified future time period.
(o) "Disaster Risk Reduction" - the concept and practice of reducing disaster risks
through systematic efforts to analyze and manage the causal factors of disasters,
including through reduced exposures to hazards, lessened vulnerability of people and
property, wise management of land and the environment, and improved preparedness
for adverse events.
(p) "Disaster Risk Reduction and Management" - the systematic process of using
administrative directives, organizations, and operational skills and capacities to
implement strategies, policies and improved coping capacities in order to lessen the
adverse impacts of hazards and the possibility of disaster. Prospective disaster risk
reduction and management refers to risk reduction and management activities that
address and seek to avoid the development of new or increased disaster risks,
especially if risk reduction policies are not put in place.
9
(q) "Disaster Risk Reduction and Management Information System" - a specialized
database which contains, among others, information on disasters and their human
material, economic and environmental impact, risk assessment and mapping and
vulnerable groups.
(r) “Disaster Victims” - persons or group of persons who have been adversely affected
by a natural or human-induced hazard who have to leave their habitual places of
residence due to exiting or impending threats, damaged shelter units, with casualty
among immediate family members or those who remained In their habitual places of
origin when still habitable but whose main source of income or livelihood had been
damaged and are experiencing hopelessness and difficulty in coping or responding
to the onslaught of the hazardous events on their own resources.
(t) "Early Warning System" - the set of capacities needed to generate and disseminate
timely and meaningful warning information to enable individuals, communities and
organizations threatened by a hazard to prepare and to act appropriately and in
sufficient time to reduce the possibility of harm or loss. A people-centered early
warning system necessarily comprises four (4) key elements: knowledge of the risks;
monitoring, analysis and forecasting of the hazards; communication or dissemination
of alerts and warnings; and local capabilities to respond to the warnings received. The
expression "end-to-end warning system" is also used to emphasize that warning
systems need to span all steps from hazard detection to community response.
10
(v) "Emergency Management" - the organization and management of resources such
as volunteers, funds, donations, food and non-food items, temporary/evacuation
centers, and responsibilities for addressing all aspects of emergencies, in particular
preparedness, response and initial recovery steps.
(w) "Exposure" - the degree to which the elements at risk are likely to experience
hazard events of different magnitudes.
(x) "Geographic Information System" - a database which contains, among others, geo-
hazard assessments, information on climate change, and climate risk reduction and
management.
(z) “Internally Displaced Persons (IDPs)” or “Persons Displaced by the Disaster” - are
persons or groups of persons who have been forced or obliged to flee or to leave their
homes or places of habitual residence, in particular as a result of or in order to avoid
the effects of natural or human-Induced disasters, and who have not crossed an
internationally recognized State border.
11
the enforcement of comprehensive land-use planning, building and safety standards,
and legislation.
(dd) "National Disaster Risk Reduction and Management Plan" or "NDRRMP" - the
document to be formulated and implemented by the Office of Civil Defense (OCD) that
sets out goals and specific objectives for reducing disaster risks together with related
actions to accomplish these objectives.
The NDRRMP shall provide for the identification of hazards, vulnerabilities and risks
to be managed at the national level; disaster risk reduction and management
approaches and strategies to be applied in managing said hazards and risks; agency
roles, responsibilities and lines of authority at all government levels; and vertical and
horizontal coordination of disaster risk reduction and management in the pre-disaster
and post-disaster phases and the budgetary resources to implement the plan. It shall
be in conformity with the NDRRM Framework.
(ff) "Preparedness" - pre-disaster actions and measures being undertaken within the
context of disaster risk reduction and management and are based on sound risk
analysis as well as pre-disaster activities to avert or minimize loss of life and property
such as, but not limited to, community organizing, training, planning, equipping,
stockpiling, hazard mapping, insuring of assets, and public information and education
initiatives.
(gg) "Private Sector" - the key actor in the realm of economy, which is important in the
production and distribution of goods and services to meet the physical needs of
human beings. The private sector comprises private corporations, households and
nonprofit institutions serving households.
12
(hh) "Public Sector Employees" - all persons in the civil service.
{II) "Risk" - the combination of the probability of an event and its negative
consequences. Also, the probability of harmful consequences, or expected losses
{deaths, injuries, properties, livelihoods, economic activity disruption or environment
damage) resulting from Interactions between natural, human-induced hazards and
vulnerable conditions.
(mm) "Risk Assessment" - a methodology to determine the nature and extent of risk
by analyzing potential hazards and evaluating existing conditions of vulnerability that
together could potentially harm exposed people, property, services, livelihood and the
environment on which they depend. Risk assessments with associated risk mapping
include: a review of the technical characteristics of hazards such as their location,
intensity, frequency and probability; the analysis of exposure and vulnerability
including the physical, social, health, economic and environmental dimensions; and
the evaluation of the effectiveness of prevailing and alternative coping capacities in
respect to likely risk scenarios.
13
Investment decisions and to address operational risks such as those of business
disruption, production failure, environmental damage, social impacts and damage
from fire and natural hazards.
(oo) "Risk Transfer" - the process of formally or informally shifting the financial
consequences of particular risks from one party to another whereby a household,
community, enterprise or state authority shall obtain resources from the other party
after a disaster occurs, in exchange for ongoing or compensatory social or financial
benefits provided to that other party.
(pp) "State of Calamity" - a condition involving mass casualty and/or major damages
to property, disruption of means of livelihoods, roads and normal way of life of people
In the affected areas as a result of the occurrence of natural or human-induced hazard.
(qq) "Sustainable Development" - development that meets the needs of the present
without compromising the ability of future generations to meet their own needs. It
contains within it two (2) key concepts: (1) the concept of "needs", in particular, the
essential needs of the world's poor, to which overriding priority should be given; and
(2) the Idea of limitations imposed by the state of technology and social organizations
on the environment's ability to meet present and future needs. It is the harmonious
integration of a sound and viable economy, responsible governance, social cohesion
and harmony, and ecological integrity to ensure that human development now and
through future generations is a life-enhancing process.
(rr) "Volunteer" - individual/person or group who for reasons arising from their socio
-developmental, business and corporate orientation, commitment or conviction
contribute time, service, and resources whether full time or part time base to a just
and essential social development cause, mission or endeavor in the belief that their
activity is mutually meaningful and beneficial to public interest as well as to
themselves.
14
public Information and awareness, limited official recognition of risks and
preparedness measures, and disregard for wise environmental management.
15
EXECUTIVE SUMMARY
Rationale
The passage of Republic Act no. 10121, otherwise known as the “The Philippine
Disaster Risk Reduction and Management Act of 2010”, mandates the State to uphold
16
the people’s constitutional rights to life and property by addressing the root causes
of vulnerabilities to disasters, strengthening the country’s institutional capacity for
disaster risk reduction and management, and building the resilience of local
communities to disasters, including climate change impacts. This further provides
the basis for the establishment of the Local Disaster Risk Reduction and Management
Council and Office, which shall be responsible for setting the direction, development,
implementation, and coordination of disaster risk reduction and management
programs within their territorial jurisdiction.
The advent of RA 10121 instigated the institution of the Provincial Disaster Risk
Reduction and Management Council (PDRRMC) through Executive Order No. 07-11 on
March 18, 2011 and thereafter the establishment of the Provincial Disaster Risk
Reduction and Management Office (PDRRMO), which was created through Executive
Order No. 10-13 dated July 30, 2013, to serve as the Secretariat and the Operational
Center of the Provincial Disaster Risk Reduction and Management Council (PDRRMC).
The Provincial Government of Agusan del Sur (PGAS) funded the construction
of a new PDRRMC Operation Center and Headquarters to accommodate its search,
rescue and emergency arm, as well as the Bureau of Fire Protection- Office of the
Provincial Fire Marshal.
This search and rescue, fire and emergency hub now operates 24/7 and serves
as the dynamic and proactive nerve of the Provincial Government of Agusan del Sur
(PGAS) and Provincial Disaster Risk Reduction and Management Council (PDRRMC)
in times of crisis and disasters. Throughout the years, the Provincial Government
have been all out on its efforts to train and establish local search, rescue and
emergency response teams in the municipalities/ city, as well as in all the barangays
in the province through Search and Rescue – Agusan del Sur (SARAS) programs and
activities. Through SARAS, the Provincial Disaster Risk Reduction and Management
Office continue to advocate the essence of disaster prevention and mitigation,
preparedness, response and rehabilitation and recovery. Currently, the Provincial
Disaster Risk Reduction and Management Council (PDRRMC) through the Provincial
Disaster Risk Reduction and Management Office (PDRRMO) had lobbied in the local
councils to institute Disaster Risk Reduction and Management (DRRM) initiatives
17
pursuant to Republic Act No. 10121. At present all municipalities and city have local
search and rescue teams in placed.
The challenge posed to the Provincial Government and its component LGU’s is
to further enhance, strengthen and maintain the level of involvement of all
stakeholders in all the thematic areas for disaster resiliency, namely Prevention and
Mitigation, Preparedness, Response and Rehabilitation and Recovery. The said
involvement which illustrates strong partnership with various stakeholders is
reflected in the 6 year Disaster Risk Reduction Plan. Collective efforts among
stakeholders – both government and civil society organizations have exhausted all
means and efforts to craft a pro-active and effective plan of actions to address the
effects of climate change and various disasters that are a common threat to all.
The contents of this plan reflects the urgency and importance of putting into
place the necessary actions to undertake during disaster mitigation and preparation,
appropriate response in times of calamities and proper rehabilitation interventions
after the onslaught of natural disasters. Under the thematic area of Prevention and
Mitigation it has 1 long term goal with 1 main objective, 3 outcomes with 7 major
programs and 28 corresponding projects and activities. For the thematic area of
Preparedness 1 long term goal have been identified with 11 corresponding objectives
of which it has 3 outcomes, of which 4 major programs have been identified and 113
projects and activities. Furthermore, for the Response thematic area, 1 goal and 1
objective have been identified, with 1 outcome, 2 major programs and 35
corresponding projects and activities. For the Rehabilitation and Recovery thematic
area, it has 1 goal, 1 objective with 4 outcomes identified and 13 major programs with
40 corresponding projects and activities.
18
guarantee the continuity and sustainability of the DRRM initiatives, thereby ensuring
the core purposes of DRRM is carried out and achieved “so that others may live.”
19
A. ECOLOGICAL PROFILE
A.1 Demography
Table 1:
The province is projected that by year 2020 will increase of about 57,199
individuals from 2015 and will continue to increase in year 2030 to 891,539 population,
and will still remain as the province with the largest population among provinces in
the region. The province is projected to reach of about 1.2 Million population by year
2050.
20
The projection is based on Annual Population Growth Rate from year 2000 to
2015, wherein Caraga has an APGR of 1.44. Although Agusan del Sur has the largest
population since year 2000 until 2015, it only ranks third among province’s in the
region with 1.51 APGR which is higher than the region’s APGR of 0.07. It can be noted
that Surigao del Norte has the highest APGR of 1.74 followed by Butuan City of 1.56.
Table 2:
21
Table 3:
Table 1 shows that the province’s total population has increased by 6.74% or
44,235 persons from 656,418 in year 2010 to 700,653 in year 2015. The data also shows
of an population increase from year 2000 to 2015 of about 25.27%. In addition, Bayugan
City has remained with the largest population among municipalities in the province
from CY 2010 to 2015, followed by Prosperidad. Municipalities with least population
are Sta. Josefa and La Paz.
22
Population
Percentage
City/Municipality Actual
Increase/Decrease
2000 2010 2015 2000-2015 2010-2015
Bayugan City 93,623 99,361 103,202 10.23% 3.87%
Bunawan 26,704 37,482 45,151 69.08% 20.46%
Esperanza 44,151 51,897 54,801 24.12% 5.60%
La Paz 20,880 28,562 28,217 35.14% -1.21%
Loreto 31,365 39,474 42,501 35.50% 7.67%
Prosperidad 70,815 76,628 82,631 16.69% 7.83%
Rosario 28,675 38,280 46,683 62.80% 21.95%
San Francisco 56,968 70,986 74,542 30.85% 5.01%
San Luis 25,901 32,733 32,109 23.97% -1.91%
Sibagat 28,685 30,985 30,442 6.13% -1.75%
Sta. Josefa 22,730 25,156 26,729 17.59% 6.25%
Talacogon 30,879 37,224 38,374 24.27% 3.09%
Trento 41,696 47,193 51,565 23.67% 9.26%
Veruela 36,222 40,457 43,706 20.66% 8.03%
23
Table 5:
Projected Population
Using the APGR for year 2000-2015 in Table 5, the province is projected to have
an increasing population trend from year 2020 of 757,852 total population until year
2050 of 1.2 Million total population. The projections show that Bayugan City still lead
with largest number of population from year 2020 until 2040, and Bunawan is projected
to lead by year 2050.
24
The municipalities of Prosperidad and San Francisco followed Bayugan City in
year 2020 based on the projections with 86,993 and 81,531 populations, respectively,
and will still remain at the same rank until 2030. In projected year 2040, San Francisco
and Bunawan will place second and third as to number of population. However, this is
projected to change in year 2050 that Bunawan, Rosario and San Francisco will lead
with the largest number of population among city/municipalities.
Table 6:
Land Area
Agusan del Sur occupies a total land area of 8,965.50 sq. km. In terms of land
area distribution in the province, Loreto has the largest area of 1,389.40 sq. km or 16%
of the total area followed by San Luis with 1,186.42 sq. km, Esperanza with 1,001.18
sq. km. or 11%. Those municipalities with smallest areas include Sta. Josefa with
188.01 sq. km. or 2%, Rosario with 296.01 sq. km. or 3%, Talacogon with 330.84 sq. km
or 4%, Veruela with 332.08 sq. km. or 4%, and San Francisco with 355.91 sq. km. or 4%
to the total land area.
25
Figure 1:
Based on 2015 population data released by PSA, the province has a gross
population density of 78 persons per sq. km. Municipalities with high gross population
density include San Francisco of 209 persons per sq. km., Bayugan City of 191
persons per sq. km., Rosario of 158 persons per sq. km., Prosperidad of 147 persons
per sq. km., and Sta. Josefa of 142 persons per sq. km. In addition, municipalities with
low gross population density are La Paz of 26 persons per sq. km., San Luis of 27
persons per sq. km., and Loreto of 31 persons per sq. km. The gross population
density is a computation of the total population of a certain area over the total land
area.
26
Table 7:
Population Density
City/Municipality Actual Projected
2000 2010 2015 2020 2030 2040 2050
Bayugan City 174 184 191 198 211 225 240
Bunawan 62 87 104 124 176 250 355
Esperanza 44 52 55 59 68 78 91
La Paz 19 26 26 28 35 42 52
Loreto 23 28 31 34 41 51 62
Prosperidad 126 137 147 155 172 190 211
Rosario 97 129 158 186 257 355 492
San Francisco 160 199 209 229 274 328 392
San Luis 22 28 27 29 34 39 45
Sibagat 57 62 61 62 64 67 70
Sta. Josefa 121 134 142 150 167 186 208
Talacogon 93 113 116 125 144 167 193
Trento 56 63 69 74 85 98 113
Veruela 109 122 132 140 159 180 204
The high density of San Francisco is attributed to the influx of people due to
the Service Sector where malls and financial institutions, and other commercial
services are available and accessible as it has been strategically located in a junction
going to Surigao del Sur, Bislig City, Butuan City, and Davao City. In addition, Bayugan
City ranks second with high population density where large establishment and
commercial services can be observed, including some wood companies.
Generally, municipalities with high density are mostly highway towns while
those with low density are located along Agusan River which have bigger areas and
usually affected by flood during rainy season.
Indigenous Population
There are 222,377 total indigenous peoples (IPs) or 30.34% out of 735,459 total
population of the province based on CBMS 2015. The data shows a decrease of 11%
of IPs population in 2015 from 2012. Among the municipalities, La Paz has the largest
IP population of 78% and followed by San Luis (60%), Loreto (51%), Talacogon (49%),
Bunawan (46%), Esperanza (44%).
27
IP Population
Total Population
Municipality 2012 2015
Total Total
2012 2015 % Total % Total
Magnitude Magnitude
Bayugan 106,385 116,678 12,031 11.31% 12,832 11.00%
Bunawan 43,578 49,432 24,046 55.18% 22,636 45.79%
Esperanza 56,024 58,795 26,472 47.25% 25,688 43.69%
La Paz 31,244 29,423 24,812 79.41% 23,004 78.18%
Loreto 36,262 42,346 20,215 55.75% 21,692 51.23%
Prosperidad 79,737 84,967 24,989 31.34% 10,382 12.22%
Rosario 47,471 44,861 16,943 35.69% 16,793 37.43%
San Francisco 68,265 75,364 16,641 24.38% 9,819 13.03%
San Luis 30,798 35,144 19,266 62.56% 21,035 59.85%
Santa Josefa 24,060 27,995 3,786 15.74% 3,229 11.53%
Sibagat 28,857 31,838 6,439 22.31% 6,806 21.38%
Talacogon 38,890 42,648 23,604 60.69% 20,994 49.23%
Trento 54,526 58,184 22,758 41.74% 19,208 33.01%
Veruela 36,983 37,784 8,624 23.32% 8,259 21.86%
Agusan del Sur 683,080 735,459 250,626 36.69% 222,377 30.24%
Data Source: CBMS 2012 and 2015
28
Agusan del Sur is served by seventeen (17) hospitals – seven (7) government
and ten (10) private clinics/hospitals. Of the government hospitals, five (5) are
operated and maintained by the Provincial Government.
29
2 Agusan Valley Hospital 10 Primary
3 Sto. Niño Medical 10 Primary
Hospital
4 Franco Clinic & Hospital 10 Primary
5 Rico Medical Clinic & 10 Primary
Hospital
6 San Francisco Doctor’s 100 Level1
Hospital
7 Philsaga Mining Hospital 14 Infirmary
8 De Leon Medical Clinic 14 Infirmary
9 Bravo-Solde Medical 14 Infirmary
Clinic
10 Cabanban Medical Clinic 14 Infirmary
Data Source: PHO, CY 2015 Annual Report
As of December 2015, the DOPMH has exceeded its bed occupancy rate based
on the DOH standard. For a 100-bed hospital, occupancy rate of DOPMH reached to
153.70% making it overcrowded. While the four (4) district hospitals are underutilized
with an average bed occupancy rate of 74.25% in 2015 from 55.44% occupancy rate in
2013. Although, there was an increase of occupancy rate, the district hospitals are still
underutilized which contributed to the overcrowding of DOPMH.
30
Authorized Percentage
2013 2015
Name of Hospital Bed Point
Baseline Accomplishment
Capacity Change
Community
Hospital
4 Loreto District 10 59.58% 70.52% 10.94%
Hospital
5 Talacogon 30 50% 83% 33%
District
Hospital
Data Source: PHO, CY 2015 Annual Report
Moreover, the hospitals are performing better in the average net death rate with
0.284% compared to the DOH standard of not more than 2% deaths. Among the
hospitals, the DOPMH has the highest net death rate with 0.80% while LDH has zero
percent death rate in 2015. Only DOPMH has shown an increase in its net death rate
by 0.10% from 0.70% in 2013 to 0.80% in 2015. Meanwhile, TDH has the highest
reduction of net death rate from 2013 to 2015.
Of the 19,227 pregnant women expected to give birth, 9,726 or 51% have made
at least 4 prenatal care visits, an increase of 7% compared to last year which was only
44%. As shown in the graph below, there is an increasing trend of the annual live-
births which indicates positive results on the intervention undertaken particularly on
health education and promotion. In addition, there is an increase of 16.16% from
15,923 in 2013 to 18,497 in 2014 and continually increased by 7.7% from 2014 to 19,922
in 2015.The increase is attributed by the continued advocacy on the importance of
prenatal visits that improved the health seeking behavior among pregnant women in
2015.
32
DOH
Indicator 2013 2014 2015
Standard
Maternal Mortality 52/100,000 75/100,000 59/100,000 60/100,000
Rate
Data Source: PHO, CY 2015 Annual Report
The decrease in the MMR from 75/100,000 deaths in 2013 to 60/100,000 deaths
in 2015 can be attributed to increasing facility-based delivery and births attended by
skilled birth attendants. However, the province is still below the DOH standards on the
two indicators. As of 2015, facility-based delivery and births attended by skilled birth
attendants have 4% and 2% gap respectively based on DOH standards.
33
Data Source: PHO, CY 2015 Annual Report
The infant mortality rate (IMR) is also erratic in the three (3) years reported.
Figure below shows the trend of IMR. There is a slight increase from 5.08/1,000 live
births in 2013 to 5.56/1,000 live births in 2014. Accordingly, a dramatic drop is
observed from 5.56/1,000 live births in 2014 to 3.43/1,000 live births. The province has
performed better than that of the DOH standard with a target of 12/1,000 live births.
In addition, the province has also a better performance compared to the DOH
Standard of 25/1,000 live births for under five mortality rate (UFMR) in the span of three
(3) years (2013-2015) even though the trend is fluctuating. From the baseline of
5.71/1,000 live births in 2013, the rate of under five mortality has increased to
34
6.92/1,000 live births in 2014. Eventually, the rate has decreased from 6.92/1,000 live
births in 2014 to 6.12/1,000 live births in 2015.
35
Accordingly, children are given complete vaccination against Tuberculosis
(TB), Diphteria, Pertusis, Tetanus, Hepatitis B, Haemophilus, Influenza B (HiB),
Poliomyelitis, Diarrhea, Pneumonia, Measles, Mumps and Rubella. These diseases can
be prevented and immunization must be received by infants before reaching one (1)
year. The program’s target is to reach every child in every purok or barangay.
Malnutrition prevalence rate for the province has been constantly decreasing
in the past three years. The figure below shows the decreasing trend of the prevalence
rate from 7.15% in 2013 5.59% in 2015. The challenge for the province is in sustaining
its performance.
The incidence of poor oral health condition of children below six (6) years old
is rising. As shown in Table 36, it increased by 23.94% from 5,259 in 2014 to 6,518 in
2015. However, the condition of other age-group decreased by 61.32% from 22,900 in
2014 to 8,858 in 2015.
Table 15. Oral Health Status of Under 6-YO Old Children, 201-2015
Under Six Years Old Children %
Oral Health
2014 2015 Increase/
Indicators
Male Female Total Male Female Total Decrease
Total number with 2,393 2,863 5,259 2,953 3,565 6,518 23.84
dental caries
Total number with 131 161 292 244 311 555 90.07
gingivitis/periodontal
diseases
Data Source: PHO, CY 2015 Annual Report
37
Total number with 1,918 4,410 6,328 592 863 1,455 -77.01
gingivitis/periodontal
diseases
Data Source: PHO, CY 2015 Annual Report
Dengue prevention and control shows erratic trend from 2013-2015. The cases
have dramatically increased by 1,094 cases or 149% from 2013 to 2014. In 2015, a
reduction of 633 cases or 35% is noted from 2014. To combat the increase in cases,
PHO intensifies its information and education campaign (IEC) in 13 municipalities and
one (1) city on dengue prevention and control through symposium in schools and
38
barangays to sustain community support. PHO also emphasizes that environmental
clean-up is the most effective way to control the disease and the implementation of
Aksyon Barangay Kontra Dengue (ABKD) using the four measures (Mag 4S Tayo) to
fight dengue – 1) Search and Destroy; 2) Seek Early Consultation; 3) Self-Protection;
and, 4) Say No to Indiscriminate Fogging/Say Yes to Fogging in Hotspot and Outbreak
Areas and also 4 O’Clock Habit. Moreover, targeted two (2) misting sprays for dengue
disease control are procured in support to the PHO’s campaign.
Animal bite cases of the province have increased over the past three years.
From 2013, there is an increase of 205 cases or 9.9% in 2015. The Provincial Health
Office and the Provincial Veterinary Office conduct massive information
dissemination campaign to all stakeholders throughout the province. Both continue
their interventions to help control or even eliminate the prevalence of rabies. DOH
39
through the Regional Office provides rabies vaccine to all credited animal bite center
to cater all animal bite cases.
40
Data Source: PHO, CY 2015 Annual Report
41
The PSWDO is responsible in the provision of social welfare services and
facilities including the development of the children’s (aging 3-5 years old) physical,
mental and social emotional domains under the ECCD Program.
For the past three school years, the number 3-5 year old children with ECCD
experience is increasing. From SY 2012-2013 to SY 2014-2015, an increase of 2,410
children or 11.55%. Of the 56,107 total population of 3-5 year old children in 2015,
41.50% has ECCD experience.
Figure 12. Number of 3-5 Year Old Children with ECCD Experience
42
Data Source: C/M/PSWDO
As of 2015, a total of 618 day care centers with 611 day care workers are in the
315 barangays of the province. Of the total day care workers, 590 workers are provided
with honorarium. DCWs with permanent, casual and JO status are not included.
In the span of three (3) years, there is a steep increase of registered senior
citizen members. From 17,330 registered members in 2013, increase in membership
has almost doubled with 16,789 additional members or 96.88% making it 34,119 in
2015. Such positive development contributed to bigger number of elderly enjoying the
benefits and privileges afforded to them thru the “Expanded Senior Citizens Act of
2010”.
As of 2015, the number of PWDs registered is about 51% of the total population
of 8,348 persons based on 2015 CBMS. These members are already beneficiaries of
the 20% discounts on medical, transportation, food, recreation and others as provided
in the Magna Carta of Person with Disability. The table below shows the increasing
trend of the registered PWDs.
44
Figure 15. Registered Persons with Disability, 2013-2015
Women Development
45
The province also had conducted advocacies on women protection laws,
magna carta of women, and role of women in building the community. As of 2015, a
total 1,570 women have participated in these undertakings. The increased awareness,
understanding and commitment to address the causes and effects of violence on
women is seen as some of the factors that contributed to the significant increase on
different cases involving women sector.
Out-of-School Youth
46
potent means in reaching out the out-of-school youths gained notable progress in the
last three (3) years.
As of 2015, there are already 148 barangays with PYAs with 4,324 members, an
increase of 83 barangays or 127% and increase of 3,649 members or 540% from 65
barangays and 675 members in 2013.
Moreover, the OSY in Agusandel Sur has reached to 93,775 based on the CBMS
data. It is about 63% of the 147,355 total youth population (ages 15-24 years old).
Children
Over the span of three (3) years, data on violence against children shows a
fluctuating trend where 2014 posts the highest number of cases with 264, an increase
of 133 cases or 102% compared to the 2013 with only 131 cases. The implementation
of various activities of the department and those of the partner local government units,
non- government and civil society organizations has influenced the decrease on the
incidence of abuse committed against children from 264 in 2014 to 157 in 2015 as
recorded in the PNP. A reduction of 107 cases or 40.50% is noted from 2014 to 2015.
The trend in number of Children in Conflict with the Law (CICL) is erratic from
2013-2015. An abrupt increase is noted from 2013 with 14 cases to 2014 with 41 cases.
From 2014 to 2015, a decrease of 16 cases or 36% is reported.
47
Figure 18. Number of Children in Conflict with the Law, 2013-2015
The province through the PSWDO has facilitated emergency response through
provision of relief assistance to the affected families. This seeks to address the
immediate needs of the victims through augmenting support to the assistance already
extended by the concerned barangays and municipalities.
On January 2014 and December 2014, Tropical Depression Agaton which was
elevated to Tropical Storm (TS) after two weeks and Tropical Storm Seniang hit both
the upland and the lowland areas of the province. Flooding in low lying areas is
widespread affecting 44,572 families which stayed 24 hours in few barangays and
stayed for several days in other flood prone barangays.
In the span of two years (2014-2015), a total of 34,591 families are provided with
emergency relief assistance in 182 barangays which are hit hard by the tropical storms
and flooding. Meanwhile, there are also 330 internally displaced families due to armed
conflict provided with food packs in San Luis.
48
Assistance to Individual In Crisis Situation (AICS)
From 2014 to 2015, a total of 4,186 families in difficult circumstance have been
provided with assistance ranging from medical, burial, food and transportation.
Education
Basic Education
49
districts are along the Agusan River. The table below shows the disaggregation of the
school districts.
Division of Agusandel Sur has a total of 396 public elementary schools and 26
private elementary schools. For secondary level, there are 86 public schools and 14
secondary schools. There are 29 implementing units and 57 non-implementing units
in the public secondary schools.
Meanwhile, the Division of Bayugan City has a total of five (5) districts –
Bayugan Central, Bayugan East, Bayugan North, Bayugan South, and Bayugan West,
with 55 elementary schools and 10 public secondary schools. Of the total elementary
schools, 33 schools are pure monograde, 12 pure multigrade, and 10 combination
(mono-multigrade). The public secondary schools are composed of five (5) fiscally
implementing unit/empowered units and five (5) non-implementing units.
As shown in the figure below, the elementary school net enrollment rate (NER)
has a fluctuating trend in the span of three years for Agusandel Sur Division. SY 2012-
50
2013 posts the highest NER with 99.94% which drops to 92.82% in SY 2013-2014 and
has slightly increased by 93.14% in SY 2014-2015. Based on the graph, female learners
have higher NER than male learners.
Figure 18. Elementary School Net Enrollment Rate (NER) by Sex, 2012-2015
For the Bayugan City Division, the elementary school net enrollment rate (NER)
has a fluctuating trend in the span of three years. SY 2014-2015 posts the highest NER
with 95.44%, a slight increase from that of the SY 2013-2014 with 94.79%. However, in
SY 2015-2016, the NER drops to 93.41% from that of the SY 2014-2015. Based on the
graph, female learners have higher NER than male learners.
Figure 19. Elementary School Net Enrollment Rate (NER) by Sex, 2013-2016
51
Data Source: DepEd, Bayugan City
Meanwhile, the figure below shows the slightly increasing trend of the
secondary school net enrollment rate (NER) in three years for Agusan del Sur Division.
The increase of participation rate is attributed to the programs and projects
implemented by the Division that encouraged learners to continue their education.
Figure 20. Secondary School Net Enrollment Rate (NER) by Sex, 2012-2015
For Bayugan City Division, the secondary NER has a fluctuating trend in three
years. From SY 2013-2014 with 75.54%, the NER drops to 74.46% in SY 2014-2015 and
has increased to 77.07% in SY 2015-2016. In the three reported years, female
52
secondary school net enrollment rates are better than that of the male secondary
school NER.
Figure 21. Secondary School Net Enrollment Rate (NER) by Sex, 2013-2016
53
Meanwhile, the Bayugan City Division posts a decreasing trend in three years.
There is a sudden drop of elementary school CSR from SY 2013-2014 with 96.75% to
86.07% in SY 2014-2015. A further decrease has been noted from SY 2014-2015 to
83.79% in SY 2015-2016.
54
For Bayugan City Division, the secondary school cohort survival rate has
plummeted from SY 2013-2014 with 78.14% to 57.24% in SY 2014-2015 and further
drops in SY 2015-2016 with 49.14%. It is observed that for SY 2014-2015 and SY 2015-
2016 both school years post higher CSR than that of the male high school students.
Meanwhile, male students post higher CSR in SY 2013-2014 compared to female
students.
The Division also has its share in Disaster Risk Reduction Management
considering that the province is affected by natural hazards especially flooding. To
prepare these hard hit areas in the occurrence of these natural hazards, training on
skills of knowledge management, psychosocial support for teachers and students to
overcome the traumatic experience through stress debriefing and wellness
participation are conducted. These trainings are facilitated in partnership with NGOs
(Save the Children, ACCORD and SIKAP, Inc.), local government units, and the
national agencies (OCD, DILG and NEDA).
Scholarship Program
56
1. Ordinance No. 3 – 1999 Scholarship for Non-Natives
2. Ordinance No. 23 – 2001 Scholarship Fund for Masteral and
Doctoral Degrees
3. Ordinance No. 18 – 2003 Scholarship for the Poor Indigenous
Peoples of Agusan del Sur
4. Ordinance No. 4 – 2006 Scholarship Program for Medicine
Proper and Bachelor of Science in
Nursing Courses
5. Ordinance No. 14 – 2006 Scholarship Program for Medicine
Proper and Bachelor of Science in
Nursing Courses
6. Ordinance No. 54 – 2010 ADS-UPOU Distance Learning
7. Ordinance No. 107 – 2014 Expanded Scholarship
57
PWD 12 12 13 13 15
UPOU 8 8 8 6 7
Expanded 100 100 197 197 297
Baccalaureate
Degree
Total 375 374 449 447 557
Data Source: SPO
Of the total Agusanon provided with Scholarship Grant, 225 students have
graduated in different areas. Disaggregation of the graduates is:
Pagtuon Program
58
To help improve school and day care center facilities and equipment in order
to enhance the teaching and learning environment;
To strengthen monitoring and evaluation;
To provide policy recommendation related to education sector; and
To help source out external funds to support education development in the
province.
While the Pagtuon Program has been a banner program of the province, new
directions has been set making the program more oriented to the needs of the
beneficiaries and stakeholders in the education sector. Consequently, its
implementation has faced challenges such as communicating the Enhanced Pagtuon
Program, creating buy-in and ownership from among the stakeholders as well as
gaining their trust. The province is now looking into networking and linkaging with
appropriate department and stakeholders for successful implementation of the
Enhanced Program.
59
In 2015, activities conducted include: Capacity Development for Day Care
Teachers attended by 123 participants; Leadership Traiing for DepEd and Municipal
Stakeholders with 125 participants; Leadership Training for PGAS Stakeholders with
14 participants; and, Orientations and Focus Group Discussions with 100 participants.
From 2014 to 2015, the net appropriation for two (2) years amounts to
Php44,879,674.78 to support the operation and maintenance of public schools for both
elementary and high school, repair and maintenance of school buildings, educational
research, sports and citizenship development, and support to special projects.
The sports development services under the Provincial Governor’s Office led in
all sports activities of the province in coordination with DepEd and other concerned
departments and agencies.
In the span of three years, the province has been recognized internationally and
locally garnering several awards in different competitive sports event. The table below
shows the list of awards:
60
Category 2014 2015 2016
International ASEAN + Age Group 16th ASEAN + Age 2016 Chosun
Championships Group Chess University Presidential
(Macau) – Silver Championships International Poomsae
Medalist (Team (Singapore) – Gold Taekwondo
Standard); Silver Medalist (Standard Championship
Medalist (Team Individual); Silver (Gwang-ju City, South
Rapid); Bronze Medalist (Standard Korea) – Silver
Medalist (Team Blitz); Team); Silver Medalist
Bronze Medalist Medalist (Blitz 17th ASEAN + Age
(Individual Rapid) Individual) Group Chess
World Jr. Chess Asian Schools of Championships 2016
Championships in Girls Under 15 Chess (Thailand) – Champion
Mumbai – 3rd Placer Championships 12th Asian Schools
17th ASEAN Games (Singapore) – Silver Chess Championships
(Incheon, South Medalist (Standard 2016 – 17-Under Girls
Korea) – 6th Placer Individual); Silver Blitz Section (Tahbaz,
21km Medalist (Blitz Iran) - Champion
ASEAN Games Finals Individual)
(Tokyo Japan -
Representative
National BatangPinoy BatangPinoy 2016
(Boxing) – Silver (Boxing) – Silver PalarongPambansa
Medalist Medalist Chess Tournament
th
77 ArawngDabaw National Marathon Standard (Secondary
(National (Cebu City) – 1st Girls) – Gold Medalist
Tournament – 4 Gold Placer 42km Grand Finals National
Medals; 3 Silver National Marathon Age Group Chess
Medals (Camiguin) – Placer Championship – Gold
National – Age Group 42km Medalist
Chess National Marathon Milo Olympics 2016
Championship – (Bohol) – 1st Placer Karate-Do – Silver
Silver Medalist 42km Medalist (Kata);
PalarongPambansa – Silver Medalist
Silver Medalist (Kumite)
(Chess)
61
Category 2014 2015 2016
38th Milo Marathon 5k Marathon – Gold
(Butuan City) – 3 Medalist
Awardees 3k Marathon – Silver
POC-PSC National Medalist
Games – 2 Silver Lawn Tennis – 16
Medalists and 1 Under (Bronze
Bronze Medalist Medalist);
(Chess, Marathon, Single/Double
High Jump) (Bronze Medalist)
Table Tennis – 12-
year Under
(Champion)
Regional/Mi BatangPinoy BatangPinoy 6 Rounder – WBO
ndanao- (Boxing) – Gold (Boxing) – Gold “Blow by Blow
Wide Medalist (Mindanao) Medalist BakbakansaKidapawa
Ultra Marathon n – Draw Fight
(Digos-Davao City) – BakbakansaTagbina
1st Placer 60km 2016 (Boxing) –
Champion
BakbakansaMonkayo
Boxing Open
Tournament 2016 –
Champion
Regional Meet 2016 –
Champion (Standard);
Silver Medalist (Blitz);
Champion (Rapid)
Run for Safe 2016
(CARAGA) – Champion
Caraga Regional
Athletic Meet 2016
Table Tennis – Gold
Medalist
62
Category 2014 2015 2016
Taekwondo – 1 Gold
Medalist; 3 Silver
Medalists
Volleyball – Bronze
Medalist
Caraga Taekwondo
Championship 2016 – 5
Gold Medalists
Mindanao CPJ
Taekwondo
Championship 2016 – 3
Gold Medalists; 2
Silver Medalists
PulongDuterte
Championship, Davao
City – Silver Medalist
Iligan City Regional
Taekwondo
Championship – Gold
Medalist
Provincial Naliyagan Festival
Level Mano-a-Mano 2016 –
Champion
Intramurals Meet
Source: PSYDS
Included in the services of the sports and youth development are the provision
of training equipment to athletes and other sports enthusiasts, and venue during
sports events. Athletes also utilize the sports complex while they are preparing to be
sent to different competitions locally and internationally.
The Moral Recovery and Values Formation Services (MRVFS) has helped the
province in achieving its vision to be God-Centered constituents through the conduct
63
of orientations, seminars and other activities participated by provincial government
officials and employees, municipal officials and employees, barangay officials and
employees, teachers, students at different levels, inmates, and Agusan del Sur
constituents.
64
1. Establish and maintain acceptable standards for operation of drug abuse
treatment and rehabilitation center;
2. Provide usual information for decision-making, administrative planning and
development;
3. Inform and educate the constituents of the Province of Agusan del Sur on
the dangers and crippling effects of illegal drugs;
4. Provide appropriate treatment to individuals showing symptoms of
substance use disorder;
5. Implement effective and accessible outreach programs;
6. Create a cadre of homegrown potentials and volunteers to sustain and
provide continuous services to the province; and
7. Develop resources to provide recovery-oriented support services of care.
65
Sessions to 42 clients conducted which include psychoeducation,
workbook discussion, journal writing, worksheet activities, zumba and
basketball, and mass every Saturday. Clinical assessment and medical
examinations also conducted to all clients
Staff Training for Addiction Counselling at Melaka, Malaysia
Training for Stakeholders conducted
Training for MSWD re Screening for SUD
Training on Physiology and Pharmacology of Addiction
Training about Continuum Care for Substance Use Disorder
Treatment
Training on Basic Counseling Skills for Addiction Professionals
Major Crops
66
banana, abaca, and coffee. Upland Sustainable Agri-forestry Sustainable Development
(USAD) Program as a convergence program focuses on core commodities such as
rubber, cacao, and falcata. These commodities are also prioritized by DENR under the
National Greening Program (NGP). Meanwhile, PCA focuses on the production of
coconut as well as oil palm.
Rice
Rice is the major crop produced in the province. Rice industry in the province
is already considered mature thus production is not a major issue but rather on the
interfirm relationship/organizational development, processing and marketing. On
productivity, data shows that the productivity of rice in all provinces in Caraga has
decreasing trend. Moreover, the province has a productivity of 3.1M in 2015 and is
below the performance of the country for three consecutive years, but it is above the
Caraga Region. However, the province ranks second in the region next to Agusan del
Norte in terms of productivity.
Moreover, the total rice production of the province has a decreasing trend for
three consecutive years (2013-2015) of 305,171 MT, 292,019 MT and 233,526 MT (PSA
data). However, its production is the highest among the provinces in Caraga. Also, its
share of production in Caraga has consistently been posted the highest among the
provinces in Caraga.
Considerable factors for this are the significant increased in the volume of
production in the municipalities of Veruela and Prosperidad with percentage change
of 30% and 14%, respectively. This is due to the presence of irrigation facilities in both
municipalities. The production of the remaining municipalities has decreased in five-
67
year period. This is due to dry spell and the damaged of Andanan River Irrigation
System that served rice areas in Bayugan City and Esperanza.
Table 23. Annual Rice Productivity and Change, Table 24. Rice Share of Production and Percentage
2013 & 2015 Change,byGeolevel, 2013-2015
Change (% Change (%
Productivity (MT/ha.) SHARE OF PRODUCTION (%)
pts.) pts.)
Geolevel Geolevel
2013 2014 2015 2013 to 2015
2013 2014 2015 2013 to 2015
PHILIPPINES 3.89 4.00 3.90 0.01
CARAGA 100.00 100.00 100.00
..CARAGA 3.31 3.30 3.10 -0.20
....Agusan del Norte 3.50 3.63 3.26 -0.24 Agusan del Norte 16.35 17.37 15.83 (0.52)
....Agusan del Sur 3.39 3.32 3.10 -0.29 Agusan del Sur 52.27 50.83 48.52 (3.75)
....Dinagat Islands 2.36 2.22 2.16 -0.20 Dinagat Islands 1.19 1.13 1.27 0.09
....Surigao del Norte 3.04 2.88 2.93 -0.10 Surigao del Norte 11.94 11.09 12.59 0.64
....Surigao del Sur 3.19 3.34 3.19 0.00 Surigao del Sur 18.26 19.58 21.79 3.54
Source: PSA; Computation-PPDO, Agusan del Sur
Source: PSA, Computed - PPDO, Agusan del Sur
Legend: High Moderate low
Corn
68
farming. On corn productivity, the province has consistently posted the highest
productivity among the provinces in the region. The province has better performance
than the country, region and among the provinces in Caraga. However, for three year
period (2013-2015) the corn productivity of the province has a minimal decrease of
0.16 percentage points.
The share of corn production in the region has been consistently posting the
highest for three consecutive years. Corn production in the province has increased
significantly of 62% in five-year period. This is attributed by the increased of the total
area in 2015. Among the municipalities, Esperanza ranks first followed by Prosperidad
and Trento. For five-year period, Prosperidad has significant changes in production of
581% increase followed by San Francisco and Rosario.
Table 26. Corn Productivity (MT/ha.) Table 26. Corn Share of Production
and Change, 2013-2015 Change by Geolevel, 2013-2015
Change (% Change (%
Productivity (MT/ha.) SHARE OF PRODUCTION (%)
pts.) pts.)
Geolevel Geolevel
2013 2014 2015 2013 to 2015 2013 2014 2015 2013 to 2015
PHILIPPINES 2.88 2.98 2.93 0.06 CARAGA 100.00 100.00 100.00
..CARAGA 2.83 2.99 2.80 -0.03 Agusan del Norte 12.11 12.08 13.78 1.67
....Agusan del Norte 2.32 2.49 2.84 0.52 Agusan del Sur 77.15 78.04 78.97 1.81
....Agusan del Sur 3.18 3.30 3.02 -0.16 Dinagat Islands 0.02 0.05 0.10 0.09
....Dinagat Islands 1.19 1.80 1.53 0.34
Surigao del Norte 1.02 1.24 1.17 0.15
....Surigao del Norte 1.74 1.95 1.80 0.07
Surigao del Sur 9.70 8.59 5.98 (3.72)
....Surigao del Sur 1.83 2.00 1.50 -0.32
Source: PSA; Computation-PPDO, Agusan del Sur Source: PSA, Computed - PPDO, Agusan del Sur
Legend: High Moderate low Legend: High Moderate low
Oil Palm
69
The province is apparently the hub of palm oil industry in Caraga. For two years
(2014 & 2015), its performance is above the country and the region. It has the also the
highest productivity value than the country, region and other provinces in Caraga of
8.43 in 2014 and 9.14 in 2015.
For three years, the province has consistently posted the biggest share in
Caraga of 98% or 34.65% of the 35.42% of Caraga’s share in the country. Though the
production of the province has been decreasing, it has performed better than the
country, region and other provinces in Caraga.
Table 29. Oil Palm Share of Production and Change, by Geolevel, 2013 & 2015
Change (%
SHARE OF PRODUCTION (%)
pts.)
Geolevel
2013 2014 2015 2013 to 2015
Meanwhile, the area planted in the province has a slight increase of 0.77%
within three-year period. In 2013, a total of 19,041.13 has. is planted with oil palm of
70
which 10,220.20 hectares is owned by 656 individual growers and 8,820.93 hectares is
owned by companies. Sta. Josefa has the highest increase in 2013 in the area planted
followed by Rosario and Bunawan. Moreover, the biggest area planted is in Bunawan
followed by Trento and Sta. Josefa. The total estimated volume in 2013 is 174,118 MT
of which the highest volume is 16,390 MT in Rosario followed by 11,943 MT in
Prosperidad.
16,000 16,390
14,000
Vol. of Prod'n. (MT)
12,000 11,943
10,000
8,647
8,000 8,057
6,000
5,047
4,000 4,486
3,067
2,000 2,328 1,890
1,266
241 237 660
0
Bay. San San Sta.
Bun. Esp. La Paz Lor. Prosp. Ros. Tal. Trento Ver.
City Fran. Luis Jos.
Value of Prod'n. 3,067 11,943 241 2,328 5,047 1,890 8,057 4,486 237 8,647 660 16,390 1,266
71
Francisco, Sta. Josefa, Trento and Veruela. Other municipalities and a city have no
additional areas planted. Meanwhile, Filipinas Palm Oil Plantation, Inc. has the highest
area planted among the companies in the province.
Rubber
Several programs of both local and 2013 2014 2015 2013 to 2015
CARAGA 100.00 100.00 100.00
national agencies have complemented Agusan del Norte 5.04 6.13 6.10 1.05
Agusan del Sur 94.00 92.91 92.80 (1.19)
in the rubber production such as USAD Dinagat Islands - - - -
Surigao del Norte - - - -
Program of PGAS as well as the National Surigao del Sur 0.91 0.89 0.99 0.08
Greening Program (NGP) of DENR, and Source: PSA, Computation - PPDO, Agusan del Sur
Legend: High Moderate low
Philippine Rural Development Program
(PRDP) of DA funded by World Bank.
72
Table 32. Rubber Productivity, by
Geolevel, 2013-2015
Data shows that the province has a Change (%
Rubber Productivity (MT/Ha.)
pts.)
minimal share of rubber cuplump Geolevel
2013 to
2013 2014 2015 2015
production in the country but it has the
PHILIPPINES 2.40 2.08 1.79 -0.61
greatest share in Caraga of 92%. Though CARAGA 0.87 0.89 0.96 0.10
Agusan del Norte 0.66 0.84 0.96 0.30
the province has a decreasing trend in the
Agusan del Sur 0.94 0.95 1.02 0.08
value of rubber productivity, it has still Dinagat Islands - - - 0.00
Surigao del Norte - - - 0.00
achieved a better performance compared Surigao del Sur 0.14 0.14 0.18 0.04
to the region and other provinces in Source: PSA, Computation - PPDO, Agusan del Sur
Legend: High Moderate low
Caraga. This is due to the introduction of
high yielding variety of seedlings like PB160 thus increased the farmers’ awareness
on planting the said variety.
consistently posted the highest in production from 2011 to 2015 because it was not
badly hit by Typhoon Pablo.
Cacao
Another priority crop of the province is cacao. The area planted with cacao has
significantly increased by 32.7% in 2013 and 2014. This is due to the various
interventions of provincial government, DA and DENR. The presence of KENEMER that
provides quality cacao seedling has also contributed in the increase of area planted.
73
KENEMER has existing Cacao Nursery in Lapinigan, San Francisco that is considered
the biggest nursery in Asia.
The province has the greatest share of cacao production among the provinces
in Caraga. However, in terms of productivity, the province has a decreasing trend.
Also, data shows that the productivity of the province is below the region’s and the
country’s value.
74
Change (%
SHARE OF PRODUCTION (%)
points)
Geolevel
2013 2014 2015 2013-2015
CARAGA 100.00 100.00 100.00
Agusan del Norte 12.34 12.66 15.97 3.62
Agusan del Sur 43.41 50.22 50.94 7.52
Dinagat Islands - - - -
Surigao del Norte - - - -
Surigao del Sur 0.31 0.25 0.23 (0.08)
Source: PSA, Computation - PPDO, Agusan del Sur
Meanwhile, the total production of cacao in the province has been fluctuating
for the five-year period but posted the highest in 2015. Talacogon contributed the
highest in 2015, followed by Bayugan City and Sibagat. In terms of the percentage
change in production for five years, Rosario has posted the highest followed by
Loreto, and Talacogon. In terms of value chain, the raw products are processed in
Bayugan City as tablea only.
Other Crops
75
On coconut production, the province has a fluctuating trend in three years. Its
share of production in the region is only minimal of only 4.74% considering that
Surigao del Sur is the coconut hub in Caraga. The production as well as the area
harvested has no significant percentage change for three year period.
Coffee production in the province is very minimal with only 2.58% percentage
share in the region. It has a decreasing percentage change within the three-year period
of 37% however there is a slight increase in the area harvested of 3.24%.
Meanwhile, the province in 2015 has greater share in Caraga in the production
of banana and abaca of 26.22% and 28.83%, respectively. However, value adding
activity for these commodities is very minimal. Raw banana is processed into chips
while Abaca is processed into Sinamai in Sibagat. However, most of the raw materials
in Sibagat are sold to Legaspi City. Sinamai production of Sibagat cannot meet the
demand of the linked market due to lack of workerswho are willing to engage in
“tinagak” fiber that is labor intensive.
Moreover, the province has also high share in terms of the area harvested of
these two commodities in the Caraga of 34.59% for banana while 31.17% for abaca.
Table 38. Area Harvested, Percentage Share, and Percentage Change of other
Crops, 2013-2015
76
Area Harvested (has.) Percentage Percentage
Crops Caraga Region Agusan del Sur Share (%) Change (%)
2013 2014 2015 2013 2015 2015 2015 2013-2015
Coconut 191,107.00 191,108.00 191,103.00 14,884.00 14,885.00 14,885.00 7.79 0.01
Coffee 4,368.00 4,397.25 4,417.25 1,480.00 1,508.00 1,528.00 34.59 3.24
Banana 23,019.96 23,105.95 23,109.37 10,242.27 10,759.00 10,869.80 47.04 6.13
Abaca 10,437.00 10,447.00 10,477.00 3,236.00 3,236.00 3,266.00 31.17 0.93
Source: PSA; Computation - PPDO, Agusan del Sur
Carabao
Cattle
77
On cattle production, the province ranks second in the percentage share in the
Caraga next to Agusandel Norte (1st rank). The provincial government has been
supporting the cattle production through BakaAlangsaKalambuansaAgusan del Sur
(BAKAS) Project with the objective of increasing female breeder base and improving
genetic make-up of cattle. Though the province’s production shares one third in the
region, still the supply of cattle meat is not sufficient for the consumption of the
populace in the province. The province gets its supply from General Santos City and
Cotabato provinces.
Hog
78
Share of Production (%)
Geolevel
2012 2013 2014
..CARAGA 100 100 100
....Agusan del Norte 25.08 26.18 25.60
....Agusan del Sur 28.33 28.17 28.85
....Surigao del Norte 21.62 20.76 20.99
....Surigao del Sur 23.66 23.48 23.02
....Dinagat Islands 1.32 1.41 1.53
Source: PSA, Computed - PPDO, Agusan del Sur
Goat
On goat production, the province has the highest contribution among the
provinces in Caraga for two (2) years (2013 and 2014). This is followed by Agusandel
Norte then Surigao del Sur. The local government has continuously supported the
goat production through Agusandel Sur Goat Project. This aims to improve the genetic
make-up of native goats. This is implemented in a loan scheme and is also self-
revolving. The provincial government is also processing goat’s milk. Farmers are also
trained on milk processing that serves as incubation for farmers who would like to
engage in this kind of business.
Poultry
79
Table 43. Poultry Share of Production, by Geolevel,2012, 2013 & 2014
Share of Production (%)
Geolevel
2012 2013 2014
..CARAGA 100 100 100
....Agusan del Norte 49.10 57.12 53.15
....Agusan del Sur 21.91 20.28 26.06
....Surigao del Norte 12.22 10.08 9.11
....Surigao del Sur 15.37 11.41 10.73
....Dinagat Islands 1.40 1.11 0.96
Source: PSA, Computed - PPDO, Agusan del Sur
Industry
80
The industry in the province is both agri-forestry and mineral resource-based.
The industrial investments support the major commodities produced in the province
with comparative advantage such as rice, corn, rubber, oil palm, and falcata. Other
commodities which are processed are abaca, calamansi, mangosteen, and banana.
Agri-forestry Processing
On processing of industrial crops, the province has the first oil palm
processing facility established in the country. There are two processing plants
operating in the province which produce crude palm oil and kernel namely: the
Filipinas Palm Oil Plantations, Inc. in Rosario and the Agusan Plantations Inc. in
Trento. Caraga Oil Refinery Inc. (CORI) is another palm oil company that produces
refined palm oil in San Francisco.
Rubber Processing
The presence of two crumb rubber processing facilities in Rosario (VPO Farm)
and Prosperidad (FASRMCO) shows competitive advantage of the province among
provinces in Caraga in terms of value adding of rubber. However, the issue is on the
under utilization of the processing center. Its maximum capacity is not yet attained
since capitalization of the coop is not that much to cope with the 20 thousand kilos of
cuplump per day. The challenge is on the full utilization of the facility to encourage
value adding activity rather than selling raw material to outside traders. Another
challenge is the low buying price that does not encouraged farmers to harvest as well
as to process the raw material.
Grain Processing
81
Food Processing
Various food processing center are established in the province. Bayugan City
is known of its cacao production and tablea processing that is operated by MAMCO
as well as the Fruit Wine Making “Bandy Wine” established in Makiangkang, Bayugan
City. Bayugan City is known as the growth center for CDA I, with its identified role as
the “Agri-processing Center”. Other food processing centers are banana chips in
Prosperidad and Bayugan City, Lily’s calamansi juice and Mangosteen juice in
Trentoand coco sugar of Buena Palma in Sibagat. These products are already
marketed region-wide.
Wood Processing
On wood processing, ten companies are engaged in this industry. Of the total,
eight (8) wood processing plants are located in Talacogon such as Casilayan
Softwood Development Corporation; Provident Tree Farms, Inc.; Sinafal Saw Mill
Company, Inc.; Talacogon Woodworks, Inc.; ZILWOOD Corporation; Woodking
Industry, Inc.; MINDAHILA Mini Sawmill; WOODHOUSE Trade & Industry Corp.; and
WOODHOUSE Trade & Industry Coop.
Talacogon is the growth center identified in the spatial strategy (CDA IV) with
the functional role as the “wood processing center”. However, problem arises with the
release of E.O 24 that caused loss of job and income of the populace. This has
considerably contributed to high poverty in the province.
The other two (2) wood processing centers are ELMO Woods in Bayugan City
and Esperanza Wood Products Enterprise, Inc. in Esperanza.
Mining Industry
Agusan del Sur is rich in mineral resources such as gold, silver, copper,
polymetalics, limestone, gypsum, manganese, phosphatic soil, coal quarts, white clay,
and sand and gravel. Mining industries in the province are located in two
municipalities such as Rosario and Bunawan. In Rosario, three (3) gold mining
82
companies are operating namely: PHILSAGA Mining Corporation, and JTC Mining
Corporation and mining company owned by VPO.
Mining and Quarrying is the main driver for growth in Caraga Region because
of its high competitiveness. It is considered a great contributor in the achievement of
the region’s highest growth of GRDP of 9.6% from 2009-2011 (NSCB).Mining has a big
share in the income of the region and the country as a whole. However, it is significant
to ensure environmental protection and responsible mining which is supported by the
Executive Order No. 79 series of 2012. The stop operation of illegal mining is a
contributory factor of low income of households who are engaged in such activity.
Services Sector
83
The services sector in the province is considered next to AFF Sector in terms
of employment. Ideally, investment on services sector should be promoted because it
will significantly generate more employment compared to industry sector. The
province should aim more than fifty percent of employment in this sector in order to
be considered as an urbanized province. However, few investors are into services
sector which generated only 19% of the employment (CBMS data, 2015) in the
province.
84
Table 46.No. of Business Enterprises under Services Sector
In the province, San Francisco is the growth (Servicing),by Municipality, 2013-2015
center in CDA 2 that considerably fulfilled Municipality
SERVICING Change (%)
2013 2014 2015 2013 to 2015
itsrole being the “Commercial Center”.
Bayugan 111 99 132 18.92
Moreover, it has consistently been Bunawan 10 27 83 730.00
Esperanza 1 1 9 800.00
nominated as the most competitive
La Paz 2 1 5 150.00
municipality in the province. In fact it is Loreto 2 10 400.00
ranked 27th in the Competitiveness Index in Prosperidad 51 60 73 43.14
Rosario 15 28 22 46.67
2015 among the provinces in the country. It San Francisco 111 120 145 30.63
is attributed by its strategic location San Luis 1
Santa Josefa 11 9 14 27.27
catering not only the local populace but also
Sibagat 5 4 7 40.00
the populace of neighboring province like Talacogon 16 24 10 (37.50)
Surigao del Sur. Trento 63 71 36 (42.86)
Veruela 5 4 9 80.00
Agusan del Sur 403 449 555 37.72
However, Esperanza, Bunawan and Source: DTI, Agusan del Sur; computation - PPDO, ADS
La Paz apparently posted high in terms of percentage change for the past three years
considering that only few service enterprises were registered in 2013.
On the other hand, trading is also under the service sector. The total number of
business enterprise on trading in the province has been increasing from 564 in 2013
to 734 in 2015. For the past three years, the number of registrants engaged on trading
has significantly increased of 30.14%.
85
TRADING Change (%)
Municipality
2013 2014 2015 2013 to 2015
Bayugan 139 144 162 16.55
Bunawan 21 22 23 9.52
Esperanza 8 13 16 100.00
La Paz 7 6 23 228.57
Loreto 7 8 63 800.00
Prosperidad 83 84 107 28.92
Rosario 23 49 42 82.61
San Francisco 99 121 132 33.33
San Luis 1 4 9
Santa Josefa 37 24 54 45.95
Sibagat 25 8 22 (12.00)
Talacogon 18 23 17 (5.56)
Trento 79 97 45 (43.04)
Veruela 17 40 19 11.76
Agusan del Sur 564 643 734 30.14
Source: DTI, Agusan del Sur; computation - PPDO, ADS
Employment
86
Figure 28. Employment Share by Sector, ADS, CBMS 2015
Bayugan 5.4% 0.06% 0.5% 2.7% 1.0% 0.23% 0.12% 1.3% 1.0% 1.7% 0.12% 1.90% 15.95%
Bunawan 2.9% 0.34% 0.2% 0.8% 0.2% 0.82% 0.11% 0.3% 0.2% 0.5% 0.03% 0.60% 6.95%
Esperanza 5.0% 0.04% 0.3% 0.6% 0.2% 0.07% 0.09% 0.4% 0.3% 0.8% 0.02% 0.82% 8.60%
La Paz 2.5% 0.10% 0.1% 0.2% 0.1% 0.03% 0.04% 0.1% 0.1% 0.3% 0.01% 0.17% 3.88%
Loreto 3.1% 0.06% 0.1% 0.4% 0.1% 0.05% 0.04% 0.2% 0.1% 0.4% 0.01% 0.47% 5.04%
Prosperidad 4.7% 0.05% 0.5% 0.7% 0.5% 0.26% 0.15% 0.7% 0.7% 1.4% 0.06% 1.56% 11.42%
Rosario 1.7% 0.35% 0.1% 0.4% 0.2% 1.14% 0.10% 0.3% 0.3% 0.4% 0.02% 0.58% 5.66%
San Francisco 2.1% 0.06% 0.1% 0.7% 0.5% 0.51% 0.14% 0.5% 0.7% 2.2% 0.13% 1.72% 9.46%
San Luis 2.8% 0.09% 0.2% 0.4% 0.2% 0.06% 0.05% 0.3% 0.1% 0.4% 0.03% 0.43% 5.07%
Sibagat 2.3% 0.01% 0.2% 0.4% 0.2% 0.11% 0.05% 0.4% 0.2% 0.5% 0.03% 0.42% 4.71%
Sta. Josefa 2.4% 0.01% 0.0% 0.3% 0.1% 0.07% 0.04% 0.3% 0.2% 0.5% 0.03% 0.32% 4.33%
Talacogon 2.8% 0.06% 0.2% 0.6% 0.3% 0.08% 0.08% 0.3% 0.3% 0.7% 0.04% 0.60% 6.18%
Trento 3.3% 0.07% 0.2% 1.0% 0.3% 0.08% 0.05% 0.4% 0.4% 0.9% 0.05% 0.88% 7.60%
Veruela 2.4% 0.03% 0.0% 0.7% 0.1% 0.07% 0.07% 0.0% 0.1% 0.2% 0.01% 1.45% 5.13%
Agusan del Sur 43.4% 1.35% 2.7% 10.0% 4.0% 3.56% 1.12% 5.5% 4.8% 11.0% 0.58% 11.92% 100.00%
Source: CBMS 2015, Agusan del Sur
Joint Probability - PPDO, Agusan del Sur
Though the province has vast land and abundant natural resources, its
constituency belongs to poverty level and experiences the effect of climatic changes
brought by various causes like forest denudation, increasing pollution and increasing
hazard sensitive areas which eventually results to environmental degradation.
Therefore, the environment sector shall strictly enforce laws, policies and
ordinances for the protection of environmental & management of natural resources
within the province. With this, the province shall have an adaptive
community/constituency and shall have a resilient environment despite of climate
change.
89
the communities in hazard prone areas by increasing the adaptive capacity of the
community through the implementation of Programs, Projects and Activities (PPAs)
and to capacitate the community in order to reduce vulnerability.
The main issue of the sector is the vulnerability to natural calamities and human
induced hazard. Based on the series of workshop conducted in the preparation of the
plan, there are six (5) major public safety and security issues/problems that continue
to confront the province. These are low capacity of the community to deal with
disasters, increasing number of population/ areas affected by flood / landslide/soil
erosion, vehicular accidents, armed conflict, occurrence of fire and crime incidence.
There are lot of factors confronting the communities why they are not resilient
to any type of Natural Calamities and Human induced hazards: the remoteness of the
area in which Information, Education Campaign (IEC) regarding hazard/calamities is
slow and the poor Implementation of RA 10121 “The Philippine Disaster Risk
Reduction and Management Act of 2010”.
Public safety and security sector targets for the next three (3) years is to
increase number of capacitated communities from 24 barangays to 318 by 2019 to
cope with the gap of 294 barangays.
During disaster, affected communities with high poverty have also poor
capacity to rebuild their source of living in times of disaster. The current
administration provided relief operation, early recovery project and
procurement/distribution of Seedlings to replace the damaged crops and
commodities.
90
Increasing number of Population/ Areas Affected by Flood /
Landslide/Soil Erosion
The province is prone to different kind of hazard, but the most familiar are the
three (3) hazards mentioned above. Population increased yearly thereby population
affected by hazards is also increasing. Flood and slope control mitigation project are
not yet in-placed. As of 2015 a total of 49,962 household population were affected by
hazard. The table below shows the historical data.
Flooding agriculture
Flood properties.
occurrence due to 14 209 20 249,814 49,172
(2011) heavy rainfall that lasted for
Typhoon Incessant heavy rains and 14 248 18 22 1 286,280 58,412
Pablo strong winds have prevailed in
(BOPHA) - the Province of Agusan del Sur
December on December 4, 2012. This
4, 2012 resulted to the trees to uproot
and collapse on houses and
roads, swelling of rivers and
Tropical tributaries,
The triggering
week-long rains brought 14 209 11 27 284,556 58,627
Depressio by the low-pressure area
n before it became Agaton has
Agaton- wreaked havoc in Agusan del
January Sur affecting 58,627 families
2014
Tropical in
The209 barangays.
tropical storm brought 14 188 8 1 2 237,537 43,233
Storm heavy to intense rainfall to
Seniang Agusan del Sur flooding
-December
Source: barangays in the province.
DRR/CCA-Enhanced It
PDPFP 2008-2017, PDRRMO –Rapid Damage Needs
Areas exposed to flood, landslide and soil erosion hazards have been identified
through Geographical Information System (GIS) Map provided by NAMRIA and MGB,
91
but the number of population vulnerable did not decrease due to relocation site for the
affected communities was not realized. Funds for the said project were available but
the required documents to release the funds like MGB certification and liquidation
report of the barangay was not available.
Project like evacuation center was constructed to give shelter for the people
during calamities. A total of 19 evacuation centers/ multi-purpose buildings were
provided thru counterpart by the province. However, some project location of the
constructed facility was not totally safe. It is still situated at a hazard prone area.
Vehicular Accidents
92
The provincial road and bridges implemented by the provincial government follow the
standard design in implementing the road project. Road safety plan was prepared by
the Provincial Engineering Office (PEO) and adopted by the Office of the Sangguniang
Panlalawigan.
The provincial engineering office in coordination with the technical staff from
DILG central office is planning to conduct survey for the kilometer post installation in
every provincial road section. This plan and initiative could help in the establishment
of data base for transport sector.
Armed Conflict
Rebellion/ political conflict still exist in the province, data from Revised Caraga
Regional Development Plan 2013-2016 revealed that Agusan del has the highest
number of CNN-affected barangays in Caraga Region.
One of the issues that the province is still facing is the Resource-Use Induced
conflict, this includes inequitable access to natural resources, illegal mining,
boundary disputes, conflicting land use, overlapping of tenurial instrument and
inequitable sharing of royalties from natural resources.
93
2017-2019 proposed programs and projects include capacity development project and
Assistance to contributors and Actors of Peace (ACAP) Program.
Occurrence of Fire
Fire incidence has an increasing trend from 2013 to 2014. There is an increase
of 18.18% and 28.85% in 2014-2015. For the period of two years from 2013-2015, fire
incidence increased by 52.27%.
Fire Incidence
80
67
60 44 52
40
Number of Fire
20 Incidence
0
2013
2014
2015
Fire incidence is categorized into structural fire, grass fire, post fire and
vehicular fire. Rosario has the highest in number of fire incidence and 333.33%
percentage increase among the LGUs in the province from CY 2014-2015 as shown in
the table below. Fire incidence happened in Rosario are mostly grass fire according
to BFP.
94
Province/ Fire Incidence
Municipality 2013 2014 2015
Loreto 1
Prosperidad 3 8 10
Rosario 1 3 13
San Francisco 5 10 12
San Luis 1
Sta. Josefa 3 2 3
Sibagat 2 1 1
Talacogon 2 7 5
Trento 8 3
Veruela 1
Agusan del Sur 44 52 67
Data Source:
BFM
The Bureau of Fire Protection (BFP) has a total of 21 Fire Trucks owned of the
total 24 Fire Trucks in CY 2015. The remaining three (3) Fire Trucks were owned by the
Local Government Units (LGUs) of Bayugan City, Bunawan and San Luis. Base on the
data there is an increase of 20% from 2012 of fire trucks and also an increase of 17.50%
Firemen from 2012.
In CY 2012, the province is served by nine (9) Fire Stations and it increase to 11
fire stations in 2015 managed by BFP. The Municipality of La Paz, San Luis and Veruela
has their own temporary fire stations managed by their LGU’s. Based on the standard
of 1 fire truck per 28,000 populations the province should have 25 fire trucks to meet
the standard. With this computation the province proposed for additional fire truck to
meet the standard and to replace the old and damage equipment.
95
Table 51. Number of Fire Men and Fire Truck
Population
Province/ Firemen Fire Population Firemen Fire
(2012
Municipality (2012) Truck (2015) (2015 Truck
projected)
Bayugan 100,550 13 3 103,202 15 3
Bunawan 40,112 - 1 45,151 1 2
Esperanza 53,602 6 1 54,801 6 1
La Paz 30,409 - 1 28,217 5 2
Loreto 41,332 6 1 42,501 6 1
Prosperidad 77,847 10 3 82,631 10 2
Rosario 40,557 6 1 46,683 6 1
San Francisco 74,179 11 3 74,542 13 3
San Luis 34,302 - 1 32,109 - 1
Sta. Josefa 25,671 7 1 30,442 6 1
Sibagat 31,467 - 1 26,729 1 2
Talacogon 38,642 5 1 38,374 9 2
Trento 48,376 10 2 51,565 9 2
Veruela 41,362 - 43,706 1 1
OPM-Prov’l.
6 - 6
Office
Agusan del
656,418 80 20 700,653 94 24
Sur
Source: BFM , Year: 2012 & 2015
96
Crime Incidence
For the period of 2013-2015 Crime Volume has a fluctuating Change. Graph
below shows that there is an increase of 119.90% in 2014 from 1,191 crime volume in
2013.For year 2015 crime volume, there is a decrease of 8.21% from 2,619 incidents in
2014.
Crime Volume
3000
2000
1000 2619
1191
0 2,404
2013
2014
2015
Index crimes are crimes against person such as murder, homicide, physical
injuries, and rape; and crimes against properties such as robbery, theft,
carnapping/motornapping and cattle rustling. Based on the data gathered from
Philippine National Police, Agusan del Sur, crime on physical injuries topping the list
followed by murder and theft in 2015.
97
Non-index crimes are violations of special laws such as drug possession, drug
seizure, and others, attempted murder, Malicious mischief, threat, Estafa are also
prevalent non-index crime.
Bayugan City is the top in crime status both in index and non-index crime in
2015, followed by the Municipality of San Francisco and Prosperidad. As to crime
status report yearly from 2013-2015 there is an increasing trend in the number of cases
of crimes committed. An inadequate security measure is one of the issues and
concern of the sector and the lack of surveillance and response vehicle in some areas.
In 2012, the province is served by 509 police force on a ratio of 1:1,290 with the
municipality of Prosperidad having the highest ratio of 1 policeman to 2,994
population while the municipality of LaPaz has the lowest ratio of 1 policeman to 1,170
population.
99
Bunawan 40,112 22 1,823 45,151 30 1,505
Esperanza 53,602 23 2,331 54,801 28 1,957
La Paz 30,409 26 1,170 28,217 34 830
Loreto 41,332 22 1,879 42,501 25 1,700
Prosperidad 77,847 26 2,994 82,631 32 2,582
Rosario 40,557 24 1,690 46,683 32 1,459
San
74,179 36 2,061 74,542 57 1,308
Francisco
San Luis 34,302 21 1,633 32,109 27 1,189
Sibagat 31,467 23 1,368 30,442 33 922
Sta. Josefa 25,671 21 1,222 26,729 27 990
Talacogon 38,642 25 1,546 38,374 26 1,476
Trento 48,376 22 2,199 51,565 33 1,563
Veruela 41,362 23 1,798 43,706 29 1,507
Provincial Public Safety
99 101
Company (PPSC)
Police Provincial Office 56 31
Agusan del
509 1,290 700,653 602 1,164
Sur 656,418
Source: PNP ADS, year: 2012
Transportation Services
100
The province total road network has grown from 3,102.62 kilometers in 2007
to 3,220.69 kilometers in 2012. The increased of 3.81% is due to the on- going
construction of Department of Public Works and Highways in the provincial boundary/
external access and the road rehabilitation project from different funding institution.
Road Density in Agusan del Sur is 0.359 km per square km. of land area
which is much lower compared to Caraga Region with a road density of 0.44 and
0.597 road density of the country. The road density standard set by the Housing and
Land Use Regulatory Board (HLURB) is 1 kilometer per square kilometer.
On Public Buildings
For the delivery of better services to the people, the thirteen municipalities
and one city had constructed/rehabilitated their municipal buildings.
The provincial government has also Oil Filling Station, Heritage Center, and
Naliyagan Cultural Center.
Other public buildings includes School buildings for Secondary and
Elementary level, Day Care Centers, Rural Health Centers, District and Community
Hospitals, and Multi-purpose buildings in the 13 municipalities and one city.
101
B. INSTITUTIONAL
102
C. RISK PROFILE
The Province of Agusan del Sur has identified 6 Hazards, namely: Flood,
Rain-Induced Land Slide, Earthquake, Earthquake Induced Land Slide, Typhoon,
Armed-Conflict, and Liquefaction.
1. Hydro-metrological Hazards
1.1 Flood
Historical Occurrence
Flooding is the yearly natural hazard that Agusan del Sur is experiencing due
to its geographical location. Historically, there were 7 flood occurrences every
year; out of which, 3 flood occurrence were observed by local folks as high, but
we have no capability to measure the depth and no official records to back the claim.
At the center of the province lies the Agusan River which absorb waters from the 12
103
tributaries and the Agusan Marsh. The Agusan Marsh serves also as the catch
basin of the Agusan-Davao plain in Eastern Mindanao, draining the Diwata mountain
ranges of Agusan del Norte and Agusan del Sur in the east, the mountain ranges of
Bukidnon in the west and the hills of Compostela Valley in the south, with about
59 lakes within, it acts as the retarding basin for floodwaters that regularly
inundates the Agusan Valley during the northeast monsoon.
The Municipalities near the Agusan River are yearly experiencing flood
occurrence, and an enormous flood every 10 years. The Agusan River and its 12
major tributaries usually overflow and affected several lives and dwellings as well as
infrastructure and agricultural properties.
The official records of the province can only be traced from the year 1999 to
2011 with a total of 9 flood occurrences. These flood occurrences were attributed to
the heavy rainfall that lasted an average of one to two weeks. Among the flood
occurrences, it was in 1999 that there were 254 barangays affected out of the 314
barangays, 19 persons died, 53,144 families and 233,269 persons affected.
104
105
1.2. Rain- induced Landslide
Historical Occurrences
As mentioned earlier, the province belongs to the type ll climate, hence, rainfall
is eminent. Landslide/mudflows are created by the continuous heavy rains over
mountainous or hilly areas that are denuded especially the areas along the
municipalities of Sibagat, Bayugan, Prosperidad, San Francisco, Rosario, Bunawan,
and Trento or the Highway Municipalities.
In the past 10 years, there was no recorded damage other than what was
reported by the Department of Public Works and Highways (DPWH) on Infrastructure.
There were only two rainfall-induced landslides recorded, in 2002 and 2011 affecting
27 various locations/road sections. Comparing the two, the former had only Php
9,100,000.00
In the year 2002, most of the damages recorded were in the Municipality
of Esperanza while in the year 2011, highest damage in infrastructure was in the
municipality of Sibagat. Below is a table of Past Rainfalls – Induced Landslide Events.
106
Population/Areas Impact (Damage
No. Description
Affected to Infrastructure)
Tagyago Section, La Paz,
5 Heavy rainfall (eroded Ag. Sur km. 1354+915- 1,000,000.00
shoulder/slip, Jan 6-11, 2002) km. 1354+945
Heavy rainfall (eroded Osmeña Road Section, La
6 shoulder/slip, Jan 6-11, 2002) Paz km. 1355+500-km. 1,000,000.00
107
Population/Areas Impact (Damage
No. Description
Affected to Infrastructure)
Heavy rainfall (bulging of
carriageway, one lane right Afga Road Section,
side going to Davao City, Sibagat, ADS, km.
16 including shoulder, Feb. 4, 1247+142 2,500,000.00
2011)
Heavy rainfall (deference of
carriageway & shoulder due Afga Road Section,
17 to settlement of carriageway, Sibagat, ADS, km. 1247+ 2,000,000.00
Heavy rainfall (road shoulder Panaytay Road Section,
18 slip with cracks extending to Bayugan, ADS km.
carriageway, Feb. 4, 2011) 1279+650 2,000,000.00
Heavy rainfall (road shoulder Sianib Road Section,
slip, slope protection & Bayugan, ADS km.
19 concrete gutter damage, 1281+500 km. 1281+800, 3,000,000.00
Feb. 4, 2011) & km. 1282+200
Prosperidad Road
Heavy rainfall (road shoulder Section, Prosperidad,
20 slip, slope protection, Feb. 4, Agusan del Sur, km.
2011) 1296+400 1,000,000.00
Heavy rainfall (road shoulder
slip, cracks extending to Salvacion Road Section,
21 carriageway, slope protection, Prosperidad, Ag. Sur, km. 2,000,000.00
Feb. 4, 2011) 1298+300
108
Population/Areas Impact (Damage
No. Description
Affected to Infrastructure)
NRJ Butuan City-Pianing-
Heavy rainfall (four portion Tandag Road Sitio
road slip only half lane Dandanon, Brgy.
24 passable, Feb. 4, 2011) Kulambugan km. 20,000,000.00
1254+250-
NRJ km. 1256+700
Bayugan-Calaitan-
Heavy rainfall, minor soil Tandag Road, Bayugan,
25 slope collapsed Ag. Sur, km. 1268+242-
km. 1282+900
Heavy rainfall five (5) portion NRJ Bayugan-Calaitan-
of roadway Tandag Bayugan, Ag.Sur,
Depression/cut-off with two km 1282+900 km 48,000,000
26 section only half lane 1298+492
passable, but still aggravating
due to downpour of rain, with
slip on road shoulders,
27 resurfacing materials
Heavy rainfall washed
(rock/soil slope Talacogon (K1353+155- 3,000,000.00
failure road/embarkment slip) k1365+000
roadway damaged and La Paz(K1366+000-
washed out. K1368+00 3,000,000.00
109
110
Hazard Characterization
The source of Rainfall-induced Landslide (RIL) is from the Office of Mines and
Geo Science Bureau (MGD) in Surigao del Norte. During the hazard characterization
workshop held in Tagaytay City a staff from MGB provided updated shape file on RIL.
This shape file was processed using GIS software with the barangay boundary to
identify the affected area by barangay.
One factor that contributes the RIL is the denuded vegetative covers within
steep slope, most of this area situated along the national road. Based on the map
most of the high susceptibility areas are within the 50 percent and above slope
located along the boundary of Surigao del Norte (eastern side) and Bukidnon
(western side). The rain-induced landslide was experienced in all municipalities with
a total area of 714,034 hectares. Based on matrix, 233 brgys out of 314 brgys are
prone to rain-induced landslide.
The most affected municipality is in Sibagat along the national road that
affects the motorist due to damage of carriageway. It can also affect the economy of
the province since the affected area is the external road of the province. Some areas
can experience only minor damage on road shoulder in the internal circulation.
Prime agricultural land is less affected since there is no major crop within the high
susceptibility area.
1.3 Typhoon
Historical Occurrence
For two consecutive years, the province had experience typhoon, the typhoon
Sendong on December 16, 2011; and Typhoon Pablo on December 4, 2012. The
typhoon Pablo was considered one of the deadliest disaster in the whole world in
2012 accor4ding to ne international agency who studied world disaster. Typhoon
Pablo hit 13 municipalities and one city, and there were six municipalities that
were hardly hit; these were the municipalities of Bunawan, Trento, Sta. Josefa,
Veruela, Loreto, and La Paz. Table below shows the cost of damaged on
infrastructure, agriculture, and casualties in the whole province.
111
2. Geologic Hazards
Historical Occurrence
There were two records of earthquake in the province that happened in June 7
& 8, 1999. It only occurred in Bayugan and Talacogon with a total number of 9
persons injured, 28 houses damaged, Php 69,024,000.00 infrastructure damages and
Php 900,000.00 worth of agriculture properties.
Hazard Characterization
The factors that contribute to this type of hazard are the two parallel fault line
segments (Northeastern Mindanao and Agusan) across the Agusan Marsh that may
cause liquefaction and Liangga fault line segment.
For the Ground Shaking type of hazard, most of the barangays are affected.
Base on the total land area of 896,550 has of the province, 99% of this is affected
by ground shaking. On Liquefaction type of hazard, 260 out of 314 barangays are
affected with a total area of 355,669 has or 260% of the total land area.
112
The barangays affected are within the Agusan Marsh where there are several
lakes. On the Earthquake-induced Landslide, 197 out of 314 barangays were affected
with a total area of 554,365 has or 62% of the total land area. Most of the affected areas
are within the 50% above slope.
As discussed earlier, the province is prone to five (5) disasters only, but for
2011 and 2012 the province had experienced typhoon; typhoon Sendong, (2011) and
typhoon Pablo (2012) which makes six (6) hazards recorded: namely Flood, Rain-
induced Landslide, Earthquake or ground shaking, earthquake-induced Landslide,
Liquefaction, and Typhoon.
As reflected in the table below, it is flooding and typhoon that has greatly
affected the municipalities/city. Reports showed that it has the highest effect in
terms of area, population, and damages both in infrastructure and agricultural
properties.
114
C.2 Vulnerability
Agusan del Sur rainfall data of 480 mm/day has a corresponding likelihood
score of two (low), severity consequence score of seven (moderate) or within a range
of 14, which is still low. However, during prolong heavy down pour, flooding extend
to higher level. This rare scenario of flooding is projected with a return period of 39-
100 years (PAGASA). Of the 13 municipalities, ten municipalities are exposed to High
Susceptible Areas (HSA).
2.2 Built-up
The condition of building and structures reveals that most of the residential
houses, commercials establishments, and institutional buildings in the barangays
are made of light materials. During flooding, most of these houses are totally
115
destroyed, and this is the problem that the province needs to address. This condition
is also related to the zoning regulations, but according to residents, their
settlement areas are not flooded many years ago.
About 53.2 percent among families are poor. The frequent flooding resulting
to devastation is considered a big factor that even aggravates the situation of these
poor families considering that they have fewer resources to adaptation measures.
2.3 Agriculture
C.3 Capacity
The Provincial Government of Agusan del Sur has organized the Provincial
Disaster Risk Reduction Management Office under the Office of the Governor (RA
10121) headed by a designated PDRRM Officer.
Volunteers from the different sectors are organized and trained to respond in
time of calamities. Moreover continuous conduct of trainings and enhancement
workshops to better capacitate our local emergency responders.
Early Warning System (EWS) on floods, rainfall and water level are installed
by DOST, and Provincial Government through the aid of a foreign volunteer in
different strategic places province wide.
116
117
C.4. Exposure
Roads
Total national road length is 426.81 km, exposed to flooding is 135 km; HAS is
7.33 km, MSA, 58.97 km; and LSA, 68.71 km. The municipalities of Bunawan, Sta.
Josefa, Trento, Prosperidad and Talacogon road section are most affected by
flooding.
118
D. SITUATIONAL ANALYSIS: IDENTIFYING STRENGTH, WEAKNESSES,
OPPORTUNITIES AND CHALLENGES (SWOC) FOR THE FOUR DRRM THEMATIC
AREAS.
Situational Analysis
The assessment areas as basis for analysis include specific DRRM activities per
Thematic Area such as early warning system, education and training, institutionalization of
LDRRM Office, response equipment and, resettlement program. It should also include the
cross-cutting concerns which are health, human-induced disasters, gender mainstreaming,
environmental protection, cultural sensitivity or indigenous practices, and the rights based
approach.
119
Assessment
Strengths Weaknesses Opportunities Challenges
Area
Hazards Availability of Community Availability of Update
mapping provincial geo- based hazard hazard maps provincial
hazard maps map and a good hazard map
working
relationship
with lined
NGAs/CSOs
Risk Active support HVCA of Risk Come up with
assessment of PGAS on risk municipalities assessment an HVCA
assessment and barangays activities is now
initiatives of are not available a priority of the
the national national
government government
Local Strong Technical Public safety Pass safety and
ordinances on legislative staff/TWG to and security is security
safety of support focus on now part of the ordinances
communities crafting ELA
relevant local
ordinances
Financial tools Insurance No insurance Philippine Crop Access to
policies of program for Insurance Corp. financial tools
critical facilities stakeholders/ (PCIC) and GSIS
of PGAS are in farmers
placed
120
D. 2 Disaster Preparedness
Assessment
Strengths Weaknesses Opportunities Challenges
Area
Early warning Early warning No system in Strong Formulate an
system devices are place and international effective
installed technical linkages on warning system
personnel EWS down to the
grassroots
Formulation of Enhancement of No permanent Technical Updated DRRM
DRRM Plan available MDRRMO assistance of Plan as per
MDRRM Plan OCD , VSO & standardized
CSOs template
Contingency Finalization and No permanent Technical Contingency
Plan consolidation of MDRRMO assistance of Plan for specific
CP OCD , VSO & hazards
CSOs
Drills and Technical Cooperation of Technical Continuing and
simulation capability to stakeholders assistance from regular conduct
exercises conduct multi- line agencies of hazard
hazard drills specific drills &
and simulation simulations
Organization of Organized Political Leveling up of Organized
disaster disaster interventions stakeholder volunteers
volunteer volunteer awareness, down to the
groups groups acceptance and barangay level
participation
121
Conduct of Technical Inadequate Technical Regular and
disaster capability to number of assistance from evolving
preparedness conduct trainers line agencies conduct of
related trainings disaster disaster
preparedness preparedness
related trainings related trainings
Information and Available quad- Inadequate IEC Availability of Intensified IEC
education media access program down quad-media for down to the
campaign for PGAS to the IEC grassroots level
grassroots level
Assessment
Strengths Weaknesses Opportunities Challenges
Area
Rapid Damage On-going Inadequate Available RDANA
Assessment & initiatives to capacity to resources appreciation by
Needs Analysis capacitate team conduct RDANA the grassroots
(RDANA) level
Provision of c/o PSWDO
relief assistance
Search, rescue Available Inadequate Available Coordinated
and evacuation trained equipment resources deployment of
responders responders
Incident Available 19 System Ready IMTs all Deployment and
command trained simulation over the country authorization of
system (ICS) personnel as ICS
Incident
Management
Team
Emergency Available Lacks MOU Available Coordinated
Medical trained support from Immediate
Services Personnel DOH + EMS PPS Response
Livelihood c/o PEEDO,
DSWD
122
Assessment
Strengths Weaknesses Opportunities Challenges
Area
Housing c/o NHA,
HLURB, LGU
Lifelines c/o DPWH, AFP,
PNP, ASELCO,
CSOs
Education c/o DOST,
PHIVOLCS,
DEPED,
PAGASA,
MEDIA
Infrastructure c/o DPWH
123
E. THEMATIC AREA PLAN (Per Thematic Area)
124
PREVENTION AND MITIGATION
PROGRAMS/ RESPONSIBLE SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY PERSON / TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT OFFICE 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
prone and of families and a. Conduct of Once a Risk
conflict communities hazard, year for Assessme
affected particularly in vulnerability 13 nt Report
PDRRMO 14 14 14 14 4,500,000 PDRRMF
communities disaster prone and capacity municipa
by 2021 and conflict assessment lities & 1
affected areas. city
b. Periodic Periodic Infra
conduct of Audit PDRRMO /
1 1 1 1 1 1
infra audit 6 Conducted DILG 6,000,000.00 LDRRM
F
c. Updating of Up to date
the LCCAP Local Climate
Change -PPDO 1 1 1,000,000.00 LDRRM
Action Plan F
(LCCAP)
d. Periodic 13 Conflict
assessment Munici affected areas
-PNP
monitoring palitie assessed,
-AFP
and s and monitored, 14 14 14 14 14 14 1,200,000.00 LDRRM
-OPAPP F
evaluation on 1 city / and evaluated
-DILG
conflict year
affected areas
Reduced To put in-placed 3. Holistic and Infrastructure
risks adequate harmonized Development:
(vulnerability, systems, approach to
exposure, processes and prevention a. Conduct
hazards) of mechanisms to and mitigation annual
30,000 Waterways -DPWH (1ST &
disaster guarantee safety desiltation/ 5,00
Lm desilted 2ND DEO) 5,000 5,000 5,000 5,000 5,000 120,000,000.00
prone and of families and dredging of 0
-PEO LDRRMF
conflict communities waterways
affected -NIA
particularly in
communities -MLGU’s
disaster prone b. Construction Flood Control
by 2021 and conflict of flood 6 structures 1 1 1 1 1 1 60,000,000.00
affected areas. made
125
PREVENTION AND MITIGATION
PROGRAMS/ RESPONSIBLE SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY PERSON / TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT OFFICE 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
control
structures
c. Construction
of Community
community 6 Drainage 1 1 1 1 1 1 60,000,000.00
drainage made
d. Construction
of slope
Slope
protection to 72,000
protection 5M 5M 5M 5M 5M 5M 30,000,000
landslide Lm
established
prone areas
Reduced Agri-forestry
risks Development
(vulnerability, Program:
exposure,
hazards) of To put in-placed
a. Facilitate Farmers /
disaster adequate
farmers/ fisher
systems, fisher folks -PAVO
prone and folks access 120 20 20 20 20 20 20 600,000.00
processes and accessed to
conflict to crops
affected mechanisms to 3. Holistic and crops
insurance
communities guarantee safety harmonized insurance
by 2021 of families and approach to
b. Environment PENRO-LGU
communities prevention Increased
Protection - DENR
particularly in and mitigation area planted
Conduct tree
disaster prone
growing
and conflict
affected areas. c. Avian 13 Avian -PAVO
Influenza Munici influenza
Sero- palitie sero 14 14 14 14 14 14 600,000.00 LDRRM
Surveillance s and F
survellance
1 city / conducted
year
126
PREVENTION AND MITIGATION
PROGRAMS/ RESPONSIBLE SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY PERSON / TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT OFFICE 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
d. Biogas Converted -PAVO
Production gas pollutants
and to renewable
Improvement energy
127
PREVENTION AND MITIGATION
PROGRAMS/ RESPONSIBLE SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY PERSON / TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT OFFICE 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
b. Development of Disaster
Disaster Resiliency
Resiliency Index
Index for all
Municipalities
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Improved 1. To be able to 1. Strengt- Structures and
resiliency of establish a hened Systems
communities standardized partner- Creation:
on disasters coordination ships and a. Creation of LDRRMC, MDRRMC
and risks in system and services to LDRRMC, 1 LDRRMO, MDRRMO’s
procedures reduce 1
Agusan del LDRRMO, ICS, ICS, ACDVS
Sur impacts of ACDVS created
2. To be able to disasters in
b. Plans Plans MDRRMC
identify existing Agusan del
Preparation – Prepared – MDRRMO’s
projects, Sur.
programs and LDRRMP, LDRRMP,
resources of LCCAP, CP, LCCAP, CP,
different Infra Audit Plan, Infra Audit
1
stakeholders Evacuation Plan, Plan, -PESO 1
and establish a Business Evacuation -PDRRMO
system of Continuity Plan Plan, -PEEDO
complementatio Business -DTI
n Continuity
Plan
3. To be able to c. Conduct Infra Infra Audit DILG -LDRRMF
upgrade the Audit 24 Report -PDRRMO 4 4 4 4 4 4 960,000
existing Early -PEO
Warning System d. Designate 1 per EOC -PGO
(EWS) and 1 1 1 1 1 1 8,000,000.00
Emergency year Designated
128
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Formulate Operation
Contingency Center (EOC)
Plans
e. Organize Communicati -PPIO -LDRRMF
4. To be receptive Communication on Network -PIA
on the policies, Network (Civic organized -PDRRMO
protocols and 1 1 50,000
and Amateur
procedures to
Radio Group) in
ensure safety
the Province
on the identified
hazards and f. Organization of BIO & MIO -PPIO -LDRRMF
risks Barangay and organized -PIA
Municipal 2 2 300,000
Information
Officer
g. Conduct of Coordinative -PHO -LDRRMF
Coordinative meetings -MHO/CHO
Meetings and conducted
-DOH
Updating on 2 1 1 1 1 1 1 300,000
Emerging
Diseases
129
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
1. Strengt- Institutionaliza-
hened tion of Plans and
partner- Policies:
ships and a. Create position Positions -HRMO
services to for LDRRM created -LCE
reduce Officer and 3 15
impacts of LDRRMO staff
disasters in per RA 10121
Agusan del b. Risk Risk -PPIO -LDRRMF
Sur. Communication 6 communicatio -PDRRMO 1 1 1 1 1 1 6,000,000
Planning n Plan
c. Forge MOU with MOU -PROVINCIAL/ -LDRRMF
owners of MUNICIPAL/
establishment CITY TOURISM
and facilities OFFICE
which will be
utilized as Safe 2 1 1 200,000
Houses for
Tourists in areas
with Tourism
activities
130
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Volunteers
(ACDVs)
5. To be able to Competency
establish 2. Reduced Building:
Monitoring, impacts of a. Basic Search
Evaluation, disaster and Rescue
Accountability through
and Learning
Training
Increased b. Enhancement on
(MEAL) System
awareness Basic Search and
and Rescue Training
131
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
6. To be able to capacita- c. Medical First
increase ted Responder
competency of communitie Training
responders s in Agusan d. Enhancement on
del Sur Medical First
7. To be able to Responder
articulate and Training
identify their e. Training on Fire
hazards, risks, and Rescue with
vulnerabilities Simulation
and capacities f. Enhancement on
Fire and Rescue
8. To be able to Training with
demonstrate Simulation
proper g. Basic Water
preparedness Search and
measures Rescue Training
based on their h. Enhancement on
risks and Basic Water
vulnerabilities Search and
Rescue Training
9. To be able to i. Swift Water
capacitate and Rescue Training
pool key j. Enhancement on
individuals from Swift Water
the Rescue Training
communities k. Training on First
who can Aid and Basic Life
advocate and Support
teach other l. Enhancement on
residents in First Aid and Basic
their Life Support
communities Training
132
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
m. Basic Mountain
10. To Improve Search and
capacity and Rescue Training
engagement n. Enhancement on
of people’s Basic Mountain
organization Search and
in affected Rescue Training
communities o. Basic Collapse
Structure Search
and Rescue
Training
p. Enhancement on
Basic Collapse
Structure Search
and Rescue
q. Basic Urban
Search and
Rescue Training
r. Enhancement on
Basic Urban
Search and
Rescue Training
s. Training on
WASH
t. Enhancement on
WASH training
u. Training on
HEMS
v. Enhancement on
HEMS training
w. Training on MCI
x. Enhancement on
MCI training
133
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
y. Training on
Psychosocial
z. Enhancement on
Psychosocial
training
aa. Orientation on
PDRA
ab. Re-orientation
and/or updating on
PDRA
ac. Training on
RDANA
ad. Enhancement
training on RDANA
ae. Training on
PDNA
af. Enhancement
training on PDNA
ag. Training on
Basic ICS
ah. Training on
ICS (Planning
Course)
134
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
ak. Training on ICS
(For Executives)
al. Enhancement
training on ICS
an. Enhancement
training for
instructor
ao. Training on
Camp
Coordination and
Camp
Management
(CCCM)
ap. Enhancement
training on CCCM
aq. Training on
MDM
ar. Enhancement
training on MDM
as. Orientation on
Earthquake and
Fire Safety
135
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
at. Training of
Facilitators Course
au. Enhancement
training for
facilitators
av. Training on
Trainers (ToT)
aw. Enhancement
training on ToT
136
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
ba. Training and 6 Enhanced -PDRRMO 1 1 1 1 1 1 10,000,000.00
Skills Skills on
Enhancement on Response,
Response, Search,
Search, Rescue Rescue and
and Retrieval Retrieval Ops
Operations
bb. Training and 6 Enhanced -PDRRMO 1 1 1 1 1 1 1,200,000
Skills Skills on
Enhancement on MCM
MCM
bc.Communication 6 Communi -PPIO 1 1 1 1 1 1 600,000
Exercise (Inter- cation -PDRRMO
operability Excercises -PNP
communication) conducted -AFP
bd.Counter- 12 Simulations -PNP 2 2 2 2 2 2 900,000
terrorism Conducted -AFP
Simulation -PDRRMO
137
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Women Friendly
Spaces (WFS)
138
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
bo. Raising Awareness -DOH -LDRRMF
awareness on the 2 drive -PHO/MHO 1 1 200,000
Milk Code conducted
/CHO
bp. Training on Trainings -PDRRMO -LDRRMF
CMAM, MMAM conducted
and SAMM 6 and system 1 1 1 1 1 1 900,000
including system established
establishment
bq. Orientation Orientations -DOH -LDRRMF
and Training on 2 and trainings -PHO 1 1 200,000
WASH conducted
br. Training on Trainings -PSWDO -LDRRMF
Camp conducted -PDRRMO
Coordination 6 1 1 1 1 1 1 3,000,000
Camp
Management
bs. Training on Trainings -PSWDO -LDRRMF
Temporary conducted
6 1 1 1 1 1 1 600,000
Learning
Management
bt. Conduct of Simulation -PDRRMO -LDRRMF
Simulation Drills drills -DepEd
(Community and 24 conducted 4 4 4 4 4 4 1,200,000
Schools), ALL
Offices
bu. Training on Trainings -PSWDO -LDRRMF
CBDRRM / Child- 120 conducted -PDRRMO 20 20 20 20 20 20 12,000,000.00
focused CBDRRM
bv. Conduct Symposium -PENRO-LGU -LDRRMF
Symposium and organized and
Environmental 6 conducted 1 1 1 1 1 1 600,000
Clean-up
139
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
bw. Training and Trainings -PSWDO -LDRRMF
organizing of conducted -PDRRMO
child-led DRR 6 and school- 1 1 1 1 1 1 600,000
groups in at least based groups
30 schools organized
bx. MSME’s & -PEEDO
COOP Cap Dev.
trainings on:
1. Business Trainings
Continuity 6 conducted 1 1 1 1 1 1 600,000
planning
2. Bookkeeping 6 1 1 1 1 1 1 600,000
3. Product
6 1 1 1 1 1 1 600,000
development
by. Conduct Field School -PAVO
farmers’ field conducted
school on rice, 6 1 1 1 1 1 1 600,000
corn and
vegetables
bz. Knowledge Learnings/ -PSWDO
Management 6 knowledge -PPDO 1 1 1 1 1 1 600,000
managed
ca. Orientation on
Rapid Emergency
Telecommunication
s Team Operations
Manual in Disaster
Response and
Relief Operations
140
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
transparency transpa- Emergency Basic Supplies and 45,000,000.00
in rency in Supplies (Fiber Emergency resources
expenditures expendi- Boats, Life Vest, Supply procured
and tures Cap Lamps,
management managem Rescue Rope,
ent Hand-held
Radios,
Emergency light
and other high-
angle rescue
equipment
b. Operation
Expenses for Operation OpCen -PDRRMO
OpCen (w/ Center maintained 1 1 1 1 1 1 21,000,000.00
Maintenance of
Vehicle for
OpCen)
Inventory of
d. Procurement of Insecticide
Insecticide and and Aqua K-
Aqua K-Othrine Othrine (NFI)
(NFI)
Inventory of
Pesguard
e. Procurement of procured
Pesguard (NFI)
f. Procurement of Vehicle -PGO
emergency procured -PDRRMO
141
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
vehicle for pre-
positioning of
medicines, kits,
jerry cans and
quick response
and rapid
assessments
g. Procurement of Communi- -PGO
communication cation -PDRRMO
equipment and Equipment
load for HEMS
Responder
h. Procurement of CAMPOLAS -PGO
CAMPOLAS Kit Kit -PDRRMO
-PSWDO
i. Acquisition and Livestock -PAVO
development of area acquired -PEO
livestock and -DPWH
evacuation developed
area/animal
shelter
Establishment of
forage and
pasture area
j. Publication of DRR -PPIO
DRR Materials Materials -PIA
in quad-media published -PDRRMO
24 4 4 4 4 4 4 3,000,000
(Radio, TV,
Print and
Social Media)
k. Procurement of ICT -PGO
ICT Equipment Equipment -PIMO
1M 1M 1M 1M 1M 1M 6,000,000
-PDRRMO
142
PREPAREDNESS
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
l. Upgrading (Inter- Upgraded -PDRRMO
lopping) of Interloping
Backbone DX Backbone DX
(Distribution) 2 Line 1 1 1,000,000
Line
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
To secure To ensure A reliable Immediate and
and save lives immediate and response efficient response:
and efficient system that a. Conduct of
Report -PRRMC
properties of response and ensures PDRA
affected well integrated public security b. Conduct of
communities action during and safety as Report -PDRRMO
SITREPS
based on emergencies well as c. Activation of
standards delivery of Report -PDRRMC
OPCEN
143
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
during or basic social d. Activation of
immediately services to Contingency Report -PDRRMC
after disaster. the affected Plans
population. e. Activation of ICS Memo-
-PDRRMC
(if necessary) randum
f. Distribution of
pre-positioned
Resources -PSWDO
(Food and Non- Distribution -PHO
Food items), List -PRC
RESCUE and -NFA
Emergency
Equipment
g. Immediate -Length of
Deployment of Power lines
personnel with restored -ASELCO
Equipage for -No. of -TASK FORCE
Power Teams KAPATID
Restoration deployed
144
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
and/or Force and/or Force -AFP
Evacuation Evacuation -DILG
-BFP
l. Activation of No. of -DepED
Evacuation functional -C/MLGU
Centers Evacuation -RELIGIOOUS
centers SECT
m. Deployment of Establishme
Camp nt of space
Coordination for Nursing
Management Mothers,
Senior
Team
Citizens and
n. (Implementation Persons with -PSWDO
of Evacuation Disability
Management (PWDs), and
Protocols and children
Inter-Agency
Term of
Response
(TOR))
145
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
and Affected -PRC
Psychosocial Families
support:
r. Assessment and Report on
Distribution of Assessment
Water, &
Sanitation and Distribution
Hygiene of WASH
materials and materials &
other Medical medical
supplies
supplies
s. Conduct of Frequency of
Mental Health MHPSS
and conducted
Psychosocial
Support
t. Conduct Space
Spraying,
Fogging, Misting No. of
Activities in Space
Cluster, Spraying in -PHO
Hotspots & affected
Outbreak Areas areas
of Dengue
u. Implementation Traffic
of Traffic Management
Management implemented -LTO
during disaster -PNP
No. of -DPWH
v. Deployment of Volunteer
Volunteer Transport
146
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
Transport Groups
Groups deployed
w. Deployment of Road and
Maintenance Bridges
-DPWH
Taskforce cleared/
rehabilitated
x. Deployment of -PDRRMO
Search, Rescue -AFP
and Retrieval Responsible -PNP
Team -BFP
deployed -DILG
-DPWH 1&2
-PEO
-MLGU’s
y. Deployment of Updated
Price Monitoring Price and
Team Supply -DTI
Monitoring
Report
z. Deployment of Operational
Mass Casualty Team -PDRRMC
Management -DILG
Active SAR
MDM Team
aa. Activate
exclusive spaces No. of
for peoples Spaces
Provided for
Livestock, -PAVO
Livestock,
Poultry and Pets Poultry and
in Evacuation Pets
Centers
bb. Provision of
No. Drugs
Drugs &
& Biologics -PAVO
Biologics to
Provided
affected Animals
147
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
cc. Deployment of
Emergency No. of -PHO
Medical Services Referrals -PDRRMO
Team and -PRIVATE
proper referral EMS HOSPITALS
of Patients to Teams -AFP Medical
Hospitals Deployed Team
dd. Distribution of
Relief Relief and
-BFP
Assistances and Potable
-PSWDO
rationing of Water
-PRC
Potable Water Provided
ff. Activation of
-PDRRMC
RETT
Early Recovery
Program:
a. Provision of Livelihood -PEEDO
Livelihood Programs -PAVO
Support Provided -PSWD
-DTI
-DSWD
-PESO
-DOLE
b. Provision of -PAVO
Agricultural -DA
148
RESPONSE
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2017 2018 2019 2020 2021 2022 REQUIREMENT FUNDS
Production
Support:
1. Rice seeds
2. Corn seeds
Agricul-
3. Vegetables
tural inputs
seeds
provided
4. Organic
fertilizers
c. Rehabilitation of Functional -PEO
Water Systems Water -PEEDO
Systems -WATER
DISTRICTS
149
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Capacity
development
program of PO’s in
affected
communities:
-PEO
Skills a. Livelihood Livelihood -TESDA
development training activities 6 trainings -WATER 1 1 1 1 1 1 600,000
Improve conducted
among POs in DISTRICTS
capacity and
affected b. Core-Shelter Core-Shelter -PAVO -LDRRMF
engagement of constructted
communities Construction -PSWDO -TESDA
people’s 6 1 1 1 1 1 1 600,000
on livelihood, training -PEEDO -DA-ATI
organization in
shelter and -ASELCO -DSWD
affected
other c. Training on other Trainings -544TH ECB
communities
Restoration rehabilitation rehabilitation conducted -PESO
activities 6 -DOLE 1 1 1 1 1 1 600,000
and activities
improvement
of affected d. Initiate housing Forums
communities investment forum conducted
on affected 6 1 1 1 1 1 1 600,000
communities
150
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
b. Application of Plans -DPWH
disaster resilient implemented -PEO
subdivision / -NIA
6 1 1 1 1 1 1 500,000
resettlement -PICE
plan. -544TH ECB
Damaged
Infrastructure
Rehabilitation
Program:
Institutiona- Rehabilitated
a. School buildings 120 units 20 20 20 20 20 20 36,000,000
lized Buildings
Improve mechanism Rehabilitated
coordination and b. Day care centers 18 units Day Care 3 3 3 3 3 3 11,700,000
Restoration Centers -DPWH
and between and protocols for Rehabilitated -PEO
improvement among coordination c. Roads 270 Km -PSWDO 45 45 45 45 45 45 60,000,000
Roads
of affected stakeholders in to ensure Rehabilitated -NIA
communities d. Bridges 120 Lm -PHO 20 20 20 20 20 20 120,000,000
rehabilitation harmonized Bridges
and recovery initiative of Rehabilitated
Irrigation
different e. Irrigation canals 120 Lm 20 20 20 20 20 20 48,000,000
Canals
stakeholders
Rehabilitated
Flood
f. Flood control 6,000 Lm 1,000 1,000 1,000 1,000 1,000 1,000 4,800,000
Controls
151
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
Rehabilitated
g. Barangay halls 36 units Barangay 6 6 6 6 6 6 30,600,000
Halls
Rehabilitated
h. Health centers 36 units Health 6 6 6 6 6 6 30,600.000
Centers
Rehabilitated
i. Covered courts 60 units Covered 10 10 10 10 10 10 150,000,000
Courts
Water Systems Rehabilitated -WATER
Rehabilitation 3,000 Lm Water DISTRICTS 500 500 500 500 500 500 30,000,000
Program Systems
Establishment of Resettlement
new resettlement areas
6 ha established 1 1 1 1 1 1 4,800,000
areas with core
shelters
Institutiona- Rehabilitation of
lized damaged power
Improve mechanism lines:
Restoration coordination and
and between and protocols for 540 Transmission - ASELCO
improvement among coordination a. transmission Lines - NEA 90 90 90 90 90 90 178,000,000
CKTkm rehabilitated
of affected stakeholders in to ensure Sub-
communities rehabilitation harmonized 90 transmission
and recovery initiative of b. sub-transmission 15 15 15 15 15 15 99,000,000
CKTkm lines
different Rehabilitated
stakeholders Rehabilitation of Watersheds
damaged Rehabilitated
120 ha -PENRO-LGU 20 ha 20 ha 20 ha 20 ha 20 ha 20 ha 2,400,000
watersheds
152
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
15,000 Area 2,500 2,500 2,500 2,500 2,500 2,500 -DA
a. Rubber Rehabilitated 750,000,000
ha ha ha ha ha ha ha -PAVO
1,200 ha Area 200 200 200 200 200 200 -PCA
b. Cacao Rehabilitated 48,000,000
ha ha ha ha ha ha -PENRO-
1,200 ha Area 200 200 200 200 200 200 LGU
c. Coffee Rehabilitated 48,000,000
ha ha ha ha ha ha
Institutiona- 18,000 Area 3,000 3,000 3,000 3,000 3,000 3,000
d. Coconut Rehabilitated 720,000,000
lized ha ha ha ha ha ha ha
Improve mechanism 18,000 Area 3,000 3,000 3,000 3,000 3,000 3,000
e. Oil Palm Rehabilitated 720,000,000
ha ha ha ha ha ha ha
Restoration coordination and
1,200 ha Area 200 200 200 200 200 200
and between and protocols for f. Falcata Rehabilitated 36,000,000
ha ha ha ha ha ha
improvement among coordination Livestock
of affected Provision of
stakeholders in to ensure provided
communities livestock:
rehabilitation harmonized
and recovery initiative of
Quantity of
different a. large ruminants 180 Large
stakeholders -DA 30 30 30 30 30 30 -DA
heads ruminants
provided -PAVO -PAVO
Quantity of
Small
b. small ruminants 360
Ruminants 60 60 60 60 60 60
heads
provided
153
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
harmonized and schedules of
initiative of activities.
different
stakeholders a. Video
30 AVPs 5 5 5 5 5 5
Productions
30 Radio
b. Radio Plugs 5 5 5 5 5 5 -LDRRMF
Plugs
30 Publi-
c. Publications 5 5 5 5 5 5
cations
Provision of
Access Windows
for Micro
Financing to
affected
Improve communities:
Access to
Restoration coordination
new funding a. Facilitate access -PEEDO -PEEDO
and between and
sources to micro-financing SME’s, -DOLE -DOLE
improvement among -CDA -CDA
of affected (state and for SMEs and Coops
stakeholders in -DAR -DAR
communities non-state cooperatives. facilitated
rehabilitation
sources)
and recovery b. Provision of APCP
(agrarian
production credit Credit Line
program) for ARB Facilitated
areas.
154
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
rehabilitation Provision of
and recovery Livelihood and
Psycho-social
intervention:
a. Conduct Psycho-
psychosocial social
support Support
provided
b. Conduct trainings
for social
preparation of Social Prep
host communities trainings -PSWDO
and those that will conducted -RED CROSS
be relocated
d. Establishment of Child
child protection Protection
mechanisms Mechanism
Established
e. Food/cash for Assistance
work. provided
Provision of
Health and
Nutrition
interventions: -PHO
Pathway -DOH
a. Institutionalization
Referral
of referral
Institutiona-
pathways
lized
155
REHABILITATION AND RECOVERY
PROGRAMS/ SOURCE
GOALS OBJECTIVES OUT PROJECTS TARGET KEY RESPONSIBLE TIMEFRAME BUDGETARY OF
COMES ACTIVITIES OUTPUT PERSON 2016 2017 2018 2019 2020 2021 REQUIREMENT FUNDS
b. Nutrition Educational
education and activities
Micronutrient conducted
supplementation.
c. Blanket and Feeding
targeted Activities
supplementary conducted
feeding
d. Integrated Acute
management of Malnutrition
acute malnutrition Managed
156
F. MONITORING AND EVALUATION
Guiding Principles
PRINCIPLE 1: EVIDENCE-BASED
This principle means that any claim of an achievement or underachievement of a result
must be supported with evidence as identified in the performance measurement
framework (PFM). The PFM reflects the hierarchy of objectives, objectively verifiable
indicators, and means of verification, methods of data gathering and analysis,
frequency, budget, data users, and the institutional arrangements. The PMEG must
ensure that any form of M&E conducted, either project-specific or province-wide,
should abide by this principle.
PRINCIPLE 2: RESULTS-ORIENTED
A positive bias will be imposed for the monitoring and evaluation of transformational
results (outputs, outcomes, and impact). This implies that resources and efforts will
be geared towards tracking progress of these results.
PRINCIPLE 4: STAKEHOLDER-CENTERED
The focus of the M&E work will be on the outcomes and impact on the part of the
stakeholder. There will be less emphasis on the projects.
PRINCIPLE 5: FLEXIBLE
This means that the M&E performance measurement framework, systems, and tools
will be reviewed, enhanced, and innovated in an iterative manner.
157
M&E findings and analyses are meant to identify and replicate practices that have paid
off or successful. They are also meant to provide recommendations for areas or
practices that need to be enhanced or avoided.
158
Monitoring and Evaluation Activities
159
6. CONDUCT OF YEAR-END ASSESSMENTS
PPDO will provide support to the implementing offices in the conduct of year-
end assessments. PMEG will complement the operational and project-driven
assessments of implementing offices by looking into province-wide results.
160
MONITORING AND EVALUATION MATRIX
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
IMPACT
Secure, resilient and safe 24 Barangays No. of DRRCCA-capacitated M&E Survey (FGD / Every 3 years / PDRRMC Financial /
communities (2016) communities by 2019 318 Report KII) All Stakeholders / PPDO Human Resource
PREVENTION AND
MITIGATION
Outcomes
Reduced risks (vulnerability,
exposure, hazards) of M&E
disaster prone and conflict % reduced in no. of settlers Report , PDRRMC
affected communities in high risk areas CBMS CBMS data Annually / PPDO
% increased no. of
barangays with improved
institutional capacity on M&E Survey (FGD / PDRRMC
project management Report KII) Annually / PPDO
161
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Accomplish File copy HLURB,
No. of quality housing ment retrieval / site Monthly / PPDO,
constructed 6 Reports validation Annually MLGU
No. of municipalities/city
Mainstreamed DRRCCA in conducted with hazard, Risk PPDO,
the local development and vulnerability and capacity Assessmen File copy PEO,
land use planning assessment annually 14 t Reports retrieval Annually PENRO
Periodic PDRRMO
No. of barangays conducted Infra Audit File copy , DILG,
with infra audit 6 Reports retrieval Annually PEO
Copy of
Updated LCCAP every 3 Updated File copy PDRRMO
years 1 LCCAP retrieval Every 3 years , PPDO
162
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
163
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Established Livelihood
support for relocated No. of livelihood trainings Activity File copy
families conducted 6 Reports retrieval Annually
No. of participants on
livelihood trainings Activity File copy
conducted Reports retrieval Annually
No. of collaborative Activity File copy
activities conducted 6 Reports retrieval Annually PDRRMO
No. of participants on
collaborative activities Activity File copy
conducted Reports retrieval Annually PDRRMO
Developed Information
System support for periodic Accomplish File copy
forecasting, monitoring and ment retrieval / site
Early Warning Systems No. of EWS established 1 Reports validation Annually PDRRMO
Study
No. of Disaster Resiliency Writeups / File copy
Index developed 1 Report retrieval Annually PDRRMO
PREPAREDNESS
Outcomes
164
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Accomplish File copy
% of resources acquired and ment retrieval / site Monthly / PDRRMO
in placed Reports validation Annually , PPDO
Outputs
EOs,
Established structures and LDRRMC, LDRRMO, ICS and Memorand File copy PDRRMO
systems for coordination ACDVS created 1 um retrieval Annually , PPDO
LDRRMP, LCCAP, CP, Infra
Audit Plan, Evacuation Plan, Copy of
Business Continuity Plan Approved File copy PDRRMO
prepared 1 Plans retrieval Annually , PPDO
PDRRMO
No. of Infra Audit Infra Audit File copy , PEO,
conducted 24 Reports retrieval Annually DILG
165
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
MHO,
CHO
DOH,
PHO,
No. of HEMS in MLGU and File copy MHO,
BLGU level organized 1 retrieval Annually CHO
No. of Positions on LDRRM Copy of
Institutionalized Plans and Officer and staff per RA appointme File copy PHRMO,
Policies 10121 created 15 nts retrieval Annually PGO
Copy of
No. of Risk Communication Approved File copy PDRRMO
Plan prepared 6 Plan retrieval Annually , PPIO
166
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Copy of
No. of Contingency Plans approved File copy PDRRMO
formulated/updated 1 plan retrieval Annually , PPDO
No. of dengue prevention Accomplish PHO,
and control activities ment File copy MHO,
conducted 6 Reports retrieval Annually CHO
No. of community/family approved File copy
guide developed 6 guide retrieval Annually PDRRMO
No. of food security File copy PAVO,
measures established 6 retrieval Annually PEEDO
Implemented competency No. of competency building Activity File copy PDRRMO
building initiatives trainings conducted 78 reports retrieval Annually , OCD
File copy
Status retrieval / Site
No. of OpCen maintained 1 Reports Validation Annually PDRRMO
File copy
Delivery / retrieval /
No. of sets of Non-food Inventory Ocular PDRRMO
items procured and stocked 3 Reports Validation Annually , PSWDO
File copy
Delivery / retrieval /
No. of emergency vehicle Inventory Ocular PDRRMO
procured Reports Validation Annually , PHO
167
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
File copy
No. of communication Delivery / retrieval /
equipment and load for Inventory Ocular PDRRMO
HEMS responder procured Reports Validation Annually , PHO
Delivery /
No. of CAMPOLAS kit Inventory File copy PDRRMO
procured Reports retrieval Annually , PHO
No. of hectares of livestock Accomplish
area acquired and ment File copy Monthly / PDRRMO
developed Reports retrieval Annually , PAVO
File copy
Delivery / retrieval /
No. ICT equipment Inventory Ocular
procured Reports Validation Annually PDRRMO
File copy
Accomplish retrieval /
No. of Interloping backbone ment Ocular
DX line upgraded 2 Reports Validation Annually PDRRMO
File copy
No. of Emergency Accomplish retrieval /
broadcasting system ment Ocular PDRRMO
established 1 Reports Validation Annually , PPIO
168
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
File copy
Accomplish retrieval /
No. of evacuation centers ment Ocular
constructed 84 Reports Validation Annually PDRRMO
No. of National
Conciousness month Activity File copy
observed 6 reports retrieval Annually PDRRMO
RESPONSE
Outcomes
169
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
170
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Reports /
Documenta File copy PDRRMO
Temporary shelter provided tion retrieval Annually , PSWDO
171
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Updated
price and
supply
Price Monitoring Team monitoring File copy
deployed report retrieval Annually PDRRMO
Reports /
Mass casualty management Documenta File copy
deployed tion retrieval Annually PDRRMO
Exclusive spaces for
livestock, poultry and pets Accomplish
in evacuation center ment File copy
provided report retrieval Annually PAVO
Accomplish
Drugs and biologics to ment File copy
affected animals provided report retrieval Annually PAVO
Emergency Medical Services
Team deployed and proper
referral of patients to Referral File copy
hospitals report retrieval Annually PHO
172
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Accomplish
Provided early recovery No. of beneficiaries ment File copy Monthly / PDRRMO
support received Livelihood support Report retrieval Annually , PEEDO
Status /
No. of beneficiaries Accomplish File copy
received Agricultural ment retrieval / Site Monthly / PDRRMO
production support Report validation Annually , PAVO
Status /
Accomplish File copy
No. of Water systems ment retrieval / Site Monthly / PDRRMO
rehabilitated Report validation Annually , PEO
REHABILITATION AND
RECOVERY
Outcomes
% of affected hhs restored
and resumed back to
Restored and improved normal social and economic M&E Survey (FGD / PDRRMO
affected communities functions Report KII) Annually , PPDO
173
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Outputs
No. of capacity
Conducted capacity development activities
development activities for conducted for Pos in Activity File copy
Pos in affected areas affected areas 24 Report retrieval Annually PDRRMO
No. of beneficiaries
participated the capacity Activity File copy
development activities Report retrieval Annually PDRRMO
No. of sustainable
Formulated mechanisms and infrastructure design Copy of File copy PDRRMO
protocols for coordination prepared 6 designs retrieval Annually , PEO
No. of disaster resilient
subdivision / resettlement Approved File copy
plan 6 plan retrieval Annually PDRRMO
File copy
No. of CPWASH provided 6 retrieval Annually PDRRMO
Status /
Accomplish File copy
Rehabilitated damaged No. of school buildings ment retrieval / Site PDRRMO
infrastructure rehabilitated 120 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of Day care centers ment retrieval / Site PDRRMO
rehabilitated 18 Reports Validation Annually , PSWDO
Status /
Accomplish File copy
No. of KM of roads ment retrieval / Site PDRRMO
rehabilitated 270 Reports Validation Annually , PEO
174
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Accomplish File copy
No. of LM of bridges ment retrieval / Site PDRRMO
rehabilitated 120 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of LM of bridges ment retrieval / Site PDRRMO
rehabilitated 120 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of LM of irrigation ment retrieval / Site PDRRMO
canals rehabilitated 120 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of LM of flood control ment retrieval / Site PDRRMO
structures rehabilitated 120 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of barangay halls ment retrieval / Site PDRRMO
rehabilitated 36 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of health centers ment retrieval / Site PDRRMO
rehabilitated 36 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of covered court ment retrieval / Site PDRRMO
rehabilitated 60 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of LM water pipeline ment retrieval / Site PDRRMO
rehabilitated 3000 Reports Validation Annually , PEO
175
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
No. of hectares of new Accomplish File copy
resettlement areas ment retrieval / Site PDRRMO
established 6 Reports Validation Annually , PEO
Status /
Accomplish File copy
No. of CKTkm transmission ment retrieval / Site PDRRMO
lines rehabilitated 540 Reports Validation Annually , ASELCO
Status /
No. of CKTkm sub- Accomplish File copy
transmission lines ment retrieval / Site PDRRMO
rehabilitated 90 Reports Validation Annually , ASELCO
Status /
Accomplish File copy
No. of hectares of damaged ment retrieval / Site PDRRMO
watersheds rehabilitated 120 Reports Validation Annually , PENRO
Status /
Rehabilitated agro-industrial Accomplish File copy
commodities and provided ment retrieval / Site PDRRMO
livestock support No. of hectares rubber 15,000 Reports Validation Annually , PAVO
Status /
Accomplish File copy
ment retrieval / Site PDRRMO
No. of hectares cacao 1,200 Reports Validation Annually , PAVO
Status /
Accomplish File copy
ment retrieval / Site PDRRMO
No. of hectares coffee 1,200 Reports Validation Annually , PAVO
Status /
Accomplish File copy
ment retrieval / Site PDRRMO
No. of hectares coconut 18,000 Reports Validation Annually , PAVO
176
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Accomplish File copy
ment retrieval / Site PDRRMO
No. of hectares Oil Palm 18,000 Reports Validation Annually , PAVO
Status /
Accomplish File copy
ment retrieval / Site PDRRMO
No. of hectares Falcata 1,200 Reports Validation Annually , PAVO
Status /
Accomplish File copy
No. of heads small- ment retrieval / Site PDRRMO
ruminants provided 360 Reports Validation Annually , PAVO
Status /
Accomplish File copy
No. of heads large- ment retrieval / Site PDRRMO
ruminants provided 180 Reports Validation Annually , PAVO
Radio Plug File copy
Disseminated IEC materials
No. of radio plugs 30 copy retrieval Annually PPIO
for rehabilitation and
recovery initiatives File copy
No. of AVP 30 AVP copy retrieval Annually PPIO
Published File copy
No. of publications 30 Materials retrieval Annually PPIO
Status /
Accomplish
Provided Access Windows for No. of SMEs/coops ment File copy
Micro Financing facilitated Report retrieval Annually PEEDO
Status /
Accomplish
No. of ARB provided with ment File copy PDRRMO
APCP Report retrieval Annually , DAR
177
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
Status /
Implemented scholarship on No. of beneficiaries Accomplish
skills development thru provided with techvoc ment File copy
techvoc provider scholarship Report retrieval Annually TESDA
Status /
No. of beneficiaries of Accomplish
Provided livelihood and psycho-social support ment File copy
Psycho-social intervention provided Report retrieval Annually PSWDO
Status /
Accomplish
No. of beneficiaries of social ment File copy
prep trainings conducted Report retrieval Annually PSWDO
Status /
Accomplish
No. of post analysis ment File copy
conducted Report retrieval Annually PSWDO
Status /
Accomplish
No. of child protection ment File copy
mechanism established Report retrieval Annually PSWDO
Status /
No. of beneficiaries for Accomplish
food/cash for work ment File copy
assistance Report retrieval Annually PSWDO
Status /
Accomplish
Provided Health and No. of pathway referral ment File copy
Nutrition interventions system institutionalized Report retrieval Annually PHO
178
Frequency &
Assumptions/ Objectively Verifiable Data Collection OPR/ Resources
Expected Results Baseline Targets Audience of
Risk Indicators Sources Methodology PPR Needed
the Report
No. of beneficiaries on
nutrition education and Status /
micronutrient Accomplish
supplementation activities ment File copy
conducted Report retrieval Annually PHO
No. of beneficiaries on Status /
blanket and targeted Accomplish
supplementary feeding ment File copy
conducted Report retrieval Annually PHO
Status /
No. of beneficiaries on Accomplish
integrated management of ment File copy
acute malnutrition Report retrieval Annually PHO
179