Project Name: Mills Park Wading Pool Replacement Project Location: 1340 E. Dimondale Dr., Carson, CA 90746 Date of Estimate: December 10, 2014 Prepared by: Gilbert Marquez, PE
Item No. Description Quantity Units Unit Cost Total
A) GENERAL REQUIREMENTS 1 LS $5,000.00 $5,000.00
1 Mobilization / Demobilization $0.00
Business License, Cal OSHA permit, City Building
2 Permits, Los Angeles County Public Health Permits etc.
4 Remove & Dispose of reinforced concrete wading pool
$0.00 Remove & Dispose of Concrete Sidewalks / Remove & 5 Replace Interfering walkway(s) $0.00 6 Cut to fill, fine grade and compact $0.00 Haul excess soil from recirculation tank excavation to 7 approved landfill $0.00 Construct 4" SDR-35 storm drain from RWD to curb core. 8 Parkway culvert as approved by City. $0.00 9 Construct 4" sch80 PVC waste line, trench & backfill $0.00 Provide & Install Backflow assembly inside approved 10 enclosure $0.00 Join/connect water service at meter. Provide backflow w/ 11 approved enclosure. Construct 1" sch 80 PVC water main from restrooms to tank fill $0.00 Install conduit and approved conductors from main 12 electrical panel to UV reactor & motor starter. Provide new breakers as needed $0.00
C) SPLASH-PAD / HARDSCAPE / SOFTSCAPE
1 LS $63,458.00 $63,458.00 13 Construct 4" PCC spray free zone $0.00 14 Construct 6" PCC splash pad $0.00 Detailed Engineer's Estimate Agency: City of Carson Project Name: Mills Park Wading Pool Replacement Project Location: 1340 E. Dimondale Dr., Carson, CA 90746 Date of Estimate: December 10, 2014 Prepared by: Gilbert Marquez, PE
15 Construct concrete collar & apron around circulation tank
$0.00 16 Construct radius seat walls 24" x 16 w/ reinforcement $0.00 Construct new sidewalk around splash pad to join existing 17 ADA path of travel. $0.00 18 Pave parking lot trench (restripe as needed). $0.00 Patch turf, repair sprinklers to trim around tanks & 19 equipment. $0.00 PURCHASE AND INSTALLATION OF SPLASH PAD D) EQUIPMENT / WATER TREATMENT & RECIRCULATION RESERVOIR 1 LS $261,026.00 $261,026.00 Excavate 11' depth, construct reinforced concrete anchor 20 pad w/ hold downs. Install 4000 gallon storage tank. Backfill $0.00 Provide & Install sch 80 PVC plumbing laterals / 21 connections $0.00 22 Provide & Install SDR drain line $0.00 23 Install controls, disconnects, starters & clock $0.00 Excavate & Install chemical containment vessels. Pour 24 PCC collar. Install conduit/ tubing. $0.00 25 Construct sewer backwash pit $0.00 26 Install debris trap w/ rain water diverter valve. $0.00 27 Install 120VAC circuit $0.00 Install Splash Pad equipment (Scorpion, team Spray, 28 Directional Water Jet, Water Wall, Aqua Dome, Water garden, Jet Stream, etc.) $0.00 Electrical connections (ground wire, emergency shut-off, 29 controls) $0.00 $0.00 SUB-TOTAL $428,273.00 CONTINGENCIES (8%) $34,261.84 0 TOTAL: $462,534.84