TRANSFORMER INSTALLATION CHECKLIST

E118 (REV 00)11-


11
PROJECT: LOCATION:
TAG NUMBER: MANUFACTURER:

TYPE: STYLE: KVA RATING: SERIAL #:


PRIMARY VOLTAGE: FREQUENCY: PHASE:
INS. CLASS: % Z:
V HZ Ø
SECONDARY VOLTAGE: TEMP RISE: TEST EQUIPMENT IDENTIFICATION #:
V ˚C
DRY TYPE: LIQUID FILLED: PCB: __________ INDOOR: OUTDOOR:

BEFORE INSTALLING & TESTING TRANSFORMERS, OUR EMPLOYEES WILL ENSURE THAT THEY: YES N/A
INSPECT FOR EXTERNAL OR SHIPPING DAMAGE, LOOSE AND MISSING PARTS.
CHECK FOR FOREIGN MATERIAL SUCH AS PAINT OR DIRT WITHIN OR ON THE TRANSFORMER WINDINGS.
CHECK TRANSFORMER BUSHINGS FOR CRACKS AND CHIPS.
VERIFY CSA CERTIFICATION MARKING (OR EQUIVALENT).
VERIFY NAMEPLATE DATA IN ACCORDANCE WITH APPROVED DRAWINGS AND SPECIFICATIONS.
VERIFY MOUNTING INSTRUCTIONS AND INSTALLATION LOCATION (E.G. PROPER COOLING, VENTILATION, ETC.) IN
ACCORDANCE WITH MANUFACTURER’S SPECIFICATIONS.

VERIFICATION: YES N/A


CHECK COVERS AND DOORS FOR INSTALLATION AS PER MANUFACTURER’S SPECIFICATIONS.
VERIFY INSTALLATION OF BASE ATTACHMENTS, CHANNELS, ANCHOR BOLTS, ETC, IN ACCORDANCE WITH
MANUFACTURER SPECS.
VISUALLY INSPECT GASKETS & FITTINGS FOR OIL LEAKAGE.
CHECK ALL GROUNDING IN ACCORDANCE WITH SPECIFICATIONS, INCLUDING CORE GROUNDING.
CHECK THAT CASE AND GROUNDING RESISTORS ARE CORRECTLY INSTALLED TO MAIN GROUND SYSTEM.
CHECK ALL NEUTRAL INSTALLATION SIZE / CONNECTION AS PER DRAWINGS.
VERIFY THAT CONTINUITY TESTING HAS BEEN CONDUCTED (E127)
INSPECT CABLES AND CONNECTIONS (ARE THEY PROPERLY SUPPORTED AND INSULATED?)
CHECK THAT ALL CONDUCTORS ARE LABELED AND IDENTIFIED.
VERIFY TEMPERATURE INDICATORS AS PER APPROVED DRAWINGS AND SPECS.
CHECK THAT TERMINATIONS ARE COMPLETE AND VERIFIED IN ACCORDANCE WITH APPROVED DRAWINGS AND
SPECS.
PULL, TUG METHOD COMPLETED AFTER TERMINATION.
CHECK FUSE PROTECTION IN ACCORDANCE WITH MANUFACTURERS SPECIFICATIONS.
ALL HOLES ARE PLUGGED AND TIGHTLY SECURED.
TEMPORARY GROUNDS AND TOOLS REMOVED.
LIQUID FILL MUST SIT FOR 6 HOURS OR GREATER BEFORE APPLYING POWER.
VERIFY PROPER OPERATIONS OF FAN INDICATORS, PROTECTIVE DEVICES, AND TAP CHANGERS.
CHECK FOR CLEANLINESS AND PAINT SCRATCHES.
PRINT/ TYPE NAME: TRANSFORMER INSTALLATION
SIGNATURECHECKLIST
DATE
GCS ENERGY SERVICES REPRESENTATIVE:
(mm/dd/yy):
E118 (REV 00)11-
/ / 11
DATE
OWNER REPRESENTATIVE:
(mm/dd/yy):

/ /