Beruflich Dokumente
Kultur Dokumente
Identified by
Project ID 0713000239
MATERIALS INFORMATION
Geotechnical Report for Retaining Walls and Sign Posts
List of the Preconstruction Operational Status-Check Results
Cross Section Drawings
1
Housing Agency
Subject: Geotechnical Design Report for Retaining Walls and Sign Posts Associated with Route
110/Route 405 Interchange Improvement Project-Bridge No.53-1137
1.0 INTRODUCTION
In response to the request from the Office of Bridge Design South, the Office of Geotechnical
Design South (OGDS) prepared this geotechnical deign report for the proposed soil nailed and
ground anchored walls under the Bridge 53-1137, retaining walls, and sign posts associated with
the Route 110/ Route 405 interchange improvement project.
Based on Structure Advance Planning Study Request, the project involves improving the traffic
operations within I-110/I-405 interchanges on Route 110 between Torrance Blvd PM8.0 and the
Dominquez channel PM9.0 and on Route 405 between Truck Scales PM12.2 to 190th St.
PM13.2.
This project will consist of 4 mainline thru lanes on the southbound (SB) I-110, and the
realignment of the northbound (NB) Route I-405 to SB Route I-110 connector, and an aux lane
that merges with the SB Route I-405 to SB Route I-110 Connector. To accommodate the
additional aux lane, the SB Route I-405 to SB Route I-110 Connector must be shifted to the west
and require realignment, resulting in widening SB Route I-110- mainlines to the Del Amo Blvd
UC.
The general location of the project site is shown on the Vicinity Map in Figures 1a and 1b.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 2 0713000239
Project Site
According to the plan view layout, profile, and cross sections provided by the Structure Design,
the basic configuration of these retaining walls are summarized in the Table 1 are proposed at the
following locations:
Four major sign post foundations’ No. S2-5 at Sta 427+70.00; S2-6 at Sta 427+74.00; S3-3A at
Sta 466+33.60 and S3-4A at Sta 446+38.00 required geotechnical design.
According to National Geological Map Database, the subsurface materials of the project site
consist of Surfical Sediment (Qa/Qae), underlain by Shallow Marine Sediments (Qsp) and
Fernando Formation (Tfp). The Surfical Sediment (Qa/Qae) consists of alluvium, mostly loamy
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 5 0713000239
clay of valley and flood plains, and fine sand near Palos Verdes Hills. The Shallow Marine
Sediment (Qsp) consists of light gray to reddish-tan sand and pebble gravel, pebbles derived
mostly from Miocene hard siliceous shale and limestone detritus. The Fernando Formation (Tfp)
is late Pliocene age, mostly Venturian Stage and consists of mostly blue and blond sandy shale
and sandy siltstone.
The native soil is medium dense, equivalent to the moist unit weight of 120 pcf, and a friction
angle of 32 degrees. The fill material above the native soil is also medium dense silty sand with
small cohesion. The unit weight is 120 pcf and a friction angle of 34 degree and the cohesion of
50 psf. The engineering properties used for the design of the proposed retaining wall designs are
summarized in the Table 3a-3c and in Appendix C.
Poorly graded
3 40-65 Sand and Elastic γ = 120 pcf; φ = 32˚ 16-27
Silt (MH)
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 8 0713000239
Poorly graded
3 25-50 Sand and Elastic γ = 120 pcf; φ = 32˚ 22-55
Silt (MH)
2.2.4 Corrosion
CORROSIVITY
Corrosivity of subsurface materials at the depth between 10- 20 ft below the existing grade was
tested and reported on February 11, 2016 in accordance with CTM 643, 417, and 422. The test
results summarized in Table 4 and in Appendix C indicated that the subsurface materials in the
project area are corrosive.
Note:
For structural element, Caltrans considers a site corrosive if one or more of the following condition exist: pH is 5.5
or less, Choride Concentration is 500 ppm or greater, sulfate concentration is 2000 ppm or greater. The Caltrans
Corrosion Guidelines state that if the minimum resistivity is less than 1000 Ohm-cm the sample is considered to be
corrosive and testing to determine sulfate and chloride is not performed. It is shown in Red in Table 4.
2.2.5 Groundwater and Seepage
According to the available LOTBs, the groundwater was encountered at the elevation of (-10ft
MSL) 10ft below MSL from 1960 to 2000 LOTB. This groundwater elevation was used for the
liquefaction potential analysis.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 9 0713000239
Both deterministic and probabilistic seismic analysis were performed using Caltrans ARS on-line
using average shear wave velocity of 270 m/sec based on available LOTBs. According to the
analysis, there are three controlling faults near the project site, and the seismic hazard at the
project site is governed by the probabilistic seismic analysis. The controlling fault parameters
were summarized in Table 5 and Figure 3.
Based on the design ARS curve below, the estimated design PGA is 0.5g.
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5
Period (second)
Based on the Seismic Hazard Zones (Liquefaction and Earthquake-Induced Landslides) for
Torrance Quadrangle, some areas of the project site are located within Zones of Required
Investigation.
The water table is 10 ft below MSL. The facing and the toe of soil anchors is above the water
table. All the retaining walls is above the water table.
Based on Caltrans’ Geotechnical Manual on liquefaction, the site is not liquefiable by assuming
the ground water table is 45-ft below the existing surface and the SPT N values of 16. Using
Youd 2001 method with Rousch adjusted equation in evaluating liquefaction potential, it
indicated the liquefaction is unlikely in this site location.
Environmental study was conducted in November 2016. The purpose of conducting additional
investigation is to find out the extent of solid waste at the site location around Retaining Wall 72
and Soil Nailed Wall 461.
Five test pits up to 5-ft deep were excavated and four handheld boreholes were drilled. The
locations are shown in Appendix D. Three test pits-1346-119, 1346-120 and 1346-122 showed
solid waste debris. Those solid waste contained concrete and asphalt were in test pits- 1346-119
and 1346-120.
Test Pit-1346-122 at the location near the North end of soil nailed wall posed the potential
geotechnical challenge. In that test pit, Eucalyptus roots and waste sample at the depth about 4
feet were found. The waste sample contains concrete, rock fragment, textiles, fiber, plastic,
wood, paper and metal fragments.
Since the environment is anaerobic as indicated in the test pit because the debris fragments in the
test pit are relatively inert and no decomposed organic materials were observed.
The soil property in these sparse locations of solid waste can be assumed to be the same as the
property of the fill material because most of the solid waste in this locations are asphalt and
concrete.
The extent of these solid waste is difficult to identify because of the materials are varied
differently in different locations.
For the proposed retaining walls beneath Route 110/Route 405 separation and connector bridges,
four retaining wall structures were considered in this report.
This retaining wall #59 is from the tangent section between I405 South to I110 South. The
maximum retaining wall height is 8 ft. The length is about 488 ft. The footing elevation varies
from 27.17 and 41.67 from MSL. Based on LOTB records from R15-102 and R15-103, the fill
material is from the surface extended to 10 feet above MSL. This means the footing is rested
mainly on the fill material. The bulk density is about 120 pcf and the angle of friction is 34
degree and the cohesion is 50 psf. It is recommended to use footing keys for the retaining wall
foundation as shown in Table 6. The wall is supported by footings.
Based on the wall height and the soil properties, Type 1 retaining wall is recommended.
Since the ground water was encountered about 10 feet below MSL. No ground water should be
anticipated during the wall construction. However, any perched water may present during the
construction. It is expected to be temporary and will not affected the wall. But precautious
should be taken if water was observed during the construction.
This retaining wall #72 is from the tangent section between I405 North to I110 South. The
maximum retaining wall height is 10 ft. The length is about 256 ft. The footing elevation varies
from 36.67 and 41.67 from MSL. Based on LOTB records from R15-101 and R15-102, the fill
material is from the surface extended to 10 feet above MSL. This means the footing is rested on
the fill material.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 12 0713000239
In the environmental report dated December 2016, the waste material deposit may be presence.
Since the solid waste is mainly concrete and fragments of asphalt, this will not pose a major
concerns especially the materials is very sparsely distributed in the soil matrix. The material
should behave as fill material. The bulk density is about 120 pcf and the angle of friction is 34
degree and the cohesion is 50 psf as shown in Table 7.
Based on the wall height and the soil properties, Type 1 retaining wall is recommended.
Since the ground water was encountered about 10 feet below MSL. No ground water should be
anticipated during the wall construction. Any perched water may present during the
construction. It is expected to be temporary and will not affected the wall. But precautious
should be taken if water was observed during the construction.
This retaining wall #437 is along I110 South from Station 437+00 to Station 451+84.66. The
maximum retaining wall height is 14 ft. The length is about 1,484 ft. The footing elevation
varies from 11.75 to 25.17 from MSL. Based on LOTB records from R15-102 and R15-103, the
fill material is from the surface extended to 10 feet above MSL. This means the footing is rested
on the fill material. The bulk density is about 120 pcf and the angle of friction is 34 degree and
the cohesion is 50 psf as shown in Table 8. It is recommended to use footing keys for the
retaining wall foundation.
Based on the wall height and the soil properties, Type 1 retaining wall is recommended.
Since the ground water was encountered about 10 feet below MSL. No ground water should be
anticipated during the wall construction. Any perched water may present during the
construction. It is expected to be temporary and will not affected the wall. But precautious
should be taken if water was observed during the construction.
A sign post- S3-3A Sta 446+33.60 will be installed next to Retaining wall #437 to form one
monolithic structure. A 24-ft section of 14-ft height retaining wall was recommended from the
structural design. This section of the retaining wall will attach to the wall and will be protruded
about 15.6ft above the grade with the bottom of footing elevation of 15.83ft MSL. The top of
sign post pedestal is at 31.43ft above MSL.
Based on the soil properties and the design load for sign post from Structural Design, the bearing
capacity is adequate for the proposed sign post. Strength 1a condition from LRFD retaining wall
design is the most critical among LRFD design. The calculated B’ is 8.8ft and the bearing
pressure qo is 3.9 kips/sq.ft. The bearing capacity for this retaining structure to include the sign
post is 33 kips/sq.ft. Hence the bearing pressure is adequate for the sign post.
The anticipated ground water level is about -10ft from MSL. Although water will not be
presented during installation, perch water table is still posted the problem. If any perched water
is presented, dewatering and adequate compaction should be taken care of.
Three sign posts on CIDH piles (No. S2-5 at Sta 427+70.00; S2-6 at Sta 427+74.00; and S3-4A
at Sta 446+38.00) will be installed. Adopted 2015 Caltrans Standard Plan for Overhead signs
post, the recommended CIDH pile is 5-ft diameter and the length of 22-ft. Based on L-Pile
Analysis and the maximum deflection of the CIDH pile under the load is less than 0.25-in. and
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 14 0713000239
the allowable deflection is 0.5-in. Hence the sign post design is adequate using 5-ft diameter and
22-ft long CIDH pile. Since it may encounter the ground water, it is recommended to use 25-ft
long CIDH pile.
3.1.5 Ground Anchors and Soil Nails Wall #461 (Bridge Number 53E0365)
Total five ground anchors and soil nails walls will be installed along Wall #461 (Bridge Number
53E0365). Two of the segments are ground anchors walls and the other three segments are soil
nails walls as shown in Table 10.
Table 10: Wall 461 Soil Anchors and Soil Nails Design along SB Route 110 from Station
460+04 to Station 466+07.90
Total: 603.63
Based on LOTB records from R15-102 and R15-103, the fill material is from the surface
extended to 10 feet above MSL. This means the footing is rested on the fill material. The bulk
density is about 120 pcf and the angle of friction is 34 degree and the cohesion is 50 psf as
shown in Table 11.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 15 0713000239
To allow for the softening of soil during the removal of soil during the construction, the angle of
friction was reduced from phi= 34 degree to phi=32 degree as suggested by the Structural
Design. Analysis was performed, it was found the ground anchored and soil nailed retaining
wall were adequate.
Based on the environmental report in December 2016, some of the top soil may encounter
discrete solid waste pocket at the toe of the fill slope at the North end of the soil nail wall at Sta
466. The extent is very sparsely. This will not affect the ground anchored wall or soil nailed wall
soil properties.
Should this solid waste be found during the construction, all the waste materials should be
removed and treated according to EPA and California Environmental Regulations.
Two ground anchored diaphragm walls located from A-line Station 460+67.23 to Station
461+08.81 and Station 462+05.81 to Station 465+31.74. The ground anchored diaphragm walls
design was based on the subsurface condition from the available LOTBs and regional geological
information. The limit of the wall is shown in Table 12 below. The pre-stressed ground anchor
can provide lateral support to the walls, and reduce the lateral movement of the wall during and
after construction. Ground anchored wall will be installed beneath Bridge 53-1137, F, L, R and
G along the bridge abutment.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 16 0713000239
For the global design of the recommended soil anchored wall, the computer programs
SLOPE/W and CTFlex were used. Ground anchors should be inclined 12 degrees (no less than
10 degrees) from horizontal for all ground anchors.
Nominal CIDH pile capacity beneath the bridge was estimated that included the additional load
from the ground anchors. It was found the existing CIDH pile is capable of taking the additional
loading condition from ground anchors.
Unbonded length should be at least 50 feet for seating loss control upon anchor lock-off.
The soil nailed diaphragm walls will be used and the limit of the wall is shown in Table 13a and
13b. The soil nails can provide lateral support to the walls, and reduce the lateral movement of
the wall during and after construction. Soil nailed wall will be installed between Bridge 53-1137
along the bridge abutment.
For the design of the recommended soil nail walls, the computer program SNAIL was used.
Following are the geotechnical design criteria for the soil nail walls:
Wall Segment Max. Wall Min. Nail Max. Max. Nail Measured Measured
Height Position Length Hor. Vert. Inclina from Top from
(ft) MNR Spacing Spacing tion of Wall (ft) Bottom of
(ft) (ft) Angle Wall (ft))
Beg. End. Wall Row ft
Sta. Sta. Zone
Since the soil is corrosive, plastic sheathing are required for all soil nails.
For the global design of the recommended soil nailed wall, the computer programs SLOPE/W
and SNAIL were used. Soil nails should be inclined 15 degrees from horizontal as shown in
Table 13a and 13b.
Based on the evaluation of the wall types in the previous section, and available subsurface
information, OGDS recommends following retaining walls and the sign posts for this project:
• Wall #59: Standard Type 1 wall for SB Route 405 to SB Route 110 connector (Station
59+00 to Station 63+88)
• Wall#72 : Standard Type 1 wall is from the tangent section between I405 North to I110
South from Station 71+80 to 74+36
• Wall #437: Standard Type 1 wall is along I110 South from Station 437+00 to Station
451+84.66
• Wall #461 (Bridge Number 53E0365): Soil nailed and anchored Walls SB Route 110
from Station 460+04.27 to Station 466+07.90 beneath Bridge 53-1137
• Three sign posts on CIDH piles (No. S2-5 at Sta 427+70.00; S2-6 at Sta 427+74.00; and
S3-4A at Sta 446+38.00)
• One sign post- S3-3A Sta 446+33.60 next to Retaining wall #437 to form one monolithic
structure.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 19 0713000239
4.0 References
1. As built log of test borings for North Connector OC and Separation, East Connector UC
(Widen), and West Connector UC.
2. California Geological Survey Webstie.
3. Seismic Hazard Zone Report for Torrance Quadrangle.
4. Landslide and/or Liquefaction Map.
5. Fault Zone Map.
6. National Geologic Map Database for Torrance Quadrangle.
7. Environmental correspondence December 2016 from GeoSyntec (Appendix 4)
The wall zone limits for the ground anchored and soil nailed walls under Bridge No 53-1137 are
shown in the Table 12 and Table 13a and b respectively.
The Department will conduct research activities within the limits of the ground anchored wall.
This ground anchor research activities includes installation of monitoring instruments, bond
breaker, and the research ground anchors; and test and record the research ground anchors
performance.
The Contractor will install the monitoring instruments and the bond breaker on the research
ground anchors, test the research ground anchors and record the data according the modified
performance test during pullout tests of the research ground anchors as shown in Table14 under
Engineer’s direction. The locations of the research ground anchors are as shown on the Contract
Plans Sheets. The engineer will monitor the test and record the data using data logger.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 20 0713000239
The purpose of this study is to investigate the effectiveness of the bond breaker. Six research
ground anchors are to be installed. Four of the research ground anchors will include the bond
breaker. The other two as the reference ground anchors are same as the production anchors. These
research ground anchors will be instrumented as directed by the engineer.
Instrumentation
Multiple Depth Extensometer (MDE) gages are to be attached to the outside of the corrugated
sheathing of the research ground anchors. Multi-depth extensometer (MDE) comprised of an
anchor head and elongated extensometers extending down through the anchor hole.
Number of gages in each MDE for research ground anchors is shown in Table 15.
1 4
2 4
3 6
4 6
5 4
6 4
Load Cell
A calibrated load cell should be placed between the loading jack and the anchor head. All
loading schedule should be recorded electronically, displayed and stored in the data logger
software.
The MDE will be installed at the distal of following locations as directed by the engineer.
Anchor head movement should be recorded electronically, displayed and stored in the data
logger software.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 22 0713000239
Section A-A Cross Section of Un-bonded Length in Section B-B Cross Section of Bonded Length in
Ground Anchor Ground Anchor
Data Logger
The data logger must be compatible with the multi-depth extensometer read out unit. The data
logger must be able to record the load and the displacement of the ground anchor head during
testing. The data logger must have at least 16 channels, one USB connection, and a battery
system with 16-hour run-time.
The software of the data logger must be able to display real-time load and deflection data and
graph during the load test, and allow download of raw data.
Same as the production ground anchors with additional plastic pipe attached to the distal of the
ground anchor. This plastic pipe is to install MDE at the distal of the research ground anchors.
The bond breaker will be installed the bonded and un-bonded length of the research ground
anchors as shown in contract Plan Sheets. The bond breaker is wrapped around the ground anchor
sheathing and the surrounding soil. Research activities include installing and monitoring multiple
displacement gages at the locations directed by the Engineer.
Construction activities will be coordinated to prevent interference with the equipment installation
and monitoring. The engineer will order you to assist in installing the equipment. The grout pipe
must be retrieved during grouting.
All anchors after testing will be abandoned by removing the research ground anchor to 6 inches
behind the face of the wall after the completion of load test. In addition, fill the void with grout.
Use authorized methods to secure bond breaker at the interface between the bonded and
unbonded section of the ground anchor.
Expect difficult ground anchor installation due to no return of water during the site exploration
as well as loss of grout during the backfilling of the exploration hole.
Cave-in potential of the slope materials may be anticipated in areas with granular materials
during the ground anchor wall construction.
During the installation of soil anchor, presence of fissures or loose pockets may affect the
grouting operation. Should this be the case, more grouts are anticipated in these locations with
granular materials during installation.
Expect difficult soil nail or installation due to no return of water during the site exploration as
well as loss of grout during the backfilling of the exploration hole.
Cave-in potential of the slope materials may be anticipated in areas with granular materials
during the soil nail wall construction.
During the installation of soil nails, this may encounter the loose pockets of solid waste. Should
this be the case, more grouts are anticipated in areas with granular materials during installation.
For wall Zones 1, 2 and 3, at least 2 soil nails verification test shall be performed.
Three proof tests for Wall Zones 1 and 3, and seven proof tests for Zone 2 shall be performed as
shown on the contract plan.
In addition, the engineer will direct one additional proof test to be performed in Zones 1 and 3
and two additional proof tests in Zone 2. The exact location will be determined by the engineer
during the construction.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 25 0713000239
The CIDH pile for the sign post is 5-ft in diameter and 25-ft in length.
Temporary casing is needed to assist the installation of CIDH pile as there is a likelihood of
caving of the sidewall of the hole.
Hard drilling should be anticipated within gravel, cobble and boulder zones. Contractor should
have appropriate equipment to penetrate these difficult to drill zones as indicated in Section 2.1.
Should Type 1 Retaining Wall no.72 encounters the solid waste, the solid waste should be
removed at least 5-ft below grade and replaced by compacted fill and disposal of the solid waste
according to Federal or California EPS regulations. The backfill materials should be compacted
according to Caltrans general specification.
If you have any question regarding this report, please contact me (916-227-7066) or Deh-Jeng
(David) Jang (916)-227-5722.
Appendix A
Fig.A2-Retaining Wall 72
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 29 0713000239
Figure A4 Soil Anchors Walls and Soil Nails Walls Location 461- The extent of each wall zones
for Soil Nails and Ground Anchors should refer to the report and the plans.
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 31 0713000239
Appendix B
Appendix C
Laboratory Test Results
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 41 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 42 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 43 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 44 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 45 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 46 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 47 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 48 0713000239
Appendix D
Environmental Site Investigation
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 49 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 50 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 51 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 52 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 53 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 54 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 55 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 56 0713000239
RAMIN RASHEDI
01/20/2017 EA 07-293700
Page 57 0713000239
07-293701 List of Preconstruction Operational Status-Check Results
TMS STATUS
VDS # CO. FWY DIR PM CROSS STREET NAME PROBLEMS
766505 LA 405 N 12.05 TRUCK SCALE 2 Ctlr Down
766506 LA 405 N 12.05 TRUCK SCALE 2 Ctlr Down
717738 LA 405 N 12.57 MAIN Insufficient Data
718259 LA 405 N 12.57 MAIN Insufficient Data
766268 LA 405 N 12.57 MAIN No Data
772473 LA 405 N 13 N/B 405 TO S/B 110 Ctlr Down
772474 LA 405 N 13 N/B 405 TO N/B 110 Ctlr Down
772475 LA 405 N 13 N/B 405 TO N/B 110 Ctlr Down
716663 LA 405 N 13.18 N OF 110 Good
769249 LA 405 N 13.18 N OF 110 Good
716479 LA 110 N 7.98 TORRANCE Good
763532 LA 110 N 7.98 TORRANCE Good
763849 LA 110 N 7.98 TORRANCE Good
766341 LA 110 N 8.64 NB 110 TO SB 405 Insufficient Data
766340 LA 110 N 8.65 NB 110 TO NB 405 #1 Insufficient Data
766336 LA 110 N 8.66 S OF 405 Insufficient Data
766338 LA 110 N 8.66 SB 405 TO NB 110 #2 Insufficient Data
716660 LA 405 S 12.05 TRUCK SCALE 2 Ctlr Down
764657 LA 405 S 12.05 TRUCK SCALE 2 Ctlr Down
766504 LA 405 S 12.05 TRUCK SCALE 2 Ctlr Down
716661 LA 405 S 12.57 MAIN Insufficient Data
718258 LA 405 S 12.57 MAIN Insufficient Data
718260 LA 405 S 12.57 MAIN Insufficient Data
717739 LA 405 S 13.18 SB 405 TO NB 110 #1 No Data
769248 LA 405 S 13.18 N OF 110 Insufficient Data
769250 LA 405 S 13.18 N OF 110 Good
769251 LA 405 S 13.181 SB 405 to SB 110 #1 No Data
766337 LA 110 S 8.59 S OF 405 Insufficient Data
766339 LA 110 S 8.59 SB 405 TO SB 110 #2 Insufficient Data
774712 LA 110 S 8.83 CONNECTOR TO 405 Card Off
774713 LA 110 S 8.83 CONNECTOR TO 405 Good
CCTV STATUS
CCTV# CO. FWY DIR PM CROSS STREET NAME PROBLEMS
340 LA 405 S 12.50 MAIN ST NO PROBLEMS
343 LA 405 N 13.20 N/O ROUTE 110 NO PROBLEMS
341 LA 110 S 8.30 S/O ROUTE405 NO PROBLEMS
342 LA 110 S 9.54 N/O ROUTE 405 NO PROBLEMS