Sie sind auf Seite 1von 4

AZEEMUL AZAM BIN MOHAMAD

2015146281
AP2466E
THE RELATIONSHIP OF TIME AND MONEY CLAIM AS EXPOUNDED IN PAM
AND PWD SFOC

CLAIM
MONEY TIME

Client Claim Contractor EOT


from Claims from
Contractor Client

Liquidated
Damages

Direct Loss & Interim Variation Order


Expense Payment

Relationship claim between money and time

Extension of time EOT in construction contracts

Construction contracts generally allow the construction period to be extended where


there is a delay that is not the contractor's fault. If the contract administrator accepts that the
delay was caused by a relevant event, then they may grant an extension of time and the
completion date is adjusted. The contractor is required to prevent or mitigate the delay and any
resulting loss, even where the fault is not their own.

Assessing claims for an extension of time can be complicated and controversial. There
may be multiple or concurrent delays, some of which are the contractor's fault and some not.
There are many occasions where contractors contribute to delay themselves by their
performance during design periods, when producing drawings, mock ups and samples or in
inter-facing with sub-contractors.
Claims should be judged against the actual progress of the works, not the programme,
and must demonstrate the link between the breach (cause) and the delay. The contract
administrator may review extensions of time after practical completion and further adjust the
completion date. Mechanisms allowing extensions of time are not simply for the contractor's
benefit. If there was no such mechanism and a delay occurred which was not the contractor’s
fault, then the contractor would no longer be required to complete the works by the completion
date and would only then have to complete the works in a 'reasonable' time. The client would
lose any right to liquidated damages. Claims for extension of time can run alongside claims for
loss and expense (relevant matters) however, one need not necessarily lead to the other.

Relevant Case

Peak Construction (Liverpool) Ltd V Mckinney Foundation Ltd (1970)

 The Court of Appeal held that Peak was not entitled to recover Liquidated Damages
from McKinney as the corporation was not entitled to recover those Liquidated
Damages from Peak. The Court of Appeal found that at least part of the 58-week delay
had been caused by the corporation itself, and the extension of time clause in the head
contract did not enable the corporation to extend time for its own delays. Further, no
attempt had been made by the corporation to extend time. Accordingly, there was no
date from which Liquidated Damages under the head contract could commence

Definition of claim in construction

Claims commonly arise between the parties to construction contracts. This can be as a result of
problems such as; delays, changes, unforeseen circumstances, insufficient information, and
conflicts.

Claims might be made for loss and expense, extension of time, liquidated damages, and so on.
The contract should set out what can constitute a claim and how it should be dealt with. There
may also be claims associated with the appointment of consultants.
Money Claim Case Study
Crosby vs. Portland UDC (1967) and Merton LBC vs. Leach (1985)
The courts found in favour of the contractor in both occasions due to the impracticality to identify the
actual delay and cost caused by each individual matter that the ‘delay’ and ‘loss’ should be rolled up.

These two cases caused a proliferation of global claims as contractors the world over argued that events
which occurred on their contract were so complicated as to make it impracticable, if not impossible to
assess the additional expense cause by delay and disorganisation due to any one of the events in isolation
from the other events.

2. Claim in Time

In Contract act 1950, time of completion must be within “reasonable time”. In construction
contract, reasonable time is deemed to be the time offered by contractor in his tender.

Extension of Time (EOT) is the allowing the contraction period to be extended and the delay
that is not the contractor fault. If the client cause delay and there no EOT provision, the
contractor fails to grant EOT, the time will become large. c. The delaying events listed in the
standard forms of contract. i. PAM 2006 - Clause 23.8 (a)-(x) ii. PWD FORM 203A – Clause
43.1 (a)-(j)
Comparison Between PAM And PWD

PAM CONTRACT 2006 PWD FORM 203A (Rev.1/2010)

- Based on PAM 2006 clause 23.0 it - The relationship of time and money is where
is stated that the time for the the client claims either Liquidate Ascertained
contractor can claim which is Damages (LAD) towards the contractor for the
Extension of Time (EOT) but under delay when the Extension of Time (EOT) is no
the causes of relevant events which longer valid.
stated in the clauses of 23.8.
- The contractor can claim the EOT - Upon it becoming reasonable apparent that the
for continuation of work on site, but progress of the work is delayed, the contractor
when the EOT has expires and the shall forthwith give written notice to the S.O to
contractor did not finish the work, the causes of delay and relevant information
the client can claim Liquidated with supporting document enabling the said
Damages (LD) towards the officer to form an opinion as the cause and
contractor under the Clauses of 22.0 calculation of the length of delay.
PAM 2006.
- When the contractor fails to - Therefore in the period given by the S.O to
complete the works by the finish the work which is the EOT, the
completion date, the architect can
issues the certificate of non- contractor must finish the work before the EOT
completion. Thus the contractor expires, thus the contractor can also claim the
shall pay the amount of money to loss and expenses in the clause 44.0 under the
the client in amount of stated by the
PWD FORM 203A where the contractor shall
client in each day of delay.
within 30 days of the occurrence of such event
or circumstances or instruction give notice in
writing to he S.O of his intention to claim for
such direct loss or expenses together with a n
estimate of the amount of such loss and/or
expenses. But this is stated under the clause of
43.1 (c), (d), (e), (f) and (h).

Das könnte Ihnen auch gefallen