Beruflich Dokumente
Kultur Dokumente
The building shell of the Klinikum Frankfurt Hoechst in early February 2018. Interior design of the Passive House hospital
is currently underway. A test phase will follow scheduled completion next year. © Klinikum Frankfurt Hoechst
1
Exterior view of the new building in Frankfurt. According to the new plans, unobtrusive shades will be used for the façade.
The total length of the hospital building is 143 metres and it stands over 23 metres tall. © wörner traxler richter
If the energy demand of the hospital is determined in the conventional way, almost half of the future energy demand is
disregarded by the planners. The computer equipment as well as the magnetic resonance imaging equipment alone account
for eight and seven percent of the energy expenditure respectively. © Passive House Institute
Description from top: Heating, hot water generation, ventilation, cooling, lighting, computer equipment, hospital catering,
sterile supply, magnetic resonance imaging equipment, miscellaneous, “Bilanzgrenze üblicher Verfahren” - balance
boundary with conventional methods.
2
Passive House concept pays off
Due to their intensive 24-hour use,
hospitals consume large amounts of
energy. From the accident and
emergency department and
operating theatre to patient rooms,
numerous technical devices are in
continuous use and the lights are on
practically all the time. "In addition to
providing improved comfort, the
Passive House Standard is
designed to reduce the energy
demand considerably. Therefore this
energy efficient concept is
particularly valuable for hospitals
with their high energy demand,"
explains Oliver Kah of the Passive
House Institute.
Hygiene-relevant requirements
At the same time, the implementation of the Passive House Standard in hospitals must meet
special requirements, for instance regarding operating theatres. "Hospitals have extremely high
hygienic requirements, including how exhaust heat from surgery areas is to be utilised," explains
Oliver Kah.
3
Besides improved comfort, the Passive House Standard is designed to significantly reduce the demand for energy, which is
particularly valuable for hospitals with their high energy demand. © Klinikum Frankfurt Hoechst
Energy-intensive hospitals
Conventional verification methods only take the energy demand for heating and cooling,
ventilation, water and lighting into consideration. "However, the distribution of energy shows that
hospitals are usually equipped with more devices and have energy-intensive processes. If the
energy demand is calculated using conventional methods, almost half of the future energy
demand remains unconsidered," says Kah.
4
Demolition of building
The costs for the replacement
building of the Klinikum
Frankfurt Hoechst are
estimated at 263 million Euros.
The German state of Hesse is
contributing around 55 million
Euros towards this energy To avoid thermal bridging, a layer of thermal insulation is laid between the end
efficient construction. The wall of the hospital building and the brickwork above it (roof parapet).
© Passive House Institute
existing building dating from the
1960s will be demolished after the Passive House hospital starts operating. Two further
construction stages are planned on the site.
5
General information
Passive House
A Passive House is a building that does not require any conventional building heating on account of
its excellent thermal insulation. Such buildings are called "passive houses" because a major part of
their heating demand is met through "passive" sources such as solar radiation or the waste heat from
occupants and technical appliances. A Passive House thus consumes about 90 percent less heating
energy than existing buildings and 75 percent less energy than an average new construction.
Pioneer Project
The first Passive House in the world was built in Darmstadt-Kranichstein
(Germany) 25 years ago by four private homeowners on their own personal
initiative. Ever since the homeowners moved in with their families in 1991, these
terraced houses have been regarded as a pioneer project for the Passive House
Standard. 25 years later, building physicists have attested to the unimpaired
functioning of the first Passive House and its unchanged low heating energy
consumption. With its newly installed photovoltaic system, the world's first
Passive House now utilises renewable energy and received the Passive House
Plus certificate for this reason. © Peter Cook
____________________________________________________________
Pictures for editorial use: www.flickr.com/photos/passive-house-institute
The latest news on the subject of Passive House: www.twitter.com/IGPassivhaus
_______________________________________________________________
Press contact:
Katrin Krämer, Press Officer
Passive House Institute Dr. Wolfgang Feist Ɩ Rheinstr. 44/46 Ɩ 64283 Darmstadt
Telephone: +49 (0) 6151/82699-0 Ɩ E-mail: presse@passiv.de Ɩ Internet: www.passivehouse.com