Sie sind auf Seite 1von 11

Home Search Collections Journals About Contact us My IOPscience

A novel support system for shallow buried caverns based on the mining method

This content has been downloaded from IOPscience. Please scroll down to see the full text.

2016 J. Geophys. Eng. 13 123

(http://iopscience.iop.org/1742-2140/13/1/123)

View the table of contents for this issue, or go to the journal homepage for more

Download details:

IP Address: 128.192.114.19
This content was downloaded on 26/06/2016 at 13:31

Please note that terms and conditions apply.


Journal of Geophysics and Engineering

J. Geophys. Eng. 13 (2016) 123–132 doi:10.1088/1742-2132/13/1/123

A novel support system for shallow buried


caverns based on the mining method
Ding Wen-Qi1,2, Qiao Ya-Fei1,2, Jin Yue-Lang1,2 and Zhang Qing-Zhao1,2
1
  Department of Geotechnical Engineering, College of Civil Engineering, Tongji University, Shanghai,
SH 200092, People’s Republic of China
2
  Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,
Tongji University, Shanghai, SH 200092, People’s Republic of China

E-mail: zqz0726@163.com

Received 12 March 2015, revised 29 November 2015


Accepted for publication 21 December 2015
Published 1 February 2016

Abstract
In order to maintain the original appearance of the rocks on a cavern roof and protect the
ground environment, a new supporting method for shallow-buried caverns is proposed.
This study investigates the design theory and construction process. Based to this method,
some crisscross small tunnel sheds are embedded in the overburden layer. Hence a supporting
system of interaction between surrounding rocks and supporting structures is formed.
By combining the numerical calculation with monitoring measurement, we found that the
distribution of calculated deformation generally agreed with the monitoring measurements.
The monitoring results revealed that the proportion of rock shelf load-bearing reached 47%.
The self-bearing capacity of the surrounding rocks is brought into significantly play.

Keywords: small tunnel shed, shallow tunneling method, underground construction,


supporting system, construction monitoring

(Some figures may appear in colour only in the online journal)

Nomenclature uR deformation under restraint


α proportion of load for supporting structure
AConcrete cross-sectional area of reinforced c­ oncrete. γ unit weight of surrounding rocks
ATunnel cross-sectional area of the tunnel δ maximum span settlement caused by excavation
B spacing between various small tunnel sheds θ angle between measuring line and horizontal plane
ERIR flexural rigidity of embedded support
h buried depth of cavern 1. Introduction
l span of embedded support
P0 released load after excavation Over the past decades, the quantities and scales of under-
PR load sustained by supporting structure ground projects have risen rapidly in China, and many proj-
q uniform load ects have been carried out in unfavorable ground conditions.
rConcrete unit weight of reinforced concrete The development of construction techniques has enabled
u deformation of surrounding rocks the realization of large-span underground caverns and
u1 released deformation of surrounding rocks crossing engineering. However, early underground projects
u2 deformation before excavation surface reached were mostly constructed with opening excavations, which
monitoring section often led to road traffic being severely interfered with and
um measured value of deformation. the environment disrupted (Barton et al 1974, Loganathan
ue elastic deformation and Poulos 1998). The shallow tunneling method was then
up plastic deformation studied to solve these problems and bring forth controlled

1742-2132/16/010123+10$33.00 123 © 2016 Sinopec Geophysical Research Institute  Printed in the UK


J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Earth surface
Earth surface
Concrete box beam
Rock
Surrounding rock
Reinforced concrete beam
Earth surface
(Small Tunnel Shed)
Anchor bolt and shotcreting

Anchor bolt Anchor bolt


Rock

Conduit Conduit
Reinforced

concrete lining

(a) (b) (c)

Figure 1.  Supporting styles for mining method. (a) The internal support (b) the external support (c) the built-in support.

disturbance to the soundings of construction sites. This and Booker 1996). Generally, the pressure of surrounding
method can guarantee construction work safety and restrain rock for a shallow-buried cavern is calculated by using the
the land subsidence (Barton 2002). The auxiliary construc- gravity model. It is assumed that when the burial depth of
tion methods for shallow tunneling method mainly include tunnel is small, the surrounding rocks are not considered as
the freezing method (Genis et al 2007, Zhang and Chuan bearing structures since the displacement of rock may extend
2005), the pipe-shed method (Carranza-Torres and Fairhurst over the land surface, namely that the self load-bearing
2000), the pipe-roofing method (Xiao et al 2005) and the capacity of surrounding rocks and the combined action
culvert box method. between surrounding rocks and supporting structures are
In the freezing method, pipe holes are placed around the neglected (Serrano et al 2014). However, when a shallow-
tunnel, and then brine with low temperature is kept in circula- buried cavern has comparatively favorable conditions of sur-
tion. The aquiclude around the pipe holes is frozen and forms rounding rock, it is worth studying the self-bearing capacity
a frozen wall with high strength and great sealing conditions of surrounding rocks to reduce the construction costs for
(Li et al 2004). The excavation and construction work can supporting system. The objective of present study is to pro-
be performed under the protection of frozen wall. The pipe- pose a support method of small tunnel shed. This method can
shed method is widely applied in subsurface engineering take full advantage of the self load-bearing capacity of sur-
containing rocks or weak soils with a low water level, but it rounding rocks combining with the multi-arch small tunnel
is still hardly workable in large-span subsurface engineering shed. Based on this support method, the original facilities
containing saturated weak soils. In addition, pipe sheds usu- and vegetation on the ground surface could be well protected
ally cause contamination to the environment and significant and preserved.
influence to the landscape (Sari and Pasamehmetoglu 2004).
The culvert box method requires the working surface to
2.  Theory and methods
be stable during the construction process, and this method
also leads to high construction costs due to the high level of
2.1.  Supporting methods of shallow-buried cavern
underground water. The pipe-roofing method is a new type
of technique for subsurface engineering based on the mining In general, excavation methods for underground caverns can
method. Small pipe roofs can be used as the basis of large be classified into three types, i.e. open-cut method, semi-
span and large section underground structures (Karakus and open-cut method and mining method. For underground cav-
Fowell 2003). In most auxiliary construction methods, the erns constructed by using the mining method, the supporting
support system is applied after excavation, or applied with forms can be often divided into three types based on the sup-
slip casting before construction works (Xu et al 2013). port position which include internal support, external support
However, each construction method mentioned above has and embedded support (figure 1). When selecting the position
its own disadvantages and application limits. In some spe- of a cavern, the covering depth of the cavern roof should be
cial projects, the construction methods should be further considered first of all. There should be sufficient fresh rock
investigated. layers retained above the roof and the roof should be thick
For the purposes of supporting the system design of an enough to impose adequate normal pressure on the joints, so
underground cavern, the excavation and supporting methods as to form the roof arch (Palmstrom and Stille 2007). In case
should be identified primarily. The shape and size of the the thickness above the arch cannot meet the requirement,
working surface as well as the corresponding construction open excavation method is usually adopted. Anchor bolts, pre-
scheme should be estimated with full consideration of all stressed anchors and grouting reinforcement are often used
factors including safety, economy and environment (Verruijt as supplementary means to improve the bearing capacity of

124
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

deformation is oversized, a supporting system should be


adopted (Konishi et al 2002). Supporting structures can
restrain the deformation of surrounding rocks, and meanwhile
the structures are affected by the surrounding rocks. This is
the interaction between supporting structures and surrounding
Open top part
rocks. The typical curve of mechanical characteristics for sur-
rounding rocks is given in figure 5. ue is elastic deformation
and up is plastic deformation. uR is the deformation under
Sub-wall part restraint, and PR is the corresponding load. P0 is the released
load after excavation, which can be obtained by plasto-elastic
theory or through field test.
After the excavation of underground cavern, the released
load is sustained by surrounding rocks and supporting struc-
Figure 2.  Open top and sub-wall method.
tures. It is assumed that the load sustained by the supporting
Earth surface structure is PR, and then the proportion of load sustained by
Concrete beam
the supporting structure can be calculated as in equation (1).
α = PR /P0
(1)
In figure 5, u is the deformation of the surrounding rocks,
and PR decreases with the increase of u. The case u  = max (u)
Anchor bolt is equivalent to the case without any support (point A), and the
surrounding rocks are self-stabilized. For shallow-buried cav-
Central Line
erns, when the deformation develops, the relaxation load will
impose on the supporting structure. The case u = 0 is equiva-
lent to the case of rigid support (point C). The released load
from the excavation is completely sustained by the supporting
Figure 3.  Loading umbrella arch method.
structure, and the surrounding rocks do not appear to have any
surrounding rocks. External support and embedded support deformations.
are usually applied to shallow-buried caverns to avoid open For the embedded and ground support structure of shallow-
excavation. buried caverns, it is assumed that both ends of the supporting
For underground caverns with very small burying depths, structure are clamped and bear uniform load q as shown in
the open excavation method is adopted in most cases. equation (1).
However, open excavation has some limitations such as q = γ hB − γATunnel + γConcreteAConcrete
(2)
ground environmental damage, occupying large field area,
long construction period, high excavation difficulty and high where γ is the unit weight of the surrounding rocks, h is the
construction costs. The open top and sub-wall method (figure buried depth of the cavern, B is the spacing between various
2) is also used in some cases. The design and construction small tunnel sheds, ATunnel is the cross-sectional area of the
work of this method is firstly completing the cavern roof with tunnel, rConcrete is the unit weight of the reinforced concrete,
excavating shallowly and grouting, and then completing the and AConcrete is the cross-sectional area of the reinforced con-
lower-part cavern structure with cave excavation after the crete. For shallow-buried caverns, surrounding rocks above
earth is backfilled. Comparing with open excavation method, the embedded support can play partial self load-bearing
the open top and sub-wall method is preferential, since the capacity. The lower surrounding rocks are deemed as having
construction site is smaller due to the decrease of excavation no self-load-bearing capacity, and are hung on the embedded
volume, and the excavation difficulty and construction costs support (figure 6).
are also lower. For the design and construction work of a shallow-buried
For shallow and bias tunnels with a small span, a loading cavern, the supporting structure and surrounding rock above
umbrella arch construction method can be adopted (figure 3). the structure are considered as released loads after excavation,
This method can ensure that the tunnel construction is safe i.e. P0  =  q. Flexural rigidity of the embedded support is ERIR,
and accelerate the progress of construction (Dang 2003). load sustained by surrounding rocks above the embedded sup-
Otherwise, the digging piles curtain method can also be port is (1  −  α)q, load sustained by the supporting structure is
adopted (figure 4). αq and α is the proportion of load sustained by the embedded
support. It can be assumed that both ends of the embedded
support are solidly connected (figure 1(c)), i.e. the anchor
2.2.  Theory of small tunnel shed
effect between both ends of the small tunnel shed and the sur-
If the stress condition of surrounding rocks exceeds the peak rounding rocks is pretty good and no shift and rotation between
strength of rock mass, a plastic zone will appear around the them could happen. The maximum displacement of the mid-
cavern and plastic deformation will develop. If the plastic span of the embedded support can be calculated as follows:

125
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Reinforced
Longitudinal beam Reinforced
concrete plate
Digging pile concrete plate
Transverse beam
Transverse beam

Digging pile

Tunnelling with

Mining Method

Figure 4.  Digging piles curtain method.

δ R = αql 4 /(384ERIR )
(3) pi
Namely,
C
α = 384ERIRδ R /ql 4
(4) p0
where l is the span of the embedded support.
Through numerical simulation, the characteristic curve of B Slack load
the surrounding rocks can be identified (Zhang et al 2004).
The deformation of the surrounding rocks at the feature point pR
is determined as u  =  δR, and then the load sustained by the sup-
porting structure can be calculated as shown in equation (5). A
o
PR = f (δ R )
(5) u e
up u
By using equations  (1), (4) and (5) simultaneously, the
u=uR
proportion of load for supporting structure α and the load
sustained by supporting structure PR under different rigidity
of embedded support can be obtained. Meanwhile, the defor- Figure 5.  Characteristic curve of the surrounding rock.
mation during the excavation can be monitored on site, i.e.
were greyish-green in color. Tuff rocks contained mainly silica
u m = δ R. Hence through calculating the proportion of load
mineral and thin layers. In the upper depth of 0.2 m, cultivated
sustained by supporting structure and adjusting the supporting
soil (Qpd) can be found. Clays mixed with sands and rubble
parameters in a timely manner, dynamic feedback of design
stones were distributed at a depth of 0.6–0.75 m, with brown
and informational construction can be achieved.
color and slightly humidity. Highly weathered tuff rock mixed
Based on the above analysis, a new small tunnel shed sup-
port method was proposed. This method can combine the sup- rubble stone was found under the layer of clay, and the thick-
port system of a small tunnel shed and the surrounding rocks ness was 1.5–2.85 m. Then moderately weathered tuff with
in the overburden layer, and take full advantage of the self horizontal bedding appeared. Moderately weathered tuff rocks
load-bearing capacity of surrounding rocks. The small tunnel were commonly observed and widely distributed. Some other
shed structure and surrounding rocks can work together to moderately weathered rocks, such as tuffaceous sandstone
sustain the load on top and hang on the cavern roof. and tuff breccia, were distributed sparsely. To understand such
behavior of the moderately weathered tuff rock, core samples
were taken to perform the tests and to estimate the rock mass
3.  Engineering overview and construction program quality, based on the Chinese Standard for Classification of
Engineering Rock Masses (GB50218-94). The average uni-
3.1.  Engineering geology
axial compression strength of the rock samples was identi-
The Sleeping Buddha Palace project was a new scenic spot fied as approximately 25.7 MPa, and the deformation modulus
which was located in the famous scenic site at the Giant was about 1.4 GPa. The ultrasonic longitudinal wave veloci-
Buddhist Temple of Xinchang, Zhejiang Province, China. ties of intact rock (Vpr) and rock mass (Vpm) were obtained by
The geological formations mainly consisted of the tuff rock using both laboratory and field tests, which were 5200 m s−1
masses, which was the main rock type along the small tunnels. and 4700 m s−1, respectively. According to the standard
Tuff rocks were moderately to highly weathered. The weath- method (GB50218-94), the integrality coefficient Kv can be
ered faces of these rocks were brown in color and fresh parts calculated using the equation Kv  =  (Vpm / Vpr)2. Therefore, the

126
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Earth surface

Calculation unit

The upper rock

The lower rock

Cavern top

Figure 6.  Cross section of inbuilt support.

Figure 7.  Main seepage fissures in the big hall.

integrality coefficient Kv of the tuff rock was about 0.82, and fissures. Fissure B was another main seepage fissure, which
the integrality grade was estimated as intact. Furthermore, the crossed fissure A. The dip angle of fissure B was about 35°,
hardness grade of tuff rock was estimated as middle level, and and the water seepage of fissure B was less than that for fis-
the quality of tuff rock in the present study was classified as sure A. The seepage fissures of C and D were shorter than A
the third grade. and B. The dip angles of fissure C was close to 45°. Fissure C
One major fissure of longitudinal orientation along the was connected to fissure A, and its water seepage became even
cavern with an inclination of 30 degrees was found right above more obvious. Fissure D was close to fissure B, and its dip
the cavern. This fissure cut through the ground surface, and angle was close to 40°. Even though water seepage appeared
cut the central part of the rock column between the big hall during the construction process, groundwater was not gen-
and small hall in an inclined way. Since the fissure was almost erally abundant. The tuff rocks were relatively intact, so the
perpendicular to the cavern roof, the stability of the whole working face excavated normally did not contain much water,
cavern was not affected by this fissure. However, the excava- implying that the groundwater activity could hardly reduce
tion of the cavern tended to cause overall extroversion, and the the stability of the surrounding rocks.
stability of arch springs became a little worse.
Groundwater activity is an important factor related to the 3.2.  Design and construction
stability of the cavern (Yi 1997). In our study, the ground-
water was typical of bedrock fissure water, which was mainly The Sleeping Buddha Palace is composed of a main cavern
supplied from the surface precipitation. The precipitation and several vestibular small caverns (figure 8). The main body
can infiltrate into the cavern along the penetrating fissures. is the big hall of the Sleeping Buddha Palace, and the small
Because the water leakage phenomenon was observed during halls are located outside the big hall. The big hall and small
construction, fissure investigation was carried out to find the halls are connected by five parallel entries. The big hall has
seepage location. Four seepage fissures were found on the top a span of about 18 m and a height of about 12 m. The whole
of the big hall, as shown in figure 7. Fissure A was the big- cavern has a hemispheric shape. The main cavern of the the
gest seepage fissure, and its dip angle was approximately 90°. Sleeping Buddha Palace is approximately 43.5 m long, 12 m
Since fissure A almost penetrated the top of the big hall, the high and has a span of 19.8 m. The overburden layer of the
water seepage from fissure A was more obvious than other cavern is about 8–10 m.

127
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Figure 8.  On-site view of the cavern.

The design and construction works of the Sleeping Buddha corresponding construction techniques. Measurements such
Palace should meet the requirements of keeping the trees on as cavern convergence, fissure convergence, anchor rod axial
ground surface and the original appearance of rocks on the force, secondary lining reinforced bar axial force and con-
cavern top (figure 8). Since the covering layer was thin, the tact pressure, and strain monitoring were carried out. The
space between caverns on the left was small and the anti-­ arch crown settlement of the cavern could not be measured
horizontal stability was poor. Considering these limitations for construction reasons and was calculated reversely by the
at the construction site, a longitudinal connective pilot tunnel cavern convergence monitoring data. The fissure investigation
was firstly excavated in the middle of the overburden layer, was performed during construction to estimate the develop-
and the direction of this pilot tunnel is perpendicular to the ment of fissures in the excavation of rock mass. In addition, a
span (figure 9(a)). Meanwhile, timely anchor-plate retaining numerical model was set up to simulate the stages of cavern
was carried out based on the principle of NATM (figures 9(b) excavation using the finite element method in the GeoFBA
and (c)). Then multiple load-bearing small tunnels were exca- program (figure 12).
vated from the longitudinal pilot tunnel, and were along the
span direction. Anchor-plate retaining was performed at the 4.  Results and discussion
same time. Subsequently, secondary lining structures were
applied for the pilot tunnel and small tunnels to form a multi- During the whole construction process, the disturbance
arch small tunnel shed. Finally, the lower part of the large- to surrounding rocks was reduced as far as possible. Over-
span cavern was excavated. excavation was controlled strictly and under-excavation was
The construction scheme is demonstrated in figure 10, in eliminated. NATM monitoring measurements were strength-
which the roman letters indicate the excavation sequence and ened, and the information was fed back which can be used to
the Arabic numbers indicate the supporting sequence. The adjust the design quickly. For the secondary lining, one-time
detailed sequence is explained as follows: (I) excavation of overall grouting was required, and compactness was ensured
longitudinal connect pilot tunnel; (1) early-stage support; (II) (figure 13). The multi-arch small tunnel shed was stretched
excavation of horizontal small tunnel shed; (1) early-stage across the span of the cavern, and a seated length was guar-
support; (2) pilot tunnel lining; (3) reinforcement of gallery anteed at both ends of the span. Rock bolts were installed to
anchor; (III) gallery excavation; (4) anchor; (IV) small hall anchor the tunnel shed into surrounding rocks. The longi-
excavation; (5) anchor; (V) excavation of the Sleeping Buddha tudinal pilot tunnel was used for connecting the horizontal
Palace cavern; (6) anchor; (VI) excavation; (7) anchor; (VII) multi-arch small tunnel shed and providing the entrance for
excavation; (8) anchor; (VIII) excavation. Various early-stage construction of the small tunnel shed. Furthermore, the pilot
supports of surrounding rocks should be completed quickly tunnel could enhance the feasibility of construction work and
and the onsite monitoring work improved. improve the structural integrity.
The NATM was adopted for the excavation of caverns, A few fissures in the rock masses between the great hall
and an all-around monitoring and measurement system was and the small halls appeared when the cavern was excavated,
established to measure the structural internal force during but the width of fissures was usually less than 1 mm. Due to
the construction (figure 11). Based on the onsite monitoring, construction problems, some monitoring results at the site
some judgment criteria was established to evaluate the sta- were disturbed during the cavern excavation. The measured
bility of surrounding rocks and the work status of supporting data fluctuated a little, and some convergence curves were
system (Karakus and Fowell 2005). During construction mon- not smooth (figure 14). However, the trend of convergence
itoring, the appearance of data abnormality was taken as the deformation kept stable, and the final convergence defor-
basis for adjusting the supporting parameters and adopting mations were relatively small. The cumulative convergence

128
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Figure 9.  Plan and section view of the supporting structure. (a) Plan view of small tunnel shed, (b) A–A section, (c) B–B section.

deformations monitored in the big hall are given in table  1. (Ng et al 2004). Using the dynamic design approach, the small
It can be seen from table 1 that most convergence deforma- tunnel shed support method could be successfully applied to
tions are less than 2 mm, and the development trend is stable, the construction of Sleeping Buddha Palace.
indicating the fissures usually keep stable, and the stability For underground cavern projects, it was impossible to
of the cavern was not affected by the fissures. Therefore, the measure close to the work surface right after excavation, so
rock masses in the cavern were stable during and after the there was already a released deformation of surrounding rocks
construction. Based on the simulation work from different with measured value u1. In addition, before the excavation
construction stages, the consistency of calculation results surface reached the monitoring section, a deformation with
and the measured data in magnitude and trend was revealed. measure value u2 developed. These two values plus the meas-
Results showed that the distribution of calculated deforma- ured value of deformation was the absolute value of deforma-
tion of rock masses was generally agreed with the monitoring tion of the surrounding rocks, namely, u1  +  u2  +  um, wherein
measurements. By combining the numerical calculation with um was the measured value of deformation. Based on the pre-
monitoring measurements, the dynamic design can be realized vious research results, u1  +  u2  =  0.5u (Wang 1990), which

129
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Figure 10.  Construction scheme.

Big hall

Measuring line Measuring line Measuring line


NO.1 NO.2 NO.4 NO.6
NO.3 NO.5

Small hall

Figure 11.  Layout of convergence deformation measuring lines.

Figure 12.  Calculation grid and overall vector diagram.

deemed that convergence measuring line had no displacement AR  =  3.15 m2, IR  =  2.722 m4, l  =  22 m. We assumed the
on the measuring point of the rock column, then the maximum hanging lower surrounding rocks had no displacement rela-
span settlement caused by excavation of the Sleeping Buddha tive to the supporting structure, i.e. δR  =  δ, the uniformed
Palace was δ  =  2 umsinθ  =  3.1 mm, wherein θ was the angle load of the support girder could be calculated through equa-
between the measuring line and the horizontal plane. tion  (3) as αq  =  384ERIRδR, 4l 4  =  98.55 kN m−1. Based on
Take longitudinal 4 m as the calculation model (figure ­equation (2), it could be obtained that q  =  184.90 kN m−1, then
6), the cross section  burying depth was 9 m, the interface the ­proportion of overburden self-weight load of the shallow-
parameter of the box girder was ER  =  2.85  ×  107 kN m−2, buried cavern sustained by the supporting structure was

130
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Figure 13.  Excavation of the cavern during construction.

quickly supported after being excavated, hence the stability


of the support system was guaranteed. The cross section area
of the small tunnel can be adjusted flexibly. Therefore, this
support method is not only suitable for large-span shallow-
buried underground caverns, but also suitable for shallow-
buried underground caverns with special requirements of
maintaining the original conditions on the ground surface and
cavern roof.

5. Conclusions

In the present study, a new supporting method for shallow-


buried caverns based on the mining method was proposed. We
successfully applied this method to a specific project to mini-
Figure 14.  Cumulative convergence displacement of the NO.3
measuring line.
mize the damage to the surrounding environment. Through
this application, the small tunnel shed supporting method
Table 1.  Cumulative convergence deformation in the big hall. can be understood thoroughly. The main conclusions are as
Measuring Convergence Development follows:
Location line No. ­deformations (mm) trend (1) The small tunnel shed supporting method is an embedded
Big hall 1 1.56 Steady support method, and the layout can be adjusted based
2 1.06 Steady on the project needs. Our study makes an investigation
3 2.15 Steady into the design theory and construction method. This
4 1.45 Steady supporting method can be combined with numerical
5 1.36 Steady calculations and monitoring measurements to realize
6 0.41 Steady dynamic design.
(2) In traditional design methods, the self load-bearing
α  = 98.55/184.90  ×  100%  =  53%, the self-bearing propor- capacity of surrounding rocks of shallow-buried caverns
tion of surrounding rocks was 1  −  53%  =  47%. Therefore, it is hardly considered. The suggested method identified the
could be seen that the self-bearing capacity of the surrounding design parameters of the supporting structure based on
rocks played a significant role in the design and construction the principles of rock mechanics, hence reflecting the par-
work for this project. The self-bearing capacity of the sur- tial self load-bearing capacity of the surrounding rocks in
rounding rocks was brought into significantly play. a controlled way.
The main load-bearing structure of the cavern, namely the (3) For large span underground caverns, the small tunnel
multi-arch small tunnel shed, was arranged in the middle of shed supporting method has certain superiority in terms
the overburden layer, so the facilities and vegetation on the of reflecting the self load-bearing capacity of surrounding
ground surface were well protected. The original appear- rocks and reducing costs. This method can be referenced
ance of the rocks in the internal walls of the caverns was in solving an underground cavern project with the
preserved. Since the overburden layer above the cavern was requirement of protecting the ground environment and
preserved and only small tunnels were excavated, the exca- in controlled construction with slight disturbance, which
vation volume was reduced significantly, and the construc- can effectively avoid heavy excavation and satisfy the
tion costs also decreased. The load-bearing horizontal small special requirements of scenic sites for preserving the
tunnels had a relatively small cross-sectional area and were original appearance of rocks.

131
J. Geophys. Eng. 13 (2016) 123 D Wen-Qi et al

Acknowledgment Li D Y, Lu A Z and Zhang Q H 2004 Analysis of freezing method


for construction of connected aisle in Nanjing metro tunnels
This work is financially supported by National 863 Program Chin. J. Rock Mech. Eng. 23 334–8
Loganathan N and Poulos H G 1998 Analytical prediction for
(Grant No.2012AA112502) and The National Basic Research tunneling-induced ground movements in clay ASCE J.
Program of China-973 Program (Grant No.2014CB046905 Geotech. Geoen. Eng. 124 846–56
and No. 2011CB013800) and National Natural Science Foun- Ng C W W, Lee K M and Tang D K W 2004 Three-dimensional
dation of China (NO. 51578408). numerical investigations of new Austrian tunnel method twin
tunnel interactions Can. Geotech. J. 41 523–9
Sari D and Pasamehmetoglu A G 2004 Proposed support design,
References Kaletepe tunnel, Turkey Eng. Geol. 72 201–16
Serrano A, Olalla C and Galindo R A 2014 Micromechanical basis
for shear strength of rock discontinuities Int. J. Rock Mech.
Barton N, Lien R and Lunde J 1974 Engineering Classification of Min. Sci. 70 33–46
Rock Masses for the Design of Tunnel Support (Oslo: Mathisen Palmstrom A and Stille H 2007 Ground behavior and rock
and Halvorsen) pp 189–236 engineering tools for underground excavations Tunn. Undergr.
Barton N 2002 TBM Tunnelling in Jointed and Faulted Rock Space Technol. 22 363–76
(Rotterdam: Balkema) p 169 UDC GB5018-94 1994 Standard for engineering classification of
Carranza-Torres C and Fairhurst C 2000 Application of the rock masses China, UDC GB
convergence-confinement method of tunnel design to rock Verruijt A and Booker J R 1996 Surface settlements due to defor­
masses that satisfy the Hoek–Brown failure criterion Tunn. mation of a tunnel in an elastic half-plane Géotechnique 46 753–6
Undergr. Space Technol. 15 187–213 Wang J Y 1990 Principle of Informational Design and Monitoring
Dang H S 2003 Construction of shallow burring and deep tunnel for Tunnel Engineering (Beijing: China Railway Publishing
chamber with open top and subwall method J. Water Resour. House)
Archit. Eng. 1 61–2 Xiao S G, Zhu H H, Xia C C, Li X X, Shen G P and Ge J K 2005
Genis M, Basarir H, Ozarslan A, Bilir E and Balaban E 2007 Support effect analysis of upper pipe-roof during a box culvert
Engineering geological appraisal of the rock masses and being pushed within pipe-roof Chin. J. Rock Mech. Eng.
preliminary support design, Dorukhan Tunnel, Zonguldak, 24 3355–9
Turkey Eng. Geol. 92 14–26 Xu T, Xu Q, Tang C A and Ranjith P G 2013 The evolution of rock
Karakus M and Fowell R J 2003 Effects of different tunnel face failure with discontinuities due to shear creep Acta Geotech.
advance excavation on the settlement by FEM Tunn. Undergr. 8 567–81
Space Technol. 18 513–23 Yi P L 1997 Design and Construction of Modern Tunnel
Karakus M and Fowell R J 2005 Back analysis for tunnelling (Beijing: China Railway Publishing House)
induced ground movements and stress redistribution Tunn. Zhang S M, Song Y X and Zhu Y Q 2004 Numerical simulation and
Undergr. Space Technol. 20 514–24 analysis of ground reaction curve Rock Soil Mech. 25 455–8
Konishi S, Tamura T and Nishiyama T 2002 Tunnel face stability of Zhang Z Q and Chuan H E 2005 Study on the construction of
sandy ground with a clay layer on the crown Proc. Tunn. Eng. cross connection of shield tunnel connecting aisle by freezing
JSCE 12 25–32 method Chin. J. Rock Mech. Eng. 24 3211–7

132

Das könnte Ihnen auch gefallen