Supply ,installation, testing and commissioning including trial run and one year successful operation and maintenance of forced
lubricated Vertical turbine pump sets of Sixteen (16) nos. 150 cusec and two(02) nos. 50 cusec with allied Electro mechanical complete for
the proposed pumping Station of 2500 cusec .
(i)Static head
For 4.25 Cumec. = 6.3 m.(approx) & For
1.42 Cumec = 4.9 m.(Approx)
(ii) r.p.m. = 600
(iii) Bowl efficiency = 85%
(Minimum)
(b) 1.42 Cumecs discharge,< 600 rpm, Total bowl head 6.81 m (approx.)
[Item rate of Sl. 3 is included with item 1(b) ] Rs. 74.00 per job 2 jobs 110.00
a) 5 ton capacity, 30000 mm. span length travel with lift 12000 mm.
(Rate analysis enclosed) 5.00 per job 2 job 10.00
b)
Supply of all labour and T & P for lowerin the following size GI/PVC pipes with or
without slotted pipes as per the necessity from ground level and fitted and fixed up in
perfectly vertical position, including cutting and threading ofpipe and slotted pipwe
and fixing all joints, materials etc. complete and keeping the top of the casing pipe
threaded including plugging tube wells to prevent entry of foreign materials from the
obove excluding the cost of fittings and materials.
Cleaning and developing the production well using thir own compressor
c)
continuously worked till clear and adequate discharge in obtained from the
tube well including supply and use of all necessary equipments and labour as
nper direction
Supply of E.I.C.
all labours, T & P for packing the bore with washed gravel (Size P -
d) 6) around the pipes in good quality including cost of gravel etc. complete as
per direction of E.I.C.
e) Supplying all materiasls, labour and T & P and grouting with cement slurry
for sanitrary sealing around the GI casing pipe up to 3 mtrs. Below ground
level including cost of cement all complete as per direction of E.I.C.
(Supporting document of rate from P.H.E. Dept. enclosed) 10.00 per job 3 jobs 30.00
Total estimated cost of PART- A (Mechanical) = Rs. 3085.81