Bases and Surface Courses (Bituminous) Section 500
505.8 Measurement for Payment
Dense Graded Bituminous Materials shall be measured as finished work either in cubic
metres, tonnes or by the square metre at a specified thickness as indicated in the Contract
drawings, or documents, or as otherwise directed by the Engineer.
505.9 Rate
The contract unit rate for Dense Graded Bituminous Macadam shall be payment in full for
carrying out all the required operations as specified and shall include, to all components
listed in Clause 501.8.8.2. The rate shall include the provision of bitumen, at 4 percent and
4.5 percent by weight of the total mixture for grading 1 and grading 2 respectively.
The variation in actual percentage of bitumen used shall be assessed and the payment
adjusted plus or minus accordingly.
506 SAND ASPHALT BASE COURSE
506.1 Scope
This work shall consist of a base course composed of a mixture of sand, mineral filler where:
required and bituminous binder, placed and compacted upon a prepared and accepted sub-
base in accordance with these Specifications and the Jines, levels, grades, dimensions and
ctoss sections shown on the Drawings or as directed by the Engineer.
Note: Sand Asphalt Base course is used in special situations like quality coarse aggregates
not being available within economical leads and/or water needed for conventional base
course not being readily available, as in desert areas.
506.2 Materials
506.2.1 Bitumen
The bitumen shall be paving bitumen of viscosity grade VG 30 or VG 20, as specified in the
Contract, conforming to IS:73.
506.2.2 Sand
The sand shall be clean, naturally occurring or blended material free from any deleterious
substances, dry and well graded within the limits given in Table 500-14 and with other physical
properties conforming to the requirements of this Table.
183Section 500 Bases and Surface Courses (Bituminous)
Table 500-14 : Sand Grading and Physical Requirements
Sieve Size (mm) Cumulative Percentage by Weight of
Total Aggregate Passing
9.5 100
475 85-100
2.36 80-100
1.48 70-98
0.60 55-95
0.30 30-75
0.15 10-40
0.075 4-10
Plasticity Index (%) 6 max.
‘Sand equivalent (|$:2720 Part 37) 30 min
Los Angeles Abrasion Value 40 max.
(18:2386, Part 4)
Note = Maximum thickness for sand asphalt is 80 mm.
506.2.3 Filler
When required, filler shall consist of finely divided mineral matter such as rock dust, hydrated
lime or cement as approved by the Engineer. The filler shall conform to Clause 505.2.4,
506.3 Mix Design
506.3.1 Requirements for the Mix
‘Apart from conformity with the grading and quality requirements for individual ingredients, the
mixture shall meet the requirements set out in Table 500-15.
506.3.2 Binder Content
The binder content shall be optimized to achieve the requirements of the mix set out in
Table 500-15. The Marshall method for determining the optimum binder content shall be
adopted as described in the Asphalt Institute Manual MS-2.
184Bases and Surface Courses (Bituminous) Section 500
Table 500-15 : Requirements for Sand Asphalt Base Course
Parameter Requirement
Minimum stability (kN at 60°C) 2.0
Minimum flow (mm) 2
‘Compaction level (Number of blows) 2x75
Percent air voids 3-5
Percent voids in mineral aggregate (VMA) 16 min.
Percent voids filled with bitumen (VFB) 65-75
506.3.3, Job Mix Formula
The Contractor shall develop the job mix formula proposed for use in the works and submit it
to the Engineer for approval together with the following details :
i) Source and location of all materials;
ii) Proportions of all materials expressed as follows where each is
applicable:
a) Binder, as percentage by weight of total mixture;
b) Sand/Mineral filler as percentage by weight of total aggregate
including mineral filler;
iii) A single definite percentage passing each sieve for the mixed
aggregate;
iv) The results of tests enumerated in Table 500-15 as obtained by the
Contractor;
v) _ Test results of physical characteristics of aggregates to be used;
vi) Mixing temperature and compacting temperature.
While working out the job mix formula, the Contractor shall ensure that itis based on a correct
and truly representative sample of the materials that will actually be used in the work and
that the mixture and its different ingredients satisfy the physical and strength requirements of
these Specifications.
Approval of the job mix formula shall be based on independent testing by the Engineer for
which joint samples of all ingredients of the mix shall be furnished by the Contractor as
required by the former.
The approved job mix formula shall remain effective unless and until modified by the
Engineer. Should a change in the source of materials be proposed, a new job mix formula
shall be established by the Contractor and approved by the Engineer before actually using
the materials.
185