PURPOSE : This SOP gives the method of Preventive maintenance of Multimill for the
smooth operation of the equipment to achieve the desired process result of the batch.
SCOPE : This SOP covers the preventive Maintenance of Multimill ( Equipment No:
T-005/T-013) available in encore paithan.
ACCEPTANCE CRITERIA :
GENERAL CONDITIONS :
The preventive maintenance job should be carried out by a trained person under the
supervision of qualified competent person.
The operator/ technician who performs the job will enter his name/sign in "Done By"
column and responsible engineer/ supervisor will put sign in "Checked by " column of
recording format. The record will be reviewed by dept. Head monthly.
FREQUENCY :
PRECAUTIONS : The machine should always be switched off before starting the
maintenance.
Parts should be handled carefully.
Always use correct size of tools.
Precision parts should be handled very carefully and if needed hammered with Teflon
hammers with gentle strokes.
Product quality should not be jeopardized while attending the machine.
1.0 PROCEDURE :
1.1 Preventive maintenance of this equipment will be done every month in order to run
the equipment smoothly & efficiently.
1.2 The preventive maintenance will be done mostly on weekly holidays or any other
convenient day as long as Production work does not suffer.
1.3 Following things should be done for the preventive maintenance of this equipment:
2.0 ABBREVIATION : N. A.
HISTORY OF CHANGE
Version No. Effective Date Reason for Change
00 21.07.2003 Original Issue
Annexure I
The Preventive maintenance of the said equipment has been done/ Not Done & the
equipment is working /Not working Properly.
Annexure II
The Preventive maintenance of the said equipment has been done/ Not Done & the
equipment is working /Not working Properly.
Annexure III
The Preventive maintenance of the said equipment has been done/ Not Done & the
equipment is working /Not working Properly.
Annexure IV
The Preventive maintenance of the said equipment has been done/ Not Done & the
equipment is working /Not working Properly.
Annexure V
PREVENTIVE MAINTENANCE RECORD SUMMARY
Reviewed By
Reviewed By
Reviewed By