ESTIMATED COSTS
APRIL, 2018
STAGE 1
1. Preliminary Work
a) Removal of Aluminum roof cover and rafters from the existing building -
N30,000
b) Removal of electrical and sanitary fittings from the existing building –
N35,000
c) Demolishing the existing building - N140,000
d) Shielding the approach fence with the removed roof covers- N10,000
e) Auxiliary Equipment
i) 2 no. of wheelbarrows - N30,000
ii) Shovels, Diggers, Headpans etc. - N12,000
iii) Water Hose/Lines - N10,000
N267,000
2. Foundation Trench
a) Excavation of trench not more than 1 meter depth (appr. 142 meters) at
1000/meter - N142,000
b) Excavation of Column Bases. 25 No. at 1500/1 - N37,500
c) Removal of Surplus Debris - N10,000
d) Light Concrete blinding in column bases (Labour) - N15,000
N214,500
8. Plumbing
Sum - N68,000
STAGE 1 COLLECTION
1. Preliminary Work - N267,000
2. Foundation Trench - N214,500
3. Twisted Iron ReBars in Columns and Column Bases - N375,700
4. Concrete In Foundation Footing - N565,000
5. Block work In Foundation up to DPC - N649,500
6. Concrete to Short Columns and Block Holes - N62,500
7. Laterite and Hardcore Filling - N120,000
8. Plumbing - N68,000
9. Concrete In Ground Floor Slab - N731,000_
N3,053,200
STAGE 2
1. Blocks Work on Ground Floor Slab
a) 3000 no of 9” blocks at 170/1 - N 510, 000
b) 70 Bags of cement at 2550/1 - N 178, 500
c) 40 Tonnes of stone dust - N 104, 000
d) Bricklayers - N 170, 000
N 962,500
2. Lintels and Columns
a) Sawn formwork to Lintels and columns
i. 60 Nos. of 1x12x12 at 1300/1 - N 78,000
ii. 1 bag of 3” nails - N 7, 000
iii. Carpenters - N 50, 000
N 135,000
b) Twisted Iron Bars in Lintels and Columns
i. 60 lengths of y12 mm at 2100/1 - N 126, 000
ii. 40 lengths of y10 mm at N1500/1 - N 60, 000
iii. 1 roll of binding wire - N 7, 000
iv. Iron Benders - N 55, 000
v. 35 Lengths of y16mm at 3700/1 - N129,500
N377, 500
STAGE 2 COLLECTION
1. Blocks Work on Ground Floor Slab - N962,500
2. Lintels and Columns - N793,000
3. First Floor Decking Slab - N4,095,750
N5,851,250
STAGE 3
1. Blocks Work on Decking Slab
e) 3000 no of 9” blocks at 170/1 - N 510, 000
f) 70 Bags of cement at 2550/1 - N 178, 500
g) 40 tonnes of stone dust - N 104, 000
h) Bricklayers - N 210, 000
N 1,002,500
4. Lintels and Columns
b) Sawn formwork to Lintels and columns
iv. 72 Nos. of 1x12x12 at 1300/1 - N 93, 600
v. 1 bag of 3” nails - N 7, 000
vi. Carpenters - N 55, 000
N 155,600
STAGE 3 COLLECTION