Beruflich Dokumente
Kultur Dokumente
8-20XX
(proposed revision of ASME B31.8-2016)
TENTATIVE
SUBJECT TO REVISION OR WITHDRAWAL
Specific Authorization Required for Reproduction or Quotation
ASME Standards and Certification
ASME B31.8-2016
803.5 Miscellaneous Systems pressure system capable of safely absorbing the gas
control piping: all piping, valves, and fittings used to being discharged. Included in the station are piping and
interconnect air, gas, or hydraulically operated control auxiliary devices, such as valves, control instruments,
apparatus or instrument transmitters and receivers. control lines, the enclosure, and ventilating equipment,
installed in accordance with the pertinent requirements
gas processing plant: a facility used for extracting commer- of this Code.
cial products from gas.
service regulator: a regulator installed on a gas service
instrument piping: all piping, valves, and fittings used to line to control the pressure of the gas delivered to the
connect instruments to main piping, to other instru- customer.
ments and apparatus, or to measuring equipment.
production facility: piping or equipment used in produc- 803.7 Valves
tion, extraction, recovery, lifting, stabilization, separa- block or stop valve: a valve installed for the purpose of
tion, treating, associated measurement, field blocking or stopping the flow of gas in a pipe.
compression, gas lift, gas injection, or fuel gas supply.
check valve: a valve designed to permit flow in one direc-
Production facility piping or equipment must be used
tion and to close automatically to prevent flow in the
in extracting petroleum liquids or natural gas from the
reverse direction.
groundexcess flow valve:itafor
and preparing valve
transportation by pipeline.
designed to automatically stop or curb valve: a stop valve installed below grade in a service
sample piping: all piping, valves, and fittings used to
limit the flow in a gas service line line at or near the property line, accessible through a
collect samples of gas, steam, water, or oil.
when the gas flow exceeds the curb box or standpipe, and operable by a removable key
maximum anticipated flow during or wrench for shutting off the gas supply to a building.
803.6 Meters, Regulators, and Pressure Relief
normal operations. This valve is also known as a curb shutoff or curb cock.
Stations
customer’s meter: a meter that measures gas delivered to service line valve: a stop valve readily operable and acces-
a customer for consumption on the customer’s premises. sible for the purpose of shutting off the gas to the cus-
tomer’s fuel line. The stop valve should be located in
meter set assembly: the piping and fittings installed to the service line ahead of the service regulator or ahead
connect the inlet side of the meter to the gas service of the meter, if a regulator is not provided. The valve is
line and the outlet side of the meter to the customer’s also known as a service line shutoff, service line cock, or
fuel line. meter stop.
monitoring regulator: a pressure regulator installed in
series with another pressure regulator that automatically 803.8 Gas Storage Equipment
assumes control of the pressure downstream of the sta- bottle: as used in this Code, is a gas-tight structure com-
tion, in case that pressure exceeds a set maximum. pletely fabricated from pipe with integral drawn, forged,
pressure-limiting station: consists of equipment that under or spun end closures and tested in the manufacturer’s
abnormal conditions will act to reduce, restrict, or shut plant.
off the supply of gas flowing into a system to prevent bottle-type holder: any bottle or group of interconnected
the gas pressure from exceeding a predetermined value. bottles installed in one location and used only for stor-
While normal pressure conditions prevail, the pressure- ing gas.
limiting station may exercise some degree of control of
the flow of the gas or may remain in the wide open pipe-type holder: any pipe container or group of intercon-
position. Included in the station are piping and auxiliary nected pipe containers installed at one location and used
devices, such as valves, control instruments, control only for storing gas.
lines, the enclosure, and ventilating equipment, installed
in accordance with the pertinent requirements of this 804 PIPING SYSTEMS COMPONENT DEFINITIONS
Code.
pressure-regulating station: consists of equipment 804.1 Plastic Terms and Definitions
installed for automatically reducing and regulating the plastic (noun): a material that contains as an essential
pressure in the downstream pipeline or main to which ingredient an organic substance of high to ultrahigh
it is connected. Included are piping and auxiliary devices molecular weight, is solid in its finished state, and at
such as valves, control instruments, control lines, the some stage of its manufacture or processing, can be
enclosure, and ventilation equipment. shaped by flow. The two general types of plastic referred
pressure relief station: consists of equipment installed to to in this Code are thermoplastic and thermosetting.
vent gas from a system being protected to prevent the thermoplastic: a plastic that is capable of being repeatedly
gas pressure from exceeding a predetermined limit. The softened by increase of temperature and hardened by
gas may be vented into the atmosphere or into a lower decrease of temperature.
4
ASME B31.8-2016
elements are considered as incidental and are not nor- (b) electric-flash-welded pipe: pipe having a longitudinal
mally determined or reported. butt joint wherein coalescence is produced simultane-
ously over the entire area of abutting surfaces by the heat
804.7.2 Alloy Steel. 4 By common custom, steel is
obtained from resistance to the flow of electric current
considered to be alloy steel when the maximum of the
between the two surfaces, and by the application of
range given for the content of alloying elements exceeds
pressure after heating is substantially completed. Flash-
one or more of the following limits:
ing and upsetting are accompanied by expulsion of
Element Percentage metal from the joint. A typical specification is API 5L.
Copper 0.60 (c) electric-fusion-welded pipe: pipe having a longitudi-
Manganese 1.65 nal butt joint wherein coalescence is produced in the
Silicon 0.60 preformed tube by manual or automatic electric-arc
or in which a definite range or a definite minimum welding. The weld may be single or double and may be
quantity of any of the following elements is specified made with or without the use of filler metal. Typical
or required within the limits of the recognized field of specifications are ASTM A134 and ASTM A139, which
constructional alloy steels: permit single or double weld with or without the use
(a) aluminum of filler metal. Additional typical specifications are
(b) boron ASTM A671 and ASTM A672, which require both inside
(c) chromium (up to 3.99%) and outside welds and the use of filler metal.
(d) cobalt (1) spiral-welded pipe: also made by the electric-
(e) columbium fusion-welded process with either a butt joint, a lap joint,
(f) molybdenum or a lock-seam joint. Typical specifications are
(g) nickel ASTM A134, ASTM A139 (butt joint), API 5L, and
ASTM A211 (butt joint, lap joint, or lock-seam joint).
(h) titanium
(i) tungsten (d) electric-resistance-welded pipe: pipe produced in
individual lengths or in continuous lengths from coiled
(j) vanadium
skelp and subsequently cut into individual lengths. The
(k) zirconium
resulting lengths have a longitudinal butt joint wherein
or any other alloying element added to obtain a desired coalescence is produced by the heat obtained from resist-
alloying effect. ance of the pipe to the flow of electric current in a circuit
Small quantities of certain elements are unavoidably of which the pipe is a part, and by the application of
present in alloy steels. In many applications, these are pressure. Typical specifications are ASTM A53,
not considered to be important and are not specified or ASTM A135, ASTM A984, and API 5L.
required. When not specified or required, they should (e) furnace buttwelded pipe
not exceed the following amounts: (1) bell-welded: furnace-welded pipe produced in
Element Percentage individual lengths from cut-length skelp. The pipe’s lon-
gitudinal butt joint forge welded by the mechanical pres-
Chromium 0.20
Copper 0.35
sure is developed in drawing the furnace-heated skelp
Molybdenum 0.06 through a cone-shaped die (commonly known as a weld-
Nickel 0.25 ing bell), which serves as a combined forming and weld-
ing die. Typical specifications are ASTM A53 and API 5L.
804.7.3 Pipe Manufacturing Processes. Types and
(2) continuous-welded: furnace-welded pipe pro-
names of welded joints are used herein according to their
duced in continuous lengths from coiled skelp and sub-
common usage as defined in AWS A3.0, or as specifically
sequently cut into individual lengths. The pipe’s
defined as follows:
longitudinal butt joint is forge-welded by the mechanical
(a) double submerged-arc-welded pipe: pipe having a lon-
pressure developed in rolling the hot-formed skelp
gitudinal or helical butt joint produced by at least two
through a set of round pass welding rolls. Typical specifi-
passes, one of which is on the inside of the pipe. Coales-
cations are ASTM A53 and API 5L.
cence is produced by heating with an electric arc or arcs
between the bare metal electrode or electrodes and the (f) laser beam welded pipe: pipe having a longitudinal
work. The welding is shielded by a blanket of granular, butt joint made with a welding process that utilizes a
fusible material on the work. Pressure is not used, and laser beam to produce melting of full thickness of edges
filler metal for the inside and outside welds is obtained to be welded, followed by the fusion of those edges. A
from the electrode or electrodes. Typical specifications typical specification is ASTM A1006.
are ASTM A381, ASTM A1005, and API 5L. (g) seamless pipe: a wrought tubular product made
without a welded seam. It is manufactured by hot-
4
From Steel Products Manual, Section 6, American Iron and Steel working steel and, if necessary, by subsequently cold-
Institute, January 1952, pp. 6 and 7. finishing the hot-worked tubular product to produce
6
(f)
ASME B31.8-2016
tie-in: a connection where a gap is left to divide a pipeline overpressure protection: the prevention of the pressure
into test sections, or to install a pretested replacement in the system or part of the system from exceeding a
section, or in the continuous line construction at a loca- predetermined value and is typically provided by a
tion such as a river or highway crossing. device or equipment installed in a gas piping system.
tie-in weld: a tie-in connection using a weld, typically a pressure: unless otherwise stated, expressed in pounds
girth weld. per square inch (kilopascals) above atmospheric pres-
weld: a localized coalescence of metals or nonmetals pro- sure (i.e., gage pressure) and is abbreviated as psig (kPa).
duced either by heating the materials to the welding pressure test: a means by which the integrity of a piece
temperature, with or without the application of pres- of equipment (pipe) is assessed, in which the item is
sure, or by the application of pressure alone and with filled with a fluid, sealed, and subjected to pressure.
or without the use of filler material. It is used to validate integrity and detect construction
welder: one who performs manual or semiautomatic defects and defective materials.
welding. standard service pressure: sometimes called the normal
welding operator: one who operates adaptive control, utilization pressure, the gas pressure a utility undertakes
automatic, mechanized, or robotic welding equipment. to maintain at its domestic customers’ meters.
standup pressure test: a procedure used to demonstrate
welding procedures: the detailed methods and practices
the leak tightness of a low-pressure, gas service line,
involved in the production of a weldment.
introduces prominent wrinkles using air or gas as the test medium.
wrinkle bend: a pipe bend produced by a field machine or
controlled process that may result in prominent contour 805.2.2 Temperature Terms and Definitions
discontinuities on the inner radius. The wrinkle is delib- ambient temperature: the temperature of the surrounding
erately introduced as a means of shortening the inside medium, usually used to refer to the temperature of the
meridian of the bend. Note that this definition does not air in which a structure is situated or a device operates.
apply to a pipeline bend in which incidental minor, ground temperature: the temperature of the earth at pipe
smooth ripples are present. This depth.
wrought: metal in the solid condition that is formed to minimum design temperature: the lowest anticipated mate-
a desired shape by working (rolling, extruding, forging, rial temperature during service. The user of this Code
bend at
etc.), usually radius.
an elevated temperature. is cautioned that ambient and operating temperature
conditions may exist during construction, start-up, or
805.2 Design
shutdown that require special design considerations or
805.2.1 Pressure Terms and Definitions operating restrictions.
design pressure or internal design pressure: the maximum temperature: expressed in degrees Fahrenheit (°F)
pressure permitted by this Code, as determined by the [degrees Celsius (°C)].
design procedures applicable to the materials and loca-
805.2.3 Stress Terms and Definitions (16)
tions involved. It is used in calculations or analysis for
pressure design of a piping component. bending stress: the force per unit area acting at a point
along the length of a member resulting from the bending
hydrostatic test or hydrotest: a pressure test using water
moment applied at that point.
as the test medium.
compressive stress: the applied pushing force divided by
maximum allowable operating pressure (MAOP): the maxi-
the original cross-sectional area.
mum pressure at which a pipeline system may be oper-
ated in accordance with the provisions of this Code. hoop stress, SH [psi (MPa)]: the stress in a pipe of wall
thickness, t [in. (mm)], acting circumferentially in a plane
maximum allowable test pressure: the maximum internal
perpendicular to the longitudinal axis of the pipe, pro-
fluid pressure permitted by this Code for a pressure test
duced by the pressure, P [psig (kPa)], of the fluid in a
based upon the material and location involved.
pipe of diameter, D [in. (mm)], and is determined by
maximum operating pressure (MOP): sometimes referred Barlow’s formula:
to as maximum actual operating pressure, the highest
pressure at which a piping system is operated during a (U.S. Customary Units)
normal operating cycle. PD
SH p
normal operating pressure: the predicted pressure (sum 2t
of static head pressure, pressure required to overcome
(SI Units)
friction losses, and any backpressure) at any point in a
冢S 冣
piping system when the system is operating under a set PD
H p
of predicted steady-state conditions. 2 000t
8
ASME B31.8-2016
rust: corrosion product consisting of various iron oxides tension or compression test, it is also called Young’s
and hydrated iron oxides. (This term properly applies Modulus or the coefficient of elasticity.
only to iron and ferrous alloys.) probability: the likelihood of an event occurring.
shielding: preventing or diverting the flow of cathodic risk: a measure of potential loss in terms of both the
protection current from its natural path. incident probability (likelihood) of occurrence and the
stray current: current through paths other than the magnitude of the consequences.
intended circuit. span: a section of the pipe that is unsupported.
stress corrosion cracking (SCC): a form of environmental strain: the change in length of a material in response to
attack of the metal involving an interaction of a local an applied force, expressed on a unit length basis (e.g.,
corrosive environment and tensile stresses in the metal, inches per inch or millimeters per millimeter).
resulting in formation and growth of cracks.
805.2.7 Miscellaneous Terms and Definitions
805.2.6 Engineering Terms and Definitions shall or shall not: used to indicate that a provision is
brittle fracture: fracture with little or no plastic mandatory.
vortex-induced vibration (vortex
deformation. should, should not, or it is recommended: used to indicate
shedding):
design theofperiodic
life: a period time usedshedding
in designofcalculations, that a provision is not mandatory but recommended as
fluidforvortices
selected from
the purpose air or that
of verifying water
a replaceable good practice.
flow impinging
or permanent component onis suitable
the pipe for that
the anticipated
may introduce oscillatory forces on
period of service. Design life may not pertain to the life 806 QUALITY ASSURANCE
of a pipeline system because a properly maintained and
the pipeline
protected and system
pipeline consequentcan fatigue
provide service Quality Control systems consist of those planned, sys-
damage.
indefinitely. tematic, and preventative actions that are required to
ensure that materials, products, and services will meet
ductility: a measure of the capability of a material to be specified requirements. Quality Assurance systems and
deformed plastically before fracturing. procedures consist of periodic audits and checks that
elastic distortion: changes of dimensions of a material ensure the Quality Control system will meet all of its
upon the application of a stress within the elastic range. stated purposes.
Following the release of an elastic stress, the material The integrity of a pipeline system may be improved
returns to its original dimensions without any perma- by the application of Quality Assurance systems. These
nent deformation. systems should be applied to the design, procurement,
construction, testing, operating, and maintenance activi-
elastic limit: the maximum stress to which a material
ties in the applications of this Code.
may be subjected without retention of any permanent
Organizations performing design, fabrication,
deformation after the stress is removed.
assembly, erection, inspection, examination, testing,
elasticity: the property of a material that allows it to installation, operation, and maintenance application for
recover its original dimensions following deformation B31.8 piping systems should have a written Quality
by a stress below its elastic limit. Assurance system in accordance with applicable docu-
engineering assessment: a documented assessment using ments. Registration or certification of the Quality
engineering principles of the effect of relevant variables Assurance system should be by agreement between the
upon service or integrity of a pipeline system and con- contracting parties involved.
ducted by or under supervision of a competent person
with demonstrated understanding of and experience in 807 TRAINING AND QUALIFICATION OF
the application of engineering and risk management PERSONNEL
principles related to the issue being assessed.
807.1 Program
engineering critical assesment: an analytical procedure
Each operating company shall have a program to man-
based upon fracture mechanics that allows determina-
age the qualification of personnel who perform
tion of the maximum tolerable sizes for imperfections,
operating, maintenance, and construction activities that
and conducted by or under supervision of a competent
could impact the safety or integrity of a pipeline. The
person with demonstrated understanding of and experi-
program shall address, at a minimum, the following
ence in the application of the engineering principles
elements:
related to the issue being assessed.
(a) Identify those tasks for which the qualification
modulus of elasticity: a measure of the stiffness or rigidity provisions of the program apply. The tasks shall include
of a material. It is actually the ratio of stress to strain operating, maintenance, and construction activities that
in the elastic region of a material. If determined by a could impact the safety or integrity of a pipeline.
12
ASME B31.8-2016
Chapter I
Materials and Equipment
810 MATERIALS AND EQUIPMENT standard or specification and that meets the minimum
It is intended that all materials and equipment that requirements of this Code with respect to quality of
will become a permanent part of any piping system materials and workmanship may be used. This para-
constructed under this Code shall be suitable and safe graph shall not be construed to permit deviations that
for the conditions under which they are used. All such would tend to affect weldability or ductility adversely.
materials and equipment shall be qualified for the condi- If the deviations tend to reduce strength, full allowance
tions of their use by compliance with certain specifica- for the reduction shall be provided for in the design.
tions, standards, and special requirements of this Code, (b) When petitioning the Section Committee for
or otherwise as provided herein. approval, the following requirements shall be met. If
possible, the material shall be identified with a compara-
811 QUALIFICATION OF MATERIALS AND ble material, and it should be stated that the material
EQUIPMENT will comply with that specification, except as noted.
811.1 Categories Complete information as to chemical composition and
Materials and equipment fall into the following six physical properties shall be supplied to the Section
categories pertaining to methods of qualification for use Committee, and its approval shall be obtained before
under this Code: this material is used.
(a) items that conform to standards or specifications
811.2.3 Nonconformance (Unimportant Items). Rel-
referenced in this Code
atively unimportant items that do not conform to a stan-
(b) items that are important from a safety standpoint,
dard or specification [para. 811.1(c)] may be used,
of a type for which standards or specifications are refer-
provided that
enced in this Code but specifically do not conform to a
(a) they are tested or investigated and found suitable
referenced standard (e.g., pipe manufactured to a speci-
for the proposed service
fication not referenced in this Code)
(c) items of a type for which standards or specifica- (b) they are used at unit stresses not greater than 50%
tions are referenced in this Code, but that do not conform of those allowed by this Code for comparable materials
to the standards and are relatively unimportant from a (c) their use is not specifically prohibited by this Code
safety standpoint because of their small size or because 811.2.4 No Standards or Specifications Referenced.
of the conditions under which they are to be used Items of a type for which no standards or specifications
(d) items of a type for which no standard or specifica- are referenced in this Code [para. 811.1(d)] and proprie-
tion is referenced in this Code (e.g., gas compressor) tary items [para. 811.1(e)] may be qualified by the user
(e) proprietary items (see definition, para. 804.3) provided
(f) unidentified or used pipe (a) the user conducts an investigation and tests (if
811.2 Procedures for Qualification needed) that demonstrate that the item of material or
Prescribed procedures for qualifying each of these six equipment is suitable and safe for the proposed service
categories are given in the following paragraphs. (e.g., clad or duplex stainless steel pipe); or
811.2.1 Conformance. Items that conform to stan- (b) the manufacturer affirms the safety of the item
dards or specifications referenced in this Code recommended for that service (e.g., gas compressors and
[para. 811.1(a)] may be used for appropriate applica- pressure relief devices)
tions, as prescribed and limited by this Code without 811.3 Unidentified or Used Pipe
further qualification. (See section 814.)
Unidentified or used pipe [para. 811.1(f)] may be used
811.2.2 Nonconformance (Important Items). Impor- and is subject to the requirements of section 817.
tant items of a type for which standards or specifications
are referenced in this Code, such as pipe, valves, and
812 MATERIALS FOR USE IN LOW-TEMPERATURE
flanges, but that do not conform to standards or specifi-
cations referenced in this Code [para. 811.1(b)] shall be
APPLICATIONS
qualified as described in (a) or (b) below: Some of the materials conforming to specifications
(a) A material conforming to a written specification referenced for use under this Code may not have proper-
that does not vary substantially from a referenced ties suitable for operation at low temperatures. Users of
by the following
14
ASME B31.8-2016
this Code are cautioned to consider the effects of low classes, or types for which the material is marked,
temperature and the potential impact on fracture per- including those acceptable to this Code, shall not be used
formance at low temperatures. or substituted for those in the selected specification.
Whenever the minimum design temperature is below (c) All other requirements of this Code are satisfied
−20°F (−29°C), a fracture control program shall be estab- for the material selected.
lished. The program shall address parent materials, the Multiple marking shall be in accordance with the
parent material seam weld (if present), circumferential material specification, if allowed. Otherwise, multiple
butt welds, attachment welds, and any weld heat- marking shall be in accordance with the guidelines set
affected zone (HAZ). out in BPV Code, Section II, Part D, Appendix 7.
Of primary importance in the fracture control pro-
gram is the prevention of brittle fracture initiation that
can occur at small stress concentrations. As a minimum, 814 MATERIAL SPECIFICATIONS
the fracture control program shall require Charpy impact For a listing of all referenced material specifications,
energy testing at or below the minimum design temper- see Mandatory Appendix A. For a listing of standards
ature. The specific energy requirement is a function of for other commonly used materials that are not refer-
the strength of the material, its thickness, and the design enced, see Nonmandatory Appendix C.
stress. See para. 841.1.2 for additional requirements rela-
tive to fracture control for pipe. 814.1 Pipe Conforming to Referenced Standards and
Provided the manufacturer’s fracture toughness test- Specifications
ing of reference material (material standards and specifi-
Pipe that is qualified under para. 811.1(a) may be used.
cations referenced in Mandatory Appendix A or
Nonmandatory Appendix C) is performed at or below 814.1.1 Steel Pipe
the pipeline minimum design temperature and meets (a) Steel pipe manufactured in accordance with the
the requirements of the fracture control plan, additional following standards may be used:
toughness testing of the material is not required. The
welding procedure for circumferential welds shall be API 5L [Note (1)] Line Pipe
qualified as conforming to the fracture control program ASTM A53/A53M Steel, Black and Hot-Dipped,
by Charpy testing at or below the minimum design Zinc-Coated, Welded and
temperature. Seamless Pipe
ASTM A106/A106M Seamless Carbon Steel Pipe for
High-Temperature Service
813 MARKING ASTM A134 Steel, Electric-Fusion (Arc)-
813.1 Scope Welded Pipe (Sizes NPS 16
and Over)
All valves, fittings, flanges, bolting, pipe, and tubing ASTM A135/A135M Electric-Resistance-Welded
shall be marked in accordance with the marking sections Steel Pipe
of the standards and specifications to which the items ASTM A139/A139M Electric-Fusion (Arc)-Welded
were manufactured or in accordance with the require- Steel Pipe (Sizes NPS 4 and
ments of MSS SP-25. Over)
ASTM A333/A333M Seamless and Welded Steel
813.2 Die Stamping
Pipe for Low-Temperature
Die stamping, if used, shall be done with dies Service
having blunt or rounded edges to minimize stress ASTM A381 Metal-Arc-Welded Steel Pipe
concentrations. for Use With High-Pressure
Transmission Systems
(16) 813.3 Multiple Marking of Materials or Components ASTM A671 Electric-Fusion-Welded Steel
Materials or components marked as meeting the Pipe for Atmospheric and
requirements for two or more specifications (or grades, Lower Temperatures
classes, or types) are acceptable, provided ASTM A672 Electric-Fusion-Welded Steel
(a) At least one or more of the multiple markings Pipe for High-Pressure Service
include a material specification (or grade, class, or type) at Moderate Temperatures
that is permitted by this Code, and the material meets ASTM A691 Carbon and Alloy Steel Pipe,
all the requirements of that specification. Electric-Fusion-Welded for
(b) The appropriate design values and material prop- High-Pressure Service at High
erties from only the selected applicable specification (or Temperatures
grade, class, or type) shall be used. Design values and ASTM A984 Electric-Resistance-Welded
material properties from other specifications, grades, Steel Line Pipe
15
ASME B31.8-2016
ASTM A1005 Longitudinal and Helical Certain details of design and fabrication, however, nec-
Double Submerged-Arc essarily refer to equipment, such as pipe hangers, vibra-
Welded Steel Line Pipe tion dampeners, electrical facilities, engines,
ASTM A1006 Laser Beam Welded Steel Line compressors, etc. Partial specifications for such equip-
Pipe ment items are given herein, particularly if they affect
NOTE: the safety of the piping system in which they are to
(1) The provisions of API 5L, 45th edition, apply unless otherwise be installed. In other cases where this Code gives no
provided for, prohibited by, or limited by this edition of specifications for the particular equipment item, the
ASME B31.8. intent is that the safety provisions of this Code shall
(b) Cold expanded pipe shall meet the mandatory govern, insofar as they are applicable. In any case, the
requirements of API 5L. safety of equipment installed in a piping system shall
be equivalent to that of other parts of the same system.
814.1.2 Ductile Iron Pipe. Ductile iron pipe manu-
factured in accordance with ANSI A21.52, titled
Ductile-Iron Pipe, Centrifugally Cast, for Gas, may be 816 TRANSPORTATION OF LINE PIPE
used. Provisions should be made to protect the pipe, bevels,
(16) 814.1.3 Plastic Pipe and Components corrosion coating, and weight coating (if applicable)
(a) Plastic pipe and components manufactured in from damage during any transportation (highway, rail,
accordance with the following standards may be used: and/or water) of line pipe.
(1) For polyethylene (PE) pipe, use Any line pipe to be transported by railroad, inland
waterway, or by marine transportation shall be loaded
ASTM D2513 Polyethylene (PE) Gas Pressure Pipe, and transported in accordance with API RP 5L1 or
Tubing, and Fittings API RP 5LW. Where it is not possible to establish that
(2) For polyamide-11 (PA-11) pipe, use pipe was loaded and transported in accordance with
ASTM D2517 Reinforced Epoxy Resin Gas Pressure the above referenced recommended practice, the pipe
Pipe and Fittings shall be hydrostatically tested for at least 2 hr to at least
ASTM F2945 Polyamide 11 Gas Pressure Pipe, 1.25 times the maximum allowable operating pressure
Tubing, and Fittings if installed in a Class 1 Location, or to at least 1.5 times
the maximum allowable operating pressure if installed
(b) Thermoplastic pipe, tubing, fittings, and cements in a Class 2, 3, or 4 Location.
conforming to ASTM D2513 shall be produced in accor-
dance with the in-plant quality control program recom-
817 CONDITIONS FOR THE REUSE OF PIPE
mended in Annex A3 of that specification.
817.1 Reuse of Steel Pipe
814.1.4 Qualification of Plastic Piping Materials
(a) In addition to complying with the provisions of 817.1.1 Equivalent Service Level. Removal of a por-
para. 814.1.3, the user shall thoroughly investigate the tion of an existing steel line and reuse of the pipe, in
specific plastic pipe, tubing, or fitting to be used and the same line or in a line operating at the same or lower
shall determine material serviceability for the conditions rated pressure, is permitted, provided that the fracture
anticipated. The selected material shall be adequately toughness of the removed pipe is commensurate with
resistant to the liquids and chemical atmospheres that or exceeds that of the line operating at the same or lower
may be encountered. rated pressure and the used pipe meets the restrictions
(b) When plastic pipe, tubing, or fittings of different of paras. 817.1.3(a), (f), and (i). Reuse of the pipe in the
material specifications are joined, a thorough investiga- same line or in a line operating at the same or lower
tion shall be made to determine that the materials are pressure and the same or higher temperature is permit-
compatible with each other. See para. 842.2.9 for joining ted subject to the same para. 817.1.3 restrictions above
requirements. and any derations as required by Table 841.1.8-1.
Removed pipe that is reinstalled in the same location
814.2 Steel, Cast Iron, and Ductile Iron Piping need not be retested. Used pipe installed elsewhere is
Components subject to paras. 817.1.3(i) and (j).
Specific requirements for these piping components
817.1.2 Low Hoop Stress Service Level [Less Than
that qualify under para. 811.1(a) are found in Chapter III.
6,000 psi (41 MPa)]. Used steel pipe and unidentified
new steel pipe may be used for low-stress [hoop stress
815 EQUIPMENT SPECIFICATIONS less than 6,000 psi (41 MPa)] level service where no close
Except for the piping components and structural coiling or close bending is to be done, provided that
materials listed in Mandatory Appendix A and (a) careful visual examination indicates that it is in
Nonmandatory Appendix C, it is not intended to include good condition and free from split seams or other defects
in this Code complete specifications for equipment. that would cause leakage
16
This Chapter addresses the welding of pipe joints in both
wrought and cast steel materials and covers butt and fillet ASME B31.8-2016
welded joints in pipe, valves, flanges, and fittings and fillet
weld joints in pipe branches, slip-on flanges, socket weld
fittings, etc., as applied in pipelines and connections to
apparatus or equipment. This Chapter does not apply to the
welding of the seam in the manufacture of pipe.
Chapter II
Welding
Chapter III
Piping System Components and Fabrication Details
830 PIPING SYSTEM COMPONENTS AND ASME B16.33 Manually Operated Metallic Gas
FABRICATION DETAILS Valves for Use in Gas Piping
830.1 General Systems up to 175 psi (Sizes
NPS 1⁄2 Through NPS 2)
(a) The purpose of this Chapter is to provide a set of
ASME B16.34 Valves — Flanged, Threaded,
standards for piping systems covering
and Welding End
(1) specifications for and selection of all items and
ASME B16.38 Large Metallic Valves for Gas
accessories that are a part of the piping system, other
Distribution: Manually
than the pipe itself
Operated, NPS 21⁄2 (DN 65) to
(2) acceptable methods of making branch
NPS 12 (DN 300), 125 psig
connections
(8.6 bar) Maximum
(3) provisions to care for the effects of temperature ASME B16.40 Manually Operated
changes Thermoplastic Gas Shutoffs and
(4) approved methods for support and anchorage Valves in Gas Distribution
of exposed and buried piping systems Systems
(b) This Chapter does not include MSS SP-70 Gray Iron Gate Valves, Flanged
(1) pipe materials (see Chapter I) and Threaded Ends
(2) welding procedures (see Chapter II) MSS SP-71 Gray Iron Swing Check Valves,
(3) design of pipe (see Chapter IV) Flanged and Threaded Ends
(4) installation and testing of piping systems (see MSS SP-78 Gray Iron Plug Valves, Flanged
Chapter IV) and Threaded Ends
(5) special conditions for offshore application (see
(b) Valves having shell (body, bonnet, cover, and/or
Chapter VIII)
end flange) components made of cast ductile iron in
(6) special conditions for sour gas application (see
compliance with ASTM A395 and having dimensions
Chapter IX)
conforming to ASME B16.1, ASME B16.33, ASME B16.34,
ASME B16.38, ASME B16.40, or API 6D/ISO 14313 may
831 PIPING SYSTEM COMPONENTS be used at pressures not exceeding 80% of the pressure
All components of piping systems, including valves, ratings for comparable steel valves at their listed temper-
flanges, fittings, headers, special assemblies, etc., shall ature, provided the pressure does not exceed 1,000 psig
be designed in accordance with the applicable require- (6 900 kPa), and welding is not employed on any ductile
ments of this section and recognized engineering prac- iron component in the fabrication of the valve shells or
tices to withstand operating pressures and other their assembly as part of the piping system.
specified loadings. (c) Valves having shell components made of cast iron
Components shall be selected that can withstand the shall not be used in gas piping components for compres-
design, operating, and test conditions of the system in sor stations.
which the component is to be used without failure or 831.1.2 Threaded Valves. Threaded valves shall be
leakage and without impairment of their serviceability.
831.1.4 Service lines: Excess Flow Valve threaded according to ASME B1.20.1, API 5L, or API 6A.
Performance
831.1 Valves Standards.
and Pressure-Reducing Devices 831.1.3 Pressure-Reducing Devices. Pressure-
Excess flow valves
831.1.1 Valves shall be manufactured
Without Threads. Valves shall con- reducing devices shall conform to the requirements of
and tested
form to by the manufacturer
standards in accordance
and specifications referenced in this this Code for valves in comparable service conditions.
with ASTM
Code andF1802, ASTM
shall be usedF2138
only or
inMSS
accordance with the 831.2 Flanges
SP-115,
serviceorrecommendations
the manufacturer's of
written
the manufacturer. 831.2.1 Flange Types and Facings
specification.
(a) Valves manufactured in accordance with the fol- (a) The dimensions and drilling for all line or end
lowing standards may be used: flanges shall conform to one of the following standards:
API 6A Specification for Wellhead and ASME B16.1 Gray Iron Pipe Flanges
Christmas Tree Equipment and Flanged Fittings:
API 6D/ISO 14313 Specification for Pipeline Valves Classes 25, 125, and 250
23
ASME B31.8-2016
833.8 Flexibility Stresses and Stresses Due to (b) The maximum allowable sum of circumferential
Periodic or Cyclic Fatigue Loading stress due to internal pressure and circumferential
(a) The stress range in unrestrained piping due to through-wall bending stress caused by surface vehicle
thermal expansion and periodic, vibrational, or cyclic loads or other local loads is 0.9ST, where S is the specified
displacements or loads shall be computed as minimum yield strength, psi (MPa), per para. 841.1.1(a),
and T is the temperature derating factor per
SE p ME/Z para. 841.1.8.
(c) Local stresses in (a) or (b) caused by periodic or
where ME is the resultant intensified moment range from repetitive loads may require further limitations in con-
one stress state to another. The resultant intensified sideration of fatigue.
moment shall be calculated as
833.10 Buckling and Lateral Instability 833.10 Buckling and Lateral Instability
2 2 2 1/2
(a) Pipe sections
ME p [(ithat
iMi) are
+ (ioMsubjected
o) + Mt ] to significant
, lb-in. (N·m)
In order to prevent buckling in the form of wrinkling
compressive
(b) The stresses and strains
cyclic stress range due SE ≤ toSAforce-controlled
, where of the pipe wall or lateral instability, the maximum
loading, displacement-controlled loading, or both shall allowable net compressive stress is 2⁄3 of the critical buck-
be designed to prevent SA plocal buckling
f [1.25 (Sc + Sh)and
− SLglobal
] lateral ling stress estimated using a suitable stability criterion.
instability. Examples of force-controlled
f p 6N −0.2
≤ 1.0 loading include
internal pressure, self-weight of the pipe and its 834 SUPPORTS AND ANCHORAGE FOR EXPOSED
PIPING
contents, N soil
p overburden,
equivalent number external of hydrostatic
cycles during pressure, the
expected service life
and buoyancy. Examples of displacement-controlledof the piping system 834.1 General
Sc p 0.33 SuT at the minimum installed or operating
loading include differential temperature loads in
temperature
Piping and equipment shall be supported in a substan-
restrainedSh p pipe sections
0.33 andmaximum
SuT at the bending causedinstalledby orground
operating
tial and workmanlike manner, so as to prevent or reduce
movements. temperature excessive vibration, and shall be anchored sufficiently
to prevent undue strains on connected equipment.
(b) ToSprevent local buckling
L p longitudinal stresswhere the dominant
calculated according to
longitudinal load is caused by force-controlled loading,
para. 833.6(a), psi (MPa) 834.2 Provision for Expansion
longitudinal
Su pcompressive strains shall
specified minimum be limited
ultimate tensileto a
strength, Supports, hangers, and anchors should be so installed
psi (MPa)
critical buckling strain determined in accordance with an as not to interfere with the free expansion and contrac-
T p temperature derating factor per para. 841.1.8
established method. In the absence of more detailed tion of the piping between anchors. Suitable spring
hangers, sway bracing, etc., shall be provided where
information,
(c) Whenthe compressive
the computed strain limit,
stress range , should
εcfcritvaries, S E is
necessary.
be taken as
defined as the greatest computed stress range. The value
of N in such cases can be calculated as
SEE ATTACHED EQUATIONS 834.3 Materials, Design, and Installation
where N p NE + ∑ [ri5Ni] for i p 1, 2, … n All permanent hangers, supports, and anchors shall
D = nominal outside diameter of pipe, in. (mm) be fabricated from durable incombustible materials and
where modulus of steel, psi (MPa) (Table 832.5-1)
E = elastic designed and installed in accordance with good engi-
NE p number of cycles of maximum computed stress neering practice for the service conditions involved. All
pi = maximum internal design pressure, psig (MPa)
range, SE parts of the supporting equipment shall be designed
po = minimum externalofhydrostatic
Ni p number pressure, with
cycles associated psig (MPa)
stress and installed so that they will not be disengaged by
S = specified range,minimum Si yield strength, psi (MPa) movement of the supported piping.
t = nominal ri p wall
Si/Sthickness,
E in. (mm)
834.4 Forces on Pipe Joints
(c) To prevent global lateralstress
S i p any computed instability
rangeinsmaller
pipelines than SE,
psi (MPa) (a) All exposed pipe joints shall be able to sustain the
subjected to axial compression, the pipeline section shall
maximum end force, lb (N), due to the internal pressure,
be designed to limit
833.9 Local the maximum allowable net
Stresses i.e., the design pressure, psig (kPa), times the internal
compressive stress to 2⁄3 of the
(a) High local stresses are critical
usually buckling
generatedstress at struc- area of the pipe, in.2 (mm2), as well as any additional
determined in accordance with
tural discontinuities andansites established
of localmethod. loadings. forces due to temperature expansion or contraction or
Although they may exceed the material yield strength, to the weight of pipe and contents.
such stresses may often be disregarded because they (b) If compression or sleeve-type couplings are used
are localized in influence and may be self-limiting or in exposed piping, provision shall be made to sustain
relieved by local deformation. Examples include stresses the longitudinal forces noted in (a) above. If such provi-
in branch connections caused by pressure or external sion is not made in the manufacture of the coupling,
loads, or stresses at structural discontinuities. This Code suitable bracing or strapping shall be provided, but such
does not fully address the maximum allowable value design must not interfere with the normal performance
for local stresses. It is the engineer’s responsibility to of the coupling nor with its proper maintenance. Attach-
determine whether such stresses must be evaluated. ments must meet the requirements of para. 834.5.
33
2
t (pi -po )D
εcrit
cf = 0.4 - 0.0020 + 2400 � �
D 2tE
for
(𝑝𝑝𝑖𝑖 − 𝑝𝑝𝑜𝑜 )𝐷𝐷
< 0.4
2 𝑡𝑡 𝑆𝑆
and
𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡 0.4 𝑆𝑆 2
𝜀𝜀𝑐𝑐𝑓𝑓 = 0.4 − 0.0020 + 2400 � �
𝐷𝐷 𝐸𝐸
for
(𝑝𝑝𝑖𝑖 − 𝑝𝑝𝑜𝑜 )𝐷𝐷
≥ 0.4
2 𝑡𝑡 𝑆𝑆
ASME B31.8-2016
(16) 834.5 Attachment of Supports or Anchors thrust origin shall be designed to sustain the longitudi-
(a) If the pipe is designed to operate at a hoop stress nal pullout force. If such provision is not made in the
of less than 50% of the specified minimum yield strength, manufacture of the joints, suitable bracing or strapping
structural supports or anchors may be welded directly shall be provided.
to the pipe. Proportioning and welding strength require-
ments of such attachments shall conform to standard 835.5 Supports for Buried Piping
structural practice. (a) In pipelines, especially those that are highly
(b) If the pipe is designed to operate at a hoop stress stressed from internal pressure, uniform and adequate
of 50% or more of the specified minimum yield strength, support of the pipe in the trench is essential. Unequal
structural supports or anchors shall not be welded settlements may produce added bending stresses in the
directly to the pipe. Where it is necessary to provide a pipe. Lateral thrusts at branch connections may greatly
welded attachment, structural supports or anchors shall increase the stresses in the branch connection itself,
be welded to a member that fully encircles the pipe. The unless the fill is thoroughly consolidated or other provi-
connection of the pipe to the encircling member shall sions are made to resist the thrust.
be by continuous, rather than intermittent, welds or by
(b) Rock shield shall not be draped over the pipe
use of a bolted or clamped mechanical connection.
unless suitable backfill and padding are placed in the
ditch to provide a continuous and adequate support of
835 ANCHORAGE FOR BURIED PIPING the pipe in the trench.
835.1 General (c) When openings are made in a consolidated backfill
Bends or offsets in buried pipe cause longitudinal to connect new branches to an existing line, care must
forces that must be resisted by anchorage at the bend, be taken to provide firm foundation for both the header
by restraint due to friction of the soil, or by longitudinal and the branch to prevent vertical and lateral
stresses in the pipe. movements.
34
ASME B31.8-2016
冢P p 冣
2 000St (3) a pipeline is designed with a minimum design
FET
D temperature below −20°F (−29°C) as outlined in
section 812
where When a fracture toughness criterion is used, control
D p nominal outside diameter of pipe, in. (mm) can be achieved by ensuring that the pipe has adequate
E p longitudinal joint factor obtained from ductility and by either specifying adequate toughness
Table 841.1.7-1 [see also para. 817.1.3(d)] or installing crack arrestors on the pipeline to stop
F p design factor obtained from Table 841.1.6-1. In propagation.
setting the values of the design factor, F, due (b) Brittle Fracture Control. To ensure that the pipe has
consideration has been given and allowance has adequate ductility, fracture toughness testing shall be
been made for the various underthickness toler- performed in accordance with the testing procedures
ances provided for in the pipe specifications of supplementary requirements SR5 or SR6 of API 5L
listed and approved for usage in this Code. (43rd edition) or Annex G of API 5L (45th edition), or
P p design pressure, psig (kPa) (see also other equivalent alternatives. If the operating tempera-
para. 841.1.3) ture is below 50°F (10°C), an appropriate lower test tem-
S p specified minimum yield strength, psi (MPa), perature shall be used when determining adherence to
stipulated in the specifications under which the the minimum impact values in (c) and shear appearance
pipe was purchased from the manufacturer or as outlined below. The appropriate lower test tempera-
determined in accordance with paras. 817.1.3(h) ture shall be taken to be at or below the lowest expected
and 841.1.4. The specified minimum yield metal temperature during pressure testing (if with air or
strengths of some of the more commonly used gas) and during service, having regard to past recorded
piping steels whose specifications are incorpo- temperature data and possible effects of lower air and
rated by reference herein are tabulated for con- ground temperatures. The average shear value of the
venience in Mandatory Appendix D. fracture appearance of three Charpy specimens from
37
(b) Where D/t < 30, the following alternative pressure design formula may be used:
(US Customary Units)
2𝑆𝑆𝑆𝑆
𝑃𝑃 = 𝐹𝐹𝐹𝐹𝑇𝑇
𝐷𝐷 − 𝑡𝑡
(SI Units)
2,000 𝑆𝑆𝑆𝑆
𝑃𝑃 = 𝐹𝐹𝐹𝐹𝐹𝐹
𝐷𝐷 − 𝑡𝑡
Nomenclature is the same as specified in 831.1.1(a).
CVN = 3.57×10-4 σ3/2 D1/2
Pipelines, mains, and service lines [see para. 840.2.2] 0.80 0.72 0.60 0.50 0.40
Fabricated assemblies [see para. 841.1.9(a)] 0.60 0.60 0.60 0.50 0.40
removal equipment
Pipelines on bridges [see para. 841.1.9(b)] 0.60 0.60 0.60 0.50 0.40
Pressure/flow control and metering facilities [see para. 841.1.9(d)] 0.60 0.60 0.60 0.50 0.40
Liquid separators constructed of pipe and fittings without internal welding 0.40 0.40 0.40 0.40 0.40
[see para. 843.3.1(b)]
Near concentration of people in Location Classes 1 and 2 [see para. 840.3(b)] 0.50 0.50 0.50 0.50 0.40
836 0.50
40
ASME B31.8-2016
41
ASME B31.8-2016
N or fewer, or the design factor, F, is 0.4 or less. For Table 841.1.11-1 Pipeline Cover Requirements
purposes of applying this screening criterion, pressure Cover, in. (mm)
cycles larger than 50% of the MAOP in magnitude
For Rock
should be counted as full-MAOP cycles. Seam welds
Excavation [Note (1)]
that are not oriented parallel to the longitudinal axis of
Pipe Size Pipe Size
the pipe are exempt from the evaluation.
NPS 20 Larger Than
841.1.10 Protection of Pipelines and Mains From For Normal (DN 500) and NPS 20
Location Excavation Smaller (DN 500)
Hazards
(a) When pipelines and mains must be installed Class 1 24 (610) 12 (300) 18 (460)
where they will be subject to natural hazards, such as Class 2 30 (760) 18 (460) 18 (460)
washouts, floods, unstable soil, landslides, earthquake- Classes 3 and 4 30 (760) 24 (610) 24 (610)
Drainage ditch at public 36 (910) 24 (610) 24 (610)
related events (such as surface faulting, soil liquefaction, roads and railroad
and soil and slope instability characteristics), or other crossings (all
conditions that may cause serious movement of, or locations)
In addition to the above hazards, pipe exposed to
abnormal loads on, the pipeline, reasonable precautions
NOTE:
cross-currents
shall be taken to protect the pipeline, such as increasing mayexcavation
(1) Rock be susceptible
is excavation thattorequires
vortex-
blasting.
the wall thickness, constructing revetments, preventing
erosion, and installing anchors. induced vibration (“vortex shedding”) in some
(b) Where pipelines and mains cross areasflow that regimes.
are This can cause fatigue damage in
normally under water or subject to flooding (i.e., girthlakes,
welds in the exposed spans. When these
bays, or swamps), sufficient weight or anchorage exposedshall span Where conditions are encountered,
these cover provisions cannot be met or where
be applied to the line to prevent flotation.
analyses shall be undertaken to determine whether
external loads may be excessive, the pipeline shall be
(c) Because submarine crossings may be subject to encased, bridged, or designed to withstand any such
washouts due to the natural hazards of changes thisinphenomenon
the is anticipated for the given pipe
anticipated external loads. In areas where farming or
configuration,
waterway bed, water velocities, deepening of the chan- orientation
other operations might and result
the inanticipated
deep plowing, in areas
water velocity
nel, or changing of the channel location in the waterway, subjectconditions.
to erosion, or Should
in locations conditions
where future grading
design consideration shall be given to protecting exist thethat could result
is likely, such as inatthe pipe
roads, undergoing
highways, railroad crossings,
pipeline or main at such crossings. The crossing shall and ditch crossings, additional protection shall be pro-
vibration and
be located in the more stable bank and bed locations. vided. consequent
[See (e) for suggestedfatiguemethodsdamage,to provide addi-
counteracting
The depth of the line, location of the bends installed in measures
tional (burial, re-burial or vortex
protection.]
the banks, wall thickness of the pipe, and weightingshedding of devices) shall beBetween
(c) Clearance installed to reduce
Pipelines the and Other
or Mains
potential for damage.
the line shall be selected based on the characteristics of Underground Structures
the waterway. (1) There shall be at least 6 in. (150 mm) of clearance
(d) Where pipelines and mains are exposed, such as wherever possible between any buried pipeline and any
at spans, trestles, and bridge crossings, the pipelines other underground structure not used in conjunction
and mains shall be reasonably protected by distance or with the pipeline. When such clearance cannot be
barricades from accidental damage by vehicular traffic attained, precautions to protect the pipe shall be taken,
or other causes. such as the installation of casing, bridging, or insulating
material.
841.1.11 Cover, Clearance, and Casing Requirements (2) There shall be at least 2 in. (50 mm) of clearance
for Buried Steel Pipelines and Mains
(e) When
(a) Coverpipelines and for
Requirements mains
Mains.are installed
Buried mains above
wherever possible between any buried gas main and
shall grade and exposed to cross-wind
any other underground structure not used in conjunc-
conditions , the pipelines and mains shall be
be installed with a cover not less than 24 in. (610 mm). reasonably tion with the from
protected main. vortex-induced
When such clearance cannot be
vibration.
Where Such vibration
this cover can cannot
provision cause be
fatigue
met, ordamage
where in attained,
girth welds in the to
precautions exposed
protect thespan.
main shall be taken,
Analyses shall be undertaken to determine whether this phenomenon is anticipated formaterial or casing.
external loads may be excessive, the main shall be such as the installation of insulating
encased, bridged, or designed to withstand any such
the given pipe configuration, orientation and the full range
anticipated external loads. Where farming or other oper-
(d) of
Casingnaturally occurring
Requirements Under wind
Railroads, Highways,
Roads, or Streets. Casings shall be designed to withstand
conditions.
ations mightShould
resultconditions exist that
in deep plowing, could
in areas result
subject to in the
the pipe undergoing
superimposed vibration
loads. Where there and is a possibility of
consequent
erosion, or fatigue damage,
in locations wherecounteracting
future grading measures
is likely, (strakes,
water entering the casing, the endsor
vibration dampeners, of the casing shall
other vortex shedding devices) shall be installed or thebenatural
such as road, highway, railroad, and ditch crossings, sealed. frequency of theis piping
If the end sealing of a type that will retain
additional protection shall be provided. [See (e) for sug-
system changed to reduce the potential for damage.
gested methods to provide additional protection.]
the maximum allowable operating pressure of the carrier
pipe, the casing shall be designed for this pressure and
(b) Cover Requirements for Pipelines. Except for off- at least to the design factor of 0.72. Venting of sealed
shore pipelines, buried pipelines shall be installed with casings is not mandatory; however, if vents are installed
a cover not less than that shown in Table 841.1.11-1. they should be protected from the weather to prevent
43
ASME B31.8-2016
Table 841.2.3-1 Pipeline Field Cold Bend engineering analysis that considers the effects of pipeline
Requirements construction and operation on the reliability of pipe
Minimum Radius of
affected by such features. In addition, the bend shall
Deflection of Bend in Pipe meet all other provisions of this section.
Longitudinal Diameters (b) Miters. Mitered bends are permitted, provided the
Nominal Pipe Size Axis, deg [see 841.2.3(a)(3)] following limitations are met:
Smaller than NPS 12 841.2.3(a)(4) 18D
(1) In systems intended to operate at hoop stress
(DN 300) levels of 40% or more of the specified minimum yield
NPS 12 (DN 300) 3.2 18D strength, mitered bends are not permitted. Deflections
NPS 14 (DN 350) 2.7 21D caused by misalignment up to 3 deg are not considered
NPS 16 (DN 400) 2.4 24D as miters.
NPS 18 (DN 450) 2.1 27D (2) In systems intended to operate at hoop stress
NPS 20 (DN 500) 1.9 30D
levels of 10% or more but less than hoop stress levels
and larger
of 40% of the specified minimum yield strength, the
total deflection angle at each miter shall not exceed
121⁄2 deg.
(2) The maximum degree of bending on a field cold (3) In systems intended to operate at hoop stress
bend may be determined by either method in levels of less than 10% of the specified minimum yield
Table 841.2.3-1. The first column expresses the maximum strength, the total deflection angle at each miter shall
deflection in an arc length equal to the nominal outside not exceed 90 deg.
diameter, and the second column expresses the mini- (4) In systems intended to operate at hoop stress
mum radius as a function of the nominal outside levels of 10% or more of the specified minimum yield
diameter. strength, the minimum distance between miters mea-
(3) A field cold bend may be made to a shorter sured at the crotch shall not be less than one pipe
minimum radius than permitted in (2) above, provided diameter.
the completed bend meets all other requirements of this (5) Care shall be taken in making mitered joints to
section, and the wall thickness after bending is not less provide proper spacing and alignment and full
than the minimum permitted by para. 841.1.1. This may penetration.
be demonstrated through appropriate testing. (c) Elbows. Factory-made, wrought-steel welding
(4) For pipe smaller than NPS 12 (DN 300), the elbows or transverse segments cut therefrom may be
requirements of (1) above must be met, and the wall used for changes in direction, provided that the arc
thickness after bending shall not be less than the mini- length measured along the crotch is at least 1 in. (25 mm)
mum permitted by para. 841.1.1. This may be demon- on pipe sizes NPS 2 (DN 50) and larger.
strated through appropriate testing.
(5) Except for offshore pipelines, when a circumfer- 841.2.4 Pipe Surface Requirements Applicable to
Wrinkle bends
entialshall
weld not be used.
occurs in a bend section, it shall be subjected Pipelines and Mains to Operate at a Hoop Stress of 20%
to radiography examination after bending. or More of the Specified Minimum Yield Strength.
(6) All hot bends shall be made in accordance with Gouges, grooves, and notches have been found to be an
ASME B16.49. important cause of pipeline failures, and all harmful
defects of this nature must be prevented, eliminated, or
(7) Wrinkle bends shall be permitted only on sys-
repaired. Precautions shall be taken during manufacture,
tems operating at hoop stress levels of less than 30% of
hauling, and installation to prevent the gouging or
the specified minimum yield strength. When wrinkle
bends are made in welded pipe, the longitudinal weld grooving of pipe.
shall be located on or near to the neutral axis of the bend. (a) Detection of Gouges and Grooves
Wrinkle bends with sharp kinks shall not be permitted. (1) The field inspection provided on each job shall
Spacing of wrinkles shall be measured along the crotch be suitable to reduce to an acceptable minimum the
of the pipe bend, and the peak-to-peak distance between chances that gouged or grooved pipe will get into the
the wrinkles shall exceed the diameter of the pipe. On finished pipeline or main. Inspection for this purpose
pipe NPS 16 (DN 400) and larger, the wrinkle shall not just ahead of the coating operation and during the
produce an angle of more than 11⁄2 deg per wrinkle. lowering-in and backfill operation is required.
(8) Incidental ripples in the pipe surface may occur (2) When pipe is coated, inspection shall be made
along the inside radius during the forming of cold field to determine that the coating machine does not cause
bends in some pipe. Ripples having a dimension mea- harmful gouges or grooves.
sured from peak to valley not exceeding 1% of the pipe (3) Lacerations of the protective coating shall be
outside diameter are considered acceptable for all gas carefully examined prior to the repair of the coating to
service. Larger ripples may be permitted based on an determine if the pipe surface has been damaged.
45
ASME B31.8-2016
Table 841.3.2-1 Test Requirements for Steel Pipelines and Mains to Operate at Hoop Stresses (16)
of 30% or More of the Specified Minimum Yield Strength of the Pipe
1 2 3 4 5 6
Maximum
Design Factor, Permissible Test Pressure Test Prescribed
Maximum Allowable Operating
Location Class F Medium Minimum Maximum Pressure, the Lesser of
LEGEND:
DP p design pressure
MOP p maximum operating pressure (not necessarily the maximum allowable operating pressure)
TP p test pressure
GENERAL NOTES:
(a) This Table defines the relationship between test pressures and maximum allowable operating pressures subsequent to the test. If an
operating company decides that the maximum operating pressure will be less than the design pressure, a corresponding reduction in
the prescribed test pressure may be made as indicated in the Pressure Test Prescribed, Minimum column. If this reduced test pressure
is used, however, the maximum operating pressure cannot later be raised to the design pressure without retesting the line to a higher
test pressure. See paras. 805.2.1(d), 845.2.2, and 845.2.3.
(b) Gas piping within gas pipeline facilities (e.g., meter stations, regulator stations, etc.) is to be tested and the maximum allowable
operating pressure qualified in accordance with para. 841.3 and Tables 841.3.2-1 and 841.3.3-1 subject to the appropriate location
class, design factor, and test medium criteria.
(c) When an air or gas test is used, the user of this Code is cautioned to evaluate the ability of the piping system to resist propagating
brittle or ductile fracture at the maximum stress level to be achieved during the test.
NOTES:
(1) When pressure testing with air or gas, see paras. 841.3.1(c) and 841.3.2(a) through (c), and Table 841.3.3-1.
(2) Compressor station piping shall be tested with water to Location Class 3 pipeline requirements as indicated in para. 843.5.1(c).
(3) For exceptions, see paras. 841.3.2(b) and (c).
843.4.1(c)
49
ASME B31.8-2016
the inside without a key. All swinging doors located in pumps are a part of such facilities, their operation shall
an exterior wall shall swing outward. not be affected by emergency shutdown facilities.
843.1.4 Fenced Areas. Any fence that may hamper 843.3.3 Safety Devices
or prevent escape of persons from the vicinity of a com- (a) Emergency Shutdown Facilities
pressor station in an emergency shall be provided with (1) Except as noted or clarified in (a)(2) through
a minimum of two gates. These gates shall be located (a)(4), compressor station shall be provided with an
so as to provide a convenient opportunity for escape to emergency shutdown system by means of which the gas
a place of safety. Any such gates located within can be blocked out of the station and the station gas
200 ft (61 m) of any compressor plant building shall piping blown down. Operation of the emergency shut-
open outward and shall be unlocked (or capable of being down system also shall cause the shutdown of all gas
opened from the inside without a key) when the area compressing equipment and all gas-fired equipment.
within the enclosure is occupied. Alternatively, other Operation of this system shall de-energize the electrical
facilities affording a similarly convenient exit from the facilities located in the vicinity of gas headers and in the
area may be provided. compressor room, except those that provide emergency
lighting for personnel protection and those that are nec-
843.2 Electrical Facilities essary for protection of equipment. The emergency shut-
All electrical equipment and wiring installed in gas down system shall be operable from any one of at least
transmission and distribution compressor stations shall two locations outside the gas area of the station, prefera-
conform to the requirements of NFPA 70, insofar as the bly near exit gates in the station fence, but not more than
equipment commercially available permits. 500 ft (150 m) from the limits of the stations. Blowdown
Electrical installations in hazardous locations as piping shall extend to a location where the discharge of
defined in NFPA 70 and that are to remain in operation gas is not likely to create a hazard to the compressor
during compressor station emergency shutdown as pro- station or surrounding area.
vided in para. 843.3.3(a)(1) shall be designed to conform (2) Unattended field compressor stations of
to NFPA 70 for Class I, Division 1 requirements. 1,000 hp (746 kW) and less are excluded from the provi-
Liquid Removal for
sions of (a)(1).
843.3 Compressor Station Equipment (3) Each compressor station supplying gas directly
to a distribution system shall be provided with emer-
(16) 843.3.1 Gas Treating Facilities
gency shutdown facilities located outside the compres-
(a) Liquid Removal. When condensable vapors are sor station buildings by means of which all gas can be
present in the gas stream in sufficient quantity to liquefy blocked out of the station, provided there is another
under the anticipated pressure and temperature condi- adequate source of gas for the distribution system. These
tions, the suction stream to each stage of compression shutdown facilities can be either automatic or manually
(or to each unit for centrifugal compressors) shall be operated as local conditions designate. When no other
protected against the introduction of dangerous quanti- gas source is available, no shutdown facilities that might
ties of entrained liquids into the compressor. Every liq- function at the wrong time and cause an outage on the
uid separator used for this purpose shall be provided distribution system shall be installed.
with manually operated facilities for removal of liquids
(4) Notwithstanding the exceptions in (a)(2) and
therefrom. In addition, automatic liquid removal facili-
(a)(3), each compressor station handling gas that con-
ties, an automatic compressor shutdown device, or a
tains quantities or concentrations of hydrogen sulfide
high liquid level alarm shall be used where slugs of
and/or liquids sufficient to present an environmental
liquid might be carried into the compressors.
or safety hazard shall be provided with an emergency
(b) Liquid Removal Equipment. Liquid separators shall
shutdown system. The emergency shutdown system
be manufactured in accordance with Section VIII of the
and automatic or manual blowdown processes and
BPV Code, except that those constructed of pipe and
equipment must be designed to prevent the automatic
fittings without any components welded to the inside
release of hydrogen sulfide, condensable vapors, or free
of the pipe may be constructed in accordance with
liquids into the atmosphere in concentrations that may
ASME B31.8 utilizing a design factor of 0.4. The designer
be hazardous to the operator or the general public.
of the liquid removal equipment shall apply an appro-
(b) Engine Overspeed Stops. Every compressor prime
priate corrosion allowance and shall address all liquid
mover, except electrical induction or synchronous
and water hammer loads so that Code-allowable stresses
are not exceeded. motors, shall be provided with an automatic device that
is designed to shut down the unit before the maximum
843.3.2 Fire Protection. Fire protection facilities safe speed of either the prime mover or driven unit, as
should be provided in accordance with the American established by the respective manufacturers, is
Insurance Association’s recommendations. If the fire exceeded.
59
ASME B31.8-2016
operating pressure, and the limitations on maximum 849.3 Ductile Iron Service Lines
test pressure, temperature, and duration set forth in When used for service lines, ductile iron pipe shall
para. 842.4.2 shall be observed. meet the applicable requirements of section 842. Ductile
iron pipe may be used for service lines except for the
849.2 Steel Service Lines portion of the service line that extends through the build-
849.2.1 Design of Steel Service Lines ing wall. Ductile iron service lines shall not be installed
in unstable soils or under buildings.
849.1.6lines,
(a) Steel pipe, when used for service Excess shallFlow
con-Valve (EFV) Installation.
849.4 Plastic Service Lines
form to the applicable requirements The ofuse of excess
Chapter I. flow valves is recognized by the gas industry as an
effective in
(b) Steel service pipe shall be designed way to mitigate risks849.4.1
accordance associated Design
with ofexcavation
Plastic Service
damage, Lines
natural
with the requirements of paras. 841.1.1 and 841.1.9(a).
force damage, and other outside (a)force
Plastic pipe and
damage, e.g., tubing
vehicular shall be used
damage on gas for service
Where the pressure is less than 100 psig (690 kPa), the lines only where the piping strain or external loading
service lines. If the operator installs excess flow valves, they should be in
steel service pipe shall be designed for at least 100 psig will not be excessive.
accordance with the following requirements.
(690 kPa) pressure. (b) Plastic pipe, tubing, cements, and fittings used for
(a) The operator should consider serviceinstalling
lines shallan EFVconformon any to new or replaced require-
the applicable
(c) Steel pipe used for service lines shall be installed
gas service line. Such a ments serviceofline can
Chapter I. typically serve the following
in such a manner that the piping strain or external load-
categories of customers. (c) Plastic service lines shall be designed in accor-
ing shall not be excessive.
(1) A service line to a singledance familywith
residence (SFR); requirements of para. 842.2.
the applicable
(d) All underground steel service lines shall be joined
(2) A branched gas service line (d) Plastic service lines concurrently
to a SFR installed shall be joined within the
accordance
by threaded and coupled joints, compression-type fit-
primary SFR
tings, or by qualified welding or brazing methods, proce-
service line. (A
withsingle
the EFV may
applicable be installed
requirements to ofprotect
para. both
842.2.9.
dures, and operators. service lines); 849.4.2 Installation of Plastic Service Lines
(3) A branched gas service line (a)toPlastic
a SFRservice
installed offshall
lines a previously
be installed installed
in accordance
SFR gasLines
849.2.2 Installation of Steel Service service line that does not contain an EFV;
with the applicable requirements of paras. 842.3 and
(4) Multi-family installations
(a) Installation of Steel Service Lines in Bores with known
849.1.1. Particular customer
care must loadstoatprevent
be taken time of damage
(1) When coated steel pipe gas is toservice installation,
be installed as a based on installed
to plastic servicemeter capacityatless
line piping the than 1,000 to the
connection
service line in a bore, care shall be standard ft /hr (28.3 m /hr)per gas service and where the customer load
exercised 3 to prevent 3 main or other facility. Precautions shall be is to pre-
taken
not expected to increase significantly over time; or
damage to the coating during installation. vent crushing or shearing of plastic piping due to exter-
(2) When a service line is to (5) A single small commercial customer with known customer load at the damage
be installed by boring nal loading or settling of backfill and to prevent
or driving, and coated steel pipetime is toofbeservice
used, itinstallation,
shall orbased
pullouton installed
from the meter capacity,
connection up to 1,000
resulting from thermal
not be used as the bore pipe or standard
drive pipe ft /hr
3 and left in expansion or contraction. [See paras. 842.3.3(d) and (e).]
the ground as part of the service line unless it has been (b) Notwithstanding the limitations imposed in
(28.3 m /hr) served by a single gas service line and where the customer load
3
demonstrated that the coating is sufficiently durable to para. 842.3.3, a plastic service line may terminate above
is not expected to increase significantly over time.
withstand the boring or driving operation in the type of ground and outside the building, provided that
(b) Excess flow valves are not recommended (1) the abovegroundto be installed
portionif oneof or
themore
plasticof service
soil involved without significant damage to the coating.
the following
Where significant damage to the coating may result from conditions are present:
line is completely enclosed in a conduit or casing of
boring or driving, the coated service (1) Thelinegas should
service line
be willsufficient
not operate at a pressure
strength to provideof 10protection
psig (69 kPa) from or external
greater throughout
installed in an oversized bore or casing pipe of sufficient the year; damage and deterioration. Where a flexible conduit is
(2)
diameter to accommodate the service pipe. The operator has prior experience
used, the with
top of contaminants
the riser mustin the
be gas stream
attached to a solid
that could interfere
(3) In exceptionally rocky soil, coated pipe shall not with the EFV's
support. operation
The conduit or cause
or casingloss of
shall service
extend to
a a
minimum
be inserted through an open boreresidence;
if significant damage of 6 in. (150 mm) below grade.
to the coating is likely. (3) An EFV could interfere (2) withthenecessary operation
plastic service line isornot maintenance
subjected to exter-
activities,
(b) Installation of Service Lines Into or UndersuchBuildings
as removingnal liquids fromstresses
loading the line;by the customer’s meter or its con-
(1) Underground steel service (4)lines,
An when
EFV installed
meeting performance
necting piping. standards in para. 831.1.4 is not
below grade through the outer commercially available
of a to the operator; or
(c) Installation of Plastic Service Lines Into or Under
foundation wall
Buildings
building, shall be either encased in(5) The anticipated
a sleeve or otherwisemaximum flow through the service line equals or
(1) An underground plastic service line installed
protected against corrosion. Theexceeds service1,000line standard
and/or ft /hr3
through the outer foundation or wall of a building shall
(28.3 mwall
sleeve shall be sealed at the foundation 3 /hr)to prevent be encased in a rigid sleeve with suitable protection
(c) An operator should identify
entry of gas or water into the building. fromthe presence
shearing of anorexcess
action backfillflow valve in the
settlement. The sleeve
service line.
(2) Steel service lines, where installed Examples include
underground a tag, ring around the riser or
shall extend past the outside face of the foundation statement on a
under buildings, shall be encased the in aservice
gas-tight order.
conduit. sufficient distance to reach undisturbed soil or thor-
When such a service line supplies (d)the
Anbuilding
operator should
it sub- locate an excess
oughly flow valve
compacted as near
backfill. At as
thepractical
point whereto thethe sleeve
tends, the conduit shall extend into fitting connectingusable
a normally the gas service line to its
terminates source
inside theoffoundation
gas supply. or wall, the space
and accessible portion of the building. At the point between the sleeve and the service line shall be sealed
where the conduit terminates, the space between the to prevent leakage into the building. The plastic service
conduit and the service line shall be sealed to prevent line shall not be exposed inside the building.
the possible entrance of any gas leakage. The casing (2) A plastic service line installed underground
shall be vented at a safe location. under a building shall be encased in a gas-tight conduit.
72
ASME B31.8-2016
(g) the dissemination of information to the public This plan shall include a procedure to select samples of
(h) the safe restoration of service to all facilities the failed facility or equipment for laboratory examina-
affected by the emergency after proper corrective mea- tion when necessary.
sures have been taken
(i) reporting and documenting the emergency 850.6 Prevention of Accidental Ignition
850.4.2 Training Program. Each operating company Smoking and all open flames shall be prohibited in
shall have a program for informing, instructing, and and around structures, or areas under the control of
training employees responsible for executing emergency the operating company containing gas facilities (such
procedures. The program shall acquaint the employee as compressor stations, meter and regulator stations,
with the emergency procedures and how to promptly and other gas handling equipment), where possible leak-
and effectively handle emergency situations. The pro- age of gas constitutes a hazard of fire or explosion. Each
gram may be implemented by oral instruction, written operating company shall take steps to minimize the
instruction, and, in some instances, group instruction, danger of accidental ignition of gas.
followed by practice sessions. The program shall be (a) When a hazardous amount of gas is to be vented
established and maintained on a continuing basis with into open air, each potential source of ignition shall first
provision for updating as necessitated by revision of the be removed from the area and adequate fire extinguish-
See para. 850.9.1 for
written emergency procedures. Program records shall
additional guidance. ers shall be provided. All flashlights, lighting fixtures,
be maintained to establish what training each employee extension cords, and tools shall be of a type approved
has received and the date of such training. for hazardous atmospheres. Blowdown connections that
850.4.3 Liaison will direct the gas away from any electrical transmission
(a) Each operating company shall establish and main- lines must be installed or used.
tain liaison with appropriate fire, police, and other pub- (b) Suitable signs and flagmen or guards, if necessary,
lic officials, entities in or near the pipeline right-of-way shall be posted to warn others approaching or entering
(e.g., electrical and other utilities, highway authorities, the area of the hazard.
and railroads), and news media. (c) To prevent accidental ignition by electric arcing,
(b) Each operating company must have a means of an adequate bonding cable should be connected to each
communication with appropriate public officials during side of any pipe that is to be parted, tapped, squeezed-
an emergency. off, or joined, and any cathodic protection rectifiers in
(c) Emergency procedures, including the contingency the area shall be turned off. Where gas pipelines parallel
plan under para. B854.5(e), must be prepared in coordi- overhead electric transmission lines on the same right-
nation with appropriate public officials. of-way, the company operating the pipeline shall ensure
that the current carrying capacity of the bonding conduc-
850.4.4 Educational Program. An educational pro-
tor should be at least one-half of the current carrying
gram shall be established to enable customers and the
capacity of the overhead line conductors. [See also
general public to recognize a gas emergency and report
para. 861.1.3(b).] The bonding connection is to be main-
it to the appropriate officials. The educational program
tained while the pipeline is separated. When plastic pipe
shall be tailored to the type of pipeline operation and
the environment traversed by the pipeline and shall be is being parted, tapped, or joined, attention must be
conducted in each language that is significant in the given to the static electrical charges that may be present
community served. Operators of distribution systems on both the inside and outside diameters of the pipe.
shall communicate their programs to consumers and the These charges can be dissipated by using antistatic fluids
general public in their distribution area. Operators of or a water-and-detergent solution in combination with
transmission systems shall communicate their programs a moisture retaining material that must be in contact
to residents along their pipeline rights-of-way. Operators with the exposed pipe and the earth. Cutting tools and
of sour gas pipelines subject to Chapter IX shall notify squeeze-off and tapping equipment used on plastic pipe
residents affected by the contingency plan under where static charges may be present shall be grounded
para. B854.5(e) of the hazards of sour gas, the potential to drain these charges from the pipe.
source of the gas, and protective measures to take in an (d) When cutting by torch or welding is to be per-
emergency. The programs of operators in the same area formed, a thorough check shall first be made for the
shall be coordinated to properly direct reports of emer- presence of a combustible gas mixture in the area outside
gencies and to avoid inconsistencies. of the pipeline. If found, the mixture shall be eliminated
before starting welding or cutting. Monitoring of the air
850.5 Pipeline Failure Investigation mixture should continue throughout the progress of the
Each operating company shall establish procedures work.
to analyze all failures and accidents for determining the (e) Should welding be anticipated on a pipeline filled
cause and to minimize the possibility of a recurrence. with gas and the safety check under (d) above has been
76
ASME B31.8-2016
completed satisfactorily, the gas pressure must be con- the integrity of the pipeline, the damage shall be remedi-
monitoring of by
trolled excavation
a suitableactivities
means as to well
keepasa direct
slight positive ated in accordance with established procedures.
pressure in the pipeline at the welding area before start- (e) maintaining maps indicating the location of facili-
observation of excavation. Consideration should be
ing work. Precautions should be taken to prevent a back- ties. The maps should be updated to reflect new and
given todraft
the from
frequency of monitoring,
occurring at the weldingcriteria
area.for replacement facilities.
continual(f)
observation, actions
Before cutting if theorexcavator
by torch welding on a line that (f) a process to ensure the effectiveness of the pro-
refusesmay
to follow operating
contain a mixture company
of gas andrequirements
air, it shall be made gram. This process may include: trending of excavation
and documentation to bethe
safe by displacing maintained
mixture withduring
gas, air, or an inert damages and location, investigation of excavation dam-
observations.
gas. Caution must be taken when using an inert gas to ages and identification of root cause, and identification
provide adequate ventilation for all workers in the area. of preventive measures targeting excavators or locations
with high damage rates.
850.7 Blasting Effects A useful reference for identifying elements of an effec-
Each operating company shall establish procedures tive damage prevention program is the Best Practices
for protection of facilities in the vicinity of blasting activ- Guide, maintained and published by the Common
ities. The operating company shall Ground Alliance.
See Attached Insert
(a) locate and mark its pipeline when explosives are
to be detonated within distances as specified in company performing
851 PIPELINE inspections of pipelines where there
MAINTENANCE
plans. Consideration should be given to the marking of are indications that of
thePipelines
pipe could have been
minimum blasting distances from the pipelines 851.1 Periodic Surveillance
depending upon the type of blasting operation.
damaged as a result of excavation. If damage
As a means of maintaining the integrity of its pipeline
(b) determine the necessity and extent of observing system, occurs that affects
each operating the integrity
company of the pipeline,
shall establish and
or monitoring blasting activities based upon the proxim- implement theprocedures
damage shallfor be remediated
periodic in accordance
surveillance of its
ity of the blast with respect to the pipelines, the size of with
facilities. established
Studies shall beprocedures.
initiated and appropriate
charge, and soil conditions. (g) be
action shall maintaining
taken wheremaps indicating
unusual operatingtheand
location
main- of
(c) conduct a leak survey following each blasting tenance facilities.
conditionsThe maps should be updated tohis-
occur, such as failures, leakage reflect
tory, drop in flow efficiency due to internal corrosion, or
operation near its pipelines.
participating new and replacement facilities.
substantial changes in cathodic protection requirements.
850.8 Damage Prevention Program (h) assessing the effectiveness of the program.
When such studies indicate the facility is in unsatisfac-
This assessment
tory condition, may include:
a planned program shall trending
be initiatedof to
Each operating company shall have a program to
reduce the risk associated with damage to gas facilities abandon,excavation
replace, ordamages
reconditionandandlocation, investigation
proof test. If such
resulting from excavation activities. Operators should a facilityofcannot
excavation damages and
be reconditioned oridentification
phased out, the of root
consider the following elements within the program: maximum cause, and identification
allowable of preventive
operating pressure measures
shall be reduced
(a) participation in excavation notification systems, targetingwith
commensurate excavators or locationsdescribed
the requirements with highin
para. 845.2.2(c).
in places where such a system exists. Excavation notifica- damage rates.
tion systems allow excavators to provide notification to 851.2 Pipeline Patrolling
a single point of contact, which in turn forwards the
identifying Each operating company shall maintain a periodic
excavation details to participating facility owners/
pipeline patrol program to observe surface conditions on
operators. in accordanceand with
adjacent to each pipeline right-of-way, indications of
(b) identification of persons who normallyparagraph
perform 850.9.
excavations in the area in which the operator has facili- leaks, construction activity other than that performed
ties, including the public, and providing for periodic by the company, natural hazards, and any other factors
communication with these parties. The communication affecting the safety and operation of the pipeline. Patrols
could include such items as: how to determine the loca- shall be performed at least once every year in Location
tion of facilities, how to get the facilities field marked Classes 1 and 2, at least once every 6 months in Location
prior to excavating, and who to contact in the event of Class 3, and at least once every 3 months in Location
damage to the operator’s facility. Class 4. Weather, terrain, size of line, operating pres-
sures, and other conditions will be factors in determin-
(c) a process for receiving notifications of establishing
planned linesthe
of need
communication with the excavator to allow
ing for more frequent patrol. Main highways
for theofimmediate
excavations, providing the excavators with locations protection and future operation of the
and railroad crossings shall be inspected with greater
the operator’s facilities through temporary field mark-
facility.
ings, establishing lines of communication with the exca-
Communications
frequency and could
more include
closelyreview of directional
than pipelines in open
vator to ensure the immediate protection and drilling
futureplans, load restrictions, clearance requirements, hand
country.
excavation requirements
operation of the facility, and consideration of monitoring and formalized
851.2.1 Maintenance crossing
of Cover at Roadand
Crossings and
excavation activities. encroachment agreements.
Drainage Ditches. The operating company shall deter-
(d) performing inspections of pipelines where there mine by periodic surveys if the cover over the pipeline
are indications that the pipe could have been damaged at road crossings and drainage ditches has been reduced
as a result of excavation. If damage occurs that affects below the requirements of the original design. If the
77
850.9 Communication Plan
The operator shall develop and implement a communications plan to provide operating company personnel,
jurisdictional authorities, emergency response officials, potential excavators, public officials and the public with
pipeline safety information to help keep communities near pipelines safe. The information may be communicated
as part of other required communications.
Communications should be conducted as often as necessary so that appropriate individuals and authorities have
access to current information about the operator's system, operation and maintenance efforts and integrity
management program (an integrity management program is described in ASME B31.8S, “Managing System
Integrity of Gas Pipelines”).
API Recommended Practice 1162, Public Awareness Programs for Pipeline Operators, provides additional
guidance.
850.9.1 External Communications
The following items should be considered for communication to the various interested parties, such as landowners
and tenants along the rights-of-way, public officials, local and regional emergency responders, general public,
excavators and one-call centers:
(a) operating company name, location, and contact information (both routine and emergency contacts)
(b) general location information and instructions for obtaining more specific location information or maps
(c) facility description
(d) commodity transported
(e) potential hazards of a natural gas release
(f) how to recognize, report, and respond to a natural gas leak
(g) information about the operator's damage prevention program, including excavation notification phone
numbers, excavation notification center requirements, and who to contact if there is any damage
(h) general information about the operator's integrity management program, and how to obtain a summary of the
integrity management program
(i) information about the operator's emergency response program
(j) continuing liaison with emergency responders, including local emergency planning commissions, regional and
area planning committees, jurisdictional emergency planning offices, etc., to share information on each parties
capabilities in responding to pipeline emergencies, pipeline facility information, maps, and emergency response
plans
(k) dialogue with the public to convey the operator's expectations of the public as to how they can help the
operator maintain integrity of the pipeline.
850.9.2 Internal Communications
Operating company management and other appropriate personnel should understand and support the operation
and maintenance efforts, damage prevention program, emergency response program and integrity management
program. This should be accomplished through the development and implementation of an internal
communications aspect of the plan. The development and periodic review of performance measures and the
resulting adjustments to the integrity management program should also be part of the internal communications
plan.
ASME B31.8-2016
The use of nonmetallic composite repair is prohibited for repairing leaks on pipelines
operating company determines that the normal cover the pipeline shall be operated at a pressure no greater
operating over 100 psig (690 kPa). The use of nonmetallic composite repair is not
provided at the time of pipeline construction has become than 80% of the operating pressure at the time of discov-
recommended
unacceptably reduced due for
to repairing cracks
earth removal or pipe
or line move-manufacturing defects pressure
ery. The operating in pipelinesshallunless
remain at or below this
reliable engineering analysis or testing
ment, the operating company shall provide additional demonstrates the effectiveness of the repair unless sufficient
reduced pressure during these activities
protection device and installation
by providing procedure
barriers, culverts, whenpads,
concrete applied to such defects.
information becomes available to determine a different
casing, lowering of the line, or other suitable means. pressure.
Nonleaking corroded areas that must be repaired or
851.2.2 Maintenance of Cover in Cross-Country the design and fabrication
replaced are defined in para. 860.2(a). Longitudinal weld
Terrain. If the operating company learns, as a result details shall ensure that the
seams are commonly identified
pipeline design criteriaby
arevisual inspection,
of patrolling, that the cover over the pipeline in cross-
etchants, or ultrasonic testing.
met with consideration
country terrain does not meet the original design, it shall
A full encirclement welded split sleeve
given to circumferential fillet with welded
determine whether the cover has been reduced to an
ends shall havewelds (see
a design ASME PCC-2
pressure at least equal to that
unacceptable level. If the level is unacceptable, the
required for theArticle
maximum2.6) allowable operating pressure
operating company shall provide additional protection
of the pipe being repaired [see para. 841.1.1(a)]. If condi-
by replacing cover, lowering the line, or other suitable
tions require that the sleeve carry the full longitudinal
means.
stresses, the sleeve shall be at least equal to the design
851.3 Leakage Surveys strength of the pipe being repaired. Full encirclement
sleeves shall not be less than 4 in. (100 mm) in width.
Each operating company of a transmission line shall If the defect is not a leak, the circumferential fillet
provide for periodic leakage surveys of the line in its welds are optional in certain cases as described in the
operating and maintenance plan. The types of surveys following sections of para. 851.4. If circumferential fillet
selected shall be effective for determining if potentially welds are made, the sleeve’s longitudinal welds shall be
hazardous leakage exists. The extent and frequency of butt welds. The welding procedures for the circumferen-
the leakage surveys shall be determined by the operating tial fillet welds shall be suitable for the materials and
pressure, piping age, Location Class, and whether the shall consider the potential for underbead cracking.
transmission line transports gas without an odorant. Backup strips are not required. If the circumferential
fillet welds are not made, the longitudinal welds may
851.4 Repair Procedures for Steel Pipelines
be butt welds, or fillets to a side bar. The circumferential
Evaluation of pipeline defects and associated repair edges, which would have been sealed had the fillet weld
methods are discussed in paras. 851.4.1 through 851.4.5. been made, should be sealed with a coating material
Additional guidance may be found in Parts 2 and 3 of such as enamel or mastic, so that the soil environment
ASME PCC-2, Repair of Pressure Equipment and Piping, will be kept out of the area under the sleeve.
and in the following PRCI documents: Pipeline Repair Prior to the installation of a sleeve, the pipe body
Manual (original or updated version), and Pipeline shall be inspected by ultrasonic methods for laminations
Defect Assessment — A Review and Comparison of where sleeve fillet welds will be deposited onto the
Commonly Used Methods. Information on these docu- pipe body.
ments is found in Mandatory Appendix A. Consideration shall be given to the toughness charac-
If at any time a defect mentioned in the following teristics and quality of all seam welds when depositing
subsections of para. 851.4 is evident on a pipeline, tem- welds across the seam in the course of repairs.
porary measures shall be employed immediately to pro-
tect the property and the public. If it is not feasible to 851.4.1 Definition of Injurious Dents and Mechanical
make repairs at the time of discovery, permanent repairs Damage
shall be made as soon as described herein. The use of (a) Dents are indentations of the pipe or distortions
a welded patch as a repair method is prohibited, except of the pipe’s circular cross section caused by external
as provided in para. 851.4.4(e). Whenever a pipeline forces.
remains pressurized while being exposed to investigate (b) Plain dents are dents that vary smoothly and do
or repair a likely defect, the operating pressure shall not contain creases, mechanical damage [such as
be at a level that provides safety during excavation, described in (c)], corrosion, arc burns, girth, or seam
investigation and/or repair operations. welds.
(a) If there is sufficient information about the defect (c) Mechanical damage is damage to the pipe surface
to determine through engineering analysis the pressure caused by external forces. Mechanical damage includes
at which excavation, investigation, and/or repair opera- features such as creasing of the pipe wall, gouges,
Repair materials
tions may or equipment
be conducted safely, the for which
pipeline shallnobe standards
oper- or
scrapes, smeared metal, and metal loss not due to corro-
specifications
ated at or beloware this
referenced in thisthese
pressure during Code shall onlysion.
activities. be Cracking may or may not be present in conjunction
permitted if qualified
(b) If there in accordance
is insufficient information with
aboutpara.
the 811.2.4.
defect Such
with mechanical damage. Denting of the pipe may or
repairs shall be
to determine thedescribed
pressure atin detail
which in documentation
excavation, investiga- that
may is not be apparent in conjunction with mechanical
retained by the repair
tion, and/or operating company.
operations may be conducted safely, damage.
78
ASME B31.8-2016
冤 冢冢 冣冥
1/2
(c)(2). 2
冣
the pipeline are acceptable provided strain levels associ- a/t
L p 1.12 (Dt) −1
(-a)
atedFor pipelines
with operating
the deformation do at
notorexceed
above4%.30%SMYS:
It is the 1.1a / t − 0.11
operator’s responsibility to establish the quality level of
the weld. (SI Units)
冤 冥
(i) Dents of any depth that affect nonductile welds,
冤 冢冢 冣冥
1/2
2
冣
such as acetylene girth welds or seam welds that are a/t
L p 28.45 (Dt) −1
prone to brittle fracture, are injurious. 1.1a / t − 0.11
(j) The allowable height of mild ripples in carbon steel
pipe formed during the cold bending process can be
determined from Fig. 851.4.1-1, where d is the maximum where
depth or crest-to-trough dimension of the ripple and D a p measured maximum depth of ground area, in.
is the specified outside diameter of the pipe. Ripples in (mm)
carbon steel pipe are acceptable if their height is below D p nominal outside diameter of the pipe, in. (mm)
the line shown. Ripples with heights above the line may L p maximum allowable longitudinal extent of the
be demonstrated to be acceptable using a more rigorous ground area, in. (mm)
analysis. t p nominal wall thickness of pipe, in. (mm)
851.4.2 Permanent Field Repairs of Injurious Dents Grinding shall produce a smooth contour in the pipe
and Mechanical Damage wall. The remaining wall thickness shall be verified
(a) Injurious dents and mechanical damage shall be using ultrasonic testing. After grinding, the surface shall
(-b) For
removed or repaired by pipelines
one of the operating belowor
methods below, be inspected for cracks using a nondestructive surface
30% SMYS: Grinding is permitted
the operating pressure shall be reduced. The reduced examination method capable of detecting cracks and the
to exceed
pressure shall not lengths80%andof depths meeting
the operating the
pressure surface shall be inspected with a suitable etchant per
experienced by acceptance criteria of ASME B31G.
the injurious feature at the time of dis- para. 841.2.4(e). If grinding within the depth and length
covery. Pressure reduction does not constitute a perma- limitations fails to completely remove the damage, the
nent repair. damage shall be removed or repaired in accordance
(b) Removal of injurious dents or mechanical damage with (c)(2).
shall be performed by taking the pipeline out of service (4) Dents containing stress corrosion cracking may
and cutting out a cylindrical piece of pipe and replacing be repaired by grinding out the cracks to a length and
same with pipe of equal or greater design pressure, or depth permitted in para. 860.2(a) for corrosion in plain
79
ASME B31.8-2016
0.025 = 2.5%
0.020 = 2%
Gas pipelines
0.015 = 1.5%
0.010 = 1%
0.005 = 0.5%
0
0 10,000 20,000 30,000 40,000 50,000 60,000
pipe. The wall thickness shall be checked using ultra- pipeline has been reduced to a pressure that will not
sonic testing. After grinding, the surface shall be produce a hoop stress in excess of 20% of the specified
inspected for cracks using a nondestructive surface minimum yield of the pipe, and grinding of the defective
examination method capable of detecting cracks and the area can be limited so that there will remain at least
1
surface shall be inspected with a suitable etchant as per ⁄8 in. (3.2 mm) thickness in the pipe weld.
para. 841.2.4(e). If grinding within the depth and length (b) Defective welds mentioned in (a) above, which
limitations fails to completely remove the damage, the cannot be repaired under (a) above and where it is not
damage shall be removed or repaired in accordance feasible to remove the defect from the pipeline by
with (c)(1). replacement, may be repaired by the installation of a full
(d) If a dent or mechanical damage is repaired with encirclement welded split sleeve using circumferential
a sleeve not designed to carry maximum allowable fillet welds.
operating line pressure, the dent shall first be filled with (c) If a manufacturing defect is found in a double
an incompressible filler. If the sleeve is designed to carry submerged-arc-welded seam or high frequency ERW
maximum allowable operating pressure, the incom- seam, a full encirclement welded split sleeve shall be
pressible filler is recommended but not required. installed.
(e) Nonmetallic composite wrap repairs are not (d) If a manufacturing defect is discovered in a low
acceptable for repair of injurious dents or mechanical frequency ERW weld seam or any seam having a factor
damage, unless proven through reliable engineering E less than 1.0 in Table 841.1.7-1, or if hydrogen stress
tests and analysis. cracking is found in any weld zone, a full encirclement
(f) All repairs under para. 851.4.2 shall pass nonde- welded split sleeve designed to carry maximum allow-
structive inspections and tests as provided in para. 851.5. able operating pressure shall be installed.
851.4.3 Permanent Field Repair of Welds Having (e) All repairs performed under (a) through (d) above
Injurious Defects shall be tested and inspected as provided in para. 851.5.
(a) All circumferential butt welds found to have unac- (f) Corroded areas may be repaired by filling them
ceptable defects (according to API 1104) shall be repaired with deposited weld metal using a low-hydrogen weld-
in accordance with the requirements of section 827, pro- ing process. Repairs shall be accomplished in accordance
vided the pipeline can be taken out of service. Repairs with a written maintenance procedure, which when fol-
on welds may be made while the pipeline is in service, lowed will permanently restore the required wall thick-
provided the weld is not leaking, the pressure in the ness and mechanical properties of the pipeline. The
80
ASME B31.8-2016
welding procedures and welders shall be qualified 851.4.5 Permanent Field Repair of Hydrogen Stress
under para. 823.2.1. The procedures shall provide suffi- Cracking in Hard Spots and Stress Corrosion Cracking
cient direction for avoiding burn-through and minimiz- (a) If feasible, the pipeline shall be taken out of service
ing the risk of hydrogen cracking on in-service pipelines. and repaired by cutting out a cylindrical piece of pipe
For background information on developing a weld and replacing with pipe of equal or greater design
deposition repair procedure, refer to “Guidelines strength.
for Weld Deposition Repair on Pipelines” (b) If it is not feasible to take the pipeline out of ser-
(PRCI Catalog L51782) in Mandatory Appendix A. This
pressure. vice, repairs shall be made by the installation of a full
method of repair shall not be attempted on pipe that is encirclement welded split sleeve. In the case of stress
thought to be susceptible to brittle failure. corrosion cracking, the fillet welds are optional. If the
851.4.4 Permanent Field Repair of Leaks and fillet welds are made, pressurization of the sleeve is
Nonleaking Corroded Areas optional. The same applies to hydrogen stress cracking
(f) All repairs performed underspots,
in hard (a), except that a flat hard spot shall be pro-
(a) If feasible, the pipeline shall be taken out of service
(b), (c), (d) and (e) above shall
tected be a hardenable filler or by pressurization of
with
and repaired by cutting out a cylindrical piece of pipe
tested and inspectedaasfilletprovided
weldedin sleeve. Stress corrosion cracking may
and replacing with pipe of equal or greater design
para. 851.5. also be repaired per para. 851.4.2(c)(4), which describes
strength.
repairs for stress corrosion cracking in dents.
(b) If it is not feasible to take the pipeline out of ser-
vice, repairs shall be made by the installation of a full (c) All repairs performed under (a) and (b) shall be
encirclement welded split sleeve unless a patch is chosen tested and inspected as provided in para. 851.5.
in accordance with (e) below, or unless corrosion is
851.5 Testing Repairs to Steel Pipelines or Mains
repaired with deposited weld metal in accordance with
(f) below. If nonleaking corrosion is repaired with a 851.5.1 Testing of Replacement Pipe Sections.
full encirclement welded split sleeve, the circumferential When a scheduled repair to a pipeline or main is made
fillet welds are optional.
(e) below or unless a patch is by cutting out the damaged portion of the pipe as a
(c) If the leak is due to a corrosion pit, the repair may cylinder andwith a specified
replacing it with minimum
another section of pipe,
be made by the installationchosen in accordance
of a properly designedwith
bolt-(f) the replacement section of pipe shall be subjected to a
on leak clamp. below. yield strength
pressure test. The replacement section of pipe shall be
(d) A small leak may be repaired by welding a nipple tested to the pressure required for a new pipeline or
over it to vent the gas while welding and then installing repair mainplate design and
installed in the same location. The tests may be
an appropriate fitting on the nipple. fabrication
made ondetails shallprior to installation,
the pipe pressure containing type B
provided nonde-
(e) Leaking or nonleaking corroded areas on pipe of ensure that the
structive pipeline
tests meeting the requirements of section 826
not more than 40,000 psi (276 MPa) specified minimum design criteria
are made onare
allmet.
field girth butt welds after installation. If
(f) yield strength may be repaired by using a steel plate the replacement is made under controlled fire conditions
patch with rounded corners and with dimensions not (see ASME
(gas in the pipeline), fullPCC-2)
encirclement welded split
in excess of one-half the circumference of the pipe fillet sleeves may be used to join the pipe sections instead of
welded over the pitted area. The design strength of the
plate shall be the same or greater than the pipe.
butt welds. All This method
sleeve weldsofshould
repairbeshould not be
radiographed.
(See para. 851.5.2.)
(f) Small corroded areas may be repaired by filling attempted on pipe that is thought to be
them with deposited weld metal from low-hydrogen 851.5.2 susceptible to hydrogen cracking /
Nondestructive Testing of Repairs, Gouges,
Grooves, Dents, and Welds. If the defects are repaired
(e) electrodes. The higher the pressure and the greater the brittle fracture.
by welding in accordance with the provisions of
flow rate, the lesser the chance of burn-through. At 20 V
and 100 A, burn-through is unlikely to occur when the 851.5.3
para. 851.4 andLeak
any ofTesting of Leakthe
its subsections, Repairs.
weldingInshall
addition to
actual wall thicknesses exist, as shown in Table 851.4.4-1. the requirements
be examined in accordance of paras. 851.5.1
with section and 851.5.2,
826.
This method of repair should not be attempted on repairs made to leaks shall be leak tested. The leak
pipe that is thought to be susceptible to brittle fracture. 851.6 test
Pipeline
shall Leak Records in accordance with Appendix
be performed
(g) All repairs performed under (a), (b), and (d) above M, M-3(e),
Records shall be(f), or (g).
made The leak
covering all test
leakspressure shall be at
discovered
shall be tested and inspected as provided in para. 851.5. or above
and repairs made.theAll
maximum operating
pipeline breaks pressure
shall available
be reported
when the repair is placed back into service.
(c), (d), (e) and (f) 81
ASME B31.8-2016
to maintain a safe operating system. Appropriate correc- through the coating. Any such irregularities shall be
tive measures may include the following: removed. Further information can be obtained from
(1) provisions for proper and continuous operation NACE SP0169.
of cathodic protection facilities (b) Suitable coatings, including compatible field joint
(2) application of protective coating and patch coatings, shall be selected, giving consider-
(3) installation of galvanic anode(s) ation to handling, shipping, storing, installation condi-
(4) application of impressed current tion, moisture adsorption, operating temperatures of the
(5) electrical isolation pipeline, environmental factors (including the nature of
(6) stray current control the soil in contact with the coating), adhesion character-
(7) other effective measures istics, and dielectric strength.
(8) any combination of the above (c) Coating shall be applied in a manner that ensures
(b) Where it is determined that internal corrosion tak- effective adhesion to the pipe. Voids, wrinkles, holidays,
ing place could affect public or employee safety, one or and gas entrapment should be avoided.
more of the following protective or corrective measures (d) The coating shall be visually inspected for defects
shall be used to control detrimental internal corrosion: before the pipe is lowered into the ditch. Insulating type
(1) An effective corrosion inhibitor shall be applied coatings on mains and transmission lines shall be
in a manner and quantity to protect all affected portions inspected for holidays by the most appropriate method.
of the piping systems. Coating defects or damage that may impair effective
(2) Corrosive agents shall be removed by recog- corrosion control shall be repaired before the pipe is
nized methods, such as acid gas or dehydration treating installed in the ditch.
plants. (e) In addition to the provisions of paras. 841.2.2(b),
(3) Fittings shall be added for removal of water 841.2.5(b), and 841.2.5(c), care shall be exercised in han-
from low spots, or piping shall be positioned to reduce dling, storage, and installation to prevent damage to the
sump capacities. coating, including measures noted as follows:
(4) Under some circumstances, application of a (1) Minimize handling of coated pipe. Use equip-
suitable internal coating may be effective. ment least likely to damage the coating, e.g., belts or
(c) When experience or testing indicates the above cradles instead of cables.
mitigation methods will not control continuing corro- (2) Use padded skids where appropriate.
sion to an acceptable level, the segment shall be recondi- (3) Stack or store pipe in a manner that minimizes
tioned or replaced and suitably protected. damage to coating.
861.1.2 Cathodic Protection Requirements. Unless
861 EXTERNAL CORROSION CONTROL FOR STEEL it can be demonstrated by tests or experience that
PIPELINES cathodic protection is not needed, all buried or sub-
merged facilities with insulating type coatings, except
861.1 Buried/Submerged Installations facilities installed for a limited service life, shall be
All new transmission pipelines, compressor station cathodically protected as soon as feasible following
piping, distribution mains, service lines, and pipe-type installation. Minor replacements or extensions, however,
and bottle-type holders installed under this Code shall, shall be protected as covered by para. 860.3.
except as permitted under para. 862.1.2, be externally Facilities installed for a limited service life need not
coated and cathodically protected unless it can be dem- be cathodically protected if it can be demonstrated that
onstrated by test or experience that the materials are the facility will not experience corrosion that will cause
resistant to corrosion in the environment in which they applicable
it to be harmful to the public or environment. Cathodic
are installed. Consideration shall be given to the han- protection systems shall be designed to protect the bur-
dling, shipping, storing, installation conditions, and the ied or submerged system in its entirety. A facility is
service environment and cathodic protection require- considered to be cathodically protected when it meets
ments when selecting the coating materials. The one or more of the criteria established in Mandatory
Corrosion Data Survey, published by NACE International, Appendix K.
is a source of information on materials performance in NACE SP0169.
861.1.3 Electrical Isolation
corrosive environments.
(a) All coated transmission and distribution systems
861.1.1 Coatings shall be electrically isolated at all interconnections with
(a) The surface preparation should be compatible foreign systems including customer’s fuel lines, except
with the coating to be applied. The pipe surface shall where underground metallic structures are electrically
be free of deleterious materials, such as rust, scale, mois- interconnected and cathodically protected as a unit.
ture, dirt, oils, lacquers, and varnish. The surface shall Steel pipelines shall be electrically isolated from cast
be inspected for irregularities that could protrude iron, ductile iron, or nonferrous metal pipelines and
96
ASME B31.8-2016
98
ASME B31.8-2016
This Chapter of the Code covers the design, material
requirements, fabrication, installation, inspection,
testing, and safety aspects of operation and maintenance
of offshore gas transmission systems.
Chapter VIII
Offshore Gas Transmission
103
ASME B31.8-2016
in accordance with the applicable pipe specification, and flanges, and/or mechanical connectors and is typically
minus all corrosion and erosion allowances. The mini- fabricated onshore and connected to the pipeline system
mum wall thickness is used in the design equations in during installation. Some examples of prefabricated pip-
para. A842.2.2(d). ing include a riser offset, jumper, expansion loop, tie-in
near white blast cleaned: a surface that, when viewed with- spool, and prefabricated riser.
out magnification, is free of all visible oil, grease, dust, propagating buckle: a buckle that progresses rapidly along
dirt, mill scale, rust, coating, oxides, corrosion products, a pipeline caused by the effect of external hydrostatic
and other foreign matter. Random staining is limited to pressure on a previously formed buckle, local collapse,
not more than 5% of each unit area of surface [approxi- or other cross-sectional deformation.
mately 9.0 in.2 (58 cm2)], and may consist of light shad- pull tube: a conduit attached to an offshore platform
ows, slight streaks, or minor discolorations caused by through which a riser can be installed.
stains of rust, stains of mill scale, or stains of previously
pull-tube riser: riser pipe or pipes installed through a
applied coating (see NACE No. 2/SSPC-SP 10).
pull tube (e.g., J-tube or I-tube).
offshore: the area beyond the line of ordinary high water
return interval: statistically determined time interval
along the portion of the coast that is in direct contact
between successive events of design environmental con-
with the open seas and beyond the line marking the
ditions being equaled or exceeded, typically calculated
seaward limit of inland coastal waters.
as the reciprocal of the annual probability of occurence
offshore pipeline riser: the vertical or near vertical portion of the event.
of an offshore pipeline between the platform piping and riser: see offshore pipeline riser.
the pipeline at or below the seabed, including a length
of pipe of at least five pipe diameters beyond the bottom sea floor bathymetry: refers to water depths along the
elbow, bend, or fitting. Due to the wide variety of config- pipeline route.
urations, the exact location of transition between pipe- soil liquefaction: a soil condition, typically caused by
line, pipeline riser, and platform piping must be selected dynamic cyclic loading (e.g., earthquake, waves), where
on a case-by-case basis. the effective shear strength in the soil is reduced such
that the soil exhibits the properties of a liquid.
offshore pipeline system: all components of a pipeline
installed offshore for transporting gas other than pro- special assembly: a subsea pipeline section that contains
duction facility piping. Tanker or barge loading hoses pipeline components such as a buckle or fracture
are not considered part of the offshore pipeline system. arrestor, in-line sled, subsea tie-in assembly, pipeline
end manifold, pipeline end termination, in-line valve
offshore platform: any man-made fixed or permanently
assembly, side valve assembly, or subsea manifold and
anchored structure or artificial island located offshore.
is typically fabricated onshore and connected to the
pipe collapse: flattening deformation of the pipe resulting pipeline system during installation.
in loss of cross-sectional strength and circular shape,
splash zone: the area of the pipeline riser or other pipeline
which is caused by excessive external hydrostatic pres-
, floating facility, components that is intermittently wet and dry due to
sure acting alone.
wave and tidal action.
plastic deformation: a permanent deformation caused by
steel catenary riser (SCR): a catenary-shaped extension of
stressing beyond the elastic limit.
a subsea pipeline that is attached to a floating or fixed
platform piping: offshore platform.
(a) On offshore platforms producing hydrocarbons, trawl board: a structure that is attached to the bottom
platform piping is all the gas transmission piping, of commercial fishing nets and is dragged along the
appurtenances, and components between the produc- sea floor.
tion facility and the offshore pipeline riser(s). This
includes any gas compressors and piping that are not a vortex shedding: the periodic shedding of fluid vortices
part of the production facility. and resulting unsteady flow patterns downstream of a
pipeline span that may introduce dynamic forces on the
(b) On offshore platforms not producing hydrocar-
pipeline.
bons, platform piping is all the gas transmission piping,
compressors, appurtenances, and components between weight coating: any coating applied to the pipeline for
the offshore pipeline risers. increasing the pipeline specific gravity.
(c) Because of a wide variety of configurations, the
exact location of the transition between the offshore A811 QUALIFICATION OF MATERIALS AND
pipeline riser(s), the platform piping, and the production EQUIPMENT
facility must be selected on a case-by-case basis. Plastic pipe, plastic pipe with nonmetallic reinforce-
prefabricated piping: a section of riser, platform piping, ment, cast iron pipe, and ductile iron pipe shall not be
or subsea pipeline that contains fittings and butt welds, used for transporting natural gas.
104
ASME B31.8-2016
105
ASME B31.8-2016
qualified under API 1104, except that for applications and nondestructive examinations beyond the minimum
in which design, materials, fabrication, inspection, and requirements specified herein. The accuracy of the non-
testing are in accordance with BPV Code, Section VIII, destructive techniques for flaw depth measurement
welding procedures and welders shall be qualified under shall be verified by sufficient data to establish probabili-
BPV Code, Section IX. ties for the proposed inspection error allowance.
(b) Welding procedures and welders performing
hyperbaric welding under this section shall be qualified
in accordance with the testing provisions of API 1104 A830 PIPING SYSTEM COMPONENTS AND
as supplemented by AWS D3.6, Specification for FABRICATION DETAILS
Underwater Welding for Type “O” Welds.
A830.1 General
A825 STRESS RELIEVING The purpose of paras. A831 through A835 is to provide
a set of criteria for system components to be used in an
Stress relieving requirements may be waived, regard- offshore application.
less of wall thickness, provided that it can be demon-
strated that a satisfactory welding procedure without
the use of postweld heat treatment has been developed. A831 PIPING SYSTEM COMPONENTS
Such a demonstration shall be conducted on materials
and under conditions that simulate, as closely as practi- Cast iron or ductile iron shall not be used in flanges,
cal, the actual production welding. Measurements shall fittings, or valve shell components.
be taken of the tensile, toughness, and hardness proper- All system components for offshore applications shall
ties of the weld and heat-affected zone. No stress reliev- be capable of safely resisting the same loads as the pipe
ing will be required if in the run in which they are included, except “weak
(a) the measurements indicate that the metallurgical links” (e.g., breakaway couplings) designed into a sys-
and mechanical properties are within the limits specified tem to fail under specific loads. Consideration should
for the materials and intended service. , and be given to minimizing stress concentrations.
(b) an engineering analysis is conducted to ensure System components that are not specifically covered
that the mechanical properties of the weldment and the in para. 831 shall be validated for fitness by either
residual stresses without postweld heat treatment are (a) documented full scale prototype testing of the
satisfactory for the intended service. In some cases, mea- components or special assemblies, or
surement of residual stresses may be required. (b) a history of successful usage of these components
or special assemblies produced by the same design
method. Care should be exercised in any new applica-
A826 INSPECTION OF WELDS
tion of existing designs to ensure suitability for the
A826.2 Inspection and Tests for Quality Control of intended service.
Welds on Piping Systems
A826.2.1 Extent of Examination. One-hundred per- A831.1 Valves and Pressure-Reducing Devices
cent of the total number of field welds on offshore pipe- A831.1.1 Valves. In addition to the valve standards
lines and pipeline components that are subjected to listed in para. 831.1.1(a), the following specifications
loading by pipeline internal pressure shall be nonde- may be used:
structively inspected, if practical, but in no case shall
less than 90% of such welds be inspected. The inspection API Spec 6DSS/ISO 14723 Specification for Subsea
shall cover 100% of the length of such inspected welds. Pipeline Valves
A826.2.2 Standard of Acceptability. All welds that API Spec 17D Design and Operation of
are inspected must meet the standards of acceptability Subsea Production
of API 1104 or BPV Code, Section VIII, as appropriate Systems — Subsea
for the service of the weld, or be appropriately repaired Wellhead and Tree
and reinspected or removed. Equipment
106
ASME B31.8-2016
A841.2.5 Bottom Soils. Soil characteristics shall be A841.3.3 Design Environmental Loads. Loadings
considered when installation procedures are developed that should be considered under this category include,
for the following: as appropriate, those arising due to
(a) riser installation in pull tubes (a) waves
(b) laying horizontal curves in the pipeline routing (b) current
(c) pipeline bottom tows (c) wind
(d) trenching and backfilling (d) seismic events
(e) accidental loadings (e.g., trawl boards and
A841.3 Operational Design Considerations anchors)
A841.3.1 Loading Classifications. All parts of the (f) dynamic soil-induced loadings (e.g., mudslides
offshore pipeline and riser system shall be designed for and liquefaction)
the most critical combinations of operational and design (g) ice loads (e.g., weight, floating impacts, and
environmental loads, acting concurrently, to which the scouring)
system may be subjected. Wind, wave, and current
A842 STRENGTH CONSIDERATIONS
design loads should be based on a design return interval
no less than five times the design life of the pipeline or Design and installation analyses shall be based on
100 yr, whichever is smaller. accepted engineering methods, material strength, and
If the pipeline operating philosophy is such that oper- applicable design conditions.
ations with full operational loads will be maintained A842.1 Strength Consideration During Installation
during design storms, then the system shall be designed The following subsections define the minimum safety
for concurrent action of operational and design environ- requirements against failure due to yielding or buckling
mental loads. during all phases of pipeline system installation (i.e.,
If the operating philosophy is such that operations handling, laying, trenching, etc., through testing).
will be reduced or discontinued during design storm A842.1.1 Buckling. The pipeline should be
conditions, then the system shall be designed for designed and installed in a manner to prevent buckling
(a) full operational loads plus maximum coincidental during installation. Design and procedures for installa-
environmental loads tion should account for the effect of external hydrostatic
(b) design environmental loads plus appropriate pressure, bending moment, axial, and torsional loads
reduced operational loads and pipe out-of-roundness. Consideration should also
Directionality of waves, winds, and currents shall be be given to the buckle propagation phenomenon.
considered to determine the most critical expected com- Additional information for calculating buckling
bination of above loadings. stresses due to bending and external pressure can be
found in API RP 1111, para. 4.3.2.2. 4.3.2.3
A841.3.2 Operational Loads. Operational loads that
shall be considered are those forces imposed on the A842.1.2 Collapse. The pipe wall thickness shall be
pipeline system under static environmental conditions designed to resist collapse due to external hydrostatic
(i.e., excluding wind, waves, current, and other dynamic pressure. Considerations shall include the effects of mill
loadings). tolerances in the wall thickness, out-of-roundness, and
Loads that should be considered as operational loads any other applicable factors.
include Additional information for designing to prevent col- 4.3.2.2
(a) weight of unsupported span of pipe, including (as lapse can be found in API RP 1111, para. 4.3.2.1.
appropriate) the weight of A842.1.3 Allowable Longitudinal Stress. The maxi-
(1) pipe mum longitudinal stress due to axial and bending loads
(2) coatings and their absorbed water during installation shall be limited to a value that pre-
(3) attachments to the pipe vents pipe buckling and will not impair the serviceability
(4) transported contents of the installed pipeline.
(b) internal and external pressure Additional information for longitudinal load design
(c) thermal expansion and contraction can be found in API RP 1111, para. 4.3.1.1. 4.3.1.1
(d) buoyancy A842.1.4 Allowable Strains. Instead of the stress
(e) prestressing (exclusive of structurally restrained criteria of para. A842.1.3, an allowable installation strain
pipe configurations, such as in a pull-tube riser bend) limit may be used. The maximum longitudinal strain
(f) static soil-induced loadings (e.g., overburden) due to axial and bending loads during installation shall
The effects of prestressing, such as permanent curva- be limited to a value that prevents pipe buckling and will
tures induced by installation, should be considered not impair the serviceability of the installed pipeline.
when they affect the serviceability of the pipeline. A842.1.5 Installation Fatigue. Anticipated stress
Additional information for operational loads can be fluctuations of sufficient magnitude and frequency to
found in API RP 1111, para. 4.1.4. induce significant fatigue shall be considered in design.
108
ASME B31.8-2016
(16) A842.1.6 Special Assemblies. Installation of pipe- Table A842.2.2-1 Design Factors for Offshore (16)
lines with special assemblies are subject to the same Pipelines, Platform Piping, and Pipeline Risers
requirements stated in paras. A842.1.1 through A842.1.5. Hoop Stress, Longitudinal Combined
A842.1.7 Residual Stresses. The pipeline system Location F1 Stress, F2 Stress, F3
shall normally be installed in a manner so as to minimize Pipeline 0.72 0.80 0.90
residual stresses. The exception shall be when the Platform piping 0.50 0.80 0.90 [Note (1)]
designer purposefully plans for residual stresses (e.g., and risers
cold-springing of risers and pull-tube risers). When
residual stresses are significant, they should be consid- NOTE:
ered in the operating design of the pipeline system (see (1) The wall thickness used in the calculation of combined stress
for platform piping and risers shall be based upon minimum
para. A842.2).
wall thickness, tmin.
A842.1.8 Flexible Pipe. The manufacturers recom-
mended maximum loadings and minimum bending
radius shall be adhered to during installation. Flexible (U.S. Customary Units)
pipe shall be designed or selected to prevent collapse D
due to the combined effects of external pressure, axial Sh p (Pi − Pe) (2)
2t
forces, and bending. Installation procedures shall be
designed to prevent buckling (see, API
and platform
RP 17B).piping (SI Units)
冤S 冥
D
A842.2 Strength Considerations During Operations h p (Pi − Pe) (3)
2 000t
A842.2.1 Operational and Design Criteria
(a) Failure Modes. Pipelines and risers shall be or
designed against the following possible modes of failure,
as appropriate: (U.S. Customary Units)
(1) excessive yielding , D−t
Sh p (Pi − Pe) (4)
(2) buckling 2t
(3) fatigue failure
(4) ductile fracture (SI Units)
冤S 冥
(5) brittle fracture D−t
h p (Pi − Pe) (5)
(6) loss of in-place stability 2 000t
(7) propagating fracture
(8) corrosion where
(9) collapse D p nominal outside diameter of pipe, in. (mm)
(b) Other Considerations. Furthermore, consideration F1 p hoop stress design factor from Table A842.2.2-1
shall be given to impacts due to Pe p external pressure, psig (kPa)
Pi p internal design pressure, psig (kPa)
(1) foreign objects
S p specified minimum yield strength, psi (MPa)
(2) anchors
Sh p hoop stress, psi (MPa)
(3) trawlboards
T p temperature derating factor from
(4) vessels, ice keels, etc.
Table 841.1.8-1
(16) A842.2.2 Design Against Yielding. Pipelines and t p nominal wall thickness, in. (mm)
risers shall be designed against yielding in accordance NOTE: It is recommended that eq. (2) or (3) be used for D/t
with this paragraph. The combined stress calculations greater than or equal to 30 and that eq. (4) or (5) be used for D/t
and allowables of paras. 833.2 through 833.6 are super- less than 30.
seded by the provisions of (b), (c), and (d) below (see
Additional information for pressure design can be
also Table A842.2.2-1):
found in API RP 1111, paras. 4.3.1 and 4.3.2.
(a) Hoop Stress. For pipelines, risers, and platform
(b) Longitudinal Stress. For pipelines, risers, and plat-
piping, the tensile hoop stress due to the difference
form piping, the longitudinal stress shall not exceed
between internal and external pressures shall not exceed
values found from
the value given below. Sh may be calculated by either
of the following: 冨SL 冨 ≤ F 2 S
NOTE: Sign convention is such that tension is positive and com-
pression is negative. where
A p cross-sectional area of pipe material using t,
Sh ≤ F 1 ST (1) in.2 (mm2)
109
ASME B31.8-2016
110
ASME B31.8-2016
limiting combined stress values. Accordingly, the com- A842.2.7 Design of Clamps and Supports. Clamps
bined stress should not exceed values given by and supports shall be designed such that a smooth trans-
fer of loads is made from the pipeline or riser to the
(Sh (mwt) 2 − SL (mwt)Sh (mwt) + SL (mwt) 2 + 3St (mwt) 2 )1/2 ≤ F 3 S supporting structure without highly localized stresses
due to stress concentrations. When members are to be
welded to the pipe they shall fully encircle the pipe and
A842.2.3 Alternate Design for Strain. In situations
be welded to the pipe by a full encirclement weld. The
where the pipeline experiences a predictable noncyclic
support shall be attached to the encircling member and
displacement of its support (e.g., fault movement along
not the pipe.
the pipeline route or differential subsidence along the
All welds to the pipe shall be nondestructively tested.
line) or pipe sag before support contact, the longitudinal
Clamps and supports shall be designed in accordance
and combined stress limits need not be used as criteria
with the requirements of API RP 2A-WSD, Section 3.
for safety against excessive yielding, so long as the con-
Clamp and support design shall consider the corrosive
sequences of yielding are not detrimental to the integrity
effects of moisture retaining gaps and crevices and gal-
of the pipeline. The permissible maximum longitudinal vanically dissimilar metals.
strain depends on the ductility of the material, any pre-
viously experienced plastic strain, and the buckling A842.2.8 Design of Connectors and Flanges. Con-
behavior of the pipe. Where plastic strains are antici- nectors and flanges shall be such that smooth transfer
pated, the pipe eccentricity, pipe out-of-roundness, and of loads is made without high localized stresses or exces-
sive deformation of the attached pipe.
the ability of the weld to undergo such strains without
Connectors and flanges shall have a level of safety
detrimental effect should be considered. Similarly, the
against failure by yielding and failure by fatigue that is
same criteria may be applied to the pipe during construc-
comparable to that of the attached pipeline or riser.
tion (e.g., pull-tube or bending shoe risers).
A842.2.9 Design of Structural Pipeline Riser
A842.2.4 Design Against Buckling and Ovalization. Protectors. Where pipeline risers are installed in loca-
Avoidance of buckling of the pipeline and riser during tions subject to impact from marine traffic, protective
operation shall be considered in design. Modes of buck- devices shall be installed in the zone subject to damage
4.3.2.3 ling that may be possible include to protect the pipe and coating.
and (a) local buckling of the pipe wall A842.2.10 Design and Protection of Special (16)
4.3.2.4 (b) propagation buckling following local buckling Assemblies. Design of connections and special
(c) column buckling assemblies shall consider the additional forces and
Additional information for determining buckling effects imposed by a subsea environment. Such addi-
tendencies can be found in API RP 1111, paras. 4.3.2.2 tional considerations include design storm currents and
and 4.3.2.3, and Annex D. potential for seabed movement in soft sediments, soil
liquefaction, increased potential corrosion, thermal
A842.2.5 Design Against Fatigue. Stress fluctua- expansion and contraction, and stress due to installation
tions of sufficient magnitude and frequency to induce procedures. In areas of active fishing, protective mea-
significant fatigue should be considered in design. sures may be appropriate for connections and special
Loadings that may affect fatigue include assemblies.
(a) pipe vibration, such as that induced by vortex A842.2.11 Design of Flexible Pipe. Due to its com-
shedding posite makeup, the mechanical behavior of flexible pipe
(b) wave action is significantly different from steel pipe. Flexible pipe
Pipe and riser spans shall be designed so that vortex may be used for offshore pipelines if calculations and/
induced resonant vibrations are prevented, whenever or test results verify that the pipe can safely withstand
practical. When doing so is impractical, the total resul- loadings considered in paras. A841.3.2 and A841.3.3. In
tant stresses shall be less than the allowable limits in the selection of flexible pipe, consideration should be
para. A842.2.2, and such that fatigue failure should not given to its permeable nature. The possibility of implo-
result during the design life of the pipeline. sion under the combined conditions of high pressure,
Additional information for fatigue analysis can be high temperature, and very rapid depressurization
found in API RP 1111, para. 4.5. should be investigated where such conditions may be
expected. Selection of flexible pipe shall be in accordance
A842.2.6 Design Against Fracture. Materials used with API RP 17B and API Spec 17J.
for pipelines transporting gas or gas-liquid mixtures
under high pressure should have reasonably high resist- A843 COMPRESSOR STATIONS
ance to propagating fractures at the design conditions, A843.1 Compressor Station Design
or other methods shall be used to limit the extent of a The requirements of this paragraph recognize the
fracture. unique design conditions and space limitations imposed
111
ASME B31.8-2016
when designing offshore compression facilities and gas compression equipment and all gas-fired equipment
therefore relate only to offshore compression facilities. and shall de-energize the electrical facilities in the com-
It is the further intent of this section to make the pressor building, except for those that provide emer-
designer aware of personnel safety during the design gency lighting for personnel protection and those that
and operation of offshore compression facilities. are necessary for protection of equipment. The emer-
gency shutdown system shall be operable from a mini-
A843.1.1 Location of Compressor Facilities. The
mum of two locations on each deck level; that is, should
compressor facilities located on platforms should be
an offshore platform facility have more than one clearly
designed to facilitate free movement of fire fighting or
defined deck, each deck shall have a minimum of two
other emergency equipment.
shutdown locations. Blowdown piping shall extend to
A843.1.2 Enclosures. All enclosures located on an a location where the discharge of gas is not likely to
offshore platform shall be constructed of noncombusti- create a hazard to the platform facilities. Consideration
ble or limited combustible material as defined in should be given to potential entrained liquids, prevailing
NFPA 220, Chapter 2. Design of enclosures on offshore winds, and location of crew quarters if part of the plat-
platforms shall consider the loading conditions defined form facility. Under conditions of heavy liquid entrain-
in para. A841.3. ment and poor prevailing wind conditions, a separate
structure for a blowdown facility shall be considered.
A843.1.3 Exits. A minimum of two exits shall be
provided for each operating level of a compressor build- A843.3.4 Pressure-Limiting Requirements for
ing. Any elevated walkway, including engine catwalks Offshore Compression Facilities
more than 10 ft (3 m) above the deck, shall also be (c) Venting. Pressure relief valves shall be vented to
provided with two exits. The maximum distance from atmosphere such that no hazard is created. Vent lines,
any point within the compressor building to an exit common headers, and platform blowdown lines shall
shall not exceed 75 ft (23 m). Enclosure exits shall be have sufficient capacity so that they will not interfere
unobstructed and located so as to provide a convenient with the performance of the relief device.
route of escape and shall provide continuous unob-
structed passage to a place of safety. Exit doors located
A844 ON-BOTTOM STABILITY
on exterior walls shall swing outward and shall be
equipped with latches that can be readily opened from Pipeline design for lateral and vertical stability is gov-
the inside without a key. erned by sea floor bathymetry, soil characteristics, and
by hydrodynamic, seismic, and soil behavior events hav-
A843.1.5 Hazard Analysis for Offshore Compressor
ing a significant probability of occurrence during the
Stations. A hazard analysis for offshore compressor allowable stresses
life of the system. Design conditions to consider are
stations shall be conducted in accordance with
provided in the following subsections.
API RP 14J to meet the requirements of API RP 14C.
The pipeline system shall be designed to prevent hori-
A843.2 Electrical Facilities zontal and vertical movements, or shall be designed so
that any movements will be limited to values not causing
All electrical equipment and wiring installed on off- design strength to be exceeded (see section A842).
shore compression platforms shall conform to the Typical factors to be considered in the stability design
requirements of NFPA 70, if commercially available include
equipment permits. (a) wave and current forces
Electrical installations in offshore hazardous locations (b) scour and resultant spanning
as defined in NFPA 70, Chapter 5, Article 500 and that (c) liquefaction
are to remain in operation during compressor station (d) slope failure
emergency shutdown as provided in para. A843.3.3(a) Stability may be obtained by such means including,
shall be designed to conform to NFPA 70, for Class I, but not limited to, pipe submerged weight, trenching of
Division I requirements. pipe below grade, and anchoring.
The guidelines of API RP 14F should be considered When calculating hydrodynamic forces, the spatial
in electrical facility design. variance of wave forces along the length of the pipeline
may be taken into account.
A843.3 Compressor Station Equipment
Additional information on hydrostatic stability can
A843.3.3 Safety Devices be found in API RP 1111, para. 4.4.2.
(a) Emergency Shutdown Facilities. All gas compres-
sion equipment shall be provided with an emergency A844.1 Design Storm Conditions
shutdown system that will block out the gas going to Design wave and current conditions for portions of a
and from the compressor station. Operation of the emer- pipeline that will not be trenched shall be based on a
gency shutdown system shall cause the shutdown of all storm having a minimum return interval of no less than
112
ASME B31.8-2016
five times the design life or 100 yr, whichever is smaller. A844.4 Slope Failure
Portions of the pipeline system to be trenched shall be The pipeline shall be designed for slope failure in
designed for wave and current conditions based on pru- zones of known or anticipated occurrence, such as mud-
dent assessment of the period of pipe exposure. The slide zones and areas of seismic slumping. The design
most unfavorable expected combination of wave and exposure period shall be no less than the expected life
current conditions shall be used. Maximum wave and of the pipline. If it is not practical to design the pipeline
maximum current conditions do not necessarily occur system to survive the event, the pipeline shall be
simultaneously. The most unfavorable condition selec- designed for controlled breakaway with check valving
tion shall account for the timing of occurrence of the to prevent blowdown of the pipeline.
wave and current direction and magnitude.
A844.5 Soil Liquefaction
A844.2 Stability Against Waves and Currents Design for the effects of liquefaction shall be per-
formed for areas of known or expected occurrence. Soil
A844.2.1 Submerged Weight. The submerged
liquefaction normally results from cyclic wave overpres-
weight of the pipe may be designed (such as by weight
sures or seismic loading of susceptible soils. The bulk
coating) to resist or limit movement to acceptable values.
specific gravity of the pipeline shall be designed, or
Hydrodynamic forces shall be based on the wave and
alternative methods shall be selected to ensure both
current values for the design storm condition for the stress
horizontal and vertical stability.
specific location. Seismic design conditions used to predict the occur-
Wave and current directionality and concurrency shall rence of bottom liquefaction or slope failure shall have
be considered. the same recurrence interval as used for the operating
A844.2.2 Bottom Soils. The pipe-soil interaction design strength calculations for the pipeline. Occurrence
factors that are used shall be representative of the bottom of soil liquefaction due to wave overpressures shall be
conditions at the site. based on a storm return interval of no less than five
times the design life or 100 yr, whichever is smaller.
A844.2.3 Trenching. The pipeline and its appurte-
nances may be trenched below bottom grade to provide
A846 VALVES
stability. The pipeline must be designed for wave and
current stability prior to trenching. Such stability, how- Offshore transmission lines shall be equipped with
ever, need only be based on environmental conditions valves or other components to shut off the flow of gas
expected during the period of pipe exposure. to an offshore platform in an emergency.
Block valves shall be accessible and protected from
A844.2.4 Backfilling. Backfilling or other protective damage and tampering. If a blowdown valve is involved,
coverings, when necessary, shall be accomplished by it shall be located where the gas can be blown to the
using such materials and procedures to preclude dam- atmosphere without undue hazard.
age to the pipeline and coatings. Blowdown valves shall be provided so that each sec-
tion of pipeline between main line valves can be blown
A844.2.5 Anchoring. Anchoring may be used down. The sizes and capacity of the connections for
instead of or in conjunction with submerged weight blowing down the line shall be such that under emer-
to maintain stability. The anchors shall be designed to gency conditions the section of line can be blown down
withstand lateral and vertical loads expected from the as rapidly as is practicable.
design storm condition. Anchors shall be spaced to pre-
vent excessive stresses in the pipe sections between
anchors. The anchoring system and adjacent pipe shall A847 TESTING
be designed to prevent scour and resultant spanning A847.1 General Provisions
from overstressing the pipe. The effect of anchors on the
cathodic protection system shall be considered. All offshore pipelines shall be tested after installation
and prior to operation within the provisions of this
section.
A844.3 Shore Approaches
Pipe in the shore approach zone shall be trenched A847.2 Test Pressure
or bored to the depth necessary to prevent scouring, The installed pipeline system (including any SCR up
spanning, or stability problems that affect integrity and to its hang-off point) shall be hydrostatically tested to
safe operation of the pipeline during its anticipated ser- at least 1.25 times the maximum allowable operating
vice life. Seasonal variation in the near shore thickness pressure. Offshore platform piping and offshore pipeline
of sea floor sediments and shoreline erosion over the risers other than SCRs must be tested to at least 1.5 times
pipeline service life shall be considered. the maximum allowable operating pressure either before
113
ASME B31.8-2016
to the coating system, special consideration should be pattern to promote a good bond for all epoxy-based thin
given to the selection, design, and application of corro- film coatings. Welds should be inspected for irregulari-
sion control coatings, the cathodic protection system, ties that could protrude through the pipe coating, and
and other corrosion design elements. any such irregularities should be removed.
(c) Application and Inspection. The coating should be
A860.2 Evaluation of Existing Installations
applied under controlled conditions and have a high
(a) Monitoring. The operating company must rely on resistance to disbondment. Further information can be
monitoring, investigation, inspections, and corrective obtained from NACE SP0169. A holiday detector, suit-
action to control corrosion. Such activities shall be per- able for the type of coating applied, shall be used to
formed at periodic intervals sufficient to ensure that detect flaws. Flaws noted shall be repaired and retested.
adequate corrosion control is maintained. Where it is Weights or weight coating shall not damage the protec-
determined that corrosion that is taking place may be tive coating during application or installation.
detrimental to public or employee safety, the facility
(d) Coating for Weld Joints, Appurtenances, and Patching.
shall be repaired or replaced, and corrosion control mea-
sures applied or augmented. Weld joints and appurtenances shall be coated with
material that is compatible with the basic coating. A
(e) Examination When Exposed
holiday detector, designed for the type of field joint
(1) When a pipeline is lifted above water for main-
tenance or repair, the operating company shall visually material applied, may be used to detect flaws, and flaws
inspect for evidence of coating deterioration, external shall be repaired and retested.
corrosion, and where possible, the condition of any (e) Field Inspection. The pipe shall be visually
exposed anode. If excessive corrosion is present, reme- inspected prior to installation to ensure that unaccept-
dial action shall be taken as necessary. able damage has not occurred during loading, welding,
(2) If repairs are made below water, inspection for or other laying activities prior to submergence of the
evidence of external corrosion or coating deterioration pipe. Any significant damage to the coating shall be
shall be made, and necessary corrective action shall be repaired with material compatible with the pipeline
taken to maintain the corrosion protection of the coating. Care should be exercised to minimize damage
pipeline. to the coating system, particularly during laying and
trenching of the pipe.
applicable
A861 EXTERNAL CORROSION CONTROL A861.1.2 Cathodic Protection Requirements
A861.1 Submerged Installations (a) Design Criteria. An offshore facility is considered
All submerged steel pipe, valves, and related fittings to be cathodically protected when it meets the criteria
shall be externally coated and cathodically protected. All established in Section 6.2 of NACE SP0607/ISO 15589-2.
above-water piping and components shall be protected (b) Impressed Currents. Where impressed current sys-
from the particularly corrosive conditions of the salt tems are used, the system shall be designed to minimize
water atmosphere and cyclic wetting and drying. outages, and the output shall be such thatSP0115the design
A861.1.1 Coatings criterion is met. Also, consideration should be given to
(a) Coating Design. The design of coating systems for minimize the interference effect on other pipelines or
offshore installation should reflect the type of environ- structures.
ment in which the facility is to be installed. Selection of (c) Galvanic Anodes. Where galvanic anodes are used
the protective coating should be based on for protection, consideration shall be given to the quality
(1) low water absorption of the coating (i.e., the percent of exposed pipe). Also,
(2) compatibility with the type of cathodic protec- the design formula for the system should include the
tion to be applied to the system output of the anodes, the desired life of the system,
(3) compatibility with the system operating anode material, and utilization efficiency. Anodes used
temperature should be compatible with the operating temperature
(4) sufficient ductility to minimize detrimental of the pipeline and the marine environment.
cracking (d) Other. Consideration should be given to the
(5) sufficient toughness to withstand damage dur- effects on cathodic protection of variations in oxygen
ing installation content, temperature, and water/soil resistivity of the
(6) resistance to future deterioration in a sub- particular offshore environment in which the pipeline
merged environment is installed.
(7) ease of repair
(b) Cleaning and Surface Preparation. There may be A861.1.3 Electrical Isolation. Underwater pipeline
additional cleaning and surface preparation require- systems shall be electrically isolated from other metallic
ments, such as a near white metal finish and an anchor structures so that cathodic protection can be effective.
116
ASME B31.8-2016
An exception can be made when both the foreign struc- with additional protection against corrosion. This shall
ture and the pipeline are designed to be protected as a be accomplished by one or more of the following:
unit. Other general considerations include the following: (a) special coating
(a) Tie-Ins. Isolation from foreign pipelines at tie-ins (b) special protective systems and techniques
may be made by installing insulation flanges, unions, (c) other suitable measures, including selection of
or other insulating devices. When making a tie-in of a pipe material
coated line to a bare line, the two lines shall be electri-
cally isolated. A861.2.2 Surface Preparation. Coatings and other
(b) Foreign Pipeline Crossings. When crossing a foreign protective systems shall be installed on a properly pre-
pipeline, care shall be exercised to ensure adequate sepa- pared surface and in accordance with established specifi-
ration between the two lines so that the possibility for cations or manufacturer ’s recommendations. The
electrical interference is minimized. coating should resist water action, atmospheric deterio-
ration, mechanical damage, and cathodic disbondment.
(c) Pipeline Riser Support and Secondary Piping. When
installing riser piping at platforms, supporting devices A861.4 Atmospheric Corrosion Inspection
such as clamps and pipe supports shall isolate the piping
from the structure. Insulating devices shall be installed Detailed inspections shall be made periodically of all
where electrical isolation of a portion of the piping sys- piping for atmospheric corrosion. This inspection shall
tem from production piping, tanks, and other facilities is include those areas most susceptible to corrosion such
necessary to facilitate application of cathodic protection. as flanges, flange bolts, areas under pipe straps, areas
Electrical interference between electrically isolated where pipe is in contact with supports, and other places
structures shall be minimized. Wiring and piping con- where moisture collects. Where atmospheric corrosion
nections to an isolated pipeline shall also have insulation is found, prompt corrective action shall be taken. Correc-
between the pipeline and the platform. Tests shall be tive action shall consist of painting, replacement of com-
made to ensure adequate isolation, and appropriate ponents as necessary, or other action deemed
action shall be taken to ensure such isolation when appropriate by the operating company.
necessary. applicable
A861.1.4 Electrical Connections and Monitoring A862 CATHODIC PROTECTION CRITERIA
Points. Test leads shall be installed so that they are SP0115
A862.1 Criteria
mechanically secure, electrically conductive, and acces-
sible for testing. It is considered impractical to locate The criteria for cathodic protection are specified in
test leads in deep or open water. Test leads installations Section 6.2 of NACE SP0607/ISO 15589-2.
are usually limited to platforms and the pipeline
entrance to the shore. A862.3 Electrical Checks
The operating company shall take electrical readings
A861.1.7 Electrical Interference. Periodic tests shall
periodically at each test location available to ensure that
be made to ensure that electrical isolation from foreign
the cathodic protection level meets the criteria in
pipelines or other structures remains complete. Some
Section 6.2 of NACE SP0607/ISO 15589-2.
indications of electrical interference are changes in pipe-
Before each electrical test is performed, an inspection
to-electrolyte potential, changes in current magnitude
shall be made to ensure electrical continuity and that a
or direction, localized pitting, and coating breakdown.
good contact to the pipelines is made by the test
When new foreign pipelines are laid in the vicinity of
connection.
existing lines, inspections shall be made to ensure electri-
cal isolation in accordance with para. 861.1.3(a). If electri-
cal isolation cannot be attained, measures shall be taken A864 INTERNAL CORROSION CONTROL
to minimize electrical interference. Electrical isolation
from the platform should be checked and maintained A864.1 General
unless the system was specifically designed to be jointly The design and maintenance of offshore pipeline facil-
protected. ities that may carry natural gas containing carbon diox-
ide, chlorides, hydrogen sulfide, organic acids, solids or
A861.2 Above-Water Atmospheric Protection
precipitates, sulfur-bearing compounds, oxygen, or free
A861.2.1 Coatings. The splash zone area, where the water require special consideration for the control of
pipeline is intermittently wet and dry, shall be designed internal corrosion.
117
Chapter IX pertains only to gas
pipeline service that contains hydrogen
sulfide levels defined as “sour gas” in ASME B31.8-2016
this Chapter.
Chapter IX
Sour Gas Service
B800 SOUR GAS SERVICE lattice of the substance rather than through a geometrical
leak (molecular diameters versus hole dimension).
B801 GENERAL
hardness: resistance of metal to plastic deformation usu-
Chapter IX pertains only to gas pipeline service that
ally by indentation. For carbon steels, hardness can be
contains hydrogen sulfide levels defined as “sour gas”
related to the ultimate tensile strength.
in this Chapter. This Chapter is organized to parallel
the numbering and content of the first six chapters of Brinell Hardness Number (BHN): a value to express the
the Code. All provisions of the first six chapters of the hardness of metals obtained by forcing a hard steel ball
Code are also requirements of this Chapter unless specif- of specified diameter into the metal under a specified
ically modified herein. Paragraph headings follow those load. For the standard 3 000-kg load, numbers range
in the first six chapters with the prefix “B.” from 81 to 945.
If a paragraph appearing in Chapters I through VI Microhardness: any hardness measurement using an
does not have a corresponding paragraph in this indentor load less than 10 kg.
Chapter, the provisions apply to sour gas service without Rockwell Hardness: a series of hardness scales for
modification. If a paragraph in this Chapter has no cor- metals.
responding paragraph in Chapters I through VI, the (a) The Rockwell “C” (HRC) scale uses a cone dia-
provisions apply to sour gas only. mond indentor and a load of 150 kg. The scale starts at
20 for soft steels and reaches a maximum of about 67
for very hard alloys.
B802 SCOPE AND INTENT
(b) The Rockwell “B” (HRB) scale uses a hard metal
B802.1 Scope ball indentor and starts at 0 for extremely soft metals
This Chapter of the Code covers the design, material and reaches a maximum of 100 for soft steels and alloys.
requirements, fabrication, installation, inspection, test- HRB 100 p HRC 20.
ing, and safety aspects of operation and maintenance of Vickers Hardness HV 10: a value achieved by use of a
sour gas systems. diamond pyramid indentor with a load of 10 kg.
B802.2 Intent heat-affected zone (HAZ): the portion of the base metal
that was not melted during brazing, cutting, or welding,
The intent of this Chapter is to provide adequate but whose microstructure and properties were affected
requirements for the safe and reliable design, installa- by the heat of these processes.
tion, operation, and maintenance of sour gas service
pipeline systems. Requirements of this Chapter supple- hydrogen blistering: the formation of subsurface planar
ment the requirements of the remainder of this Code. cavities, called hydrogen blisters, in a metal resulting
It is not the intent of this Chapter to be all inclusive. from excessive internal hydrogen pressure. Growth of
Provisions must be made for special considerations that near-surface blisters in low-strength metals usually
are not specifically addressed. This Chapter is not results in surface bulges.
intended to prevent the development and application hydrogen-induced cracking (HIC): a cracking mechanism
of new equipment and technology. Such activity is of susceptible materials caused by atomic hydrogen dif-
encouraged as long as the safety and reliability require- fusion in the metal. The atomic hydrogen usually is
ments of this Code are satisfied. created by the corrosive reaction of hydrogen sulfide on
steel in the presence of water.
B803 SOUR GAS TERMS AND DEFINITIONS hydrogen sulfide (H2S): a toxic gaseous impurity found
chloride stress corrosion cracking: cracking of a metal under in some well gas streams. It also can be generated in
the combined action of tensile stress and corrosion in situ as a result of microbiologic activity.
the presence of chlorides and an electrolyte (usually microbiologically influenced corrosion (MIC): corrosion or
water). deterioration of metals resulting from the metabolic
diffusion: the flow of the gas through a substance in activity of microorganisms. Such corrosion may be either
which the gas actually migrates through the crystal initiated or accelerated, or both, by microbial activity.
118
This section concerns the welding of pipe in
sour gas service in both wrought and cast steel
materials. ASME B31.8-2016
microstructure: the grain size and morphology of metals B821.4 Weld Acceptance
and alloys as revealed after polishing and etching; char-
The standards of acceptability for welds of piping
acterized by grains or regions that exhibit distinct phases
systems as established in API 1104 or BPV Code, Section
of solid solutions of constituent elements.
IX, Division 1 shall be used; however, additional require-
partial pressure: the contribution of a single component, ments for hardness and residual stress should be con-
such as hydrogen sulfide, in a mixture of gases to the sidered.
total pressure of the mixture, determined by multiplying
the mol fraction (mol percent divided by 100) of hydro-
gen sulfide in the gas by the total system pressure. B822 PREPARATION FOR WELDING
radius of exposure (ROE): when dealing with sour gas, the B822.3 Seal Welds
distance from a point of release at which the hydrogen
Seal welds shall have a separate qualified procedure.
sulfide concentrations reached a specified level (fre-
quently 100 ppm or 500 ppm) determined by dispersion
B822.4 Cleaning
calculations.
Pipe that has been in sour gas service shall be thor-
sour gas: gas containing hydrogen sulfide (H2S) at 65 psia
oughly cleaned to bright metal on the inside surfaces
(450 kPa) or greater at a partial pressure of 0.05 psia
(350 Pa) or greater. See NACE MR0175/ISO 15156, titled back 1 in. (25 mm) from the weld bevel.
Petroleum and natural gas industries — Materials for use in
H2S-containing environments in oil and gas production.
B823 QUALIFICATION OF PROCEDURES AND
sulfide stress cracking (SSC): a corrosion-related cracking WELDERS
mechanism caused by exposure of susceptible materials
to sulfide ions in the presence of free water. The requirements of para. 823.1 shall not apply to this
section.
119
This section concerns the design,
installation, and testing of pipe in sour
gas service. ASME B31.8-2016
120
ASME B31.8-2016
B861 EXTERNAL CORROSION CONTROL FOR B867 STRESS CORROSION AND OTHER
STEEL PIPELINES PHENOMENA
Sour gas lines, particularly when combined with car-
B861.1 Buried/Submerged Installations bon dioxide and produced salt water, can suffer from
B861.1.2 Cathodic Protection Requirements. Unless several corrosion-related phenomena.
it can be demonstrated by tests or experience that (a) Hydrogen-Related Problems. The corrosion reaction
cathodic protection is not needed, all buried or sub- in the presence of the sulfide ion permits a high amount
merged facilities with insulating type coatings, except of liberated hydrogen atoms to enter the steel. The
facilities installed for a limited service life, shall be hydrogen causes many problems that have been given
cathodically protected as soon as feasible following different names:
installation, except that minor replacements or exten- (1) Sulfide stress cracking (SSC) occurs when the
sions shall be protected as covered by para. 860.3. alloys are too hard and/or too highly stressed in the
Facilities installed for a limited service life need not presence of corrosion with sour gas. NACE MR0175/
be cathodically protected if it can be demonstrated that ISO 15156 outlines all of the acceptable materials combi-
the facility will not experience corrosion that will cause nations to resist this type of cracking.
it to be harmful to the public or environment. Cathodic (2) Hydrogen-induced cracking (HIC) occurs when
hydrogen causes inclusions in the steel to delaminate.
applicable
protection systems shall be designed to protect the bur-
Multiple shear cracks then develop to link the delamin-
ied or submerged system in its entirety.
ations creating a stair step crack system. Use of HIC
A facility is considered to be cathodically protected
resistant materials should be considered for sour gas
when it meets one or more of the criteria established in
service.
Mandatory Appendix K.
NACE SP0169 (3) Stress-oriented hydrogen-induced cracking
Use of cathodic protection is encouraged to protect
(SOHIC) is another variant of HIC. SOHIC is HIC
buried sour gas facilities. enhanced by high-tensile stress.
(4) Hydrogen blistering consists of hydrogen atoms
diffusing inside the steel to delaminated areas and
B864 INTERNAL CORROSION CONTROL recombining to form molecules of hydrogen gas. The
resulting pressure can create large blisters on either the
B864.1 General
inside or outside surfaces of the steel.
Sour gas facilities shall be assumed to be internally (b) Chloride stress corrosion cracking is caused by
corrosive unless proven by experience to be otherwise. chlorides in the produced water. Austenitic stainless
Water dewpoint control frequently is used as a corrosion steels are particularly prone to this type of cracking. The
control method. Upset conditions or operational changes sulfide ion has a synergistic effect with the chloride ion.
may make this control method ineffective. The use of The net result is the occurrence of cracking at lower
inhibitors is also common. temperatures and at lower chloride concentrations than
normally expected. Except for small low-stressed parts
B864.2 Design of New Installations such as thermowells, use of alloys not resistant to chlo-
ride stress cracking above 140°F (60°C) is discouraged
New installations should be designed with in wet sour gas systems.
(a) suitable dedicated fittings for corrosion inhibitor (c) Microbiologically Induced Corrosion (MIC).
injection Microbiologic activity can create severe pitting-type cor-
(b) suitable dedicated fittings and valves to insert and rosion and hydrogen-related cracking in sour gas lines.
retrieve corrosion measuring devices such as probes and Use of appropriate biocides and monitoring may be
coupons needed.
124
ASME B31.8-2016
125
ASME B31.8-2016
Petroleum Gas, Hazardous Liquids, Highly Volatile *ASME B16.40-2013, Manually Operated Thermoplastic
Liquids, or Carbon Dioxide Gas Shutoffs and Valves in Gas Distribution Systems
API RP 1111 (fourth edition, December 2009, including *ASME B16.42-2011, Ductile Iron Pipe Flanges and
Errata through May 2011), Design, Construction, Flanged Fittings: Classes 150 and 300
Operation, and Maintenance of Offshore *ASME B16.47-2011, Large Diameter Steel Flanges: NPS
Hydrocarbon Pipelines (Limit State Design) 26 ThroughAPINPS 60 Metric/Inch
RP 1162 Standard
(Second Edition, December
*API Spec 6A/ISO 10423:2009 (Modified) (20th edition, *ASME B16.49-2012, Factory-Made, Wrought Steel,
2010, Reaffirmed October 2015),
October 2010, including Errata and Addenda through Buttwelding
Recommended Practice, Public Awareness and
Induction Bends for Transportation
March 2013), Specification for Wellhead and Distribution Systems
Programs for Pipeline Operators
Christmas Tree Equipment *ASME B18.2.1-2012, Square, Hex, Heavy Hex, and
*API Spec 6D/ISO 14313:2007 (23rd edition, April 2008, Askew Head Bolts and Hex, Heavy Hex, Hex Flange,
including Errata and Addenda through October 2012), Lobed Head, and Lag Screws (Inch Series)
Specification for Pipeline Valves *ASME B18.2.2-2010, Nuts for General Applications:
*API Spec 6DSS/ISO 14723:2009 (second edition, Machine Screw Nuts, Hex, Square, Hex Flange, and
December 2009), Specification for Subsea Pipeline Coupling Nuts (Inch Series)
Valves *ASME B31G-2012, Manual for Determining the
*API Spec 17D/ISO 13628-4 (second edition, May 2011, Remaining Strength of Corroded Pipelines:
including Errata through June 2013), Design and Supplement to ASME B31 Code for Pressure Piping
Operation of Subsea Production Systems — Subsea *ASME B31Q-2010, Pipeline Personnel Qualification
Wellhead and Tree Equipment *ASME B31.1-2012, Power Piping
*API Spec 17J/ISO 13628-2:2006 (third edition, July 2008, *ASME B31.3-2012, Process Piping
including Errata through August 2010), Specification *ASME B31.4-2012, Pipeline Transportation Systems for
for Unbonded Flexible Pipe Liquids and Slurries
API Std 1104 (21st edition, September 2013), Welding of *ASME B31.8S-2012, Managing System Integrity of Gas
Pipelines and Related Facilities Pipelines
Publisher: American Petroleum Institute (API), *ASME B36.10M-2004 (R2010), Welded and Seamless
1220 L Street, NW, Washington, DC 20005 Wrought Steel Pipe
(www.api.org) *ASME BPV Code: Section II, Materials; Section VIII,
Rules for Construction of Pressure Vessels; and Section
IX, Qualification Standard for Welding, Brazing, and
A-3 ASME Fusing Procedures; Welders; Brazers; and Welding,
Brazing, and Fusing Operators (2013)
*ASME B1.1-2003 (R2008), Unified Inch Screw Threads ASME SI-1-1982, ASME Orientation and Guide for Use
(UN and UNR Thread Form) of SI (Metric) Units
*ASME B1.20.1-1983 (R2006), Pipe Threads, General ASME PCC-2-2011, Repair of Pressure Equipment and
Purpose (Inch) Piping
*ASME B16.1-2010, Gray Iron Pipe Flanges and Flanged IPC2002-27124, “Development of Acceptance Criteria
Fittings: Classes 25, 125, and 250 for Mild Ripples in Pipeline Field Bends,” Proceedings
*ASME B16.5-2013, Pipe Flanges and Flanged Fittings: of IPC 2002, Fourth International Pipeline Conference,
NPS 1⁄2 Through NPS 24 Metric/Inch Standard September 2002
*ASME B16.9-2012, Factory-Made Wrought Buttwelding
Publisher: The American Society of Mechanical
Fittings
Engineers (ASME), Two Park Avenue, New York,
*ASME B16.11-2011, Forged Fittings, Socket-Welding NY 10016-5990 (www.asme.org)
and Threaded
*ASME B16.20-2012, Metallic Gaskets for Pipe Flanges:
Ring-Joint, Spiral-Wound, and Jacketed A-4 ASTM
*ASME B16.24-2011, Cast Copper Alloy Pipe Flanges ASTM A53/A53M-12, Standard Specification for Pipe,
and Flanged Fittings: Classes 150, 300, 600, 900, 1500, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and 2500 and Seamless
*ASME B16.33-2012, Manually Operated Metallic Gas ASTM A105/A105M-12, Standard Specification for
Valves for Use in Gas Piping Systems up to 175 psi Carbon Steel Forgings for Piping Applications
(Sizes NPS 1⁄2 Through NPS 2) ASTM A106/A106M-11, Standard Specification for
*ASME B16.34-2013, Valves — Flanged, Threaded, and Seamless Carbon Steel Pipe for High-Temperature
Welding End Service
*ASME B16.38-2012, Large Metallic Valves for Gas ASTM A134-96(R2012), Standard Specification for Pipe,
Distribution: Manually Operated, NPS 21⁄2 (DN 65) to Steel, Electric-Fusion (Arc)-Welded (Sizes NPS 16 and
NPS 12 (DN 300), 125 psig (8.6 bar) Maximum Over)
126
ASME B31.8-2016
ASTM A135/A135M-09, Standard Specification for ASTM D696-08⑀1, Standard Test Method for Coefficient
Electric-Resistance-Welded Steel Pipe of Linear Thermal Expansion of Plastics Between
ASTM A139/A139M-04(R2010), Standard Specification −30°C and 30°C With a Vitreous Silica Dilatometer
for Electric-Fusion (Arc)-Welded Steel Pipe (Sizes ASTM D1598-02(R2009), Standard Test Method for
NPS 4 and Over) Time-to-Failure of Plastic Pipe Under Constant
ASTM A193/A193M-12b, Standard Specification for Internal Pressure
Alloy-Steel and Stainless Steel Bolting Materials for *ASTM D2513-13, Standard Specification for
High Temperature or High-Pressure Service and Polyethylene (PE) Gas Pressure Pipe, Tubing, and
Other Special Purpose Applications Fittings
ASTM A194/A194M-12a, Standard Specification for *ASTM D2517-06(R2011), Standard Specification for
Carbon and Alloy Steel Nuts for Bolts for High Reinforced Epoxy Resin Gas Pressure Pipe and
Pressure or High Temperature Service, or Both Fittings
ASTM A307-12, Standard Specification for Carbon Steel *ASTM D2837-11, Standard Test Method for Obtaining
Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Hydrostatic Design Basis for Thermoplastic Pipe
Strength Materials or Pressure Design Basis for Thermoplastic
ASTM A320/A320M-11a, Standard Specification for Pipe Products
Alloy-Steel and Stainless Steel Bolting for *ASME F1041-02(R2008), Standard Guide for Squeeze-
Low-Temperature Service Off of Polyolefin Gas Pressure Pipe and Tubing
ASTM A333/A333M-11, Standard Specification for *ASTM F1563-01(R2011), Standard Specification for
Seamless and Welded Steel Pipe for Low-Temperature Tools to Squeeze-Off Polyethylene (PE) Gas Pipe or
*ASTM F1802-04(R2010) Standard Test Method
Service Tubing
for Performance
ASTM A354-11, Testing of Excess
Standard Flow Valvesfor Quenched
Specification ASTM F2817-13, Standard Specification for Poly (Vinyl
*ASTM F2138-12
and TemperedStandard
AlloySpecification
Steel Bolts, for
Studs, and Other Chloride) (PVC) Gas Pressure Pipe and Fittings for
ExcessExternally
Flow Valves for Natural
Threaded Gas Service
Fasteners Maintenance or Repair
ASTM A372/A372M-12, Standard Specification for ASTM F2945-15, Standard Specification for Polyamide
Carbon and Alloy Steel Forgings for Thin-Walled 11 Gas Pressure Pipe, Tubing, and Fittings
Pressure Vessels Publisher: American Society for Testing and Materials
ASTM A381-96(R2012), Standard Specification for (ASTM International), 100 Barr Harbor Drive, P.O.
Metal-Arc-Welded Steel Pipe for Use With High- Box C700, West Conshohocken, PA 19428-2959
Pressure Transmission Systems (www.astm.org)
ASTM A395/A395M-99(R2009), Standard Specification
for Ferritic Ductile Iron Pressure-Retaining Castings
for Use at Elevated Temperatures A-5 AWS
ASTM A449-10, Standard Specification for Hex Cap *AWS A3.0M/A3.0:2010, Standard Welding Terms and
Screws, Bolts and Studs, Steel, Heat Treated, 120/105/ Definitions, Including Terms for Adhesive Bonding,
90 ksi Minimum Tensile Strength, General Use Brazing, Soldering, Thermal Cutting, and Thermal
ASTM A671/A671M-10, Standard Specification for Spraying
Electric-Fusion-Welded Steel Pipe for Atmospheric *AWS D3.6M:2010, Underwater Welding Code
and Lower Temperatures
Publisher: American Welding Society (AWS), 8669 NW
ASTM A672/A672M-09, Standard Specification for
36th Street, No. 130, Miami, FL 33166 (www.aws.org)
Electric-Fusion-Welded Steel Pipe for High-Pressure
Service at Moderate Temperatures
ASTM A691/A691M-09, Standard Specification for A-6 AWWA
Carbon and Alloy Steel Pipe, Electric-Fusion-Welded
for High-Pressure Service at High Temperatures ANSI A21.14-1979, Ductile-Iron Fittings 3-Inch Through
ASTM A984/A984M-03(R2009), Standard Specification 24-Inch for Gas2
for Steel Line Pipe, Black, Plain-End, Electric- ANSI A21.52-1991, Ductile-Iron Pipe, Centrifugally
Resistance-Welded Cast, for Gas2
ASTM A1005/A1005M-00(R2010), Standard *ANSI/AWWA C111/A21.11-12, Rubber-Gasket Joints
Specification for Steel Line Pipe, Black, Plain-End, for Ductile-Iron Pressure Pipe and Fittings
Longitudinal and Helical Seam, Double Submerged- *ANSI/AWWA C150/A21.50-08, Thickness Design of
Arc Welded Ductile-Iron Pipe
ASTM A1006/A1006M-00(R2010), Standard AWWA C101-1976(R1977), Thickness Design of Cast
Specification for Steel Line Pipe, Black, Plain-End, Iron Pipe2
Laser Beam Welded
ASTM B88-09, Standard Specification for Seamless 2
This publication has been superseded, withdrawn, or is no
Copper Water Tube longer in print.
127
ASME B31.8-2016
Publisher: American Water Works Association (AWWA), MSS SP-25-2008, Standard Marking System for Valves,
6666 West Quincy Avenue, Denver, CO 80235 Fittings, Flanges, and Unions
(www.awwa.org) MSS SP-44-2010 (including May 2011 errata), Steel
Pipeline Flanges
MSS SP-70-2011, Gray Iron Gate Valves, Flanged and
A-7 CGA
Threaded Ends
Best Practices Guide (version 10.0, 2013) MSS SP-71-2011, Gray Iron Swing Check Valves, Flanged
Publisher: Common Ground Alliance (CGA), 2200 and Threaded Ends
Wilson Boulevard, Suite 102-172, Arlington, VA 22201 MSS SP-75-2008, Specification for High-Test Wrought
(www.commongroundalliance.com) Butt Welding Fittings
MSS SP-115-2010 Excess Flow Valves, 1 1/4 MSS SP-78-2011, Gray Iron Plug Valves, Flanged and
NPS
A-8andEPRI
Smaller, for Natural Gas Service Threaded Ends
Publisher: Manufacturers Standardization Society of the
EPRI EL-3106 (1983) (also published as PRCI-AGA- Valve and Fittings Industry, Inc. (MSS), 127 Park
L51418), Power Line-Induced AC Potential on Natural Street, NE, Vienna, VA 22180 (www.msshq.org)
Gas Pipelines for Complex Rights-of-Way
Configurations
Publisher: Electric Power Research Institute (EPRI),
A-13 NACE
3420 Hillview Avenue, Palo Alto, CA 94304
(www.epri.com) *ANSI/NACE MR0175/ISO 15156:2009, Petroleum and
Natural Gas Industries — Materials for Use in H2S-
A-9 GPA Containing Environments in Oil and Gas Production,
Parts 1, 2, and 3 (including all Technical Circulars
GPA Plant Operations Test Manual, Section C, Test for
20132011)
through
Hydrogen Sulfide in LPG and Gases (Tutweiler NACE Corrosion Data Survey (1985)2
Method) NACE SP0169-2007, Control of External Corrosion on
GPA Standard 2265-68, Determination of Hydrogen Underground or Submerged Metallic Piping Systems
Sulfide and Mercaptan Sulfur in Natural Gas 2012
NACE SP0177-2007, Mitigation of Alternating Current
(Cadmium Sulfate-Iodometric Titration Method) and Lightning Effects on Metallic Structures and
Publisher: Gas Processors Association (GPA), Sixty Sixty Corrosion Control Systems
American Plaza, Suite 700, Tulsa, OK 74135 *NACE SP0607-2007/ISO 15589-2:2004 (Modified),
(www.gpaglobal.org) Petroleum and Natural Gas Industries — Cathodic
, petrochemical
Protection of Pipeline Transportation Systems —
A-10 GTI Offshore Pipelines
GRI-00/0154 (2000), Design Guide for Polyethylene Gas Publisher: National Association of Corrosion Engineers
Part 2,
(NACE International), 15835 Park Ten Place, Houston,
Pipes Across Bridges
GRI-91/0284 (1991), Guidelines for Pipelines Crossing TX 77084-4906 (www.nace.org)
Highways2
Publisher: Gas Technology Institute (GTI), 1700 South
Mount Prospect Road, Des Plaines, IL 60018 A-14 NFPA
(www.gastechnology.org)
*NFPA 10-2013, Standard for Portable Fire Extinguishers
*NFPA 30-2012, Flammable and Combustible Liquids
A-11 IEEE Code
*IEEE/ASTM SI 10-2010, American National Standard *NFPA 58-2013, Liquefied Petroleum Gas Code
for Metric Practice *NFPA 59-2012, Utility LP-Gas Plant Code
*NFPA 59A-2013, Standard for the Production, Storage,
Publisher: Institute of Electrical and Electronics
and Handling of Liquefied Natural Gas (LNG)
Engineers, Inc. (IEEE), 445 Hoes Lane, Piscataway, NJ
*NFPA 70-2013, National Electrical Code (including
08854 (www.ieee.org)
Amendment 1)
*NFPA 220-2012, Standard on Types of Building
A-12 MSS Construction
MSS SP-6-2012, Standard Finishes for Contact Faces of Publisher: National Fire Protection Association (NFPA),
Pipe Flanges and Connecting-End Flanges of Valves 1 Batterymarch Park, Quincy, MA 02169
and Fittings (www.nfpa.org)
128
ASME B31.8-2016
129
Attachment B
Item 16-301
AGA Catalog No. XR0603 (October 2006), Plastic Pipe AGA Catalog No. XR0603 (October 2006), Plastic Pipe
Manual for Gas Service Manual for Gas Service
*ANSI Z223.1/NFPA 54 (2012), National Fuel Gas Code *ANSI Z223.1/NFPA 54 (20122015), National Fuel Gas
*ANSI/GPTC Z380.1 (2012, including Addenda 1 through Code
3), GPTC Guide for Gas Transmission and Distribution *ANSI/GPTC Z380.1 (20122015, including Addenda 1
Piping Systems through 3), GPTC Guide for Gas Transmission and
Gas Piping Technology Committee’s Guide Material Distribution Piping Systems
Appendix G-192-15, Design of Uncased Pipeline Gas Piping Technology Committee’s Guide Material
Crossings of Highways and Railroads (2009) Appendix G-192-15, Design of Uncased Pipeline
Publisher: American Gas Association (AGA), 400 North Crossings of Highways and Railroads (2009)
Capitol Street, NW, Washington, DC 20001 Publisher: American Gas Association (AGA), 400 North
(www.aga.org) Capitol Street, NW, Washington, DC 20001
(www.aga.org)
A-2 API A-2 API
*API Spec 5L (45th Edition, December, 2012), Specification *API Spec 5L (45th Edition, December, 2012, including
for Line Pipe1 Errata through April 2015), Specification for Line Pipe1
*API Manual of Petroleum Measurement Standards (second *API Manual of Petroleum Measurement Standards (second
edition, February 1, 2013), Chapter 21 — Flow edition, February 1, 2013), Chapter 21 — Flow
Measurement Using Electronic Metering Systems, Section Measurement Using Electronic Metering Systems, Section
1 — Electronic Gas Measurement 1 — Electronic Gas Measurement
API RP 2A-WSD (21st edition, December 2000, including API RP 2A-WSD (21st edition, December 2000, including
Errata and Supplements through October 2007) Errata and Supplements through October 2007 22nd
(reaffirmed 2010), Recommended Practice for Planning, Edition, November 2014) (reaffirmed 2010),
Designing and Constructing Fixed Offshore Platforms — Recommended Practice for Planning, Designing and
Working Stress Design Constructing Fixed Offshore Platforms — Working Stress
API RP 5L1 (seventh edition, September 2009), Design
Recommended Practice for Railroad Transportation of API RP 5L1 (seventh edition, September 2009, reaffirmed
Line Pipe May 2015) Recommended Practice for Railroad
*API RP 5LW (third edition, September 2009), Transportation of Line Pipe
Recommended Practice for Transportation of Line Pipe on *API RP 5LW (third edition, September 2009, reaffirmed
Barges and Marine Vessels May 2015), Recommended Practice for Transportation of
API RP 14C (seventh edition, March 2001, reaffirmed Line Pipe on Barges and Marine Vessels
March 2007), Recommended Practice for Analysis, API RP 14C (seventh edition, March 2001, reaffirmed
Design, Installation, and Testing of Basic Surface Safety March 2007), Recommended Practice for Analysis,
Systems for Offshore Production Platforms Design, Installation, and Testing of Basic Surface Safety
*API RP 14E (fifth edition, October 1991, reaffirmed March Systems for Offshore Production Platforms
2007), Recommended Practice for the Design and *API RP 14E (fifth edition, October 1991, reaffirmed March
Installation of Offshore Production Platform Piping 2007 January 2013), Recommended Practice for the
Systems Design and Installation of Offshore Production Platform
*API RP 14F (fifth edition, July 2008), Recommended Piping Systems
Practice for Design, Installation, and Maintenance of *API RP 14F (fifth edition, July 2008, reaffirmed April
Electrical Systems for Fixed and Floating Offshore 2013), Recommended Practice for Design, Installation,
Petroleum Facilities for Unclassified and Class I, Division and Maintenance of Electrical Systems for Fixed and
1 and Division 2 Locations Floating Offshore Petroleum Facilities for Unclassified
API RP 14J (second edition, May 2001, reaffirmed March and Class I, Division 1 and Division 2 Locations
2007), Recommended Practice for Design and Hazards API RP 14J (second edition, May 2001, reaffirmed March
Analysis for Offshore Production Facilities 2007 January 2013), Recommended Practice for Design
and Hazards Analysis for Offshore Production Facilities
NOTES: (1) Underline and blue indicates revised and new text. 1 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
*API RP 17B/ISO 13628-11:2007 (fourth edition, July 2008, *API RP 17B/ISO 13628-11:2007 (fourth edition, July 2008,
including Technical Corrigendum 1), Recommended including Technical Corrigendum 1 (fifth edition, May
Practice for Flexible Pipe 2014), Recommended Practice for Flexible Pipe
API RP 80, (1st Edition, April 2000), Guidelines for the API RP 80, (1st Edition, April 2000, reaffirmed January
Definition of Onshore Gas Gathering Lines 2013), Guidelines for the Definition of Onshore Gas
API RP 1102 (seventh edition, December 2007, including Gathering Lines
Errata through September 2012), Steel Pipelines Crossing API RP 1102 (seventh edition, December 2007, including
Railroads and Highways Errata through September 2012 March 2014, reaffirmed
*API RP 1110 (sixth edition, February 2013), December 2012), Steel Pipelines Crossing Railroads and
Recommended Practice for the Pressure Testing of Steel Highways
Pipelines for the Transportation of Gas, Petroleum Gas, *API RP 1110 (sixth edition, February 2013),
Hazardous Liquids, Highly Volatile Liquids, or Carbon Recommended Practice for the Pressure Testing of Steel
Dioxide Pipelines for the Transportation of Gas, Petroleum Gas,
API RP 1111 (fourth edition, December 2009, including Hazardous Liquids, Highly Volatile Liquids, or Carbon
Errata through May 2011) Design, Construction, Dioxide
Operation, and Maintenance of Offshore Hydrocarbon API RP 1111 (fourth edition, December 2009, including
Pipelines (Limit State Design) Errata through May 2011 fifth edition, September 2015)
*API Spec 6A/ISO 10423: 2009 (Modified) (20th edition, Design, Construction, Operation, and Maintenance of
October 2010, including Errata and Addenda through Offshore Hydrocarbon Pipelines (Limit State Design)
March 2013), Specification for Wellhead and Christmas *API Spec 6A/ISO 10423: 2009 (Modified) (20th edition,
Tree Equipment October 2010, including Errata and Addenda through
*API Spec 6D/ISO 14313:2007 (23rd edition, April 2008, March 2013 February 2016), Specification for Wellhead
including Errata and Addenda through October 2012), and Christmas Tree Equipment
Specification for Pipeline Valves *API Spec 6D/ISO 14313:2007 (23rd edition, April 2008,
*API Spec 6DSS/ISO 14723:2009 (second edition, 24th edition, August 2014 including Errata and Addenda
December 2009), Specification for Subsea Pipeline Valves through October 2012 June 2016), Specification for
*API Spec 17D/ISO 13628-4 (second edition, May 2011, Pipeline and Piping Valves
including Errata through June 2013), Design and *API Spec 6DSS/ISO 14723:2009 (second edition,
Operation of Subsea Production Systems—Subsea December 2009), Specification for Subsea Pipeline Valves
Wellhead and Tree Equipment *API Spec 17D/ISO 13628-4 (second edition, May 2011,
*API Spec 17J/ISO 13628-2:2006 (third edition, July 2008, including Errata and Addenda through June 2013 October
including Errata through August 2010), Specification for 2015), Design and Operation of Subsea Production
Unbonded Flexible Pipe Systems—Subsea Wellhead and Tree Equipment
API Std 1104 (21st edition, September 2013), Welding of *API Spec 17J/ISO 13628-2:2006 (third edition, July 2008,
Pipelines and Related Facilities including Errata through August 2010 (4th edition, May
Publisher: American Petroleum Institute (API), 1220 L 2014), Specification for Unbonded Flexible Pipe
Street, NW, Washington, DC 20005-4070 (www.api.org) API Std 1104 (21st edition, September 2013, including
Errata and Addenda through May 2016), Welding of
Pipelines and Related Facilities
Publisher: American Petroleum Institute (API), 1220 L
Street, NW, Washington, DC 20005-4070 (www.api.org)
NOTES: (1) Underline and blue indicates revised and new text. 2 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
*ASME B1.1-2003 (R2008), Unified Inch Screw Threads *ASME B1.1-2003 (R2008), Unified Inch Screw Threads
(UN and UNR Thread Form) (UN and UNR Thread Form)
*ASME B1.20.1-1983 (R2006), Pipe Threads, General *ASME B1.20.1-19832013 (R2006), Pipe Threads, General
Purpose (Inch) Purpose (Inch)
*ASME B16.1-2010, Gray Iron Pipe Flanges and Flanged *ASME B16.1-20102015, Gray Iron Pipe Flanges and
Fittings: Classes 25, 125, and 250 Flanged Fittings: Classes 25, 125, and 250
*ASME B16.5-2013, Pipe Flanges and Flanged Fittings NPS *ASME B16.5-2013, Pipe Flanges and Flanged Fittings NPS
½ Through NPS 24 Metric/Inch Standard ½ Through NPS 24 Metric/Inch Standard
*ASME B16.9-2012, Factory-Made Wrought Buttwelding *ASME B16.9-2012, Factory-Made Wrought Buttwelding
Fittings Fittings
*ASME B16.11-2011, Forged Fittings, Socket-Welding and *ASME B16.11-2011, Forged Fittings, Socket-Welding and
Threaded Threaded
*ASME B16.20-2012, Metallic Gaskets for Pipe Flanges: *ASME B16.20-2012, Metallic Gaskets for Pipe Flanges:
Ring-Joint, Spiral-Wound, and Jacketed Ring-Joint, Spiral-Wound, and Jacketed
*ASME B16.24-2011, Cast Copper Alloy Pipe Flanges and *ASME B16.24-2011, Cast Copper Alloy Pipe Flanges and
Flanged Fittings: Classes 150, 300, 600, 900, 1500, and Flanged Fittings: Classes 150, 300, 600, 900, 1500, and
2500 2500
*ASME B16.33-2012, Manually Operated Metallic Gas *ASME B16.33-2012, Manually Operated Metallic Gas
Valves for Use in Gas Piping Systems up to 125 psi (Sizes Valves for Use in Gas Piping Systems up to 125 psi (Sizes
NPS ½ Through NPS 2) NPS ½ Through NPS 2)
*ASME B16.34-2013, Valves — Flanged, Threaded, and *ASME B16.34-2013, Valves — Flanged, Threaded, and
Welding End) Welding End)
*ASME B16.38-2012, Large Metallic Valves for Gas *ASME B16.38-2012, Large Metallic Valves for Gas
Distribution: Manually Operated, NPS 2½ (DN 65) to NPS Distribution: Manually Operated, NPS 2½ (DN 65) to NPS
12 (DN 300), 125 psig (8.6 bar) Maximum 12 (DN 300), 125 psig (8.6 bar) Maximum
*ASME B16.40-2013, Manually Operated Thermoplastic *ASME B16.40-2013, Manually Operated Thermoplastic
Gas Shutoffs and Valves in Gas Distribution Systems Gas Shutoffs and Valves in Gas Distribution Systems
*ASME B16.42-2011, Ductile Iron Pipe Flanges and *ASME B16.42-2011, Ductile Iron Pipe Flanges and
Flanged Fittings: Classes 150 and 300 Flanged Fittings: Classes 150 and 300
*ASME B16.47-2011, Large Diameter Steel Flanges: NPS *ASME B16.47-2011, Large Diameter Steel Flanges: NPS
26 Through NPS 60 Metric/Inch Standard 26 Through NPS 60 Metric/Inch Standard
*ASME B16.49-2012, Factory-Made, Wrought Steel, *ASME B16.49-2012, Factory-Made, Wrought Steel,
Buttwelding Induction Bends for Transportation and Buttwelding Induction Bends for Transportation and
Distribution Systems Distribution Systems
*ASME B18.2.1-2012, Square, Hex, Heavy Hex, and Askew *ASME B18.2.1-2012 (including Errata July 2013), Square,
Head Bolts and Hex, Heavy Hex, Hex Flange, Lobed Hex, Heavy Hex, and Askew Head Bolts and Hex, Heavy
Head, and Lag Screws (Inch Series) Hex, Hex Flange, Lobed Head, and Lag Screws (Inch
*ASME B18.2.2-2010, Nuts for General Applications: Series)
Machine Screw Nuts, Hex, Square, Hex Flange, and *ASME B18.2.2-20102015, Nuts for General Applications:
Coupling Nuts (Inch Series) Machine Screw Nuts, Hex, Square, Hex Flange, and
*ASME B31G-2012, Manual for Determining the Coupling Nuts (Inch Series)
Remaining Strength of Corroded Pipelines: Supplement to *ASME B31G-2012, Manual for Determining the
ASME B31 Code for Pressure Piping Remaining Strength of Corroded Pipelines: Supplement to
*ASME B31Q-2010, Pipeline Personnel Qualification ASME B31 Code for Pressure Piping
*ASME B31Q-20102014 Pipeline Personnel Qualification
NOTES: (1) Underline and blue indicates revised and new text. 3 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
NOTES: (1) Underline and blue indicates revised and new text. 4 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
ASTM A53/A53M-12, Standard Specification for Pipe, ASTM A53/A53M-12, Standard Specification for Pipe,
Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Steel, Black and Hot-Dipped, Zinc-Coated, Welded and
Seamless Seamless
ASTM A105/A105M-12, Standard Specification for Carbon ASTM A105/A105M-1214, Standard Specification for
Steel Forgings for Piping Applications Carbon Steel Forgings for Piping Applications
ASTM A106/A106M-11, Standard Specification for ASTM A106/A106M-1115, Standard Specification for
Seamless Carbon Steel Pipe for High-Temperature Service Seamless Carbon Steel Pipe for High-Temperature Service
ASTM A134-96(R2012), Standard Specification for Pipe, ASTM A134-96(R2012), Standard Specification for Pipe,
Steel, Electric-Fusion (Arc)-Welded (Sizes NPS 16 and Steel, Electric-Fusion (Arc)-Welded (Sizes NPS 16 and
Over) Over)
ASTM A135/A135M-09, Standard Specification for ASTM A135/A135M-09(R2014), Standard Specification
Electric-Resistance-Welded Steel Pipe for Electric-Resistance-Welded Steel Pipe
ASTM A139/A139M-04(R2010), Standard Specification ASTM A139/A139M-04(R2010)16, Standard Specification
for Electric-Fusion (Arc)-Welded Steel Pipe (Sizes NPS 4 for Electric-Fusion (Arc)-Welded Steel Pipe (Sizes NPS 4
and Over) and Over)
ASTM A193/A193M-12b, Standard Specification for Alloy- ASTM A193/A193M-12b16, Standard Specification for
Steel and Stainless Steel Bolting Materials for High Alloy-Steel and Stainless Steel Bolting Materials for High
Temperature or High-Pressure Service and Other Special Temperature or High-Pressure Service and Other Special
Purpose Applications Purpose Applications
ASTM A194/A194M-12a, Standard Specification for ASTM A194/A194M-12a16, Standard Specification for
Carbon and Alloy Steel Nuts for Bolts for High Pressure Carbon and Alloy Steel Nuts for Bolts for High Pressure
or High Temperature Service, or Both or High Temperature Service, or Both
ASTM A307-12, Standard Specification for Carbon Steel ASTM A307-1214, Standard Specification for Carbon Steel
Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Bolts, Studs, and Threaded Rod 60 000 PSI Tensile
Strength Strength
ASTM A320/A320M-11a, Standard Specification for Alloy- ASTM A320/A320M-11a15a, Standard Specification for
Steel and Stainless Steel Bolting for Low-Temperature Alloy-Steel and Stainless Steel Bolting for Low-
Service Temperature Service
ASTM A333/A333M-11, Standard Specification for ASTM A333/A333M-1116, Standard Specification for
Seamless and Welded Steel Pipe for Low-Temperature Seamless and Welded Steel Pipe for Low-Temperature
Service Service
ASTM A354-11, Standard Specification for Quenched and ASTM A354-11, Standard Specification for Quenched and
Tempered Alloy Steel Bolts, Studs, and Other Externally Tempered Alloy Steel Bolts, Studs, and Other Externally
Threaded Fasteners Threaded Fasteners
ASTM A372/A372M-12, Standard Specification for Carbon ASTM A372/A372M-1215, Standard Specification for
and Alloy Steel Forgings for Thin-Walled Pressure Vessels Carbon and Alloy Steel Forgings for Thin-Walled Pressure
ASTM A381-96(R2012), Standard Specification for Metal- Vessels
Arc-Welded Steel Pipe for Use With High-Pressure ASTM A381-96(R2012), Standard Specification for Metal-
Transmission Systems Arc-Welded Steel Pipe for Use With High-Pressure
ASTM A395/A395M-99(R2009), Standard Specification Transmission Systems
for Ferritic Ductile Iron Pressure-Retaining Castings for ASTM A395/A395M-99(R2009R2014), Standard
Use at Elevated Temperatures Specification for Ferritic Ductile Iron Pressure-Retaining
Castings for Use at Elevated Temperatures
NOTES: (1) Underline and blue indicates revised and new text. 5 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
ASTM A449-10, Standard Specification for Hex Cap ASTM A449-1014, Standard Specification for Hex Cap
Screws, Bolts and Studs, Steel, Heat Treated, 120/105/90 Screws, Bolts and Studs, Steel, Heat Treated, 120/105/90
ksi Minimum Tensile Strength, General Use ksi Minimum Tensile Strength, General Use
ASTM A671/A671M-10, Standard Specification for ASTM A671/A671M-1016, Standard Specification for
Electric-Fusion-Welded Steel Pipe for Atmospheric and Electric-Fusion-Welded Steel Pipe for Atmospheric and
Lower Temperatures Lower Temperatures
ASTM A672/A672M-09, Standard Specification for ASTM A672/A672M-0914, Standard Specification for
Electric-Fusion-Welded Steel Pipe for High-Pressure Electric-Fusion-Welded Steel Pipe for High-Pressure
Service at Moderate Temperatures Service at Moderate Temperatures
ASTM A691/A691M-09, Standard Specification for Carbon ASTM A691/A691M-09(R2014), Standard Specification
and Alloy Steel Pipe, Electric-Fusion-Welded for High- for Carbon and Alloy Steel Pipe, Electric-Fusion-Welded
Pressure Service at High Temperatures for High-Pressure Service at High Temperatures
ASTM A984/A984M-03(R2009), Standard Specification ASTM A984/A984M-03(R2009), Standard Specification
for Steel Line Pipe, Black, Plain-End, Electric-Resistance- for Steel Line Pipe, Black, Plain-End, Electric-Resistance-
Welded Welded
ASTM A1005/A1005M-00(R2010), Standard Specification ASTM A1005/A1005M-00(R2010), Standard Specification
for Steel Line Pipe, Black, Plain-End, Longitudinal and for Steel Line Pipe, Black, Plain-End, Longitudinal and
Helical Seam, Double Submerged-Arc Welded Helical Seam, Double Submerged-Arc Welded
ASTM A1006/A1006M-00(R2010), Standard Specification ASTM A1006/A1006M-00(R2010), Standard Specification
for Steel Line Pipe, Black, Plain-End, Laser Beam Welded for Steel Line Pipe, Black, Plain-End, Laser Beam Welded
ASTM B88-09, Standard Specification for Seamless Copper ASTM B88-0914, Standard Specification for Seamless
Water Tube Copper Water Tube
ASTM D696-08e1, Standard Test Method for Coefficient of ASTM D696-08e116, Standard Test Method for Coefficient
Linear Thermal Expansion of Plastics Between −30°C and of Linear Thermal Expansion of Plastics Between −30°C
30°C With a Vitreous Silica Dilatometer and 30°C With a Vitreous Silica Dilatometer
ASTM D1598-02(R2009), Standard Test Method for Time- ASTM D1598-02(R2009)15a, Standard Test Method for
to-Failure of Plastic Pipe Under Constant Internal Pressure Time-to-Failure of Plastic Pipe Under Constant Internal
*ASTM D2513-13, Standard Specification for Polyethylene Pressure
(PE) Gas Pressure Pipe, Tubing, and Fittings *ASTM D2513-1314e1, Standard Specification for
*ASTM D2517-06(R2011), Standard Specification for Polyethylene (PE) Gas Pressure Pipe, Tubing, and Fittings
Reinforced Epoxy Resin Gas Pressure Pipe and Fittings *ASTM D2517-06(R2011), Standard Specification for
*ASTM D2837-11, Standard Test Method for Obtaining Reinforced Epoxy Resin Gas Pressure Pipe and Fittings
Hydrostatic Design Basis for Thermoplastic Pipe Materials *ASTM D2837-1113e1, Standard Test Method for
or Pressure Design Basis for Thermoplastic Pipe Products Obtaining Hydrostatic Design Basis for Thermoplastic
*ASME F1041-02(R2008), Standard Guide for Squeeze-Off Pipe Materials or Pressure Design Basis for Thermoplastic
of Polyolefin Gas Pressure Pipe and Tubing Pipe Products
*ASTM F1563-01(R2011), Standard Specification for Tools *ASME F1041-02(R2008R2016), Standard Guide for
to Squeeze-Off Polyethylene (PE) Gas Pipe or Tubing Squeeze-Off of Polyolefin Gas Pressure Pipe and Tubing
ASTM F2817-13 Standard Specification for Poly (Vinyl *ASTM F1563-01(R2011), Standard Specification for Tools
Chloride) (PVC) Gas Pressure Pipe and Fittings for to Squeeze-Off Polyethylene (PE) Gas Pipe or Tubing
Maintenance or Repair *ASTM F2817-13 Standard Specification for Poly (Vinyl
ASTM F2945-15 Standard Specification for Polyamide 11 Chloride) (PVC) Gas Pressure Pipe and Fittings for
Gas Pressure Pipe, Tubing, and Fittings Maintenance or Repair
Publisher: American Society for Testing and Materials ASTM F2945-15 Standard Specification for Polyamide 11
(ASTM International), 100 Barr Harbor Drive, P.O. Box Gas Pressure Pipe, Tubing, and Fittings
C700, West Conshohocken, PA 19428-2959 Publisher: American Society for Testing and Materials
(www.astm.org) (ASTM International), 100 Barr Harbor Drive, P.O. Box
C700, West Conshohocken, PA 19428-2959
(www.astm.org)
NOTES: (1) Underline and blue indicates revised and new text. 6 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
*AWS A3.0M/A3.0:2010, Standard Welding Terms and *AWS A3.0M/A3.0:2010, Standard Welding Terms and
Definitions, Including Terms for Adhesive Bonding, Definitions, Including Terms for Adhesive Bonding,
Brazing, Soldering, Thermal Cutting, and Thermal Brazing, Soldering, Thermal Cutting, and Thermal
Spraying Spraying
*AWS D3.6M:2010, Underwater Welding Code *AWS D3.6M:2010 (including Errata), Underwater
Publisher: American Welding Society (AWS), 550 NW Welding Code
LeJeune Road, Miami, FL 33126 (www.aws.org) Publisher: American Welding Society (AWS), 550 NW
LeJeune Road, Miami, FL 33126 (www.aws.org)
A-6 AWWA A-6 AWWA
ANSI A21.14-1979, Ductile-Iron Fittings 3-Inch Through ANSI A21.14-1979, Ductile-Iron Fittings 3-Inch Through
24-Inch for Gas2 24-Inch for Gas2
ANSI A21.52-1991, Ductile-Iron Pipe, Centrifugally Cast, ANSI A21.52-1991, Ductile-Iron Pipe, Centrifugally Cast,
for Gas2 for Gas2
AWWA C101-1976(R1977), Thickness Design of Cast Iron AWWA C101-1976(R1977), Thickness Design of Cast Iron
Pipe2 Pipe2
*ANSI/AWWA C111/A21.11-12, Rubber-Gasket Joints for *ANSI/AWWA C111/A21.11-12, Rubber-Gasket Joints for
Ductile-Iron Pressure Pipe and Fittings Ductile-Iron Pressure Pipe and Fittings
*ANSI/AWWA C150/A21.50-08, Thickness Design of *ANSI/AWWA C150/A21.50-0814, Thickness Design of
Ductile-Iron Pipe Ductile-Iron Pipe
Publisher: American Water Works Association (AWWA), Publisher: American Water Works Association (AWWA),
6666 West Quincy Avenue, Denver, CO 80235 6666 West Quincy Avenue, Denver, CO 80235
(www.awwa.org) (www.awwa.org)
A-7 CGA A-7 CGA
Best Practices Guide (version 10.0, 2013) Best Practices Guide (version 10.0, 2013 13.0, 2016)
Publisher: Common Ground Alliance (CGA), 1421 Prince Publisher: Common Ground Alliance (CGA), 1421 Prince
Street, Alexandria, VA 22314 Street, Alexandria, VA 22314
(www.commongroundalliance.com) (www.commongroundalliance.com)
A-8 EPRI A-8 EPRI
EPRI EL-3106 (1983) (also published as PRCI-AGA EPRI EL-3106 (1983) (also published as PRCI-AGA
L51418, Power Line-Induced AC Potential on Natural Gas L51418, Power Line-Induced AC Potential on Natural Gas
Pipelines for Complex Rights-of-Way Configurations) Pipelines for Complex Rights-of-Way Configurations)
Publisher: Electric Power Research Institute (EPRI), 3420 Publisher: Electric Power Research Institute (EPRI), 3420
Hillview Avenue, Palo Alto, CA 94304 (www.epri.com) Hillview Avenue, Palo Alto, CA 94304 (www.epri.com)
A-9 GPA A-9 GPA
GPA Standard 2265-68, Determination of Hydrogen Sulfide GPA Standard 2265-68, Determination of Hydrogen Sulfide
and Mercaptan Sulfur in Natural Gas (Cadmium Sulfate- and Mercaptan Sulfur in Natural Gas (Cadmium Sulfate-
Iodometric Titration Method) Iodometric Titration Method)
GPA Plant Operations Test Manual, Section C, Test for GPA Plant Operations Test Manual, Section C, Test for
Hydrogen Sulfide in LPG and Gases (Tutweiler Method) Hydrogen Sulfide in LPG and Gases (Tutweiler Method)
Publisher: Gas Processors Association (GPA), 6526 East Publisher: Gas Processors Association (GPA), 6526 East
60th St., Tulsa, OK 74145 (www.gpaglobal.org) 60th St., Tulsa, OK 74145 (www.gpaglobal.org)
NOTES: (1) Underline and blue indicates revised and new text. 7 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
GRI-00/0154 (2000), Design Guide for Polyethylene Gas GRI-00/0154 (2000), Design Guide for Polyethylene Gas
Pipes Across Bridges Pipes Across Bridges
GRI-91/0284 (1991), Guidelines for Pipelines Crossing GRI-91/0284 (1991), Guidelines for Pipelines Crossing
Highways2 Highways2
Publisher: Gas Technology Institute (GTI), 1700 South Publisher: Gas Technology Institute (GTI), 1700 South
Mount Prospect Road, Des Plaines, IL 60018 Mount Prospect Road, Des Plaines, IL 60018
(www.gastechnology.org) (www.gastechnology.org)
A-11 IEEE A-11 IEEE
*IEEE/ASTM SI 10-2010, American National Standard for *IEEE/ASTM SI 10-2010, American National Standard for
Metric Practice Metric Practice
Publisher: The Institute of Electrical and Electronics Publisher: The Institute of Electrical and Electronics
Engineers (IEEE), 445Hoes Lane, Piscataway, NJ 08854 Engineers (IEEE), 445Hoes Lane, Piscataway, NJ 08854
(www.ieee.org) (www.ieee.org)
A-12 MSS A-12 MSS
MSS SP-6-2012, Standard Finishes for Contact Faces of MSS SP-6-2012, Standard Finishes for Contact Faces of
Pipe Flanges and Connecting-End Flanges of Valves and Pipe Flanges and Connecting-End Flanges of Valves and
Fittings Fittings
MSS SP-25-2008, Standard Marking System for Valves, *MSS SP-25-20082013, Standard Marking System for
Fittings, Flanges, and Unions Valves, Fittings, Flanges, and Unions
MSS SP-44-2010 (including May 2011 errata), Steel *MSS SP-44-2010 (including May 2011 errata), Steel
Pipeline Flanges Pipeline Flanges
MSS SP-70-2011, Gray Iron Gate Valves, Flanged and MSS SP-70-2011, Gray Iron Gate Valves, Flanged and
Threaded Ends Threaded Ends
MSS SP-71-2011, Gray Iron Swing Check Valves, Flanged MSS SP-71-2011, including Errata through February 2013,
and Threaded Ends Gray Iron Swing Check Valves, Flanged and Threaded
MSS SP-75-2008, Specification for High-Test Wrought Butt Ends
Welding Fittings MSS SP-75-20082014, Specification for High-Test High-
MSS SP-78-2011, Gray Iron Plug Valves, Flanged and Strength, Wrought, Butt-Welding Fittings
Threaded Ends MSS SP-78-2011, Gray Iron Plug Valves, Flanged and
Publisher: Manufacturers Standardization Society of the Threaded Ends
Valve and Fittings Industry, Inc. (MSS), 127 Park Street, Publisher: Manufacturers Standardization Society of the
NE, Vienna, VA 22180 (www.mss-hq.com) Valve and Fittings Industry, Inc. (MSS), 127 Park Street,
NE, Vienna, VA 22180 (www.mss-hq.com)
NOTES: (1) Underline and blue indicates revised and new text. 8 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
*NFPA 10-2013, Standard for Portable Fire Extinguishers *NFPA 10-2013, Standard for Portable Fire Extinguishers
*NFPA 30-2012, Flammable and Combustible Liquids Code *NFPA 30-20122015, Flammable and Combustible Liquids
*NFPA 58-2013, Liquefied Petroleum Gas Code Code (including Errata 1)
*NFPA 59-2012, Utility LP-Gas Plant Code *NFPA 58-20132014, Liquefied Petroleum Gas Code
*NFPA 59A-2013, Standard for the Production, Storage, and (including Amendments 1-4 and Errata 1-2)
Handling of Liquefied Natural Gas (LNG) *NFPA 59-20122015, Utility LP-Gas Plant Code
*NFPA 70-2013, National Electrical Code (including *NFPA 59A-20132016, Standard for the Production,
Amendment 1) Storage, and Handling of Liquefied Natural Gas (LNG)
*NFPA 220-2012, Standard on Types of Building *NFPA 70-20132014, National Electrical Code (including
Construction Amendments 1-8)
Publisher: National Fire Protection Association (NFPA) 1 *NFPA 220-20122015, Standard on Types of Building
Batterymarch Park, Quincy, MA 02169-7471 Construction
(www.nfpa.org) Publisher: National Fire Protection Association (NFPA) 1
Batterymarch Park, Quincy, MA 02169-7471
(www.nfpa.org)
NOTES: (1) Underline and blue indicates revised and new text. 9 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
Handbook of Polyethylene Pipe, second edition, November Handbook of Polyethylene Pipe, second edition, November
2007 (including Errata Sheet, June 6, 2012) 2007 (including Errata Sheet, June 6, 2012)
TR-3/2004, Policies and Procedures for Developing TR-3/20042016, Policies and Procedures for Developing
Hydrostatic Design Basis (HDB), Pressure Design Basis Hydrostatic Design Basis (HDB), Pressure Design Basis
(PDB), Strength Design Basis (SDB), and Minimum (PDB), Strength Design Basis (SDB), and Minimum
Required Strength (MRS) Ratings for Thermoplastic Required Strength (MRS) Ratings for Thermoplastic
Piping Materials or Pipe Piping Materials or Pipe
TR-4/2013, Listing of Hydrostatic Design Basis (HDB), TR-4/20132016, Listing of Hydrostatic Design Basis
Hydrostatic Design Stress (HDS), Strength Design Basis (HDB), Hydrostatic Design Stress (HDS), Strength Design
(SDB), Pressure Design Basis (PDB) and Minimum Basis (SDB), Pressure Design Basis (PDB) and Minimum
Required Strength (MRS) Ratings For Thermoplastic Required Strength (MRS) Ratings For Thermoplastic
Piping Materials or Pipe Piping Materials or Pipe
TR-33/2006, Generic Butt Fusion Joining Procedure for TR-33/20062012, Generic Butt Fusion Joining Procedure for
Polyethylene Gas Pipe Polyethylene Gas Pipe
TR-41/2002, Generic Saddle Fusion Joining Procedure for TR-41/2002, Generic Saddle Fusion Joining Procedure for
Polyethylene Gas Piping Polyethylene Gas Piping
TR-45/2008 Butt Fusion Joining Procedure for Field Joining TR-45/20082016 Butt Fusion Joining Procedure for Field
of Polyamide-11 (PA-11) Pipe Joining of Polyamide-11 (PA-11) Pipe
Publisher: Plastics Pipe Institute (PPI), 105 Decker Court, Publisher: Plastics Pipe Institute (PPI), 105 Decker Court,
Irving, TX 75062 (www.plasticpipe.org) Irving, TX 75062 (www.plasticpipe.org)
A-16 PRCI A-16 PRCI
PRCI PR-185-9734 (PRCI Catalog L51782), Guidelines for PRCI PR-185-9734 (PRCI Catalog L51782), Guidelines for
Weld Deposition Repair on Pipelines (1998) Weld Deposition Repair on Pipelines (1998)
PRCI PR-186-0324 (PRCI Catalog L52047), Updated PRCI PR-186-0324 (PRCI Catalog L52047), Updated
Pipeline Repair Manual (2006) Pipeline Repair Manual (2006)
PRCI PR-218-05404 (PRCI Catalog L52314), Pipeline PRCI PR-218-05404 (PRCI Catalog L52314), Pipeline
Defect Assessment — A Review and Comparison of Defect Assessment — A Review and Comparison of
Commonly Used Methods (2010) Commonly Used Methods (2010)
PRCI PR-218-9307 (PRCI Catalog L51716), Pipeline Repair PRCI PR-218-9307 (PRCI Catalog L51716), Pipeline Repair
Manual (1994) Manual (1994)
Publisher: Pipeline Research Council International, Inc. Publisher: Pipeline Research Council International, Inc.
(PRCI), 3141 Fairview Park Drive, Falls Church, VA (PRCI), 3141 Fairview Park Drive, Falls Church, VA
22042 (www.prci.org) 22042 (www.prci.org)
1 1
See Note in para. 814.1.1 regarding the use of the 45th See Note in para. 814.1.1 regarding the use of the 45th
edition of API 5L. edition of API 5L.
2 2
This publication has been superseded, withdrawn, or is no This publication has been superseded, withdrawn, or is no
longer in print. longer in print.
NOTES: (1) Underline and blue indicates revised and new text. 10 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
ASME B31.8-2016
NOTE: An asterisk (*) indicates standards that have been C-4 ASME
accepted as American National Standards by the American
National Standards Institute (ANSI). *ASME B1.20.3-1976 (R2013), Dryseal Pipe Threads
(Inch)
*ASME B16.3-2011, Malleable Iron Threaded Fittings:
C-1 AGA Classes 150 and 300
*ASME B16.4-2011, Gray Iron Threaded Fittings:
AGA Catalog XL1001 (December 2010, including
Classes 125 and 250
Errata 1 and 2), Classification of Locations for
*ASME B16.14-2010, Ferrous Pipe Plugs, Bushings, and
Electrical Installations in Gas Utility Areas
Locknuts With Pipe Threads
Directional Drilling Damage Prevention Guidelines for
*ASME B16.15-2011, Cast Copper Alloy Threaded
the Natural Gas Industry (December 2004)
Fittings: Classes 125 and 250
Publisher: American Gas Association (AGA), 400 *ASME B16.18-2012, Cast Copper Alloy Solder Joint
North Capitol Street, NW, Washington, DC 20001 Pressure Fittings
(www.aga.org) *ASME B16.22-2012, Wrought Copper and Copper Alloy
Solder-Joint Pressure Fittings
C-2 API *ASME B16.25-2012, Buttwelding Ends
*ASME B31.12-2011, Hydrogen Piping and Pipelines
API RP 2A-LRFD (first edition, July 1993, including Publisher: The American Society of Mechanical
Errata and Supplements through February 1997; reaf- Engineers (ASME), Two Park Avenue, New York,
firmed May 2003), Recommended Practice for NY 10016-5990 (www.asme.org)
Planning, Designing, and Constructing Fixed
Offshore Platforms — Load and Resistance Factor
Design1 C-5 ASTM
*API RP 500 (third edition, December 2012), ASTM A6/A6M-13, Standard Specification for General
Recommended Practices for Classification of Requirements for Rolled Structural Steel Bars, Plates,
Locations for Electrical Installations at Petroleum Shapes, and Sheet Piling
Facilities Classified as Class I, Division 1 and ASTM A20/A20M-11, Standard Specification for
Division 2 General Requirements for Steel Plates for Pressure
API Spec 5B (15th edition, April 2008), Specification for Vessels
Threading, Gauging, and Thread Inspection of Casing, ASTM A29/A29M-12, Standard Specification for
Tubing, and Line Pipe Threads General Requirements for Steel Bars, Carbon and
Publisher: American Petroleum Institute (API), Alloy, Hot-Wrought
1220 L Street, NW, Washington, DC 20005 ASTM A36/A36M-12, Standard Specification for
(www.api.org) Carbon Structural Steel
ASTM A47/A47M-99(R2009), Standard Specification for
Ferritic Malleable Iron Castings
C-3 ASCE ASTM A48/A48M-03(R2012), Standard Specification for
Gray Iron Castings
ASCE Manuals and Reports on Engineering Practices
ASTM A125-96(R2007), Standard Specification for Steel
No. 89 — Pipeline Crossings Handbook (June 1996)
Springs, Helical, Heat-Treated
Publisher: American Society of Civil Engineers ASTM A126-04(R2009), Standard Specification for Gray
(ASCE), 1801 Alexander Bell Drive, Reston, VA 20191 Iron Castings for Valves, Flanges, and Pipe Fittings
(www.asce.org) ASTM A181/A181M-12, Standard Specification for
Carbon Steel Forgings, for General-Purpose Piping
1
This publication has been superseded, withdrawn, or is no *ASTM A182/A182M-13, Standard Specification for
longer in print. Forged or Rolled Alloy and Stainless-Steel Pipe
131
ASME B31.8-2016
Flanges, Forged Fittings, and Valves and Parts for ASTM B43-09, Standard Specification for Seamless Red
High-Temperature Service Brass Pipe, Standard Sizes
ASTM A197/A197M-00(R2011), Standard Specification ASTM B61-08, Standard Specification for Steam or Valve
for Cupola Malleable Iron Bronze Castings
ASTM A216/A216M-12, Standard Specification for Steel ASTM B62-09, Standard Specification for Composition
Castings, Carbon, Suitable for Fusion Welding, for Bronze or Ounce Metal Castings
High-Temperature Service ASTM B68/B68M-11, Standard Specification for
ASTM A217/A217M-12, Standard Specification for Steel Seamless Copper Tube, Bright Annealed
Castings, Martensitic Stainless and Alloy, for ASTM B75/B75M-11, Standard Specification for
Pressure-Containing Parts, Suitable for High- Seamless Copper Tube
Temperature Service ASTM B249/B249M-12, Standard Specification for
ASTM A225/A225M-12, Standard Specification for General Requirements for Wrought Copper and
Pressure Vessel Plates, Alloy Steel, Manganese- Copper-Alloy Rod, Bar, Shapes, and Forgings
Vanadium-Nickel ASTM B251-10, Standard Specification for General
Requirements for Wrought Seamless Copper and
ASTM A234/A234M-11a, Standard Specification for
Copper-Alloy Tube
Piping Fittings of Wrought Carbon Steel and Alloy
ASTM B584-13, Standard Specification for Copper Alloy
Steel for Moderate and High-Temperature Service
Sand Castings for General Applications
ASTM A242/A242M-13, Standard Specification for
High-Strength Low-Alloy Structural Steel Publisher: American Society for Testing and Materials
(ASTM International), 100 Barr Harbor Drive, P.O.
ASTM A283/A283M-12a, Standard Specification for
Box C700, West Conshohocken, PA 19428-2959
Low and Intermediate Tensile Strength Carbon Steel
(www.astm.org)
Plates
ASTM A285/A285M-12, Standard Specification for
Pressure Vessel Plates, Carbon Steel, Low- and C-6 AWWA
Intermediate-Tensile Strength
*AWWA C207-13, Steel Pipe Flanges for Waterworks
ASTM A350/A350M-12, Standard Specification for
Service — Sizes 4 in. Through 144 in. (100 mm
Carbon and Low-Alloy Steel Forgings, Requiring
Through 3,600 mm)
Notch Toughness Testing for Piping Components
ASTM A377-03(R2008) ⑀1 , Standard Index of Publisher: American Water Works Association (AWWA),
Specifications for Ductile-Iron Pressure Pipe 6666 West Quincy Avenue, Denver, CO 80235
ASTM A420/A420M-10a, Standard Specification for (www.awwa.org)
Piping Fittings of Wrought Carbon Steel and Alloy
Steel for Low-Temperature Service C-7 GTI
ASTM A487/A487M-93(R2012), Standard Specification
for Steel Castings Suitable for Pressure Service GRI-00/0154 (2001), Design Guide for Pipes Across
ASTM A502-03(R2009), Standard Specification for Bridges
Rivets, Steel, Structural GRI-00/0192.01 (2001), GRI Guide for Locating and
Using Pipeline Industry Research. Section 1: Fracture
ASTM A515/A515M-10, Standard Specification for
Propagation and Arrest
Pressure Vessel Plates, Carbon Steel, for Intermediate-
GRI-00/0192.02 (2001), GRI Guide for Locating and
and Higher-Temperature Service
Using Pipeline Industry Research. Section 2: Defect
ASTM A516/A516M-10, Standard Specification for
Assessment
Pressure Vessel Plates, Carbon Steel, for Moderate-
GRI-00/0192.03 (2001), GRI Guide for Locating and
and Lower-Temperature Service Using Pipeline Industry Research. Section 3:
ASTM A575-96(R2013) ⑀1 , Standard Specification for Identifying Types of Defects and Causes of Pipeline
Steel Bars, Carbon, Merchant Quality, M-Grades Failures
ASTM A576-90b(R2012), Standard Specification for Steel GRI-00/0192.04 (2001), GRI Guide for Locating and
Bars, Carbon, Hot-Wrought, Special Quality Using Pipeline Industry Research. Section 4:
ASTM A694/A694M-08, Standard Specification for Hydrostatic Testing
Carbon and Alloy Steel Forgings for Pipe Flanges, GRI-00/0192.05 (2001), GRI Guide for Locating and
Fittings, Valves, and Parts for High-Pressure Using Pipeline Industry Research. Section 5: Line Pipe
Transmission Service GRI-00/0192.06 (2001), GRI Guide for Locating and
ASTM B21/B21M-12, Standard Specification for Naval Using Pipeline Industry Research. Section 6: Welding
Brass Rod, Bar, and Shapes GRI-00/0192.07 (2001), GRI Guide for Locating and
ASTM B42-10, Standard Specification for Seamless Using Pipeline Industry Research. Section 7: Fittings
Copper Pipe, Standard Sizes and Components
132
ASME B31.8-2016
133
Attachment C
Item 16-301
*MSS SP-55-2011, Quality Standard for Steel Castings for *MSS SP-55-2011, Quality Standard for Steel Castings for
Valves, Flanges, Fittings, and Other Piping Components Valves, Flanges, Fittings, and Other Piping Components
— Visual Method for Evaluation of Surface Irregularities — Visual Method for Evaluation of Surface Irregularities
MSS SP-61-2013, Pressure Testing of Valves MSS SP-61-2013, Pressure Testing of Valves
Publisher: Manufacturers Standardization Society of the Publisher: Manufacturers Standardization Society of the
Valve and Fittings Industry, Inc. (MSS), 127 Park Street, Valve and Fittings Industry, Inc. (MSS), 127 Park Street,
NE, Vienna, VA 22180 (www.mss-hq.com) NE, Vienna, VA 22180 (www.mss-hq.com)
C-9 OTHER C-9 OTHER
ANSI Z17.1-1973, American National Standard for ANSI Z17.1-1973, American National Standard for
Preferred Numbers1 Preferred Numbers1
Publisher: American National Standards Institute (ANSI), 25 Publisher: American National Standards Institute (ANSI), 25
West 43rd Street, New York, NY 10036 (www.ansi.org) West 43rd Street, New York, NY 10036 (www.ansi.org)
Horizonal Directional Drilling — Good Practices Guidelines Horizonal Horizontal Directional Drilling — Good Practices
(third edition, 2008) Guidelines (third edition, 2008)
Publisher: HDD Consortium, available through North Publisher: HDD Consortium, available through North
American Society for Trenchless Technology (NASTT), American Society for Trenchless Technology (NASTT),
7745 Morgan Road, Liverpool, NY 13090 7745 Morgan Road, Liverpool, NY 13090
(www.nastt.org) (www.nastt.org)
PRCI PR-227-03110 (2008), Installation of Pipelines Using PRCI PR-227-03110 (2008), Installation of Pipelines Using
Horizontal Directional Drilling, — An Engineering Design Horizontal Directional Drilling, — An Engineering Design
Guide Guide
Publisher: Pipeline Research Council International (PRCI), Publisher: Pipeline Research Council International (PRCI),
3141 Fairview Park Drive, Falls Church, VA 22042 3141 Fairview Park Drive, Falls Church, VA 22042
(www.prci.org) (www.prci.org)
1 1
This publication has been superseded, withdrawn, or is no This publication has been superseded, withdrawn, or is no
longer in print. longer in print.
NOTES: (1) Underline and blue indicates revised and new text. 16 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
GRI-00/0154 (2000), Design Guide for Pipes Across GRI-00/0154 (2000), Design Guide for Pipes Across
Bridges Bridges
GRI-00/0192.01 (2001), GRI Guide for Locating and Using GRI-00/0192.01 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 1: Fracture Pipeline Industry Research. Section 1: Fracture
Propagation and Arrest Propagation and Arrest
GRI-00/0192.02 (2001), GRI Guide for Locating and Using GRI-00/0192.02 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 2: Defect Assessment Pipeline Industry Research. Section 2: Defect Assessment
GRI-00/0192.03 (2001), GRI Guide for Locating and Using GRI-00/0192.03 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 3: Identifying Types Pipeline Industry Research. Section 3: Identifying Types
of Defects and Causes of Pipeline Failures of Defects and Causes of Pipeline Failures
GRI-00/0192.04 (2001), GRI Guide for Locating and Using GRI-00/0192.04 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 4: Hydrostatic Testing Pipeline Industry Research. Section 4: Hydrostatic Testing
GRI-00/0192.05 (2001), GRI Guide for Locating and Using GRI-00/0192.05 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 5: Line Pipe Pipeline Industry Research. Section 5: Line Pipe
GRI-00/0192.06 (2001), GRI Guide for Locating and Using GRI-00/0192.06 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 6: Welding Pipeline Industry Research. Section 6: Welding
GRI-00/0192.07 (2001), GRI Guide for Locating and Using GRI-00/0192.07 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 7: Fittings and Pipeline Industry Research. Section 7: Fittings and
Components Components
GRI-00/0192.08 (2001), GRI Guide for Locating and Using GRI-00/0192.08 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 8: Pipeline Repair Pipeline Industry Research. Section 8: Pipeline Repair
Methods Methods
GRI-00/0192.09 (2001), GRI Guide for Locating and Using GRI-00/0192.09 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 9: Mechanical Pipeline Industry Research. Section 9: Mechanical
Damage Damage
GRI-00/0192.10 (2001), GRI Guide for Locating and Using GRI-00/0192.10 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 10: Corrosion Pipeline Industry Research. Section 10: Corrosion
GRI-00/0192.11 (2001), GRI Guide for Locating and Using GRI-00/0192.11 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 11: Stress Corrosion Pipeline Industry Research. Section 11: Stress Corrosion
Cracking Cracking
GRI-00/0192.12 (2001), GRI Guide for Locating and Using GRI-00/0192.12 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 12: Industry Statistics Pipeline Industry Research. Section 12: Industry Statistics
GRI-00/0192.13 (2001), GRI Guide for Locating and Using GRI-00/0192.13 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 13: Offshore Pipelines Pipeline Industry Research. Section 13: Offshore Pipelines
GRI-00/0192.14 (2001), GRI Guide for Locating and Using GRI-00/0192.14 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 14: In-Line Inspection Pipeline Industry Research. Section 14: In-Line Inspection
GRI-00/0192.15 (2001), GRI Guide for Locating and Using GRI-00/0192.15 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 15: Special Situations Pipeline Industry Research. Section 15: Special Situations
GRI-00/0192.16 (2001), GRI Guide for Locating and Using GRI-00/0192.16 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 16: Risk Assessment Pipeline Industry Research. Section 16: Risk Assessment
GRI-00/0192.17 (2001), GRI Guide for Locating and Using GRI-00/0192.17 (2001), GRI Guide for Locating and Using
Pipeline Industry Research. Section 17: Geographical Pipeline Industry Research. Section 17: Geographical
Information Systems Information Systems
GRI-96/0368 (1996), Guidelines for the Application of GRI-96/0368 (1996), Guidelines for the Application of
Guided Horizontal Drilling to Install Gas Distribution Pipe Guided Horizontal Drilling to Install Gas Distribution Pipe
Publisher: Gas Technology Institute (GTI), 1700 South Publisher: Gas Technology Institute (GTI), 1700 South
Mount Prospect Road, Des Plaines, IL 60018 Mount Prospect Road, Des Plaines, IL 60018
(www.gastechnology.com) (www.gastechnology.com)
NOTES: (1) Underline and blue indicates revised and new text. 15 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
ASTM A694/A694M-08, Standard Specification for Carbon ASTM A694/A694M-0816, Standard Specification for
and Alloy Steel Forgings for Pipe Flanges, Fittings, Valves Carbon and Alloy Steel Forgings for Pipe Flanges,
and Parts for High-Pressure Transmission Service Fittings, Valves and Parts for High-Pressure Transmission
ASTM B21/B21M-12, Standard Specification for Naval Service
Brass Rod, Bar, and Shapes ASTM B21/B21M-1214, Standard Specification for Naval
ASTM B42-10, Standard Specification for Seamless Copper Brass Rod, Bar, and Shapes
Pipe, Standard Sizes ASTM B42-1015a, Standard Specification for Seamless
ASTM B43-09, Standard Specification for Seamless Red Copper Pipe, Standard Sizes
Brass Pipe, Standard Sizes ASTM B43-0915, Standard Specification for Seamless Red
ASTM B61-08, Standard Specification for Steam or Valve Brass Pipe, Standard Sizes
Bronze Castings ASTM B61-0815, Standard Specification for Steam or
ASTM B62-09, Standard Specification for Composition Valve Bronze Castings
Bronze or Ounce Metal Castings ASTM B62-0915, Standard Specification for Composition
ASTM B68/B68M-11, Standard Specification for Seamless Bronze or Ounce Metal Castings
Copper Tube, Bright Annealed ASTM B68/B68M-11, Standard Specification for Seamless
ASTM B75/B75M-11, Standard Specification for Seamless Copper Tube, Bright Annealed
Copper Tube ASTM B75/B75M-11, Standard Specification for Seamless
ASTM B249/B249M-12, Standard Specification for General Copper Tube
Requirements for Wrought Copper and Copper-Alloy Rod, ASTM B249/B249M-1215a, Standard Specification for
Bar, Shapes, and Forgings General Requirements for Wrought Copper and Copper-
ASTM B251-10, Standard Specification for General Alloy Rod, Bar, Shapes, and Forgings
Requirements for Wrought Seamless Copper and Copper- ASTM B251-10, Standard Specification for General
Alloy Tube Requirements for Wrought Seamless Copper and Copper-
ASTM B584-13, Standard Specification for Copper Alloy Alloy Tube
Sand Castings for General Applications ASTM B584-1314, Standard Specification for Copper Alloy
Publisher: American Society for Testing and Materials Sand Castings for General Applications
(ASTM International), 100 Barr Harbor Drive, P.O. Box Publisher: American Society for Testing and Materials
C700, West Conshohocken, PA 19428-2959 (ASTM International), 100 Barr Harbor Drive, P.O. Box
(www.astm.org) C700, West Conshohocken, PA 19428-2959
(www.astm.org)
C-6 AWWA C-6 AWWA
*AWWA C207-13, Steel Pipe Flanges for Waterworks *AWWA C207-13, Steel Pipe Flanges for Waterworks
Service — Sizes 4 in. Through 144 in. (100 mm Through Service — Sizes 4 in. Through 144 in. (100 mm Through
3,600 mm) 3,600 mm)
Publisher: American Water Works Association (AWWA), Publisher: American Water Works Association (AWWA),
6666 West Quincy Avenue, Denver, CO 80235 6666 West Quincy Avenue, Denver, CO 80235
(www.awwa.org) (www.awwa.org)
NOTES: (1) Underline and blue indicates revised and new text. 14 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
ASTM A216/A216M-12, Standard Specification for Steel ASTM A216/A216M-1216, Standard Specification for Steel
Castings, Carbon, Suitable for Fusion Welding, for High- Castings, Carbon, Suitable for Fusion Welding, for High-
Temperature Service Temperature Service
ASTM A217/A217M-12, Standard Specification for Steel ASTM A217/A217M-1214, Standard Specification for Steel
Castings, Martensitic Stainless and Alloy, for Pressure- Castings, Martensitic Stainless and Alloy, for Pressure-
Containing Parts, Suitable for High-Temperature Service Containing Parts, Suitable for High-Temperature Service
ASTM A225/A225M-12, Standard Specification for ASTM A225/A225M-12, Standard Specification for
Pressure Vessel Plates, Alloy Steel, Manganese- Pressure Vessel Plates, Alloy Steel, Manganese-
Vanadium-Nickel Vanadium-Nickel
ASTM A234/A234M-11a, Standard Specification for Piping ASTM A234/A234M-11a15, Standard Specification for
Fittings of Wrought Carbon Steel and Alloy Steel for Piping Fittings of Wrought Carbon Steel and Alloy Steel
Moderate and High-Temperature Service for Moderate and High-Temperature Service
ASTM A242/A242M-13, Standard Specification for High- ASTM A242/A242M-13, Standard Specification for High-
Strength Low-Alloy Structural Steel Strength Low-Alloy Structural Steel
ASTM A283/A283M-12a, Standard Specification for Low ASTM A283/A283M-12a13, Standard Specification for
and Intermediate Tensile Strength Carbon Steel Plates Low and Intermediate Tensile Strength Carbon Steel Plates
ASTM A285/A285M-12, Standard Specification for ASTM A285/A285M-12, Standard Specification for
Pressure Vessel Plates, Carbon Steel, Low- and Pressure Vessel Plates, Carbon Steel, Low- and
Intermediate-Tensile Strength Intermediate-Tensile Strength
ASTM A350/A350M-12, Standard Specification for Carbon ASTM A350/A350M-1215, Standard Specification for
and Low-Alloy Steel Forgings, Requiring Notch Carbon and Low-Alloy Steel Forgings, Requiring Notch
Toughness Testing for Piping Components Toughness Testing for Piping Components
ASTM A377-03(R2008)e1, Standard Index of ASTM A377-03(R2008R2014)e1, Standard Index of
Specifications for Ductile-Iron Pressure Pipe Specifications for Ductile-Iron Pressure Pipe
ASTM A420/A420M-10a, Standard Specification for Piping ASTM A420/A420M-10a16, Standard Specification for
Fittings of Wrought Carbon Steel and Alloy Steel for Low- Piping Fittings of Wrought Carbon Steel and Alloy Steel
Temperature Service for Low-Temperature Service
ASTM A487/A487M-93(R2012), Standard Specification ASTM A487/A487M-93(R2012)14, Standard Specification
for Steel Castings Suitable for Pressure Service for Steel Castings Suitable for Pressure Service
ASTM A502-03(R2009), Standard Specification for Rivets, ASTM A502-03(R2009R2015), Standard Specification for
Steel, Structural Rivets, Steel, Structural
ASTM A515/A515M-10, Standard Specification for ASTM A515/A515M-10(R2015), Standard Specification
Pressure Vessel Plates, Carbon Steel, for Intermediate- and for Pressure Vessel Plates, Carbon Steel, for Intermediate-
Higher-Temperature Service and Higher-Temperature Service
ASTM A516/A516M-10, Standard Specification for ASTM A516/A516M-10(R2015), Standard Specification
Pressure Vessel Plates, Carbon Steel, for Moderate and for Pressure Vessel Plates, Carbon Steel, for Moderate and
Lower-Temperature Service Lower-Temperature Service
ASTM A575-96(2013)e1, Standard Specification for Steel ASTM A575-96(2013)e1, Standard Specification for Steel
Bars, Carbon, Merchant Quality, M-Grades Bars, Carbon, Merchant Quality, M-Grades
ASTM A576-90b(R2012), Standard Specification for Steel ASTM A576-90b(R2012), Standard Specification for Steel
Bars, Carbon, Hot-Wrought, Special Quality Bars, Carbon, Hot-Wrought, Special Quality
ASTM A984/A984M-03(R2009), Standard Specification
for Steel Line Pipe, Black, Plain-End, Electric-Resistance-
Welded1
ASTM A1005/A1005M-00(R2010), Standard Specification
for Steel Line Pipe, Black, Plain-End, Longitudinal and
Helical Seam, Double Submerged-Arc Welded1
ASTM A1006/A1006M-00(R2010), Standard Specification
for Steel Line Pipe, Black, Plain-End, Laser Beam
Welded1
NOTES: (1) Underline and blue indicates revised and new text. 13 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
*ASME B1.20.3-1976 (R2013), Dryseal Pipe Threads (Inch) *ASME B1.20.3-1976 (R2013), Dryseal Pipe Threads (Inch)
*ASME B16.3-2011, Malleable Iron Threaded Fittings: *ASME B16.3-2011, Malleable Iron Threaded Fittings:
Classes 150 and 300 Classes 150 and 300
*ASME B16.4-2011, Gray Iron Threaded Fittings: Classes *ASME B16.4-2011, Gray Iron Threaded Fittings: Classes
125 and 250 125 and 250
*ASME B16.14-2010, Ferrous Pipe Plugs, Bushings, and *ASME B16.14-20102013, Ferrous Pipe Plugs, Bushings,
Locknuts With Pipe Threads and Locknuts With Pipe Threads
*ASME B16.15-2011, Cast Copper Alloy Threaded Fittings: *ASME B16.15-20112013, Cast Copper Alloy Threaded
Classes 125 and 250 Fittings: Classes 125 and 250
*ASME B16.18-2012, Cast Copper Alloy Solder Joint *ASME B16.18-2012, Cast Copper Alloy Solder Joint
Pressure Fittings Pressure Fittings
*ASME B16.22-2012, Wrought Copper and Copper Alloy *ASME B16.22-20122013, Wrought Copper and Copper
Solder Joint Pressure Fittings Alloy Solder Joint Pressure Fittings
*ASME B16.25-2012, Buttwelding Ends *ASME B16.25-2012, Buttwelding Ends
*ASME B31.12-2011, Hydrogen Piping and Pipelines *ASME B31.12-20112014, Hydrogen Piping and Pipelines
Publisher: The American Society of Mechanical Engineers Publisher: The American Society of Mechanical Engineers
(ASME), Three Park Avenue, New York, NY 10016; (ASME), Three Park Avenue, New York, NY 10016;
Order Department: 22 Law Drive, Box 2900, Fairfield, NJ Order Department: 22 Law Drive, Box 2900, Fairfield, NJ
07007-2900 (www.asme.org) 07007-2900 (www.asme.org)
C-5 ASTM C-5 ASTM
ASTM A6/A6M-13, Standard Specification for General ASTM A6/A6M-1316, Standard Specification for General
Requirements for Rolled Structural Steel Bars, Plates, Requirements for Rolled Structural Steel Bars, Plates,
Shapes, and Sheet Piling Shapes, and Sheet Piling
ASTM A20/A20M-11, Standard Specification for General ASTM A20/A20M-1115, Standard Specification for
Requirements for Steel Plates for Pressure Vessels General Requirements for Steel Plates for Pressure Vessels
ASTM A29/A29M-12, Standard Specification for Steel ASTM A29/A29M-1215, Standard Specification for Steel
Bars, Carbon and Alloy, Hot-Wrought, General Bars, Carbon and Alloy, Hot-Wrought, General
Requirements for Requirements for
ASTM A36/A36M-12, Standard Specification for Carbon ASTM A36/A36M-1214, Standard Specification for Carbon
Structural Steel Structural Steel
ASTM A47/A47M-99(R2009), Standard Specification for ASTM A47/A47M-99(R2009R2014), Standard
Ferritic Malleable Iron Castings Specification for Ferritic Malleable Iron Castings
ASTM A48/A48M-03(R2012), Standard Specification for ASTM A48/A48M-03(R2012), Standard Specification for
Gray Iron Castings Gray Iron Castings
ASTM A125-96(R2007), Standard Specification for Steel ASTM A125-96 (R2007R2013)e1, Standard Specification
Springs, Helical, Heat-Treated for Steel Springs, Helical, Heat-Treated
ASTM A126-04(R2009), Standard Specification for Gray ASTM A126-04(R2009R2014), Standard Specification for
Iron Castings for Valves, Flanges, and Pipe Fittings Gray Iron Castings for Valves, Flanges, and Pipe Fittings
ASTM A181/A181M-12, Standard Specification for Carbon ASTM A181/A181M-1214, Standard Specification for
Steel Forgings, for General-Purpose Piping Carbon Steel Forgings, for General-Purpose Piping
*ASTM A182/A182M-13, Standard Specification for *ASTM A182/A182M-1316, Standard Specification for
Forged or Rolled Alloy and Stainless-Steel Pipe Flanges, Forged or Rolled Alloy and Stainless-Steel Pipe Flanges,
Forged Fittings, and Valves and Parts for High- Forged Fittings, and Valves and Parts for High-
Temperature Service Temperature Service
ASTM A197/A197M-00(R2011), Standard Specification ASTM A197/A197M-00(R2011R2015), Standard
for Cupola Malleable Iron Specification for Cupola Malleable Iron
NOTES: (1) Underline and blue indicates revised and new text. 12 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
Item 16-301
NOTE: An asterisk (*) indicates standards that have been accepted as NOTE: An asterisk (*) indicates standards that have been accepted as
American National Standards by the American National Standards American National Standards by the American National Standards
Institute (ANSI). Institute (ANSI).
C-1 AGA C-1 AGA
AGA Catalog XL1001 (December 2010, including Errata 1 AGA Catalog XL1001 (December 2010, including Errata 1
and 2), Classification of Locations for Electrical and 2), Classification of Locations for Electrical
Installations in Gas Utility Areas Installations in Gas Utility Areas
Directional Drilling Damage Prevention Guidelines for the Directional Drilling Damage Prevention Guidelines for the
Natural Gas Industry (December 2004) Natural Gas Industry (December 2004)
Publisher: American Gas Association (AGA), 400 North Publisher: American Gas Association (AGA), 400 North
Capitol Street, NW, Washington, DC 20001 Capitol Street, NW, Washington, DC 20001
(www.aga.org) (www.aga.org)
C-2 API C-2 API
API RP 2A-LRFD (first edition, July 1993, including Errata API RP 2A-LRFD (first edition, July 1993, including Errata
and Supplements through February 1997; reaffirmed May and Supplements through February 1997; reaffirmed May
2003), Recommended Practice for Planning, Designing, 2003), Recommended Practice for Planning, Designing,
and Constructing Fixed Offshore Platforms — Load and and Constructing Fixed Offshore Platforms — Load and
Resistance Factor Design11 Resistance Factor Design1
*API RP 500 (third edition, December 2012), *API RP 500 (third edition, December 2012, including
Recommended Practices for Classification of Locations Errata through January 2014), Recommended Practices for
for Electrical Installations at Petroleum Facilities Classification of Locations for Electrical Installations at
Classified as Class I, Division 1 and Division 2 Petroleum Facilities Classified as Class I, Division 1 and
API Spec 5B (15th edition, April 2008), Specification for Division 2
Threading, Gauging, and Thread Inspection of Casing, API Spec 5B (15th edition, April 2008, reaffirmed April
Tubing, and Line Pipe Threads 2015), Specification for Threading, Gauging, and Thread
Publisher: American Petroleum Institute (API), 1220 L Inspection of Casing, Tubing, and Line Pipe Threads
Street, NW, Washington, DC 20005 (www.api.org) Publisher: American Petroleum Institute (API), 1220 L
Street, NW, Washington, DC 20005 (www.api.org)
C-3 ASCE C-3 ASCE
ASCE Manuals and Reports on Engineering Practices No. ASCE Manuals and Reports on Engineering Practices No.
89 — Pipeline Crossings Handbook (June 1996) 89 — Pipeline Crossings Handbook (June 1996)
Publisher: American Society of Civil Engineers (ASCE), Publisher: American Society of Civil Engineers (ASCE),
1801 Alexander Bell Drive, Reston VA 20191 1801 Alexander Bell Drive, Reston VA 20191
(www.asce.org) (www.asce.org)
NOTES: (1) Underline and blue indicates revised and new text. 11 of 16
(2) Strikethrough and red indicates deleted text (4/13/18)
ASME B31.8-2016
Table D-1 Specified Minimum Yield Strength for Steel Pipe Commonly Used
in Piping Systems (Cont’d)
Type SMYS,
Spec. No. Grade [Note (1)] psi (MPa)
GENERAL NOTE: This Table is not complete. For the minimum specified yield strength of other grades
and grades in other approved specifications, refer to the particular specification.
NOTES:
(1) Abbreviations: BW p furnace buttwelded; DSA p double submerged-arc welded; EFW p electric
fusion welded; ERW p electric resistance welded; LW p laser welded; S p seamless.
(2) Intermediate grades are available in API 5L.
(3) See applicable plate specification for SMYS.
135
ASME B31.8-2016
PE 2606 1.250
PE 2706 1.250
PE 2708 1,250
PE 3608 1,600
PE 3708 1,600
PE 3710 1,600
PE 4708 1,600
PE 4710 1.600
GENERAL NOTES:
(17.2)
(a) Long-Term Hydrostatic Strength Values for Thermoplastic Pipes
(21.7)
Covered by ASTM D2513. The values apply only to materials
(13.8)
and pipes meeting all the requirements of the basic materials
(8.6)
and ASTM D2513. They are based on engineering test data (11.0)
obtained in accordance with ASTM D1598 and analyzed in
accordance with ASTM D2837. A list of commercial compounds (8.6)
meeting these requirements is published yearly by the Plastics (8.6)
Pipe Institute. (8.6)
(b) HDB Values for Reinforced Thermosetting Pipes Covered by (11.0)
ASTM D2517. The value is established in accordance with
ASTM D2517. In the absence of an established HDB, the value (11.0)
is 11,000 psi (75.8 MPa). (11.0)
(11.0)
(11.0)
(27.6)
(27.6)
(13.8)
(21.7)
136
ASME B31.8-2016
MANDATORY APPENDIX F
EXTRUDED HEADERS AND WELDED BRANCH CONNECTIONS1
143
ASME B31.8-2016
factors F p 0.60, E p 1.00, and T p 1.00. For dimensions, Total A3 provided p 1.844 in.2
see Fig. F-6. See also Fig. F-5.
F-2.1.1 Header. Nominal wall thickness required:
F-2.1.4 Reinforcement Provided by Header F-2.1.2M Outlet. Nominal wall thickness required:
This must be multiplied by 35,000/46,000 [see d p inside diameter of opening p 219.08 − 2 ⴛ 8.179
para. 831.4.1(f)]. p 202.72 mm
35,000
Effective A′2 p 0.295 ⴛ p 0.224 in.2 F-2.1.3M Reinforcement Required
46,000
Required area:
AR p dt p 202.72 ⴛ 7.178 p 1 455.2 mm2
A3 p AR − A1 − A′2
p 2.259 − 0.231 − 0.224 p 1.804 in.2 F-2.1.4M Reinforcement Provided by Header
Area p (15.500 − 8.625) ⴛ 0.250 p 1.719 in.2 F-2.1.5M Effective Area in Outlet (16)
145
ASME B31.8-2016
Fig. F-6
or L p 21/2H p 2.5 ⴛ 7.92 p 19.812 mm. Use L p temperature is 100°F. Design factors F p 0.60, E p 1.00,
19.812 mm and T p 1.00. For dimensions, see Fig. F-7.
147
ASME B31.8-2016
Fig. F-7
The use of end welds is optional (see Fig. I-3). AR p dt p 390.55 ⴛ 7.178 p 2 803.5 mm2
148
ASME B31.8-2016
This must be multiplied by 241.3/317.2 [see Area p 7.92 ⴛ (736.6 − 406.4) p 2 616.8 mm2
para. 831.4.1(f)].
Two 6.35 mm welds to outlet:
Effective A′2 p 64.80 ⴛ 241.3/317.2 p 49.30 mm2
1
/2 ⴛ (0.25 ⴛ 0.25) ⴛ 2 p 40.32 mm2
Required area:
Total A 3 provided p 2 657.1 mm2
A3 p AR − A1 − A′2
p 2 803.5 − 291.56 − 49.30 p 2 462.6 mm2 The use of end welds is optional (see Fig. I-3).
149
ASME B31.8-2016
MANDATORY APPENDIX K
CRITERIA FOR CATHODIC PROTECTION1
Reprinted with permission from the National Association of Corrosion Engineers’ NACE Standard RP0169, Section 6.
Asterisk (*) denotes word change from NACE text.
This entire appendix has been deleted
165
ASME B31.8-2016
reference electrode contacting the electrolyte. This polar- reference electrode contacting the electrolyte, equal to
ization voltage shift is to be determined by interrupting that required for the most anodic metal should be main-
the protective current and measuring polarization decay. tained. If amphoteric structures are involved that could
When the current is initially interrupted, an immediate be damaged by high alkalinity (see paras. 6.3.2.3 and
voltage shift will occur. The voltage reading after the 6.3.2.4), they should be electrically isolated with insulat-
immediate shift shall be used as the base reading from ing flanges or the equivalent.
which to measure polarization decay. See precautionary
notes in paras. 6.3.2.3 and 6.3.2.4. 6.4 Alternative Reference Electrodes
6.3.2.3 Excessive Voltages. Notwithstanding the
alternative minimum criteria in para. 6.3.2.1 and 6.4.1 Other standard reference electrodes may be
para. 6.3.2.2, aluminum, if cathodically protected at volt- substituted for the saturated copper-copper sulfate ref-
ages in excess of 1.20 V measured between the structure erence electrodes. Two commonly used electrodes are
surface and a saturated copper-copper sulfate reference listed below along with their voltage equivalent to
electrode contacting the electrolyte and compensated −0.85 V referred to saturated copper-copper sulfate ref-
for the voltage (IR) drops other than those across the erence electrode:
structure-electrolyte boundary, may suffer corrosion
resulting from the buildup of alkali on the metal surface. 6.4.1.1 Saturated KCl calomel reference elec-
A voltage in excess of 1.20 V should not be used unless trode: −0.78 V.
previous test results indicate no appreciable corrosion 6.4.1.2 Silver-silver chloride reference electrode
will occur in the particular environment.
used in sea water: −0.80 V.
6.3.2.4 Alkaline Soil Conditions. Since aluminum
may suffer from corrosion under high pH conditions 6.4.2 In addition to these standard reference elec-
and since application of cathodic protection tends to trodes, an alternative metallic material or structure may
increase the pH at the metal surface, careful investiga- be used in place of the saturated copper-copper sulfate
tion or testing should be made before applying cathodic reference electrode if the stability of its electrode poten-
protection to stop pitting attack on aluminum structures tial is assured and if its voltage equivalent referred to a
in environments with a natural pH in excess of 8.0. saturated copper-copper sulfate reference electrode is
6.3.3 Copper Structures established.
6.3.3.1 A minimum negative (cathodic) polariza-
tion voltage shift of 100 mV measured between the struc- 6.5 Special Considerations
ture surface and saturated copper-copper sulfate
6.5.1 Special cases, such as stray currents and stray
reference electrode in the electrolyte. This polarization
electrical gradients, may exist which require the use of
voltage shift is to be determined by interrupting the
criteria different from those listed above. Measurements
protective current and measuring the polarization decay.
of current loss and gain on the structure and current
When the current is initially interrupted, immediate
voltage shift will occur. The voltage reading after the tracing in the electrolyte have been useful in such cases.
immediate shift shall be used as the base reading from 6.5.2 Abnormal conditions sometimes exist where
which to measure polarization decay. protection is ineffective or only partially effective. Such
6.3.4 Dissimilar Metal Structure conditions may include elevated temperatures, dis-
6.3.4.1 A negative (cathodic) voltage, between all bonded coatings, shielding, bacterial attack, and
structure surfaces and a saturated copper-copper sulfate unusual contaminants in the electrolyte.
166
ASME B31.8-2016